The provided document is a Statement of Work (SOW) Attachment 11 containing detailed photographs for the HVAC repairs at Buildings 4, 3rd Floor Pavilion - Phase 2. The photographs document the planned refrigerant line routing and equipment placement for a Variable Refrigerant Flow (VRF) heat pump system installation.
The nine photographs provide visual guidance for contractors, showing:
- Outdoor VRF unit locations on the 4th floor
- Refrigerant line routing paths through walls between the 4th and 3rd floors
- Hallway and pavilion area routing instructions
- Specific wall and ceiling penetration points
- Indoor cassette unit locations in the pavilion area (marked with red boxes)
- Routing of refrigerant lines above the drop ceiling and through hallway spaces
The images include blue lines indicating proposed refrigerant line paths and blue/red boxes highlighting specific installation locations and equipment placement, serving as a critical visual reference for the HVAC system installation project.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW ATTACHMENT 11
PHOTOGRAPHS
BUILDINGS 4 – 3rd Floor Pavilion HVAC Repairs – Phase 2 Sheet 1 of 3.
PHOTO 1 -- Looking East – 4th Floor -- Blue line shows Outdoor VRF Unit Location
PHOTO 2 – Looking North – 4th Floor – Blue line shows Outdoor VRF Unit Location
PHOTO 3 – Reverse Side of Wall – Outdoor VRF Unit PHOTO 4 – Refrigerant line routing must go through wall here from 4th floor to 3rd
Floor Hallway. Blue box shows location at wall.
Sheet 2 of 3.
PHOTO 5 – Refrigerant line routing must go through wall here from 4th floor to
3rd Floor Hallway. Blue box shows location at wall.
PHOTO 6 – 3rd Floor Hallway to Pavilion Area. Route refrigerant lines above hallway unit and drop ceiling. Temp Removal of Hallway HVAC may be required.
Blue line shows refrigerant line routing.
c
PHOTO 7 – 3rd Floor Pavillion Area – Looking West – Refrigerant lines enter here from hallway. Blue line shows refrigerant line routing.
PHOTO 8 – 3rd Floor Pavillion Area – Looking East from Hallway door. Route refrigerant lines to each Indoor Cassette. Blue line shows refrigerant line routing.
Sheet 3 of 3.
PHOTO 9 – 3rd Floor Pavillion Area – Looking East – North side of room. Route refrigerant lines to each Indoor Cassette. Blue line shows refrigerant line routing. Red boxes indicate location of Indoor cassette location (2 shown)
PHOTO 9 – 3rd Floor Pavillion Area – Looking East – South side of room. Route refrigerant lines to each Indoor Cassette. Blue line shows refrigerant line routing. Red boxes indicate location of Indoor cassette location (2 shown)