This is a Statement of Work (SOW) for boiler preventative and corrective maintenance services at Fermi National Accelerator Laboratory (FermiLab) in Batavia, Illinois.

FermiLab, a Department of Energy facility operated by Fermi Forward Discovery Group (FFDG), seeks a subcontractor to provide preventative and corrective maintenance services for heating boiler systems across the 6,800-acre site located in DuPage and Kane counties. The subcontractor must supply all labor, materials, equipment, tools, transportation, and supervision necessary to execute the work. Preventative maintenance services include visual inspections, leak and corrosion detection, burner and heat exchanger cleaning, safety control testing and calibration, combustion verification, valve and gauge inspection and adjustment, lubrication, electrical connection verification, and comprehensive system documentation. Special attention is required for boilers at the New Muon Lab (NML) and Central Utility Building (CUB) facilities, which require boilermakers to disassemble, clean, and reassemble two boilers at each location, followed by service technician tuning. All services must be performed by qualified, trained, and licensed technicians compliant with federal, state, local, and FFDG safety regulations, including OSHA requirements and proper personal protective equipment use. Preventative maintenance reports must be submitted after each inspection, and corrective maintenance reports must document work performed, parts replaced, and system status. The subcontract requires two full work days advance notice for utility shutdowns (five days for radiography sources). The estimated period of performance runs from October 1, 2026, through September 30, 2031. Deliverables include inspection and maintenance reports as needed and invoices.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW DATE: 5/18/2026

PROJECT TITLE: Boiler Preventative and Corrective Maintenance Services FERMILAB SUBCONTRACT SPECIALIST: Seth Mercil, smercil@fnal.gov FERMILAB POINT OF CONTACT: Tim Burger, tburger@fnal.gov COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Kane☒

INTRODUCTION

Fermi National Accelerator Laboratory (FermiLab) is seeking a subcontractor to provide preventative and corrective maintenance services for heating boiler systems at the facility. The Fermilab site is 6,800 acres and is owned by the Department of Energy (DOE) and operated by the Fermi Forward Discovery Group (FFDG).

This Statement of Work defines the scope, terms, and conditions for providing preventative and corrective maintenance services for heating boiler systems to ensure continued safe, reliable, and efficient operation.

The subcontractor shall provide all labor, materials, equipment, and supervision necessary to perform the work indicated in the scope of work below. A Service Coordinator will be assigned to provide oversight of the project.

SCOPE OF WORK

Preventative Maintenance (PM)

The Subcontractor shall provide scheduled preventative maintenance inspections and services for all covered heating boilers. The Subcontractor shall furnish all properly qualified personnel, tools, transportation, and equipment with appropriate accessories, except as provided by Fermilab, and shall plan, coordinate and assure effective execution of the boiler inspection services checklist described in Attachments 1-4.

Please note that boilers in the New Muon Lab (NML) and Central Utility Building (CUB) facilities will require boilermakers to disassemble, clean, and reassemble two boilers at each location. Once cleaning is complete, a service technician will be needed to tune the boilers and return them to service.

PM services shall include, but are not limited to (detailed PM requirements are listed in Attachments 1-4):

• Visual inspection of boiler systems, components, and controls

• Inspection for leaks, corrosion, and wear

• Cleaning of burners, heat exchangers, and related components

• Testing and calibration of safety controls and devices

• Verification of proper combustion and system efficiency

• Inspection and adjustment of valves, gauges, and piping

• Lubrication of moving parts as required

• Verification of electrical connections and controls

• Documentation of system condition and deficiencies documented as requested by FFDG.

Statement of Work Infrastructure Services Division mailto:smercil@fnal.gov mailto:tburger@fnal.gov

• Submission of an inspection report with recommendations documented as requested by

FFDG.

Frequency:

Preventative maintenance inspections shall be performed per requirements in Attachments 1-4.

PERSONNEL QUALIFICATIONS

All services shall be performed by qualified, trained, and licensed technicians experienced in boiler maintenance and repair. Technicians shall comply with all applicable codes, standards, and safety regulations.

SAFETY AND COMPLIANCE

The subcontractor shall adhere to all federal, state, local, and FFDG safety regulations, including OSHA requirements. Proper personal protective equipment (PPE) shall be used at all times.

REPORTING AND DOCUMENTATION

1) Preventative maintenance reports shall be submitted after each inspection and documented as requested by FFDG.

2) Corrective maintenance reports shall document work performed, parts replaced, and system status following the repair.

3) Service logs shall be maintained and made available upon request.

EXCLUSIONS

Unless otherwise specified, the following are excluded:

a) Major system upgrades or replacements

b) Work outside normal service hours (unless authorized)

c) Non-boiler related systems

COVERED EQUIPMENT

All equipment related to this subcontract is included in the attachments listed below. The preventative maintenance required and the preventative maintenance schedule for each boiler type is also included in the attachments:

• Attachment 1 ATMOSPHERIC BOILERS REVISED 05262020

• Attachment 2 CONDENSING BOILERS REVISED 05272020

• Attachment 3 ELECTRIC BOILERS REVISED 05282020

• Attachment 4 ADDENDUM CERTIFICATES AND STAMPS

• Attachment 5 EQUIPMENT LIST

GOVERNMENT FURNISHED PROPERTY

FERMILAB FURNISHED SERVICES which must be coordinated with the Subcontractor’s work, such as requests for de-energizing electrical equipment or any utility shutdown (electrical, mechanical ducts, sprinklers, alarms, water, etc.), shall be arranged through Fermilab with at least two (2) full work days advance notice from the Subcontractor, except for use of radiography sources, which will require five

(5) full work days advance notice. This does not apply to de-energizing electrical service required during the execution of inspection or repair maintenance service. The contractor will be responsible for de-energizing electrical service using LOTO.

PLACE OF PERFORMANCE

Fermi National Accelerator Laboratory, Batavia, IL, Sitewide.

ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE

EST START DATE: 10/1/2026 EST END DATE: 9/30/2031

DELIVERABLES

Inspection/Maintenance/Repairs Reports (as needed/requested)

Invoice(s)

[END OF DOCUMENT]

Preventative Maintenance (PM)
The Subcontractor shall provide scheduled preventative maintenance inspections and services for all covered heating boilers. The Subcontractor shall furnish all properly qualified personnel, tools, transportation, and equipment with appropriate access...
Please note that boilers in the New Muon Lab (NML) and Central Utility Building (CUB) facilities will require boilermakers to disassemble, clean, and reassemble two boilers at each location. Once cleaning is complete, a service technician will be nee...