SOW Attachment 1 - Project Milestone Outline.pdf
PDF 101 KB Posted
- Solicitation number
- 36C24124R0028
About this file
This document is a Project Milestone Outline for the design and construction phases of a project at the Edward P. Boland VA Medical Center in Leeds, Massachusetts. The project involves repairs to the sewer system and bathrooms in Building 1.
The outline provides a detailed schedule of design submittals and construction activities, including design completion percentages, deliverables, and review/approval timelines. Key milestones include: 10% design at 45 days, 30% design at 90 days, 50% design at 135 days, 70% design at 195 days, 90% design at 225 days, and 100% design at 255 days. The construction period of performance is 270 days, with contract closeout activities to be completed within 380 days. Required deliverables include drawings, specifications, cost estimates, investigation reports, and as-built documentation. The project will be procured under Solicitation Number 36C24124R0028 issued by the Department of Veterans Affairs.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Edward P. Boland VAMC, Central Western Massachusetts Healthcare System 421 N Main Street Leeds, MA 01053
Attachment 1
6/28/2023
Design % complete Days Due Date Design Submissions Construction submissions Upon Completion & Approval NTP 0 TDB Bond Bond
Insurance Insurance NTP Letter/Project Checklist executed & Returned Proceed with submittals Look ahead schedule for site Investigation Proceed with non invasive site investigation
10% 45 #VALUE! Design Quality Assurance/Quality Control (QA/QC) Plan Site Specific Safety Plan Conceptual Plans / Basis of Design – Preliminary User Group Meetings & Field Surveys
Contractor CQC Plan
Basis of Design Narrative Project Baseline schedule Meeting Minutes from previous teleconference or meeting Draft Submittal Register Field survey findings/reports Phase 1 design complete Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above
60 #VALUE! VA review and Approval of 10% submission VA Submittal Review Approved limited invasive site investigation Phase 1 Materials Submittal HAZMAT / NESHAP Investigation
20% 60 #VALUE!
Meeting Minutes from previous teleconference or meeting Phase 1 ICRA Plan Updated Comment Matrix Phase 1 Materials Submittals Specification Table of Contents ICRA Materials Submission Field survey findings/reports
75 #VALUE! VA Submittal Review Phase 1 Construction
30% 90 #VALUE! 30% Schematic Design (SD)- Submittal Register Project Narrative Updated Project Baseline schedule 30% Schematic Drawings Specification Table of Contents Investigation Reports Design Calculations Space Planning Data Initial Cost Estimate Meeting Minutes from previous teleconference or meeting Updated Comment Matrix
Leeds, MA 01053
Attachment 1
6/28/2023
HAZMAT / NESHAP Report Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above
105 #VALUE! VA review and Approval of 30% submission VA Submittal Review Agreed upon material submittals ICRA wall constructon Approved, limited demolition, Site investigation
40% 105 #VALUE!
Meeting Minutes from previous teleconference or meeting Demolition Plan Updated Comment Matrix Abatement plan (if Necessary) Specifications Agreed upon material submittals Field survey findings/reports
120 #VALUE! VA review and Approval of 35% submission VA Submittal Review
50% 135 #VALUE! Narrative Agreed upon material submittals 50% Design Drawings Updated Project Baseline schedule 50% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above
150 #VALUE! VA review and Approval of 50% submission VA Submittal Review Approved Demolition Approved Construction
60% 165 #VALUE!
Meeting Minutes from previous teleconference or meeting Updated Comment Matrix Specification Table of Contents Field survey findings/reports
70% 195 #VALUE! Narrative Agreed upon material submittals 70% Design Drawings Updated Project Baseline schedule 70% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate
Leeds, MA 01053
Attachment 1
6/28/2023
Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above
210 #VALUE! VA review and Approval of 70% submission VA Submittal Review Approved Demolition Approved Construction
80% 210 #VALUE!
Meeting Minutes from previous teleconference or meeting Updated Comment Matrix Specification Table of Contents Field survey findings/reports
90% 225 #VALUE! Narrative Remaining material submittals 90% Design Drawings Updated Project Baseline schedule 90% Specifications (edited) Investigation reports Design Calculations Space Planning Data Cost Estimate Two (2) half-size paper bond sets of drawings – Include alternates if necessary All documents in any of the electronic formats listed above
240 #VALUE! VA review and Approval of 90% submission VA Submittal Review Approved Demolition Approved Construction
100% 255 #VALUE! Narrative Remaining material submittals 100% Design Drawings Updated Project Baseline schedule 100% Specifications (final edits) Final Investigation reports Final Design Calculations Final Space Planning Data Final Cost Estimate Two (2) half-size paper bond sets of drawings Two (2) full-size paper bond sets of drawings Physical Security Compliance Report BIM / AutoCAD files All documents in any of the electronic formats listed above
100% 270 #VALUE! VA review and Approval of 100% submission VA Submittal Review All Construction Activities
270+65 Construction Period of Performance
Leeds, MA 01053
Attachment 1
6/28/2023
365 #VALUE! Contract Closeout Certification of compliance CQC Punchout inspection Two (2) half-size paper bond sets of Record Drawing/As-builts O&M Manuals Two (2) full-size paper bond sets of Record Drawing/As-builts CQC Punchlist corrective work BIM / AutoCAD files of Record Drawing/As-builts Prefinal inspection
Prefinal Punchlist corrective work HAZMAT Waste Manifests Training Warranties Final Acceptance Demobilization Release of Claims/Final Invoice
100% 380 #VALUE! VA review and Approval of closeout documents Contract Completion
Notes:
1. All specification requirements (pre-con submittals, material submittals and shop drawing required for the activity) must be met prior to starting the activity
2. Aproved construction is defined as: Necessary submitals have been approved and remainder of design is not likely effect the
Sheet1
File details come from the government source that posted it. Updated .