Solicitation - W9128F27RA045.pdf

PDF 7 MB Posted

Attached to
Mather Fueling System Repairs
Solicitation number
PANNWD26P028176
Issued by

About this file

This is a Request for Proposal (RFP) for construction services to repair and upgrade the fueling system at Mather Air Force Base in California.

The solicitation is issued by the U.S. Army Corps of Engineers (USACE), Omaha District, under solicitation number W9128F27RA045, with a project number of 028176. The project, titled "Mather Fueling System Repairs," involves comprehensive modifications to a 12,000-gallon jet fuel (F-24) horizontal aboveground storage tank and surrounding fueling infrastructure. Work includes installing sampling and gauging hatches and a mechanical clock gauge on tank manways, recoating the tank exterior, replacing collision barriers, adding a full-length catwalk, and replacing audible and visual alarms. Additional scope includes repairing and sloping the remote containment basin drainage system, replacing asphalt near the fueling facility and truck offload area with concrete, repairing refueler parking concrete, replacing the fuel dispenser monitor with a non-coalescing filter and hand pump water draw-off system, replacing the POL operations building in kind, and relocating the generator outside the compartmentalized unit. An ATG system upgrade from Veeder Root TLS-350 Plus to TLS-450 Plus is also included. Offers are due by 27 November 2026 at 2:00 PM local time, with the contractor to begin performance within 10 calendar days of notice to proceed and complete all work within 365 calendar days. The Government anticipates award of a firm fixed-price contract. Performance and payment bonds are required within 10 calendar days of award. Liquidated damages are set at $1,070.00 per calendar day of delay. The contract magnitude is between $1,000,000 and $5,000,000, and this project will be awarded without discussions. Three optional line items address handling and disposal of petroleum-contaminated soil, lead-based paint, and asbestos-containing material.

View the file

Other files

File Type Posted
Davis Bacon Wage Determinations - CA20260007.pdf PDF
RFP Drawings.pdf PDF
27-R-A045-Specs.pdf PDF
Mather Selection Criteria.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

Created On:

08 Oct 2026, 15:31 PM Central Daylight Time

DRAFT

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Patrick.Ferguson Line

Patrick.Ferguson Line

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

Additional Information/Notes

Offerors must insert a price on all numbered items of the CLIN pricing schedule. Prices include both design and construction. Failure to do so may result in the offer being unacceptable. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price. The Government reserves the right to exercise Option Items 0010 through 0011 any time during required excavations for the contract. Abbreviations: Minor Construction (MC); Maintenance and Repair (MR); Demolition (DEMO).

1. Funds are not presently available for this acquisition. No contract award will be made until funds are made available.

2. (FAR 52.217-5) EVALUATION OF OPTIONS

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

*** END OF NARRATIVE 1 ***

Item Supplies/Service Quanti ty

Unit Unit Price Amount

0001 Facility AVGAS - (Jet Fuel (F-24) Tank) - (MR) - Includes all work to install a sampling gauge hatch on a manway, install a clock type mechanical gauge on a manway, recoat the exterior of the tank, replace the collision barriers, add a catwalk that extends across the entirety of the tank, and replace the audible and visual alarms.

1 Job

W9128F27RA045

Pricing Arrangement: Firm Fixed Price

0002 Facility PCB08 - (Remote Containment Basin) - (MR) - Includes all work to fix the remote containment basin drainage issue.

Pricing Arrangement: Firm Fixed Price

1 Job

0003 Facility PRKFF - (Asphalt) - (MR) - Includes all work to replace the asphalt on the NE side of the fueling facility.

Pricing Arrangement: Firm Fixed Price

1 Job

0004 Facility PRKFT - (Refueler Parking)

- (MR) - Includes all work to repair the refueler parking concrete.

Pricing Arrangement: Firm Fixed Price

1 Job

0005 Facility FUEL1 - (Fuel Dispenser) - (MR) - Includes all work to replace the dispenser fuel monitor with a noncoalescing filter and install a water draw off system with a hand pump

Pricing Arrangement: Firm Fixed Price

1 Job

0006 1 Job

Facility FUEL3 - (Truck Offload /Fillstand) - (MR) - Includes all work to replace the asphalt near the loading/unloading facility with a concrete path.

Pricing Arrangement: Firm Fixed Price

0007 Facility ATG - (Equipment) - Includes all work to complete supplying, installation, and testing ATG system on Fuel Storage Tank, AVGAS.

Pricing Arrangement: Firm Fixed Price

1 Job

0008 Facility FUELG - (Generator) - (MR)

- Includes all work to relocate the generator that is inside the compartmentalized area.

Pricing Arrangement: Firm Fixed Price

1 Job

0009 Facility FUEL5 - (New POL Ops Building) - (MR) - Includes all work to remove existing POL Ops building. Includes all work to provide a new building of the same size and location and include all heating/cooling and electrical infrastructure.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

All work complete for stockpiling, handling, and proper disposal of petroleum contaminated soil and notification to regulatory agencies for petroleum contaminated soil that cannot be reused on-site for backfill purposes. The Government reserves the right to exercise this option at any time during the contract performance period.

Exercising this option will not extend the period of performance.

See FAR 52.217-5 Evaluation of Options.

Pricing Arrangement: Firm Fixed Price

20 Actual Tons

Option Line Item

All work complete for handling and proper disposal of lead-based paint and paint containing chromium. The government reserves the right to exercise this option at any time during the contract performance period. Exercising this option will not extend the period of performance. See FAR 52.217-5 Evaluation of Options.

Pricing Arrangement: Firm Fixed Price

50 Squar e Foot

Option Line Item

All work complete for handling and proper disposal of asbestos containing material. The government reserves the right to exercise this option at any time during the contract performance

50 Squar e Foot period. Exercising this option will not extend the period of performance. See FAR 52.217-5 Evaluation of Options.

Product Service Code: Y1GC

Pricing Arrangement: Firm Fixed Price

Section 00 21 00 - Instructions

1.2 OFFEROR'S QUESTIONS AND COMMENTS

Submit questions and/or comments relative to these documents via Bidder Inquiry as indicated below. See instructions on when e-mail is appropriate.

Only submit proprietary questions and/or comments relative to these bidding (proposal) documents or if the Bidder Inquiry system (See Below) is out of service directly to the Contract Specialist:

Contract Specialist: samuel.v.obrist@usace.army.mil

Contracting Officer: dawn.s.barnett@usace.army.mil

1.2.1 BIDDER INQUIRY

Technical inquiries and questions relating to technical requirements, proposal procedures, or bonds are to be submitted via Bidder Inquiry (in ProjNet at https://www.projnet.org/projnet/) No Later Than 14 calendar days after the bid walk, in order that they may be given consideration and acted upon prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key and follow the instructions listed below. A prospective vendor who submits a comment/question will receive an acknowledgement of it via email, followed by an answer from our technical team.

All timely questions and approved answers will be made available through ProjNet.

The Solicitation Number is: W9128F-27-RA045

The Bidder Inquiry Key is: MJMBE3-SFUEV3

a. Registration for ProjNet Bidder Inquiry Access

If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

8. Follow online screen instructions to enter specific bidder inquiries for the project.

c. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

d. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

e. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

The magnitude of this project is between $1,000,000 and $5,000,000. This project will be awarded WITHOUT discussions.

The Government reserves the right to employ AI tools/platforms to assist in specified support tasks ( e.g., summarizing voluminous content, highlighting compliance with basic solicitation requirements, organizing proposal data for evaluator review, etc.).

AI is used as a tool to support decision-makers, but will not be used to make evaluative judgments or selections, or to replace the independent assessment of source selection personnel.

Source selection personnel remain exclusively responsible for the accuracy, integrity, and final approval of all acquisition actions, to include final evaluations, adjectival ratings, best value determinations, and selection decisions.

Any AI platform or tool used by the Government adheres to requirements Department of War (DoW) cybersecurity frameworks at Impact Level 5 (IL5) or higher to safeguard contractor bid, proposal, and proprietary data and prohibits the use of contractor data for training external or commercial AI models.

*** END OF NARRATIVE 1 ***

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-7 System for Award Management- Registration. (Deviation 2026- O0038)

2026-02

52.214-34 Submission of Offers in the English Language.

1991-04

52.214-35 Submission of Offers in U.S.

Currency.

1991-04

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (Deviation 2026- O0038)

2026-02

52.225-10 Notice of Buy American Requirement-Construction Materials.

2014-05

DFARS Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.204-7024 Notice on the Use of the Supplier Performance Risk System.

2023-03

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.

2023-01

FAR Provisions Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.216-1 Type of Contract. (Deviation 2026-O0038)

2026-02

Type of Contract (Feb 2026) (Deviation 2026-O0038)

The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.

(End of provision)

52.252-1 Solicitation Provisions Incorporated by Reference.

1998-02

Solicitation Provisions Incorporated by Reference (Feb 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/far-overhaul https://www.acquisition.gov/dfars

(End of provision)

Section 00 22 00 - Supplementary Instructions

See Attached: Mather Selection Criteria

*** END OF NARRATIVE 1 ***

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.217-5 Evaluation of Options. (Deviation 2026-O0038)

2026-02

Section 00 45 00 - Representations and Certifications

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.

2024-09

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements- Representation.

2017-01

52.223-1 Biobased Product Certification.

(Deviation 2026-O0038)

2026-02

52.223-4 Recovered Material Certification. 2008-05

52.240-90 Security Prohibitions and Exclusions Representations and Certifications. (Deviation 2026- O0038)

DFARS Provisions Incorporated by Reference

Date

Alternate Deviation

Variation Effective Date

252.203-7005 Representation Relating to Compensation of Former DoD Officials.

2022-09

252.204-7008 Compliance with Safeguarding Covered Defense Information Controls.

2016-10

252.225-7055 Representation Regarding Business Operations with the Maduro Regime.

2022-05

252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region- Representation.

2023-06

FAR Provisions Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.203-2 Certificate of Independent Price Determination.

1985-04

Certificate of Independent Price Determination (Apr 1985)

(a) The offeror certifies that-

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to-

(i) Those prices;

(ii) The intention to submit an offer; or

(iii) The methods or factors used to calculate the prices offered.

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory-

(1) Is the person in the offeror's organization responsible for determining the prices being offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to paragraphs (a)(1) through (a)(3) of this provision; or

(2)

(i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to paragraphs (a)(1) through (a)(3) of this provision ____[insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization];

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) of this provision have not participated, and will not participate, in any action contrary to paragraphs (a)

(1) through (a)(3) of this provision; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to paragraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) above, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

DFARS Provisions Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services-Representation.

2021-05

PROHIBITION ON THE ACQUISITION OF COVERED DEFENSE TELECOMMUNICATIONS

EQUIPMENT OR SERVICES-REPRESENTATION (MAY 2021)

The Offeror is not required to complete the representation in this provision if the Offeror has represented in the provision at 252.204-7016, Covered Defense Telecommunications Equipment or Services-Representation, that it "does not provide covered defense telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument."

(a) . "Covered defense telecommunications equipment or services," "covered Definitions mission," "critical technology," and "substantial or essential component," as used in this provision, have the meanings given in the 252.204-7018 clause, Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services, of this solicitation.

(b) . Section 1656 of the National Defense Authorization Act for Fiscal Year 2018 Prohibition (Pub. L. 115-91) prohibits agencies from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

(c) . The Offeror shall review the list of excluded parties in the System for Award Procedures Management (SAM) at for entities that are excluded when providing any https://www.sam.gov equipment, system, or service to carry out covered missions that uses covered defense telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless a waiver is granted.

(d) . If in its annual representations and certifications in SAM the Offeror has Representation represented in paragraph (c) of the provision at 252.204-7016, Covered Defense Telecommunications Equipment or Services-Representation, that it "does" provide covered defense telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument, then the Offeror shall complete the following additional representation:

The Offeror represents that it will not provide covered defense telecommunications equipment or services as a part of its offered products or services to DoD in the performance of any award resulting from this solicitation.

(e) . If the Offeror has represented in paragraph (d) of this provision that it "will Disclosures provide covered defense telecommunications equipment or services," the Offeror shall provide the following information as part of the offer:

(1) A description of all covered defense telecommunications equipment and services offered (include brand or manufacturer; product, such as model number, original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable).

(2) An explanation of the proposed use of covered defense telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition referenced in paragraph (b) of this provision.

(3) For services, the entity providing the covered defense telecommunications services (include entity name, unique entity identifier, and Commercial and Government Entity (CAGE) code, if known).

(4) For equipment, the entity that produced or provided the covered defense telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known).

Section 00 50 00 - Contracting Forms and Supplements

All attachments are hereby incorporated by full text and are made part of solicitation W9128F27RA045.

1. 27-R-A045 - Specs

2. Davis Bacon Wage Determinations - CA20260007

3. Mather Selection Criteria

4. RFP Drawings

*** END OF NARRATIVE 1 ***

Section 00 70 00 - Conditions of the Contract

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.222-7 Withholding of Funds. (Deviation 2026-O0038)

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items.

(Alternate I)

2008-05 Alternate I 2008-05

Alternate I (May 2008). As prescribed in 23.108(b)(2), redesignate paragraph (b) of the basic clause as paragraph (c) and add the following paragraph (b) to the basic clause:

(b) The Contractor shall execute the following certification required by the Resource Conservation and Recovery Act of 1976 ( 42 U.S.C. 6962(i)(2)(C)):

Certification

I, ____(name of certifier), am an officer or employee responsible for the performance of this contract and hereby certify that the percentage of recovered material content for EPA-designated items met the applicable contract specifications or other contractual requirements.

____[Signature of the Officer or Employee]

____[Typed Name of the Officer or Employee]

____[Title]

____[Name of Company, Firm, or Organization]

____[Date]

(End of certification)

Section 00 72 00 - General Conditions

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-7 Anti-Kickback Procedures. 2020-06

52.203-12 Limitation on Payments to Influence Certain Federal Transactions.

2020-06

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation 2026-O0038)

2026-02

52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)

2026-02

52.204-19 Incorporation by Reference of Representations and Certifications.

2014-12

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation 2026- O0038)

2026-02

52.209-10 Prohibition on Contracting With 2026-02

Inverted Domestic Corporations.

(Deviation 2026-O0038)

52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)

2026-02

52.219-8 Utilization of Small Business Concerns. (Deviation 2026- O0038)

2026-02

52.219-9 Small Business Subcontracting Plan. (Deviation 2026-O0038)

2026-02

52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)

2026-02

52.222-8 Payrolls and Basic Records.

(Deviation 2026-O0038)

2026-02

52.222-9 Apprentices and Trainees.

(Deviation 2026-O0038)

2026-02

52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)

2026-02

52.222-11 Subcontracts (Labor Standards).

(Deviation 2026-O0038)

2026-02

52.222-12 Contract Termination-Debarment. 2014-05

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.

2014-05

52.222-14 Disputes Concerning Labor Standards. (Deviation 2026- O0038)

2026-02

52.222-15 Certification of Eligibility. 2014-05

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method). (Deviation 2026- O0038)

2026-02

52.222-35 Equal Opportunity for Veterans.

(Deviation 2026-O0038)

2026-02

52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)

2026-02

52.222-37 Employment Reports on Veterans. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.222-54 Employment Eligibility Verification. (Deviation 2026- O0038)

2026-02

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)

2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0040, Revision 1)

2026-04

52.223-2 Reporting of Biobased Products 2026-02

Under Service and Construction Contracts. (Deviation 2026- O0038)

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.232-8 Discounts for Prompt Payment. 2002-02

52.232-23 Assignment of Claims. 2014-05

52.232-27 Prompt Payment for Construction Contracts.

2017-01

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-39 Unenforceability of Unauthorized Obligations.

2013-06

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-1 Disputes. (Deviation 2026- O0038)

2026-02

52.233-1 Disputes. (Deviation 2026- O0038) (Alternate I)

2026-02 Alternate I 2026-02

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026-

2026-02

O0038)

52.236-5 Material and Workmanship.

(Deviation 2026-O0038)

2026-02

52.236-7 Permits and Responsibilities.

(Deviation 2026-O0038)

2026-02

52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)

2026-02

52.242-5 Payments to Small Business Subcontractors.

2017-01

52.242-14 Suspension of Work. 1984-04

52.243-5 Changes and Changed Conditions. (Deviation 2026- O0038)

2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-04

52.246-12 Inspection of Construction. 1996-08

52.246-21 Warranty of Construction. 1994-03

52.247-68 Report of Shipment (REPSHIP). 2006-02

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form).

1984-04

DFARS Clauses Incorporated by Reference

Number Title Effective Alternate Variation

Date Deviation Effective Date

252.201-7000 Contracting Officer's Representative.

1991-12

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7003 Control of Government Personnel Work Product.

1992-04

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.

2024-05

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.

2019-05

252.225-7012 Preference for Certain Domestic Commodities.

2022-04

252.225-7048 Export-Controlled Items. 2013-06

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.232-7010 Levies on Contract Payments. 2006-12

252.236-7000 Modification Proposals--Price Breakdown.

1991-12

252.236-7005 Airfield Safety Precautions. 1991-12

252.243-7001 Pricing of Contract Modifications. 1991-12

252.247-7023 Transportation of Supplies by Sea.

2024-10

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.211-12 Liquidated Damages- Construction.

2000-09

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,070.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.219-14 Limitations on Subcontracting.

(Deviation 2026-O0038)

2026-02

Limitations on Subcontracting (Feb 2026) (Deviation 2026-O0038)

(a) This clause does not apply to the unrestricted portion of a partial set-aside.

(b) , as used in this clause, means a first-tier subcontractor, Definition. Similarly situated entity including an independent contractor, that-

(1) Has the same small business program status as that which qualified the prime contractor for the award ( , for a small business set-aside contract, any small business concern, without e.g.

regard to its socioeconomic status); and

(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.

(c) This clause applies only to-Applicability.

(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);

(3) Contracts that have been awarded on a sole-source basis in accordance with sections 19.105, 19.106, 19.107, and 19.108;

(4) Orders expected to exceed the simplified acquisition threshold and that are set aside for small business concerns under multiple-award contracts, as described in 8.4 and 16.5;

(5) Orders, regardless of dollar value, that are set aside in accordance with sections 19.105, 19.106, 19.107, and 19.108 under multiple-award contracts, as described in 8.4 and 16.5; and

(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.

(d) An independent contractor shall be considered a subcontractor.Independent contractors.

(e) By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for-

(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;

(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;

(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or

(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.

(f) The Contractor shall comply with the limitations on subcontracting as follows:

(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause-

By the end of the base term of the contract and then by the end of each subsequent option period; or

[X] By the end of the performance period for each order issued under the contract.

(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.

(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.

(1) In a joint venture comprised of a small business protege and its mentor approved by the Small Business Administration, the small business protege shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protege in the joint venture must be more than administrative functions.

(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.

(End of clause)

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items.

2008-05

Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

. As used in this clause-(a) Definitions means a material or finished product that has served its intended use Postconsumer material and has been discarded for disposal or recovery, having completed its life as a consumer item.

Postconsumer material is a part of the broader category of "recovered material."

"Recovered material" means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

The Contractor, on completion of this contract, shall-(b)

Estimate the percentage of the total recovered material content for EPA-designated item(s) (1) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to Project Manager, Scott Matrangos

(End of clause)

52.223-11 Ozone-Depleting Substances.

(Deviation 2026-O0038)

2026-02

Ozone-Depleting Substances (Feb 2026) (Deviation 2026-O0038)

(a) Definition. As used in this clause-

Ozone-depleting substance means any substance the Environmental Protection Agency designates in 40 CFR part 82 as-

(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or

(2) Class II, including, but not limited to, hydrochlorofluorocarbons.

(b) Requirement. In accordance with 40 CFR 82.84(a)(5), the Contractor shall label products that contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j(b), (c), (d), and (e) and 40 CFR part 82, subpart E, as follows:

Warning: Contains (or manufactured with, if applicable) *____, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.

* The Contractor shall insert the name of the substance(s).

52.225-9 Buy American-Construction Materials. (Deviation 2026- O0038)

2026-02

Buy American-Construction Materials (Feb 2026) (Deviation 2026-O0038)

(a) . As used in this clause-Definitions

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

NONE

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical .components

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A) of this clause.(1)

(3) The procedures in paragraph (b)(3)(i)(A) of this clause will no longer apply as of January (2) 1, 2030.

(B) .For domestic construction material that is a critical item or contains critical components

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3) (i)(B) of this clause.(1)

(3) The procedures in paragraph (b)(3)(i)(B) of this clause will no longer apply as of January (2) 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)

(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use…

This is the start of the file's text. The full file is on GovTribe.