This document is a Request for Proposal (RFP) issued by the U.S. Army Contracting Command to existing Area I & II General Construction Multiple Award Indefinite Delivery Indefinite Quantity (MAIDIQ) contractors for the installation of a Tension Fabric Structure (TFS) tent at Camp Hovey in the Republic of Korea.
The RFP specifies the work to be performed, which includes civil, architectural, mechanical, and electrical work. The construction period is 90 calendar days. The estimated price range for the work is between $500,000 and $1,000,000. Offers are due by 10 September 2024. To be eligible for award, offerors must be Korean contractors as defined in the RFP and must submit the required documentation to establish their eligibility. Award will be made to the responsible offeror submitting the lowest priced, technically acceptable offer. This contract will be paid for with Republic of Korea Ministry of National Defense funds, and no U.S. government funds will be obligated under this contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0012168567 a.This is a Request for Proposal (RFP) issued to existing Area I & II General Construction Multiple Aw ard Indefinite Delivery Indefinite Quantity (MAIDIQ) Contractors only Contract Number: W91QVN-24-D-0059, 0060, 0061, 0062, 0063, 0064, 0065, 0066, 0067, 0068, 0069, 0070, 0071, 0072, 0073, 0074, 0075, 0076, 0077, 0078, 0084, 0085, 0098, 0102, 0106.
b.Site Visit: All MAIDIQ contractors w ho intend to propose on this solicitation are strongly recommended to attend the Site Visit. See Section L for the schedule.
c.If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the “No-off er letter” by closing date and time specif ied in the solicitation.
d.CONSTRUCTION PRICE RANGE Pursuant to FAR 36.204 the estimated price range is betw een $500,000 and $1,000,000.
SFC MIDDLETON, ANTWOINE N. 315-755-1380
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
03-Sep-2024
(RFP)
(IFB)
X
CALL:
Installation TFS (Tension Fabric Structure), Camp Casey
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________10 Sep 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO CASEY
UNIT#15289
APO AP 96224-6224
UNITED STATES
W90VN8
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
11:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
#320257
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W90VN824R0072 29
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W90VN824R0072
Section A - Solicitation/Contract Form
ELIGIBILITY FOR AWARD
ELIGIBILITY FOR AWARD OF ROK MND CONTRACTS
(a) This solicitation is conducted under the LCS program and will result in a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States (US) shall be obligated for payment due under a contract resulting from this solicitation.
(b) In accordance with the International Agreement between the US and ROK, titled “Implementation Arrangement for the Special Measures Agreement” (hereinafter “International Agreement”), signed by the parties in 2019:
The parties hereby agree that all LCS work must be accomplished in the ROK or its territorial waters and that all equipment and supplies that are to be acquired with ROK Government funds shall be manufactured in the ROK, and all LCS service work shall be carried out by Korean contractor(s), the Korea Railroad Corporation, or the ROK military.
The term ‘Korean contractor” in implementing the LCS program in Section V, Paragraph 3 (of the 2019 SMA IA) is defined as follows:
1. An entity, that, including its parent, is a domestic corporation under the Korean Corporation Tax Act and whose domestic status is recorded in the Certified Copy of Register or its successor document. A parent is defined as an entity that holds more than 50/100 of the total issued and outstanding shares in another company, as reflected in the Stock Change Certificate; or
2. An individual who has Korean nationality.
(c) In order to establish eligibility for a LCS contract, the offeror shall submit the documents listed below with their proposal prior to the closing date/time established in the solicitation. The contracting officer will determine the offeror’s eligibility status as a Korean contractor solely on the basis of these documents.
(1) Prime Contractor Registration: The offeror shall submit its Certified Copy of Register (등기부 등본
(유효사항)), as certified and submitted to the ROK Supreme Court (대법원). In order to qualify as a
Korean Contractor, the fourth block of the offeror's Certified Copy of Register [등기부 등본 (유효사항)] must state an address that is physically located in the Republic of Korea.
(2) Prime Contractor Stock Change Certification: The offeror shall submit its most recent Stock Change
Certificate (주식 변동 상황 명세서), as certified and submitted to the ROK Local Tax Office (국세청). The prime contractor’s tock Change Certificate (주식 변동 상황 명세서) will be evaluated to determine if the prime contractor has ap Parent (as defined in the International Agreement extract above).
(3) If the Prime Contractor has a Parent, the offeror shall submit the Parent’s Certified Copy of Register
(등기부등본 (유효사항)) as certified and submitted to the ROK Supreme Court (대법원). In order for the
Prime Contractor to qualify as a Korean Contractor, the fourth block of the offeror’s Parent’s Certified
Copy of Register (등기부 등본 (유효사항)) must state an address that is physically located in the Republic of Korea.
(4) To validate if an individual is “Korean nationality”, the following documents shall be submitted:
Business Registration (사업자 등록증)
Basic Certificate (기본 증명서)
Certificate of Business Fact (사업사실증명서)
(Issued by National Tax Service showing partnership/owners, shares, and date when the business was jointly owned)
(d) To summarize the requirements stated above:
(1) An offeror that does not have a “Parent” will submit 2 documents to establish that the offeror is a Korean Contractor: 1) Offeror's Certified Copy of Register, and 2) Offeror's Stock Change Certificate.
(2) An offeror that does have a “Parent” will submit 3 documents to establish that the offeror is a Korean Contractor: 1) Offeror's Certified Copy of Register, 2) Offeror's Stock Change Certificate, and 3) Parent's Certified Copy of Register.
(3) An Offeror that does not have Stock Change Certificate will submit: 1) Business Registration, 2) Basic Certificate, and 3) Certificate of Business Fact.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0010 1 Job
L WORK
FFP
L WORK
FOB: Destination
PURCHASE REQUEST NUMBER: 0012168567
PSC CD: 5680
NET AMT
Section C - Descriptions and Specifications
DESCRIPTIONS AND SPECIFICATION
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO TITLE LOCATION
320257 Installation Tent Camp Hovey
1. DESCRIPTION: The work to be performed to installation tent is described below and executed by one or more of the groups.
1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications.
1.2. Work by In-House Labor: Not applicable to this project.
1.3. Work by Troop Labor: Not applicable to this project.
2. PRINCIPAL FEATURES: This project includes the following principal features:
2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.
None
2.2. Schedule #II, New Construction (L): All work shall be in accordance with the attached drawings and specifications.
The contractor must complete all work within the construction period of 90 days.
2.2.1. Civil Work
2.2.1.1. Connect 150mm PVC sewer line to new movable toilet
2.2.1.2. Connect 50mm PVC water line to new movable toilet using 50mm tapping saddle.
2.2.1.3. Install Ino-block D-step.
2.2.1.4. Restore granite curb.
2.2.1.5. Restore AC pavement.
2.2.1.6. Restore solid sodding with top soil.
TP I-1
2.2.2. Architectural Work
2.2.2.1. Provide TFS (Tension Fabric Structure) tent (55m x 20m) and install on existing concrete foundation and remove tent after completion. (TFS tent need a 3-year warranty for maintenance)
2.2.2.2. Install doors and frames including hardware sets as shown on floor plan and schedule.
2.2.2.3. Install partitions as shown on floor plan and schedule.
2.2.2.4. Apply epoxy coating with non-slip grits on existing concrete floor.
2.2.2.5. Furniture (tables & chairs) and equipment will be moved to tent or temporary spaces.
2.2.2.6. Provide disconnection and connection of equipment.
2.2.2.7. Provide new movable toilet facility including all toilet accessories as shown on dwg.
2.2.2.8. Connect mechanical and electrical utility line to new toilet.
2.2.3. Mechanical Work
2.2.3.1. Relocate existing kitchen equipment from DFAC to small DFAC as shown on drawings.
2.2.3.2. Connect to kitchen equipment and utility line(hot, cold (stainless steel 304) & sewer piping and all associated accessories for small DFAC as shown on drawings.
2.2.3.3. Install new dishwasher, table roller, pre-washing table and clean dish table and all associated accessories in the small DFAC as shown on drawings.
2.2.3.4. Install new packaged heat pump units(30sets) including piping, conc. Pad and all associated accessories in the small DFAC as shown on drawings.
2.2.3.5. Install new dehumidifiers(6sets) in the small DFAC as shown on drawings.
2.2.3.6. Install new fire extinguisher(8sets) and all associated accessories in the small DFAC as shown on drawings.
2.2.3.7. Install new air curtains(10sets) and all associated accessories in the small DFAC as shown on drawings.
2.2.3.8. Install new ceiling fans(4sets) and all associated accessories in the small DFAC as shown on drawings.
2.2.4. Electrical Work
2.2.4.1. Install new interior/ exterior lighting fixtures, exit lights, toggle switches, 3way switches, wires, raceway and conduits.
2.2.4.2. Install new receptacles, pull boxes, junction boxes, dry type transformer, safety switches with associated wiring & conduits for kitchen equipment.
2.2.4.3. Install new safety switches, motor controllers, junction boxes, control/power wires and conduits for mechanical systems.
2.2.4.4. Install new underground telecommunication line from existing equipment rack of communication room at building s4035, Cp Hovey to cashier counter in tent DFAC, data outlet (dual modular jacks), LAN cable and conduit.
TP I-2
Special Note: Contractor shall use air freight to deliver all off-shore materials such as switches, receptacles, safety switches, etc. to meet the construction period.
TP I-3
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION- 1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
The Standard Technical Detail Specifications:
The work shall conform to the most current version of the listed standards/specifications below.
DIVISION 01 – GENERAL REQUIREMENTS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED
MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS
MATERIALS
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT, TARGET
HOUSING & CHILD OCCUPIED FACILITIES
TP II-1
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALANTS
DIVISION 08 – OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOODEN DOORS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 – FINISHES
09 29 00 GYPSUM BOARD
09 90 00 PAINTS AND COATINGS
DIVISION 10 – SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 14 02 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
DIVISION 12 – FURNISHINGS
12 36 00 COUNTERTOPS
DIVISION 22 – PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
TP-II-2
DIVISION 26 – ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 33 - UTILITIES
33 11 00 WATER DISTRIBUTION
TP II-3
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. Material Approval Submittal:
(1) The contractor shall submit a shop drawing submittal schedule and the material approval request with all supporting documents to the COR within 14 days after receipt of NTP.
(2) The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL
PROCEDURES.
2. Extended warranty - FAR 52.246-21
2.1. Extended warranty list
2.2. Contractor shall submit to COR the Warranty Certification with 4025 for the listed items.
2.3. Contractor shall submit to COR Warranty management plan and approve it before 30 days of pre-warranty conference. (OMA Sec 01 78 00)
2.4. Contractor shall have the Pre-Warranty Conference before Contract Close Date. (OMA Sec 01 78)
2.5. Warranty Information and Data
2.5.1. Contractor shall submit Warranty tag design, COR shall review and approve it for the listed and shall install it for the listed items. (OMA Sec 01 78 00)
2.5.2. Submit the O&M Manual with Manufacture’s instruction for DPW training. (OMA Sec 01 78 00)
3. The contractor shall have personnel on site for the sprinkler work and the fire alarm work upon Government's direction, who are certified by the National Institute for Certification in Engineering Technologies (NICET) Level III or equivalent. Equivalent Certificates in Korea are the followings which are issued by the Human Resource Development Service of Korea.
TP III-1
If the contractor doesn’t have personnel who are certified by NICET, the contractor shall have two personnel that one is certified for (1) and the other for (2) below.
(1) Engineer Fire Fighting Facilities - Electrical (소방설비기사 -전기)
(2) Engineer Fire Fighting Facilities - Mechanical (소방설비기사 -기계)
4. Environmental Requirements in Contract
L/N Warranty Item Description Warranty
Period (Yrs) Certification (Yes / No)
Warranty Tag (Yes / No)
Repair Time after call
1 Tent Maintenance 3 Y Y 24 Hrs
2 LED Light Product 10 Y Y 7 Days
The Contractor shall perform work consistent with the relevant policy and objectives identified in Installation’s Environmental Management System (EMS). The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by Installation’s EMS, including pollution prevention, waste reduction, energy use, and natural resource protection. The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In addition, the Contractor shall advise their employees of their roles and responsibilities identified by the EMS and how these requirements affect their work performed under this contract. The Contractor is responsible for ensuring that the Contractor and any persons involved in the supervision or performance of the contract complete all required Environmental training.
In the event of any environmental nonconformance or noncompliance associated with the contracted services, the contractor shall take corrective and/or preventative actions. In the event of any noncompliance with any federal, state, or local environmental law, regulation or requirement, the Contractor shall immediately respond by taking all appropriate corrective actions and notifying the Contracting Officer’s Representative (COR) and the Environmental Office. For any nonconformance with the EMS, the Contractor shall take corrective action and initiate further preventative action, as required by the Environmental Office.
All on-site contractor personnel shall complete necessary safety and environmental training specified for the type of work conducted on-site. Upon contract award, the COR will notify the EMS Manager to arrange Environmental training for appropriate staff.
Additionally, when ordering supplies for use on Installation, all contractor personnel must favor energy-efficient, recycled or reclaimed material whenever practicable.
The responsibilities of all contractor personnel include:
(1) Comply with all applicable environmental laws, regulations and installation environmental policies.
(2) Control and prevent spills or hazardous substances releases IAW installation Spill Prevention
Plan.
(3) Ensure dust, debris, materials, trash, etc., do not become air borne and travel off the project site.
TP III-2
(4) Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, topsoil and land forms without approval, except in areas indicated on the drawings or specified to be cleared.
(5) Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated.
(6) Open burning is prohibited on the Government premises IAW installation environmental policy.
(7) Participate in installation’s recycling program.
(8) Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Environmental Office.
Storage, describing, packaging, labeling, marking and placarding of hazardous waste and hazardous material IAW applicable environmental laws, regulations and local environmental policies. Transport hazardous waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(9) Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling. Handling, storage, and disposal of solid waste must be conducted to prevent contamination. Transport solid waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(10) Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must.
(11) When potential cultural or historic items are inadvertently found during construction activities, immediately cease activities in the vicinity of the discovery and report the findings to the Environmental Office.
(12) Participate in installation’s Integrated Pest Management (IPM) program whenever practicable.
(13) Minimize interference with disturbance to, and damage to fish, wildlife, and plants including their habitat.
5. CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW
COVER SHEET
After Notice to process is issued, COR shall take following action, Section IV. Standard Contract Language/Contract Clause Applicability and/or Additional SOW Language.
TP III-3
A. AT Level I training. This standard language is for contractor employees with an area of performance within as Army controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within 30 calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil B. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
B-a. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
C. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
D. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0010 Destination Government Destination Government
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 Calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days. The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section I - Contract Clauses
5152.232-4028 – Funding of ROK MND Funded Contracts
FUNDING OF ROK MND FUNDED CONTRACTS
(a) Funding advisement: This contract, any modifications (including exercise of option(s)) thereto, and any delivery or task orders thereunder, shall be paid with ROK funds and shall cite “MOA Contract
- funded by ROK MND” (in lieu of citing appropriations and accounting data). No U.S. funds, appropriated or other, are or will be obligated under this contract.
(b) Limitation of US liability: The U.S. Government shall incur no liability, and no appropriated or other funds of the United States shall be obligated, for payment for services, supplies, claims, or other costs arising out of or under this contracts, delivery or service orders, exercises of options, or other modifications.
(c) Identification of invoices: Contractor shall state clearly “MOA Contract - funded by ROK MND” on all invoices for performance under contracts, delivery or service orders that are designated as “MOA Contract - funded by ROK
MND.”
(d) Funding carry-over:
(1) The Contractor will make every reasonable effort to obtain completion of all performance under the contract and to obtain, approve, and forward Contractor’s invoices under the contract before the end of the calendar year of the contract. In the event that any work initiated under the contract cannot be completed by the end of the calendar year, the Contractor shall furnish the Contracting Officer and USFK, ATTN: FKJ4-P-G, not later than 30 November, the following information:
(i) A list of work that apparently will not be completed and invoiced by, and apparently will require payments after, the end of the calendar year;
(ii) Estimated price of work that apparently will be carried beyond the calendar year; and
(iii) Date of anticipated completion of the work.
(2) The ROK MND shall seek mutually agreeable procedures for payment for work carried over to the next calendar year.
(e) Availability of ROK Funds for the Next Calendar Year:
(1) This contract is funded with calendar year ROK MND funds, from date of award through 31 December of the year in which the contract is awarded and/or into which the contract is extended. ROK MND funds are not available for performance, under this contract, beyond 31 December of the current contract’s calendar year period. Any obligation and/or legal liability on the part of ROK MND for the next calendar year’s performance, including exercise of any option to extend the services/contract, is contingent upon the Contracting Officer’s explicit notification to the Contractor of availability of that new calendar year’s ROK MND funds, from which contractual payment(s) can be made.
(2) Unavailability of ROK MND funds until a few months into the new calendar year may necessitate a break in performance of the contract until those funds become available. In the event of a break in performance because of unavailability of the new calendar year’s ROK MND funds for obligation under the contract, that break in performance shall not be deemed a breach or default of the contract.
5152.233-4008 – Choice of Law and Disputes under ROK MND Funded Contracts
CHOICE OF LAW AND DISPUTES, ROK MND FUNDED CONTRACTS
(a) This contract shall be construed and interpreted in accordance with the substantive laws of the United States of America. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with U.S.
law.
(b) All disputes arising under, or relating to, this contract shall be resolved under this clause.
(c) “Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. A claim arising under a contract, unlike a claim relating to that contract, is a claim that can be resolved under a contract clause that provides for the relief sought by the claimant; however, a written demand or written assertion by the Contractor seeking the payment of money exceeding $100,000 is not a claim under the clause until certified as required by subparagraph (d)(2) below. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the clause. The submission may be converted to a claim under the clause, by complying with the submission and certification requirements of this clause, if it is disputed either as to liability or amount or is not acted upon in a reasonable time.
(d) The contractor shall have the right to submit to the Contracting Officer, disputes, demands, and/or claims, relating to or arising under this contract, only on the issue of whether the Government should and will certify performance, for payment by the ROK Government. The contractor shall not submit to the U.S. Government, nor will the Contracting Officer accept, any disputes, demands, or claims for compensation for work, which the U.S.
Government has certified as completed.
(e) Procedures
(1) A claim by the contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the Government against the Contractor shall be subject to a decision by the Contracting Officer.
(2) For contractor’s claims exceeding $100,000, the contractor shall submit with the claim a certification that –
(i) The claim is made in good faith;
(ii) Supporting data are accurate and complete to the best of the contractor's knowledge and belief; and
(iii) The amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable.
(3) Individuals
(i) If the contractor is an individual, the certification shall be executed by that individual.
(ii) If the contractor is not an individual, the certification shall be executed by –
(A) A senior company official in charge at the contractor's plant or location involved; or
(B) An officer or general partner of the contractor having overall responsibility for the conduct of the contractor's affairs.
(f) For contractor’s claims of $100,000 or less, the Contracting Officer will, if requested in writing by the contractor, render a decision within 60 days of the request. For contractor-certified claims over $100,000, the Contracting Officer will, within 60 days, decide the claim or notify the contractor of the date by which the decision will be made.
(g) The Contracting Officer's decision shall be final unless the contractor appeals the decision within 30 days of the Contracting Officer's decision, to the Principal Assistant Responsible for Contracting (PARC). In the event that the contractor does appeal the decision of the Contracting Officer, the appeal shall be heard by and decided by the PARC and/or a panel of U.S. officials, chaired by the PARC. The decision of this panel shall be final.
(h) The contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, or action arising under the contract, and comply with any decision of the Contracting Officer.
(i) This contract is not subject to the Contract Disputes Act of 1978, as amended (41 U.S. Code, Sections 601-613).
Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with this local clause, 5152.233-4008.
Section J - List of Documents, Exhibits and Other Attachments
LIST OF DOCUMENTS, EXHIBITS AN
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), issued by the Department of the Army, Installation Management Agency, Korea Region Office and located on http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/STANDARD-DETAIL-DRAWINGS- FOR-OMA-PROJECTS-KOREA_20151130.pdf, all of which form a part of the specifications.
Ring No. Sheet No. Description Date
1 T-1 TITLE SHEET 29 AUG 24
CIVIL
2 C-1 LOCATION PLAN AND GENERAL NOTES 29 AUG 24
3 C-2 SITE LAYOUT PLAN, UTILITY PLAN AND SCOPE OF
WORK
29 AUG 24
4 C-3 MISC. DETAILS 29 AUG 24
ARCHITECTURAL
5 A-1 GENERAL NOTE AND SCOPE OF WORK 29 AUG 24
6 A-2 DFAC TENT LAYOUT PLAN 29 AUG 24
7 A-3 WALL SECTION AND DOOR DESCRIPTION 29 AUG 24
8 A-4 MOVABLE TOILET PLAN AND NOTES 29 AUG 24
MECHANICAL
9 M-1 MECHANICAL MATERIAL INDICATIONS & SYMBOLS
AND ABREVIATION
29 AUG 24
10 M-2 GENERAL NOTES, SCOPE OF WORK AND NOTE 29 AUG 24
11 M-3 MECHANICAL EQUIPMENT SCHEDULE-1 AND NOTE 29 AUG 24
12 M-4 GROUND NEW HVAC PLAN-1 AND NOTE 29 AUG 24
M-5 M-6
M-7
E-1 E-2 E-3
GROUND NEW HVAC PLAN-2, LEGEND AND NOTE
SMALL DFAC TENT KITCHEN EQUIPMENT PLAN-1
AND FOOD SERVICE EQUIPMENT & UTILITY
SCHEDULE-1. LEGEND & NOTE-1&2
SMALL DFAC TENT KITCHEN EQUIPMENT PLAN-2
AND FOOD SERVICE EQUIPMENT & UTILITY
SCHEDULE-2, PARTIAL PLAN, LEGEND & NOTE
A-1
ELECTRICAL
LEGEND, GENERAL NOTES AND SCOPE OF WORKS
NEW LIGHTING PLAN
LIGHTING FIXTURE DETAILS AND SCHEDULE
E-4
E-5 E-6 E-7 E-8
NEW POWER PLAN FOR KITCHEN EQUIPMENT/
FOOD SERVICE EQUIPMENT & UTILITY SCHEDULE
NEW POWER PLAN FOR MECHANICAL EQUIPMENT
PANELBOARD "K1", "K2" & "K3" LOAD SCHEDULE
PANELBOARD "P1", "P2" & "P3" LOAD SCHEDULE
TELECOMMUNICATION LINE PLAN
29 AUG 24
29 AUG 24
29 AUG 24
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
ATTACHMENT: CONTRACTOR’S TAX EXEMPTION DECLARATION
(1) References:
(i) Contract clause, "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _________ No ________
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. _________ Input VAT on transportation leased/rented for this contract. _________ Input VAT on equipment leased/rented for this contract. _________ Input VAT on services purchased for this contract. _________ Output VAT on total contract amount. _________
(iv) Special Excise (Petroleum) Tax:
No. of Unit Price Total Tax Liters w/o Tax Tax/Unit Amount
Regular Gasoline __________ (L) ₩_________ ₩________ ₩_________
Premium Gasoline __________ (L) ₩_________ ₩________ ₩_________
Diesel __________ (L) ₩_________ ₩________ ₩_________
Other __________ (L) ₩_________ ₩________ ₩_________
(3) Name of Oil Company Refinery from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except for ROK MND-funded contracts and delivery orders), and Special Excise Tax.
Contractor’s Signature
Section L - Instructions, Conditions and Notices to Bidders
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for
Date: 06 SEP 2024 Time: 1330 Korea Standard Time POC: Mr. Pak, Chi Hwan
DSN: 722-4547
(c) Participants will meet at Location: DFAC Camp Hovey Building S-4158
(d) Escort : Any Contractor who needs escort shall bring Korea identification card , passport or driver license (주민등록증, 여권 혹은 운전면허증) and contact to Mr. Pak, Chi Hwan
(e) Interested participants shall email the following information to COR, Mr. Pak, Chi Hwan (chi.h.pak.ln@mail.mil, 722-4547) NLT 1500 hours, 5 SEP 2024.
* Company Name & Name of Site Visit attendees
Government does not receive any information from interested site visit participants, the Government will cancel the Site Visit without notice.
INSTRUCTION TO OFFEROR
1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL
a. The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215- 1(f)(4).
b. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.
2. SUBMISSION OF PROPSAL
a. The offeror shall email offer to the contract specialist, SFC Middleton (email address:
antwoine.n.middleton.mil@army.mil) and the contracting officer, Mr. Kim, Chong Nak (chongnak.kim.ln@army.mil) by the Korea local closing time and date which can be found in Block 13 on page 1 of this solicitation. After submission of the offer, the offeror shall send an additional email shall to the contract specialist to verify if offer is received. It is the offeror responsibility to verify receipt of offer from contract specialist before the Korea local closing time and date. All questions should be emailed to antwoine.n.middleton.mil@army.mil within three (3) calendar days after the solicitation is issued.
b. CLOSING DATE: The electronic offer shall be submitted by 1100 hrs on the closing date of RFP.
3. SUBMISSION REQUIREMENTS
a. PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in Section B - Supplies or Services and Prices.
b. DETAILED OFFER BREAKDOWN: The detailed offer breakdown must clearly identify all costs that can materially impact the statement of work.
c. SECTION K - Representations, Certifications and Other Statements of Offerors
d. SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.
e. SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.
f. COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.
g. Following documents shall be submitted with the proposal.
(1) Prime Contractor Registration: The offeror shall submit its Certified Copy of Register (등기부 등본
(유효사항)), as certified and submitted to the ROK Supreme Court (대법원). In order to qualify as a
Korean Contractor, the fourth block of the offeror's Certified Copy of Register [등기부 등본 (유효사항)] must state an address that is physically located in the Republic of Korea.
(2) Prime Contractor Stock Change Certification: The offeror shall submit its most recent Stock Change
Certificate (주식 변동 상황 명세서), as certified and submitted to the ROK Local Tax Office (국세청). The prime contractor’s Stock Change Certificate (주식 변동 상황 명세서) will be evaluated to determine if the prime contractor has a Parent (as defined in the International Agreement extract above).
(3) If the Prime Contractor has a Parent, the offeror shall submit the Parent’s Certified Copy of Register
(등기부등본 (유효사항)) as certified and submitted to the ROK Supreme Court (대법원). In order for the
Prime Contractor to qualify as a Korean Contractor, the fourth block of the offeror’s Parent’s Certified
Copy of Register (등기부 등본 (유효사항)) must state an address that is physically located in the Republic of Korea.
(4) To validate if an individual is “Korean nationality”, the following documents shall be submitted:
Business Registration (사업자 등록증)
Basic Certificate (기본 증명서)
Certificate of Business Fact (사업사실증명서)
(Issued by National Tax Service showing partnership/owners, shares, and date when the business was jointly owned)
(d) To summarize the requirements stated above:
(1) An offeror that does not have a “Parent” will submit 2 documents to establish that the offeror is a Korean Contractor: 1) Offeror's Certified Copy of Register, and 2) Offeror's Stock Change Certificate.
(2) An offeror that does have a “Parent” will submit 3 documents to establish that the offeror is a Korean Contractor:
1) Offeror's Certified Copy of Register, 2) Offeror's Stock Change Certificate, and 3) Parent's Certified Copy of Register.
(3) An Offeror that does not have Stock Change Certificate will submit: 1) Business Registration, 2) Basic Certificate, and 3) Certificate of Business Fact.
ARMY CONTRACT WRITING SYSTEM
Army Contract Writing System (ACWS) Transition Information for Offerors
a. The Army Contracting Enterprise (ACE) is in the process of deploying new solicitation and contract writing software to Army contracting offices worldwide. Known as the Army Contract Writing System (ACWS), this modern software suite will soon replace most existing Army contract writing systems, including the system used to create and release this Solicitation.
b. During this transition period, Offerors are hereby advised:
1. The Contracting Office may use any combination of contract writing systems to create and release documents related to this solicitation (e.g. solicitation amendments and awards, if any). Due to this:
i. This solicitation may contain different offer submission instructions than other solicitations released by the same Contracting Office (e.g. requiring offer submission via the PIEE Solicitation Module vs. e-mail). Offerors should review all offer submission instructions contained in the solicitation documents and direct any questions or concerns to the Contract Specialist or Contracting Officer.
ii. If the Contracting Office switches contract writing systems prior to award, documents you receive from the Contracting Officer or view on SAM.gov or other forums may appear noticeably different than the initial solicitation or previous solicitations or awards from the same Contracting Office. This is normal and expected.
iii. A change between contract writing systems may cause important information concerning solicitation response (amendments) or accepted terms (awards) to take on different formatting or appear in different parts of later documents issued. Offerors shall review all documents carefully to locate this important information and direct any questions or concerns to the Contract Specialist or Contracting Officer.
2. The Government does not intend to use the transition between contract writing systems to effect any changes to solicitation or award terms and conditions without accompanying document narratives explicitly stating such changes are deliberate and desired. While the Contract Specialist and Contracting Officer will take care to minimize or eliminate any inadvertent changes when adapting to the new contract writing software, you, as the Offeror, may still be the first to spot such errors. Therefore, Offerors shall:
i. Notify the Contracting Officer immediately if any observed changes, removals, or additions affect your award eligibility, violate or alter existing quote/proposal terms, or could affect…