SOW Attachment 1 - Project Milestone Outline.pdf

PDF 101 KB Posted

Attached to
Z2DA--631-23-004 Repair Sewer and Bathrooms Building 1
Solicitation number
36C24124R0028
Issued by

About this file

This document is a Project Milestone Outline for the design and construction phases of a project at the Edward P. Boland VA Medical Center in Leeds, Massachusetts. The project involves repairs to the sewer system and bathrooms in Building 1.

The outline provides a detailed schedule of design submittals and construction activities, including design completion percentages, deliverables, and review/approval timelines. Key milestones include: 10% design at 45 days, 30% design at 90 days, 50% design at 135 days, 70% design at 195 days, 90% design at 225 days, and 100% design at 255 days. The construction period of performance is 270 days, with contract closeout activities to be completed within 380 days. Required deliverables include drawings, specifications, cost estimates, investigation reports, and as-built documentation. The project will be procured under Solicitation Number 36C24124R0028 issued by the Department of Veterans Affairs.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Edward P. Boland VAMC, Central Western Massachusetts Healthcare System 421 N Main Street Leeds, MA 01053

Attachment 1

6/28/2023

Design % complete Days Due Date Design Submissions Construction submissions Upon Completion & Approval NTP 0 TDB Bond Bond

Insurance Insurance NTP Letter/Project Checklist executed & Returned Proceed with submittals Look ahead schedule for site Investigation Proceed with non invasive site investigation

10% 45 #VALUE! Design Quality Assurance/Quality Control (QA/QC) Plan Site Specific Safety Plan Conceptual Plans / Basis of Design – Preliminary User Group Meetings & Field Surveys

Contractor CQC Plan

Basis of Design Narrative Project Baseline schedule Meeting Minutes from previous teleconference or meeting Draft Submittal Register Field survey findings/reports Phase 1 design complete Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above

60 #VALUE! VA review and Approval of 10% submission VA Submittal Review Approved limited invasive site investigation Phase 1 Materials Submittal HAZMAT / NESHAP Investigation

20% 60 #VALUE!

Meeting Minutes from previous teleconference or meeting Phase 1 ICRA Plan Updated Comment Matrix Phase 1 Materials Submittals Specification Table of Contents ICRA Materials Submission Field survey findings/reports

75 #VALUE! VA Submittal Review Phase 1 Construction

30% 90 #VALUE! 30% Schematic Design (SD)- Submittal Register Project Narrative Updated Project Baseline schedule 30% Schematic Drawings Specification Table of Contents Investigation Reports Design Calculations Space Planning Data Initial Cost Estimate Meeting Minutes from previous teleconference or meeting Updated Comment Matrix

Leeds, MA 01053

Attachment 1

6/28/2023

HAZMAT / NESHAP Report Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above

105 #VALUE! VA review and Approval of 30% submission VA Submittal Review Agreed upon material submittals ICRA wall constructon Approved, limited demolition, Site investigation

40% 105 #VALUE!

Meeting Minutes from previous teleconference or meeting Demolition Plan Updated Comment Matrix Abatement plan (if Necessary) Specifications Agreed upon material submittals Field survey findings/reports

120 #VALUE! VA review and Approval of 35% submission VA Submittal Review

50% 135 #VALUE! Narrative Agreed upon material submittals 50% Design Drawings Updated Project Baseline schedule 50% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above

150 #VALUE! VA review and Approval of 50% submission VA Submittal Review Approved Demolition Approved Construction

60% 165 #VALUE!

Meeting Minutes from previous teleconference or meeting Updated Comment Matrix Specification Table of Contents Field survey findings/reports

70% 195 #VALUE! Narrative Agreed upon material submittals 70% Design Drawings Updated Project Baseline schedule 70% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate

Leeds, MA 01053

Attachment 1

6/28/2023

Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above

210 #VALUE! VA review and Approval of 70% submission VA Submittal Review Approved Demolition Approved Construction

80% 210 #VALUE!

Meeting Minutes from previous teleconference or meeting Updated Comment Matrix Specification Table of Contents Field survey findings/reports

90% 225 #VALUE! Narrative Remaining material submittals 90% Design Drawings Updated Project Baseline schedule 90% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above

240 #VALUE! VA review and Approval of 90% submission VA Submittal Review Approved Demolition Approved Construction

100% 255 #VALUE! Narrative Remaining material submittals 100% Design Drawings Updated Project Baseline schedule 100% Specifications (final edits) Final Investigation reports Final Design Calculations Final Space Planning Data Final Cost Estimate Two (2) half-size paper bond sets of drawings Two (2) full-size paper bond sets of drawings Physical Security Compliance Report BIM / AutoCAD files All documents in any of the electronic formats listed above

100% 270 #VALUE! VA review and Approval of 100% submission VA Submittal Review All Construction Activities

270+65 Construction Period of Performance

Leeds, MA 01053

Attachment 1

6/28/2023

365 #VALUE! Contract Closeout Certification of compliance CQC Punchout inspection Two (2) half-size paper bond sets of Record Drawing/As-builts O&M Manuals Two (2) full-size paper bond sets of Record Drawing/As-builts CQC Punchlist corrective work BIM / AutoCAD files of Record Drawing/As-builts Prefinal inspection

Prefinal Punchlist corrective work HAZMAT Waste Manifests Training Warranties Final Acceptance Demobilization Release of Claims/Final Invoice

100% 380 #VALUE! VA review and Approval of closeout documents Contract Completion

Notes:

1. All specification requirements (pre-con submittals, material submittals and shop drawing required for the activity) must be met prior to starting the activity

2. Aproved construction is defined as: Necessary submitals have been approved and remainder of design is not likely effect the