SOW Attachment F - Schedule of Submittals.xlsx
XLSX spreadsheet 36 KB Posted
- Attached to
- Repair Fence Refueling Parking Area
- Solicitation number
- FA309926Q0007
About this file
This is a Schedule of Submittals document for a Design-Build project (Project #25-1011) to repair and replace the chain link security fence at the Refueling Parking Area at Laughlin Air Force Base. The schedule outlines all required contractor submittals organized across four notice-to-proceed (NTP) phases with specific deadlines and deliverable requirements.
Pre-construction submittals (NTP 1-3) include AF Form 103 within 7 days of NTP 1; design-related items such as a 65% design package, 95% design package, and 100% design package with 42-day and 35-day intervals respectively following government approvals; and compliance documentation including Entry Access Lists, OPSEC and Antiterrorism training proof, Contractor Safety Plan, QC Manager Qualifications, QC Plan, Construction Site Plan, and Traffic Control Plan—all due within 30 days of NTP 3. Environmental and hazardous material submittals include Hazardous Material Approvals, Asbestos Hazard Abatement Plans, TCEQ water system notifications and forms, and related certifications, with most due prior to NTP 4. Construction phase submittals (NTP 4) include QC Daily Inspection Reports, weekly Progress Schedule Forms, biweekly meeting minutes, Materials Testing reports, and Hazmat Usage Logs submitted monthly. Final submittals include Records of Existing Conditions within 14 days of NTP 2, As-Built Drawings within 2 weeks of Final Inspection, Operation and Maintenance Data, Completion Inspection punchlist, Draft and Final DD Form 1354 documents, and a Construction Warranty Management Plan. Digital copies are required for all submittals, with paper copy requirements specified for select items such as design drawings.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # 25-1011 PROJECT TITLE: REPAIR FENCE REFUELING PARKING AREA, F2420 SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | C = Construction Project D = Design Project | LAUGHLIN DIV 01 SPECIFICATIONS | ENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFB | STATEMENT OF WORK OR OBJECTIVES | NUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
APPR
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DIS
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
| NTP 1 - AF Form 103 | ||||||
| Submit AF Form 103 | C | 2.2 | 2.6.7, 6.1, 6.4 | Submit 7 days after Notice to Proceed 1 | ||
| Submit completed and approved AF Form 103 | 2.2 | 2.6.7, 6.1, 6.4 | Within 49 days from NTP 1 | |||
| On-Site Investigation Agenda | D | 6.4 | 14 Calendar days prior to NTP 2 | |||
| NTP 2 - Design | ||||||
| Entry Access List (EAL) | D | 1.8.2 | 2 Weeks prior to base access | |||
| Proof of OPSEC Training | D | 2.4 | 2 Weeks prior to base access | |||
| Antiterrorism Level I Awareness Training | C, D | 2.4 | 2 Weeks prior to base access | |||
| Summary of site investigation | D | 6.4 | NLT 14 Days after NTP 2 | |||
| 95% Design Package | D | 6.4 | 2 (drawings only) | NLT 42 days after Government approved 65% design submittal | ||
| 100% Design Package | D | 6.4 | 2 (drawings only) | NLT 35 calendar days after Government approved 95% design submittal | ||
| Statement of Work | D | 3.1.3.8 | NLT 35 calendar days after Government approved 95% design submittal | |||
| Initial Progress Schedule | D | 6.1.1 | Within 5 Days after receiving NTP1 | |||
| Progress Schedule Form and Contract Progress Report | C, D | 6.1.1, 6.1.2 | Biweekly | |||
| Meeting Minutes | D | 6.2.1 | NLT 3 Days after meeting | |||
| NTP 3 - Pre Construction | ||||||
| Entry Access List (EAL) | C | 1.8.2 | 2 Weeks prior to base access | |||
| Proof of OPSEC Training | C, D | 2.4 | 2 weeks prior to base access | |||
| Contractor Safety Plan | C | 3.2.2 | NLT 30 days after NTP 3 | |||
| Certificate of Contractor Safety Compliance | 3.2.3 | NLT 7 days after NTP 3 | ||||
| QC Manager Qualifications | C, D | 4.2.3 | NLT 7 days after NTP 3 | |||
| QC Plan | C, D | 4.2.4 | NLT 30 days after NTP 3 | |||
| Construction Site Plan | 12.1 | NLT 30 days after NTP 3 | ||||
| Hazardous Material Approval (Safety Data Sheets) | C | 3.2.1 | NLT 30 days after NTP 3 (as required) | |||
| Hazardous Waste Training Certificate | 3.2.2 | Prior to NTP 4 |
(as required) Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 4 (as required)
| Public Water System Notification | 3.4.1 | NLT 30 days after NTP 3 (as required) |
| Customer Service Inspection Certificate (TCEQ Form 20699) | 3.4.1 | Prior to NTP 4 |
(as required) TCEQ Public water system plan review submittal form (TCEQ Form 10233) 3.4.1 Prior to NTP 4 (as required) Clean Water Act TCEQ’s General Permit 3.4.2 Prior to NTP 4 (as required)
| Asbestos Hazard Abatement Plan | 3.5.2.1 | NLT 10 days prior to construction start |
| Copy of notification to Department of State Health Services | 3.5.2.1 | NLT 10 days prior to construction start |
| Worker/Area Protection Plan | 3.5.2.2 | Prior to NTP 4 |
(as required) FOD Plan C 14.1 Prior to NTP 4 (as required)
| Traffic Control Plan | C, D | 12.2 | 5.3, 5.5 | NLT 30 Days after NTP 3 | |||
| Records of Existing Conditions | C, D | 1.5, 7.1.1 | 4.2, 4.4, 5.5 | NLT 30 Days after NTP 3 | |||
| Submittals per Contractor's Design SOW | D | 10.4.4 through 10.4.11 | TBD | ||||
| NTP 4 - Construction | |||||||
| Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record | C | 5.1 / 6.2 | NLT 45 days from the date of signature of receiving facility | ||||
| Hazardous Waste Disposal Manifests | C | 5.2 / 6.2 | As required, prior to removal from Government property | ||||
| Hazmat Usage Log | C | 6.1 | End of each month during construction | ||||
| QC Daily Inspection Reports | C | 4.2.6 | Weekly | ||||
| Progress Schedule Form and Contract Progress Report | C | 6.1 | Biweekly | ||||
| Meeting Minutes | C | 6.2.1 | NLT 3 Days after meeting | ||||
| Records of Existing Conditions | C | 7.1.1 | NLT 14 days after NTP 2 | ||||
| Materials Testing | C | 7.1.3 | As required, within 7 days of test | ||||
| Submittals per Contractor's Design SOW | C | 10.4.4 through 10.4.11 | TBD | ||||
| Operation and Maintenance Data | C | 10.4.12 | NLT 2 weeks after Final Inspection | ||||
| As Built Drawings/CAD Files | C | 10.4.13 | 2 (D size) | NLT 2 weeks after Final Inspection | |||
| Completion Inspection (QC Manager Punchlist) | C | 13.4 | NLT 3 days after Pre-Final Inspection | ||||
| Draft DD Form 1354 | C | 13.3 | Prior to Pre-Final Inspection | ||||
| Final DD Form 1354 | C | 13.3 | At Final Inspection | ||||
| Submittal registry at 95% | C | 3.1.6 | NLT 42 days after Government approved 65% design submittal | ||||
| Submittal registry at 100% | C | 3.1.6 | NLT 35 calendar days after Government approved 95% design submittal | ||||
| Construction Warranty Management Plan | C | 13.2 | NLT 2 weeks after Final Inspection | ||||
| Project Specific Submittals | |||||||
| N/A | N/A | ||||||
| N/A | N/A | ||||||
| N/A | N/A | ||||||
| N/A | N/A | ||||||
| N/A | N/A | ||||||
| N/A | N/A | ||||||
| Schedule of Submittals Template, Feb 05 (SAF/AQCP) |
Task Order # FA3099-16-D-0002-0002 SOW Atch 2
&"Times New Roman,Regular"&12Page &P of &N