SOW Attachment 1. ATMOSPHERIC_BOILERS_REVISED_05262020.pdf
PDF 61 KB Posted
- Solicitation number
- SM-382236
About this file
This document is a boiler maintenance punch list for atmospheric water boilers that must be completed by a qualified boiler contractor by October 1 to ensure the boiler is ready for operation.
The maintenance scope includes comprehensive inspection and testing of all boiler components, systems, and safety features. Key water boiler tasks include performing lockout-tagout procedures with LOTO 2 training and NFPA 70 documentation; inspecting and cleaning pilot burner assemblies, flame sensors, tubing, and wiring; removing and cleaning burners with replacement pricing provided prior to authorization; checking burner primary air settings using a combustion analyzer; inspecting boiler castings, piping, and insulation; performing gas train leak detection using electronic devices; evaluating flue piping pitch (0.25 inches per foot) and draft with a draft gauge tool; testing draft diverters and spill switches with documented methodology; inspecting flue dampers and rotational end switches; verifying makeup water system and expansion tank conditions; testing pressure relief valves using lift test methods; checking all operating and limit controls; verifying gas supply line pressure with a manometer; conducting boiler firing tests following manufacturer recommendations; testing low water cutout manual reset with vendor explanation; performing carbon monoxide testing to ensure 0 PPM with appropriate testing equipment; performing combustion analysis with documented analyzer knowledge; and providing documentation for A.S.M.E. CSD-1 compliance. The water pumps section requires checking boiler recirculating and bypass pump operation and reporting unusual findings. In-house craft responsibilities include checking hot water supply circulating pump rotation, pump motor mounts, pump amperes, pump and motor bearings, and tightening all pump motor electrical connections.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATMOSPHERIC BOILERS
HAVE A QUALIFIED BOILER CONTRACTOR PERFORM AN ANNUAL INSPECTION OF BOILER FOLLOWING
MANUFACTURER'S RECOMMENDATION. BOILER TO BE READY FOR OPERATION BY OCTOBER 1.
BOILER MAINTENANCE PUNCH LIST:
WATER BOILERS
• PERFORM LOCK OUT- TAG OUT (LOTO) ON GAS AND ELECTRICAL POWER TO BOILER // LOTO 2
TRAINING AND NFPA 70 DOCUMENTATION
• CHECK CONDITION OF ALL COVERS AND REMOVABLE PANELS
• CHECK AND CLEAN PILOT BURNER ASSEMBLY ORIFICE REPLACE IF NEEDED // CHECK AND
VERIFY PILOT FLAME // VENDOR TO CONFIRM HOW THIS WILL BE VERIFIED
• CHECK AND CLEAN PILOT FLAME SENSOR REPLACE IF NEEDED
• CHECK PILOT TUBING AND FITTINGS FOR LEAKS OR CRACKS REPAIR AS NEEDED
• CHECK PILOT BURNER GROUNDING CONTINUITY
• CHECK PILOT WIRING
• REMOVE AND CLEAN BURNERS
• CHECK BURNERS FOR RUST AND DISCOLORATION: REPLACE IF NEEDED – THE VENDOR TO
PROVIDE PRICING PRIOR TO REPLACEMENT AUTHORIZATION
• CHECK BURNER PRIMARY AIR SETTING (WHERE APPLICABLE) / VENDOR TO HAVE COMBUSTION
ANALYZER TOOL AND DEMONSTRATED OR DOCUMENTED ABILITY TO PERFORM ANALYSIS
• CHECK CONDITION OF BURNER COMPARTMENT INSULATION
• FLUE BRUSH BETWEEN CASTINGS // PROVIDE FLUE BRUSH OF PROPER SIZES AND NEED
CONFIRMATION OF PROPER SIZES
• CLEAN BURNER COMPARTMENT
• CHECK BOILER CASTINGS AND PIPING FOR FLUID LEAKS // VISUAL INSPECTION OF FLUID LEAKS
• CHECK GAS TRAIN FOR LEAKS / VENDOR TO PROVIDE ELECTRONIC GAS LEAK DETECTION DEVICE
• CHECK FLUE PIPING FOR BREACHING AND DETERIORATION // VISUAL AND USE OF CO DETECTOR
• CHECK FLUE PIPING FOR PROPER PITCH AND NEGATIVE DRAFT // 0.25 INCHES PER FOOT //
DRAFT GAUGE TOOL REQUIRED
• CHECK DRAFT DIVERTER AND SPILL SWITCH //PROVIDE YOUR METHODOLGY OF HOW FLUE GAS
SPILL SWITCHES WIILL BE TESTED
• CHECK FLUE DAMPER AND ROTATIONAL END SWITCHES
• CHECK MAKEUP WATER SYSTEM NOTE: (SOME REQUIRE 30% PROPYLENE GLYCOL/WATER MIX)
// GLYCOL TESTER NEEDED
• CHECK EXPANSION TANK AND FLUID LEVEL
• CHECK BOILER PRESSURE AND TEMPERATURE GAGES FOR PROPER OPERATION // PER
MANUFACTURER RECOMMENDATIONS
• CHECK PRESSURE RELIEF VALVE OPERATION TEST FOR PROPER FLOW AND LEAK TIGHTNESS
//LIFT TEST METHOD IS TO BE UTILIZED
• CHECK ALL OPERATING AND LIMIT CONTROLS
• CHECK GAS SUPPLY LINE PRESSURE // MANOMETER DEVICE IS NEEDED
• CHECK OPERATION OF HIGH & LOW GAS PRESSURE SAFETY LIMITS /
• TEST FIRE BOILER // FOLLOW MANUFACTURER RECOMMENDATIONS FOR TEMPERATURE RATE
OF RISE TO PREVENT METAL STRESS / TUBE SHEET LEAKS
• TEST OPERATION OF LOW WATER CUT OUT MANUAL RESET // VENDOR TO PROVIDE
EXPLANATION OF HOW THIS IS DONE IN THEIR PROPOSAL
• CHECK OPERATION OF BURNER CONTROL
• CHECK ALL BURNERS VISUALLY FOR FLAME CONDITION
• CHECK FLUE PIPING FOR SPILLAGE // CHECK FOR OBSTRUCTIONS, VISUAL INSPECTION AND
WITH CO DETECTOR, FLUE WILL BE HOT TO TOUCH, CHECK FOR LEAKS
• PERFORM CARBON MONOXIDE TEST IN BOILER ROOM ENSURE 0 PPM // CARBON MONOXIDE
TESTER AND KNOWLEDGE OF HOW TO USE THE TOOL
• PERFORM COMBUSTION ANALYSIS // VENDOR TO HAVE A COMBUSTION ANALYZER AND
DOCUMENTED OR DEMONSTRATED KNOWLEDGE OF ANALYZER USAGE
• PROVIDE DOCUMENTATION OF FINDINGS FOR A.S.M.E. CSD-1 COMPLIANCE //DOCUMENTED
OR DEMONSTRATED FAMILIARITY AND UNDERSTANDING OF THIS STANDARD
WATER PUMPS
• CHECK BOILER RECIRCULATING PUMP AND BYPASS PUMP OPERATION
• REPORT ANY UNUSUAL FINDINGS
IN HOUSE CRAFTS TO:
• CHECK HWS CIRCULATING PUMP ROTATION
• CHECK PUMP MOTOR MOUNTS
• CHECK PUMP AMPERES
• CHECK PUMP AND MOTOR BEARINGS
• TIGHTEN ALL PUMP MOTOR ELECTRICAL CONNECTION
File details come from the government source that posted it. Updated .