This is a request for proposal for an Army Military Payroll total solution. The U.S. Army Contracting Command - Aberdeen Proving Ground on behalf of the Project Manager Integrated Personnel and Pay System - Army under U.S. Army Program Executive Office Enterprise Information Systems requires the development of an Army Military Payroll solution. The solicitation seeks to develop payroll functionality for Active Army, Army National Guard, and Army Reserve personnel. Notices were released on October 27, 2023, November 22, 2023, and January 3, 2024 providing draft versions of the RFP. The final RFP response date has not yet been set. The agency intends to award a single contract but has not specified an award date. Pricing terms, set asides, and other contractual details are not provided in the available documents.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED//FOR OFFICIAL USE ONLY
Integrated Personnel and Pay System – Army (IPPS-A)
Environmental Designs (ED)
21 October 2019
IPPS-A Environmental Design v1.15 21 October 2019 i
REVISION HISTORY
ii
Table of Contents Contents 1 Introduction and Purpose
1.1 Introduction
1.2 Document Purpose
1.3 Document Overview
1.4 Reference Documents
2 Background
2.1 Legacy Systems and IPPS-A
2.2 Data Centers
3 Applications
4 IPPS-A Environmental Design and Data Center Architectural Overview
4.1 Hierarchical Framework
4.1.1 Sites
4.1.2 Zones
4.1.3 Enclaves
4.1.4 Application Stacks
4.1.5 Environments
4.2 Environmental Systems Management and Change Control
4.2.1 Service-Level Agreements (SLAs)
4.2.1.1 DISA
4.3 Site High-Level Design
4.3.1 IPPS-A Increment II SDC
4.3.1.1 DISA DATA CENTER 2 Enclaves/Environments
4.3.2 IPPS-A Increment II PDC
4.3.2.1 IPPS-A Increment II Production Data Center Enclaves/Environments
4.3.3 SuperCluster Capacity Planning
4.3.4 Hardware and Software inventory
5 IPPS-A Increment II Environment Prerequisites
5.1 Data Center Remote Access
5.2 Software Download Capability
Appendix A: Acronyms and Abbreviations ............................................................................. A-1
Appendix B: Consolidated Reference Documents ....................................................................B-1
Appendix C: Reference Terms ..................................................................................................C-1 iii
List of Figures
Figure 3-1 Software Architecture
Figure 4-1 Application Stack Example
Figure 4-2 Server to Environment Mapping Example
Figure 4-3 DISA Dev (Zone B) Environment Requirements
Figure 4-4 DISA Test (Zone A) Environment Requirements
Figure 4-5 DISA SDC/COOP Environment Requirements
Figure 4-6 DISA PDC Environment Requirements
Figure 4-7 Environments by Enclave
Figure 4-8 Zone B Development and Tools Enclaves/Environments
Figure 4-9 Zone A Test and Demonstration Enclave/Environments
Figure 4-10 Secondary Data Center/COOP Production/Training Enclave/Environments
Figure 4-11 R3 Secondary Production/COOP Enclaves/ Environments
Figure 4-12 Primary Data Center (PDC)Production/Reporting and Training Enclaves/ Environments
Figure 4-13 XXXX Capacity Planning
Figure 4-14 Test SuperCluster XXXX Capacity Planning
Figure 4-15 XXXX SuperCluster Capacity Planning
Figure 4-16 XXXX Capacity Planning
Figure 4-17 XXXX Capacity Planning
Figure 4-18 XXXX Capacity Planning
Figure 4-19 XXXX Capacity Planning
List of Tables
Table 1-1 Reference Documentation
1 INTRODUCTION AND PURPOSE
1.1 Introduction
The Army currently relies on more than 60 separate legacy information systems to provide personnel and pay management for all components (Active, Guard, and Reserve). These systems were designed at different times, reside on different hardware platforms, use a variety of in-house and commercial software, and vary widely in their functionality.
To consolidate these systems, the Army is developing and implementing the Integrated Personnel and Pay System – Army (IPPS-A), a Web-based tool, available 24 hours a day, accessible to Soldiers, Human Resources (HR) professionals, Combatant Commanders, personnel and pay managers, and other authorized users throughout the Army.
1.2 Document Purpose
The purpose of this document is to provide the design of the servers and environments, the functionality of the software components, and a list of hardware and software to support those capabilities for IPPS-A Increment II Prototype, Development, Test, Support Tools, and Primary/ Secondary Production enclaves. The document is intended to show the enterprise IPPS-A Increment II architecture in relation to software and hardware, as well as high-level processes critical to the program. It is not a detailed procedural guide. The hardware and software list is complete as of the delivery of this document, but changes to these configuration items are expected and this document is updated accordingly.
This document describes the environment within the Development/Test/Secondary Data Center (SDC) Hosting Center, and the Increment II Primary Data Center (PDC).
A detailed itemization of tasks to be performed to instantiate each environment is not included in this document; however, it is incorporated into the IPPS-A Increment II Integrated Master Schedule (IMS).
Although this document is a Quality Assurance Surveillance Plan (QASP) deliverable, it should be considered a living document that can be updated during post-analysis phase activities.
A Code Migration Plan is covered in the Configuration Management Plan.
1.3 Document Overview
This document contains a brief overview of the technical architecture for the IPPS-A Increment II system. This includes a high-level view of the environments hosted at the IPPS-A Increment II PDC at the Defense Information Systems Agency (DISA) Data Center in DATA CENTER 1; the IPPS-A Increment II SDCs at the DISA Data Center in DATA CENTER 1.
This document is designed for the following audiences:
• IPPS-A Stakeholders – Reference for technical components.
• Architects – Reference for the implementation of a specific architectural component covered in this document.
• Managers – Reference to gain an understanding of the technical approach.
• Administrators – Framework for the design approach and for knowledge transfer purposes.
This document defines and describes the IPPS-A Increment II Data Center’s infrastructure prerequisites and environments, which are implemented as part of IPPS-A Increment II activities to meet the requirements of the IPPS-A program. The infrastructure components discussed in this document may be used for future program releases as defined in technical architecture specifications of future releases. This document is revisited over the course of the project life cycle to confirm accuracy and reflect changes in design.
A high-level overview of the IPPS-A Increment II Data Center infrastructure is captured in this document and includes the following:
• Logical view of the environments
• Physical view of the servers, storage, and network
• Server and virtual machine (VM) specifications
• Environment prerequisites
• Application overviews to provide a basis of functionality within the environments
• Hardware and software inventory lists
• References to the applicable IPPS-A Functional Baseline
1.4 Reference Documents
Table 1-1 contains a list of cited references and supporting material used in the development of this document.
Table 1-1 Reference Documentation
Document Title Date
2 BACKGROUND
2.1 Legacy Systems and IPPS-A
Overall, Army legacy personnel and pay systems vary greatly in modernity, maintainability, and functionality, resulting in deficiencies that cause numerous processing errors, manual workarounds, and increasing processing costs. In addition, they are based on Component-unique business practices that manage Component-unique data. Some interfaces have been operating for decades on what is now obsolete hardware. The difficulty in integrating the Army’s Component-unique data elements into meaningful information presents problems in monitoring deployments, responding to needs of family members, and implementing personnel and pay policies.
The Army employs a hybrid solution for IPPS-A using Enterprise Resource Planning (ERP) software and Agile development to deliver integrated personnel and pay capabilities, building on the trusted database and PeopleSoft foundation delivered as IPPS-A Increment I (see Increment I Technical Architecture Specification Documentation). Increment II utilizes the current versions of PeopleSoft (version 9.2) and Oracle RDBMS (version 12c or higher) along with application technologies outside of the core ERP, to meet user requirements for the total system. IPPS-A is developed and deployed incrementally, delivering full integrated personnel and pay management functionality gradually in the form of multiple releases. As such, current versions are subject to change.
IPPS-A is a combination of Agile, Modular, and traditional engineering methodologies in its development with the SI. The IPPS-A Project Management Office (PMO) and SI determine which methodology is the best fit for each activity. For example Agile development lends itself to requirements and third-party applications development and design; Modular development methodology lends itself to PeopleSoft Fit/Gaps, data management, design, and traditional engineering can best be used for the network and system design.
2.2 Data Centers
The IPPS-A Increment II Primary and Secondary Data Centers and the Prototyping/ Demonstration Hosting Center are geographically segregated: the Increment II PDC is hosted at the DISA Data Center in DATA CENTER 1 and provides Primary Production, Reporting, and Training Environments; the Increment II SDC is hosted at the Data Center in DATA CENTER 2 and provides Development, Test, and Continuity of Operations Plan (COOP) environments.
3 APPLICATIONS
Applications necessary to support the IPPS-A Increment II solution including the commercial off-the-shelf (COTS) business software packages include, but are not limited to:
REMOVED See RFP for most current list of applications
Figure 3-1 provides a Software Architecture. The current version of this figure is accessible on SharePoint at Software Architecture.
Figure 3-1 Software Architecture
4 IPPS-A ENVIRONMENTAL DESIGN AND DATA CENTER ARCHITECTURAL
OVERVIEW
This section provides a brief overview of the technical architecture for the IPPS-A Increment II system and the high-level view of the components at the IPPS-A Increment II hosting centers.
The IPPS-A Increment II hosting data centers include the PDC at DISA’s Data Center in DATA CENTER 1; the IPPS-A Increment II SDC at DISA’s Data Center in DATA CENTER 2.
4.1 Hierarchical Framework
The organization of the IPPS-A system environmental design is identified in a tiered structure.
Within the structure are defined layers. These levels include sites, zones, enclaves, application stacks, and environments.
4.1.1 Sites
The first tier of the environmental design is the site level. The term sites refers to the hosting data center that fulfills specific requirements for phases of the Software Development Life Cycle (SDLC). The current sites include:
• DISA DATA CENTER 2 Data Centers The purpose of the infrastructure at DISA DATA CENTER 2 is to support enclaves and environments for Development, Demonstration, Test, and R2 COOP activities.
• DISA DATA CENTER 1 Data Center
− DISA DATA CENTER 1 infrastructure hosts enclaves and environments to support primary transactional, reporting, and training activities.
4.1.2 Zones
According to the DISA Test and Development Enclave STIG dated 22 January 2016, a zone breakdown has been developed to establish the security baselines, which must be in place for each test and development environment. DISA has identified zones for various types of activities. For IPPS-A Increment II, two of these zones are utilized to support the SDLC.
• Zone A. IPPS-A utilizes Zone A to support its Test enclave and the environments contained within that enclave. The following is an extract from the Enclave STIG. Acronyms are identified in Appendix A. According to the Enclave STIG:
− “The Zone A environment is typically configured as a mirrored operational network for final end stage testing. This environment will have connectivity to the live operational network for final data testing prior to the product or application deployment into the operational network.”
− “Since the Zone A environment mimics the operational network, the supporting infrastructure will comply with all applicable Department of Defense (DoD) policy and security requirements. Prior to being granted connectivity, it will go through a risk assessment for the Connection Approval Process. The environment is required to hold at minimum, an IATO for connectivity to the Defense Information Systems Networks (DISN) or other live operational network within the DoD. An Interim Authority to Test
(IATT) may be obtained where the test environment requires testing of live operational data that cannot be mirrored or make use of sanitized data. The Information Security System Manager (ISSM) will conduct a security risk assessment for the requested IATT approved by the Authorizing Official (AO).”
• Zone B. The IPPS-A Development enclave, Release 2 sustainment, Release 3 – 4, and dot development environments contained within that enclave, and a subset of support tools will be implemented within Zone B. The following is an extract from the Enclave STIG.
Acronyms are identified in Appendix A. According to the Enclave STIG:
− “Zone B follows and is similar to Zone A from a network connectivity perspective, but with much stricter control mechanisms in the infrastructure supporting the environment.”
− “The Zone B environment is the designated zone permitting connectivity for moving sanitized data for testing purposes along with development of applications destined for a live and operational DoD network. The environment will have an IA-compliant infrastructure where it is separated from other test and development zones through the use of a firewall. Network segmentation is important in the environment because there will be areas where development and testing of products will take place with systems that will not be IA compliant. Network segments where development systems need access to tools or information outside of the environment will need to transit through a test and development DMZ for both inbound and outbound traffic. Network segments with systems that are not IA compliant will have all traffic blocked at the T&D DMZ. Non-compliant designated network segments within the environment will not have access to any systems on network segments or other designated segments used in development since the network segments will have access to the Defense Information System Network (DISN) through the T&D DMZ. An Active Directory solution has been requested and is being implemented within Zone B to accommodate Windows Tools servers. Requirements for Zone B ESM and EBN services have been requested from DISA however solutions have not yet been approved for operation within Zone B.”
The SDC/COOP and Production enclaves and their associated environments are hosted in a network segmentation boundary not defined as a zone, but simply as Production. Like Zone A, the supporting infrastructure complies with all applicable DoD policy and security requirements.
Prior to being granted connectivity, it goes through a risk assessment for the Connection Approval Process. A Support Tools Enclave is implemented in COOP to support Production, COOP, and Zone A environments.
4.1.3 Enclaves
Enclaves are defined as a group of environments logically segmented to support a defined phase of the SDLC. These phases include Development, Testing, SDC/COOP, and PDC. Additional Tools enclaves have been identified within the various sites and zones that support the capabilities of one or more enclaves. These capabilities include but are not limited to program support tools, such as monitoring, performance testing, log aggregation, and remote access. The planned IPPS-A Increment II enclaves are as follows:
• Development (DISA DATA CENTER 2, Zone B.) – Enclave supports environments necessary to conduct releases 3, 4 and dot release development activities for the IPPS-A Increment II system (one enclave per release).
• Support Tools (DISA DATA CENTER 2, Zone B) – Enclave hosts remote access Operational Environments (OEs) necessary to support the Zone B Development enclave.
• Test (DISA DATA CENTER 2, Zone A) – Enclave supports environments necessary to provide Development that requires PII, Product Level Testing (PLT), Demonstrations, and Production Staging for releases 2, 3, 4 and dot releases of the IPPS-A Increment II system (one enclave per release).
• Support Tools (DISA DATA CENTER 2, COOP) – Enclave hosts remote access and program support tools OEs necessary to support the COOP/SDC, and Zone A enclaves. The enclave also provides the primary program support tools capabilities such as OEM, HP Performance Center, Cameo, HP ALM, Splunk, Stonebranch Universal Controller, Stat, Teamforge, and UCMDB.
• SDC/COOP (DISA DATA CENTER 2, Production) – Enclave supports Releases 2 and 4 SDC Transactional, Reporting, and Training environments necessary to provide SDC/COOP capabilities for the IPPS-A Increment II system.
• ITE2-C - Enclave supports R3 SDC Transactional, Reporting, and Training environments necessary to provide SDC/COOP capabilities for the IPPS-A Increment II system.
• PDC (DISA DATA CENTER 1, Production) – Enclave supports PDC and Training environments necessary to provide PDC production capabilities for the IPPS-A Increment II system.
• ITE2 - Enclave supports R3 PDC Transactional, Reporting, and Training environments necessary to provide Primary capabilities for the IPPS-A Increment II system.
• Support Tools (DISA DATA CENTER 1, Production) – Enclave hosts remote access and program support tools OEs necessary to support the PDC enclave.
4.1.4 Application Stacks
The term Application Stack represents a set of servers (OEs) and associated application(s) that provide the capabilities of the application(s) (i.e., HCM Web, Application, and Batch) to environments. In an application stack, multiple environments can be supported by configuring those servers to support multiple environments through the use of domains, instances, or projects and pointing each domain/project at separate databases. Application stacks are used to increase the efficiency of servers, while reducing maintenance and licensing costs.
Each enclave is designed with the number of application stacks necessary to support the number of environments.
Figure 4-1 provides an example of how application stacks are used. This figure is accessible on SharePoint at Application Stack Example.
Figure 4-1 Application Stack Example
Figure 4-2 provides an example of how servers support multiple environments. This spreadsheet associated with this figure is accessible on SharePoint at Server to Environment Mapping example
Figure 4-2 Server to Environment Mapping Example
4.1.5 Environments
An environment is supported by application stacks, databases, and configurations that meet a predefined requirement and/or deliver a predefined capability (i.e., Core, Data, Payroll, and Security). Each enclave has environments identified based on the requirements of the requester.
The document that captures the environment requirements by site/enclave is accessible on SharePoint at Environment Requirements. The purpose of the environments may change to satisfy the needs of IPPS-A development and deployment.
Figure 4-3 identifies the requirements for development (Zone B) environments hosted at DISA
DATA CENTER 2.
Figure 4-3 DISA Dev (Zone B) Environment Requirements
Figure 4-4 identifies the requirements for Test (Zone A) environments hosted at DISA DATA
CENTER 2.
Figure 4-4 DISA Test (Zone A) Environment Requirements
Figure 4-5 identifies the requirements for SDC/COOP environments hosted at DISA DATA
CENTER 2.
Figure 4-5 DISA SDC/COOP Environment Requirements
Figure 4-6 identifies the requirements for Production environments hosted at DISA DATA
CENTER 1.
Figure 4-6 DISA PDC Environment Requirements
Figure 4-7 identifies the environment build status by site and enclave. The current version of this figure is accessible on SharePoint at Environments by Enclave.
Figure 4-7 Environments by Enclave
Institutional (and Self- Development/
Qualif ication) Training
HCM
CRM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Informatica Gradkell
HCM
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
ESB
OHS
Informatica Gradkell
Config Baseline
HCM
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
ESB
OHS
Informatica Gradkell
Integrated Test
(PLT) SSO/CAC
Data Configuration
HCM
Ab Initio
ESB
Data Test
HCM
Ab Initio
ESB
HCM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Informatica Gradkell
Operational Training
DISA Data Center 2 PDC
KEY
DISA Data Center 1 Zone B Enclave DISA Data Center 1 Zone A Enclave
AMRDEC
Release 2 Development Enclave (App & OS STIG)
DISA Data Center 1 SDC/COOP
ALTESS
Release 2 Fit/Gap
Increment 2 Environments Build Status
UNCLASSIFIED
Last Updated: 09/24/2019
Support Tools
HP ALM
Cameo
Iris Intelligence SharePoint
PeopleTools TOAD/SQL Dev
Putty Ultra Edit/ Compare
Fit/Gap
HCM
Portal
CRM
ELM
OBIEE
Ab Initio
UPK
OPA
Release 2 AMRDEC Support Tools R2 SDC – Transactional
SDC – Reporting/Training
XXX02 IOE: 1/09/17
XXX06 IOE: 2/14/17
R2 PDC – Transactional
XXX03 IOE: 3/22/17
PDC – Reporting/Training
XXX04 IOE: 3/30/17
Primary Reporting
OBIEE
OBIA/ODI
R3 Reporting/Training (DIT/Prod)
R3 Transactional (DIT/Prod) XXX11 IOE: 10/15/18
XXX05 IOE: 10/21/16
XXX12 IOE: 8/10/17
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
Training
Core Dev
HCM
Portal
CRM
ELM
Elastic Search
OBIEE
OBIA/ODI
OPA
GRC
OAM/OIM/OID
Ab Initio
ESB
Data
HCM
Ab Initio
ESB
Functional/Unit Testing (FUT)
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
GRC
OAM/OIM/OID
OPA
ESB
Security
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
GRC
OIM/OUD
Development/ Admin Tools
Stat Jenkins
Subversion Cobol Compiler
PeopleTools TOAD/SQL Dev
Putty Ultra Edit/ Compare
UPK
Program Support Tools
Iris Intelligence HP Agile Mgr.
HP ALM
Cameo
HP BPT
HP UFT
C-Factory
HP UCMDB
Adobe Captivate
OEM
Payroll
HCM
OPA
GP RRE Test
Data
HCM
Ab Initio
XXX01 IOE: 12/13/16
Tools Sub-Enclave Supporting Zone B, Zone A and DISA Data Center 1 SDC (Located at DC1)
OEM
Elastic Search
Audit Vault Stonebranch
Splunk
GRC
Qlik
Production Support Tools
Development/ Admin Tools
IOE: 3/2/17
IOC: 8/31/17
FOC: 2/28/18
1 2 3 4 5 6 7 8 9
PeopleTools Stat
Jenkins Subversion
Cobol Compiler SoapUI
UPK
TOAD/SQL DEV
Putty Ultra Edit / Compare
Program Support Tools
HP Agile Mgr.
HP ALM
Cameo
HP UFT
HP BPT
C-Factory
HP UCMDB
HP PC
*IRIS
*Migration in progress
UNCLASSIFIED
Secondary Production
HCM
Portal
CRM
ELM
Ab Initio
OAM/OIM
OUD
OPA
ESB
OHS
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OPA
Operational Training
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OPA
IOE: O/S configured & hardened (DISA) IOC: Software Installed/Configured (IPPS-A) FOC: Environment Ready for Users
IOE dates for Zone B, Zone A, COOP, & PROD are per DISA plans.
IOC & FOC dates for Zone A, COOP, & PROD are per SI IMS and are tentative until final delivery.
Environment FOC Ready. CM and App Sec activities completed.
Release 2 Test Sub-Enclave (App & OS STIG)
Institutional (and Self-
Development/ Qualif ication)
Training
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
OIM/OAM
OUD
OHS
Payroll (with Cobol) SSO/CAC
HCM
OPA
GP RRE Test
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
OPA
ESB
Integrated Test
(PLT) SSO/CAC
HCM
Ab Initio
ESB
Data Test
Release 4 Test Sub-Enclave (App & OS STIG)
Production Staging
HCM
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
ESB
OHS
Informatica Gradkell
Primary Production
HCM
Portal
CRM
ELM
Ab Initio
OAM/OIM
OUD
OPA
ESB
OHS
HCM
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
Primary Production
HCM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
Operational Training
HCM
CRM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
Institutional Training
Institutional Training
Release 3 Test Sub-Enclave (App & OS STIG)
HCM
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
Integrated Test
(PLT) SSO/CAC
HCM
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
HCM
Portal
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OPA
OHS
Operational Training
HCM
Portal
CRM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OPA
OHS
Institutional Training Production
Reporting
OBIEE
OBIA/ODI
Secondary Reporting
OBIEE
OBIA/ODI
Release 2-4 Development (Bug Fixes/Sustainment) Sub-Enclave
HCM
Portal
CRM
OBIEE
OBIA/ODI
OPA
Institutional (and Self- Development/
Qualif ication) Training
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OIM
OUD
OPA
ESB
FUT
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OIM
OUD
OPA
ESB
Sustainment
Dot Release Test Sub-Enclave
ITE
DOT Releases
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
OPA
Production Staging
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
OPA
OHS
GRC
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
AB Initio
GRC
OAM/OIM
OUD
OPA
ESB
Config Baseline
* NonPS Files Only
CM BASELINE
(ECR req.)
CM BASELINE
(ECR req.)
CM BASELINE
(ECR req.)
CM BASELINE
(ECR req.)
CM BASELINE
(ECR req.)
UPKs/Data
Release 3 /4 Prototype/Demonstration Enclave (App & OS No STIG)
Release 2 Training UPK Development Environment
Prototype
HCM
Portal
CRM
ELM
*FSCM
OBIEE
OBIA/ODI
Ab Initio
GRC
OAM/OIM/OID
OPA
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
GRC
OAM/OIM
OID
OPA
Demonstration
(STIG) SSO/CAC
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
UPK Dev
CM BASELINE
(ECR req.)
PDC Support Tools Enclave
PeopleTools Cobol Compiler
TOAD/SQL DEV
Putty Ultra Edit/Compare
Admin Tools
Release 3 ITE2C – SDC Reporting/Training
(DIT/COOP)
XXX06 IOE: 2/01/20
R3 SDC Transactional
(DIT/COOP) XXX05 IOE: 2/01/20
HCM
CRM
ELM
Ab Initio
OAM/OIM
OUD
ESB
Gradkell Informatica
COOP
Production
HCM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
Operational Training
HCM
CRM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
Institutional Training
Production Reporting
OBIEE
OBIA/ODI
Config Baseline
CM BASELINE
(ECR req.)
CM BASELINE
(ECR req.)
XXX12 IOE: 10/15/18
Dot Release Development Sub-Enclave
Dot Release
FUT
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
Release 3 Development Sub-Enclave (App & OS STIG)
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
FUT/QA
*Data Dev
HCM
Ab Initio
ESB
R2 to R3 Migration
Staging (Database only no front end)
HCM
Portal
CRM
ELM
HCM
CRM
ELM
OBIEE
Gradkell
Institutional Training Dev (data and web pages only)
Unified Baseline Development Sub-Enclave (App & OS STIG)
Portal
CRM
ELM
UBL Core Dev (PUM retrofits)
HCM
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
Core Dev
Dev0
Roles and Permissions
*Security Dev
HCM
CRM
ELM
OIM
OUD
Dot Release
DEV
HCM
Portal
CRM
ELM
OBIEE
OBIA/ODI
OPA
HCM
CRM
Gradkell
OAM/OIM
OUD
ESB
Ab Initio
OHS
Release 4 Development Sub-Enclave (App & OS STIG)
Data
HCM
Ab Initio
ESB
HCM
CRM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
Institutional (and Self- Development/
Qualif ication) Training
Dev0
HCM
CRM
ELM
Ab Initio
OAM/OIM
OUD
ESB
Gradkell Informatica
Security
HCM
CRM
ELM
OAM/OIM
OUD
HCM
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
ESB
Gradkell Informatica
FUT/QA
HCM
CRM
ELM
OBIEE
OBIA/ODI
Ab Initio
OAM/OIM
OUD
ESB
Gradkell Informatica
Core Dev
Conversions/Data Only
Data Configuration
HCM
Ab Initio
ESB
Institutional Training Test
Payroll (with Cobol) SSO/CAC
HCM
GP RRE Test HCM
ELM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
Operational Training
Production Staging
HCM
CRM
ELM
OBIEE
OBIA/ODI
Gradkell
Informatica
OAM/OIM
OUD
ESB
Ab Initio
OHS
Performance Testing
HCM
Portal
CRM
ELM
OIM
OUD
OPA
OHS
HCM
CRM
ELM
OIM
OUD
ESB
Gradkell
Performance Testing
Performance Testing
OBIEE
OBIA/ODI
Performance Testing
OBIEE
OBIA/ODI
BI Dev
OBIEE
OBIA
HCM
CRM
ELM
Qlik Data Test
HCM
Ab Initio
ESB
HCM
CRM
OBIEE
OBIA/ODI
OAM/OIM
OUD
OHS
Gradkell
4.2 Environmental Systems Management and Change Control
Coordination for Systems Management activities are executed according to the Service-Level Agreements (SLAs) with each data center. Changes to all enclaves/environments are made in accordance with established SLAs and the Configuration Management Plan.
4.2.1 Service-Level Agreements (SLAs)
Effective management of IPPS-A resources is dependent on the SLAs negotiated between IPPS-A and hosting data centers. This section outlines the SLAs established with each data center.
4.2.1.1 DISA
An SLA covering IPPS-A assets hosted in DISA data centers is accessible on SharePoint at
DISA SLA.
4.3 Site High-Level Design
Each site is designed to meet requirements and deliver capabilities for specific phases of the SDLC. This section provides a high-level design for each site along with a logical view of the enclaves, application stacks, and environments required to deliver those capabilities.
4.3.1 IPPS-A Increment II SDC
The DISA Defense Enterprise Computing Center (DECC) located at DATA CENTER 2, hosts the infrastructure supporting IPPS-A Increment II Test, Development, and SDC enclaves. These enclaves are supported by five Oracle SuperClusters and one Oracle ZFS storage appliance. Two additional Infiniband-connected SuperClusters are being procured to provide DIT/Release 3 production capabilities.
SuperCluster XXXX, in Zone B, supports development environments and is configured with two 4-node Oracle Real Application Clusters (RAC) supporting Increment II development and administrative Oracle 12c or higher databases. XXXX is configured with four electrically isolated Physical Domains (PDOMs). Each PDOM contains one database and three general purpose Logical Domains (LDOMs) for a total of four database LDOMs and 12 general purpose LDOMs.
SuperCluster XXXX and XXXX, in Zone A, are two Infiniband-connected SuperClusters that support Test enclave environments. XXXX supports Releases 2 and 3 test, BI Dev, Data Config, and Demonstration environments and is configured with one, 4-node Oracle RAC supporting test enclave 12c or higher databases. XXXX supports Release 4 test environments and is also configured with one, 4-node Oracle RAC supporting test enclave 12c or higher databases.
XXXX and XXXX are each configured with four electrically isolated Physical Domains (PDOMs). Each PDOM contains one database and two general purpose Logical Domains (LDOMs) for a total of four database LDOMs and eight general purpose LDOMs.
Two SuperClusters, XXXX and XXXX, support SDC/COOP transactional and reporting/training environments respectively. Both SuperClusters also support a Performance Test environment that provides the same performance characteristics as Production. SuperCluster XXXX is configured with one 4-node RAC and supports the SDC transactional environment. XXXX is configured with two 4-node RACs and supports the SDC reporting and training environments within the SDC enclave.
For Release 4 SDC capabilities, XXXX and XXXX will be replaced by two tech refreshed Infiniband-connected SuperClusters. SuperClusters XXXX and XXXX are being procured in order to support Release 3 DIT and SDC capabilities. XXXX will be configured with one 4-node RAC and support the R3 SDC transactional environment. XXXX will be configured with two 4-node RACs and support the SDC reporting and training environments within the SDC enclave.
For tools and other applications that cannot be hosted on the SuperCluster’s Scalable Processor Architecture (SPARC) platform, x86 capabilities are supported on DISA capacity services.
4.3.1.1 DISA DATA CENTER 2 Enclaves/Environments
DISA DATA CENTER 2 supports five IPPS-A enclaves located within two zones and “Production.” These enclaves include:
• Development (Zone B)
• Support Tools (Zone B)
• Test and Demonstration (Zone A)
• Support Tools (COOP)
• COOP/SDC (Secondary/COOP Production/Training) The Development, Test, and SDC Enclaves contain Application Stacks that support one or more environments.
Figure 4-8 identifies the application stacks and OEs that support the Development environments.
Due to the size of this drawing, the figure is representative of the current full version. Select the icon or access the figure on SharePoint at Zone B Development and Tools Enclaves/Environments.
Figure 4-8 Zone B Development and Tools Enclaves/Environments
UNCLASSIFIED
DISA DC1 Zone B Development and Tools Enclaves/Environments
UNCLASSIFIED
GR
C
1XXXXXHPAG0
GRC-App1
GR
C
2XXXXXHPAG1
GRC-App2
R2 Dev Sust
R2 FUT
Sust
In fo rm at ica
XXXXXHPAGS
Informatica-App1
R3 Dev R3 Dev0 R3 FUT/QA
R3 Inst Train Dev
R3 Oper Train Dev
In fo rm at ica
XXXXXHPAGT
Informatica-App2
El as tic
XXXXXHPAI8
ELAST-App1
R2 Dev Sust
R2 Data Dev Sust
R2 Inst Train Sust
R3 FUT
Sust
El as tic
2XXXXXHPAI9
ELAST-App2
R3 Inst Train DevR3 FUT/QA R3 Data Dev
R3 Dev R3 Dev0
El as tic
3XXXXXHPAJA
ELAST-App3
XXXXXXSHUA8
TOOLS1-Support
File Server-1
XXXXXXSHUA9
TOOLS1-Support
PeopleTools-1
XXXXXXSHPAA7
TOOLS1-App
PUM-1
W W W
XXXXXXSHUA2
TOOLS1-Support Remote Desktop-1
XXXXXXSHUA3
TOOLS1-Support Remote Desktop-2
XXXXXXSHUA4
TOOLS1-Support Remote Desktop-3
W W W
XXXXXXSHUA5
TOOLS1-Support Remote Desktop-4
XXXXXXSHUA6
TOOLS1-Support Remote Desktop-5
XXXXXXSHUA7
TOOLS1-Support Remote Desktop-6
W W W
X8
Su pp or t T oo ls
Sp lu nk
XXXXXHPAJB
Splunk-App1
R2 Dev Sust R2 Data Dev Sust
R2 Inst Train Sust
R2 Security Dev Sust
R2 FUT
Sust
R2-R3 Staging
R3 Dev R3 Dev0 R3 Data Dev
R3 FUT/QA R3 Security Dev
R3 Inst.
Train Dev
St on eb ra nc h
XXXXXHPAI0
Stonebranch-App1
R2 Dev Sust
R2 Inst Train Sust
R2 FUT
Sust
St on eb ra nc h
XXXXXHPAI1
Stonebranch-App2
R3 Dev R3 Dev0 R3 FUT/QA
R3 Data Dev
R3 Sec Dev
R3 Inst Train Dev
De ve lo pm en t S up er
Cl us te r X
XX
X
XXXXXAD003
GRC-App1
XXXXXAD307
CTRLM-App1
XXXXXAD209
LDAP-App1
XXXXXWD208
OBIEE-Web2
XXXXXWB204
OBIEE-Web1
XXXXXWD219
Mail-Web1
O Es fo r D ec om m iss io n
XXXXXDD201
DB-RAC1-Node1
XXXXXDD202
DB-RAC1-Node2
XXXXXDD203
DB-RAC1-Node3
XXXXXDD204
DB-RAC1-Node4
De v
Da ta ba se
R
AC
ES
B
XXXXXWD001
P-ESB-Web1
XXXXXWD306
P-ESB-Web1
R3 Dev R3 Dev0 R3 FUT/QA
ES
B
XXXXXWD207
P-ESB-Web2
XXXXXWD307
P-ESB-Web2
R2 FUT
Sust
Ab In iti o
XXXXXAD230
AbInitio-Web3
XXXXXAD212
AbInitio-App3
R2 Dev Sust R2 Data Dev Sust
R2 FUT
Sust
O
BI
EE
XXXXXAD330
OBIEE-App10
R3 Dev0
O
BI
EE
XXXXXAD329
OBIEE-App9
O
BI
EE
XXXXXAD328
OBIEE-App8
R3 Inst Train Dev
O
BI
EE
XXXXXAD327
OBIEE-App7
R3 FUT/QA
O
BI
EE
XXXXXAD326
OBIEE-App6
R2 FUT Sust
O
BI
EE
XXXXXAD325
OBIEE-App5
R3 Dev
O
BI
EE
XXXXXAD229
OBIEE-App4
O
BI
EE
XXXXXAD228
OBIEE-App3
R2 Dev Sust
O
BI
EE
XXXXXAD213
OBIEE-App2
O
BI
EE
XXXXXAD204
OBIEE-App1
R2 Inst Train Sust
Ab In iti o
XXXXXWD300
AbInitio-Web3
XXXXXAD300
AbInitio-App3
Ab In iti o
XXXXXWD004
AbInitio-Web1
XXXXXAD006
AbInitio-App1
R3 Dev R3 Dev0 R3 FUT/QA
R3 Data Dev
R3 Data Conv. Dev
Gr ad ke ll
XXXXXAD312
Grad-App1
R3 Dev R3 Dev0 R3 FUT/QA
R3 Inst Train Dev
Gr ad ke ll
XXXXXAD313
Grad-App2
XXXXXAA204
HCM-App1
XXXXXAA005
HCM-Batch1
XXXXXWB203
HCM-Web1
HC
M
R3 Dev R3 Dev0 R3 FUT/QA
XXXXXAD201
HCM-App2
XXXXXAD202
HCM-Batch2
XXXXXWD205
HCM-Web2
HC
M
R3 Data Dev
XXXXXAD210
HCM-App3
XXXXXAD211
HCM-Batch3
XXXXXWD206
HCM-Web3
HC
M
R3 Inst Train Dev
XXXXXAD220
HCM-App4
XXXXXAD221
HCM-Batch4
XXXXXWD215
HCM-Web4
HC
M
R2-R3 Staging
R3 Sec Dev
XXXXXAD316
HCM-App5
XXXXXAD320
HCM-Batch5
XXXXXWD308
HCM-Web5
HC
M
R2 Dev Sust
XXXXXAD317
HCM-App6
XXXXXAD320
HCM-Batch5
XXXXXWD309
HCM-Web6
HC
M
R2 FUT
Sust
XXXXXAD318
HCM-App7
XXXXXAD321
HCM-Batch7
XXXXXWD310
HCM-Web7
HC
M
R2 Inst Train Sust
XXXXXAD319
HCM-App8
XXXXXAD321
HCM-Batch7
XXXXXWD311
HCM-Web8
HC
M
XXXXXAS001
Portal-App1
XXXXXAS002
Portal-Batch1
XXXXXWS001
Portal-Web1
Po rt al
R3 Dev R3 Dev0
XXXXXAD001
Portal-App2
XXXXXAD002
Portal-Batch2
XXXXXWD212
Portal-Web2
Po rt al
R3 FUT/QA
XXXXXAD218
Portal-App3
XXXXXAD219
Portal-Batch3
XXXXXWD214
Portal-Web3
Po rt al
R3 Inst Train Dev
R3 Oper Train Dev
XXXXXAD222
Portal-App4
XXXXXAD223
Portal-Batch4
XXXXXWD216
Portal-Web4
Po rt al
R2-R3 Staging
XXXXXAD336
Portal-App5
XXXXXAD340
Portal-Batch5
XXXXXWD316
Portal-Web5
Po rt al
R2 Dev Sust
XXXXXAD337
Portal-App6
XXXXXAD341
Portal-Batch6
XXXXXWD317
Portal-Web6
Po rt al
R2 Security Dev Sust R4 Dev0
XXXXXAD338
Portal-App7
XXXXXAD342
Portal-Batch7
XXXXXWD312
Portal-Web7
Po rt al
R2 Fut Sust R4 FUT/QA
XXXXXAD339
Portal-App8
XXXXXAD343
Portal-Batch8
XXXXXWD319
Portal-Web8
Po rt al
R2 Inst Train Sust
R4 Oper Train Dev
R4 Inst Train Dev
XXXXXAA001
CRM-App1
XXXXXAD203
CRM-Batch1
XXXXXWD201
CRM-Web1
CR
M
R3 Dev R3 Dev0
XXXXXAD301
CRM-App4
XXXXXAD304
CRM-Batch4
XXXXXWD301
CRM-Web4
CR
M
R2 Dev Sust
XXXXXAD205
CRM-App2
XXXXXAD206
CRM-Batch2
XXXXXWD213
CRM-Web2
CR
M
R3 FUT/QA R3 Sec Dev
XXXXXAD224
CRM-App3
XXXXXAD225
CRM-Batch3
XXXXXWD217
CRM-Web3
CR
M
R3 Inst Train Dev
XXXXXAD302
CRM-App5
XXXXXAD305
CRM-Batch5
XXXXXWD302
CRM-Web5
CR
M
R2 Fut Sust
XXXXXAD303
CRM-App6
XXXXXAD306
CRM-Batch6
XXXXXWD303
CRM-Web6
CR
M
R2 Inst Train Sust
XXXXXAD309
ELM-App5
XXXXXAD311
ELM-Batch5
XXXXXWD305
ELM-Web5
EL
M
R2 Inst Train Sust
R2 FUT
Sust
XXXXXAD207
ELM-App1
XXXXXAD208
ELM-Batch1
XXXXXWD202
ELM-Web1
EL
M
R3 Dev R3 Dev0
XXXXXAA002
ELM-App2
XXXXXAA003
ELM-Batch2
XXXXXWD209
ELM-Web2
EL
M
R3 FUT/QA R3 Sec Dev
XXXXXAD226
ELM-App3
XXXXXAD227
ELM-Batch3
XXXXXWD218
ELM-Web3
EL
M
R3 Inst Train Dev
XXXXXAD308
ELM-App4
XXXXXAD310
ELM-Batch4
XXXXXWD304
ELM-Web4
EL
M
R2 Dev Sust
O
PA
XXXXXAD005
OPA-App1
R3 FUT/QA R3 Inst Train Dev
R3 Oper Train Dev
R3 Dev R3 Dev0
O
PA
XXXXXAD231
OPA-App2
R2 Dev Sust
R2 Inst Train Sust
R2 FUT
Sust
O
PA
XXXXXAD231
OPA-App2
R4 FUT/QA R4 Inst Train Dev
R4 Oper Train Dev
R4 Dev R4 Dev0
O
AM
XXXXXAD322
OAM-App5
R2 Dev Sust R4 Dev R4 Dev0
O
AM
XXXXXAD323
OAM-App6
R2 FUT
Sust R4 FUT/QA R4 Sec
Dev
O
AM
XXXXXAD324
OAM-App7
R2 Inst Train Sust
R4 Inst Train Dev
R4 Oper Train Dev
O
AM
XXXXXAD008
OAM-App5
R3 Dev
O
AM
XXXXXAD009
OAM-App2
O
AM
XXXXXAD214
OAM-App3
R3 FUT/QA R3 Sec Dev
O
AM
XXXXXAD215
OAM-App4
R3 Inst Train Dev
R3 Oper Train Dev
O
IM
XXXXXAD007
OIM-App1
R3 Dev R3 Dev0 R3 FUT/QA
O
IM
XXXXXAD217
OIM-App2
R3 Sec Dev
R3 Inst Train Dev
O
IM
XXXXXAD333
OIM-App3
R2 Dev Sust
R2 FUT
Sust
O
IM
XXXXXAD334
OIM-App4
R2 Inst Train Sust
O
UD
XXXXXAD004
OUD-App1
R3 Dev R3 Dev0 R3 FUT/QA
O
UD
XXXXXAD216
OUD-App2
R3 Sec Dev
R3 Inst Train Dev
R3 Oper Train Dev
O
UD
XXXXXAD331
OUD-App3
R2 Dev Sust
R2 FUT
Sust
O
UD
XXXXXAD332
OUD-App4
R2 Inst Train Sust
O
HS
R2 Dev Sust
XXXXXWD312
OHS-Web5
O
HS
XXXXXWD313
OHS-Web6
O
HS
XXXXXWD314
OHS-Web7
R2 FUT
Sust
O
HS
R2 Inst Train Sust
XXXXXWD315
OHS-Web8
O
HS
XXXXXWD002
OHS-Web1
R3 Dev
O
HS
XXXXXWD003
OHS-Web2
R3 Dev0
O
HS
R3 FUT/QA R3 Sec Dev
XXXXXWD210
OHS-Web3
O
HS
R3 Inst Train Dev
R3 Oper Train Dev
XXXXXWD211
OHS-Web4
XXXXXAD344
SES-App1
XXXXXAD314
GRC-App2
XXXXXAD345
SES-App2
XXXXXAD315
GRC-App3
XXXXXWD321
PSRPT-Web1
Co nv er ge d / Ca pa ci ty S er vi ce s x
O
Es
TBD
TBD
TBD
TBD
R2-R3 Staging
TBD
TBD
TBD TBD
TBD
TBD
R2 Dev Sust
Last Modified 09/24/2019
Figure 4-9 identifies the application stacks and OEs that support the Test environments. Due to the size of this drawing, the figure is representative of the current full version, accessible on SharePoint at DISA Zone A Test and Demonstration Enclave/Environments.
Figure 4-9 Zone A Test and Demonstration Enclave/Environments
REMOVED
Figure 4-10 identifies the application stacks and OEs that support the Secondary Standby/COOP production and training environments. The latest version of this drawing is located on SharePoint at Secondary Data Center/COOP Production/Training Enclave/Environments.
Figure 4-10 Secondary Data Center/COOP Production/Training Enclave/Environments
REMOVED
Figure 4-11 is a representation that identifies the application stacks and OEs that support the Release 3 Secondary Standby/ COOP production and training environments to be built in DATA CENTER 2. The latest version of this drawing is located on SharePoint at R3 SDC COOP Enclaves/ Environments.
Figure 4-11 R3 Secondary Production/COOP Enclaves/ Environments
4.3.2 IPPS-A Increment II PDC
The DISA DECC located in DATA CENTER 1 hosts the production infrastructure supporting IPPS-A for Increment II production capabilities. SuperCluster XXXX supports the Release 2 primary production transactional environment. SuperCluster XXXX supports Release 2 primary reporting and training environments. Each SuperCluster is configured with four electrically isolated PDOMs. Each PDOM contains one database and three general purpose LDOMs for a total of four database LDOMs and 12 general purpose LDOMs per SuperCluster. XXXX is configured with one 4-node RAC-supporting Oracle 12c or higher PDC databases. XXXX is configured with two, 4-node RAC-supporting Oracle 12c or higher PDC databases. One RAC is dedicated for reporting databases and the second is dedicated for training databases.
For Release 3, SuperCluster XXXX will support the primary production transactional environment. SuperCluster XXXX will support Release 3 primary reporting and training environments.
4.3.2.1 IPPS-A Increment II Production Data Center Enclaves/Environments DISA DATA CENTER 1 supports the following two enclaves within one zone and Production:
• PDC (Primary Production/Reporting and Training)
• Remote Desktop and Support Tools Tools requirements for providing remote access capabilities and managing applications and databases hosted on the Oracle SuperClusters are accomplished via capacity services OEs.
Figure 4 identifies the application stacks and OEs that support the Release 2 primary production transactional. The latest version of this drawing is located on SharePoint at PDC Production/Reporting and Training Enclave/Environments.
Figure 4-12 Primary Data Center (PDC)Production/Reporting and Training Enclaves/ Environments
Due to finalization of decommission decisions impacting R3 PDC footprint, drawings representing Release 3 PDC will be completed and added to SharePoint in a future version of this document.
4.3.3 SuperCluster Capacity Planning
Capacity planning tracks the projected utilization of resources required by OEs. Virtual central processing unit (vCPU) and Capacity Planning are referenced in the Oracle PeopleSoft HRMS
9.1 FP2 Self-Service Using Oracle Database (DB) for Oracle Solaris (Unicode) on Oracle SPARC M6-32 Servers whitepaper located under Infrastructure/Requirements on SharePoint at SPARC M6-32 Planning Whitepaper. All NIPR planning capacity worksheets are located on SharePoint at SuperCluster Capacity Planning Worksheets.
Figure 4-13 identifies the OEs hosted on the Zone B XXXX SuperCluster and their projected utilization.
Figure 4-13 XXXX Capacity Planning Figure 4-14 identifies the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-14 Test SuperCluster XXXX Capacity Planning
REMOVED
Figure 4-15 identifies the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-15 XXXX SuperCluster Capacity Planning
REMOVED
Figure 4-16 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-16 XXXX Capacity Planning
Figure 4-17 provides the template to be used to identify the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-17 XXXX Capacity Planning
Figure 4-18 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-18 XXXX Capacity Planning
Figure 4-19 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-19 XXXX Capacity Planning
REMOVED
Figure 4-19 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-20 XXXX Capacity Planning
Figure 4-19 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-21 XXXX Capacity Planning
Figure 4-19 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-22 XXXX Capacity Planning
Figure 4-19 provides the OEs hosted on the XXXX SuperCluster and their projected utilization.
Figure 4-23 XXXX Capacity Planning
4.3.4 Hardware and Software inventory
The Hardware inventory for IPPS-A is captured in several Infrastructure artifacts including the DISA Master Server List (MSL), Monthly SuperCluster Inventory, and Consolidated Hardware Inventory Spreadsheet.
Once an SRF has been submitted, and the list of required infrastructure resource names are identified, the OEs are added to the DISA IPPS-A MSL. The MSL identifies the following:
• DISA Project under which the OEs were implemented
• Requested or assigned server name
• Server role
• LDOM placement
• Tier
• Operating System
• Cores/ RAM
• Storage requirements The latest version of the MSL is available on SharePoint at DISA Master Server List
DISA provides a monthly SuperCluster Inventory Spreadsheet that identifies the current status/utilization of all NIPR SuperClusters including:
• OE LDOM placement
• LDOM cores, VCPU, and RAM allocations
• Storage utilization The latest available version of the monthly inventory is located on SharePoint at DISA Monthly SuperCluster Inventory.
The new Consolidated Hardware Inventory consolidates the information from the MSL and Monthly SuperCluster Inventory to deliver the following in a single spreadsheet:
• Server name (CSHIP)
• Server Role
• SuperCluster or Capacity Services designation
• LDOM (if applicable)
• Cores
• VCPUs
• RAM
• Whether the server has been submitted for decommissioning
The Consolidated Hardware Inventory spreadsheet is available on SharePoint at Consolidated Hardware Inventory.
The R2 Production Hardware/Software Baseline is available on SharePoint at R2 Hardware/Software Baseline.
5 IPPS-A INCREMENT II ENVIRONMENT PREREQUISITES
Installation, implementation, development, testing, and sustainment of environments in the DISA hosting data centers require tools and services to access IPPS-A hosted infrastructure. The required tools and services are based on the role of the user.
5.1 Data Center Remote Access
In order to provide developers, application administrators, testers, and program support personnel the access to backend servers, a remote access solution must be implemented. The remote access solution must be sufficiently sized to support the number of concurrent users per role. The solution must also support the installation of the toolsets required by personnel based on their identified role. The VDI application requirements are accessible on SharePoint at VDI Requirements.
5.2 Software Download Capability
Application Administrators must have the ability to download the software required to install, configure, and maintain applications in all enclaves and environments. This capability must support the requirement to download large files (i.e., 20+ Gigabytes) without interruption. The speed of the download must be sufficient to accommodate individual downloads within a reasonable timeframe (i.e., an eight-hour work day for a large file).
A-1
Appendix A: Acronyms and Abbreviations Acronym Definition
AKO-S Army Knowledge Online-Secret Internet Protocol Router Network (SIPRNet)
ALM Application Lifecycle Management
AO Authorizing Official
BI Business Intelligence
BPT Business Process Testing
CDRL Contract Data Requirement List
CSHIP DISA term for a server name
CM Configuration Management
CAC Common Access Card
COOP Continuity of Operations Plan
COTS Commercial Off-The-Shelf
CR Change Request
CRM Customer Relationship Management
DECC Defense Enterprise Computing Center
DISA Defense Information Systems Agency
DISN Defense Information Systems Networks
DIT Developer Integration Testing
DMZ Demilitarized Zone
DoD Department of Defense
EBN Enterprise Backup Network
ECB Engineering Control Board
ECN Engineering Change Notification
ECR Engineering Change Request
ELM Enterprise Learning Management
ERP Enterprise Resource Planning System
ESB Enterprise Service Bus
ESM Enterprise Systems Management
FOC Full Operating Capability
FUT Functional User Test(ing)
GP Global Payroll
A-2
Acronym Definition
GRC Governance Risk and Compliance
HCM Human Capital Management
HP Hewlett Packard
HR Human Resources
HW Hardware
IA Information Assurance
IATO Interim Authority To Operate
IATT Interim Authority to Test
IdM Identity Manager
IMS Integrated Master Schedule
IRIS Integrated Risk Information System
IOC Initial Operating Capability
IOE Initial Operating Environment
IPPS-A Integrated Personnel and Pay System – Army
IRM Integrated Road Map
ISSM Information Security System Manager
ITE Integrated Testing Environment
LDOM Logical Domain
MFT Managed File Transfer
MOA Memorandum of Agreement
MSL Master Server List
NIPR Nonsecure Internet Protocol Router
OAM Oracle Access Manager
OBIA Oracle Business Intelligence Analytics
OBIEE Oracle Business Intelligence Enterprise Edition
ODI Oracle Data Integration
OE Operational Environments
OEM Oracle Enterprise Manager
OHS Oracle HTTP Server
OID Oracle Internet Directory
OIM Oracle Identity Manager
A-3
Acronym Definition
OOB Out of Band
OPA Oracle Policy Automation
OPM Oracle Policy Modeling
OS Operating System
OSC Oracle SuperCluster
OUD Oracle Unified Directory
PDC Primary Data Center
PDOM Physical Domain
PLT Product Level Testing
PMBOK Project Management Body of Knowledge
PMO Project Management Office
PMP Project Management Plan
PROD Production
PS PeopleSoft
QASP Quality Assurance Surveillance Plan
QC Quality Control
RAC Real Application Clusters
RAM Random Access Memory
RDBMS Relational Database Management System
RDP Remote Desktop Protocol
REQ Request or Requirements
RFAAP Radford Army Ammunition Plant
RRE Risk Reduction Exercise
SDC Secondary Data Center
SDLC Software Development Lifecycle
SED Software Engineering Directorate
SI System Integrator
SIPRNet Secret Internet Protocol Router Network
SLA Service-Level Agreement
SLM Service-Level Manager
A-4
Acronym Definition
SOA Service-Oriented Architecture
SP Sensitive Products
SPARC Scalable Processor Architecture
SRF Service Request Form
SQL Structured Query Language
SRB Soldier Record Brief
SSO Single Sign On
STIG Security Technical Implementation Guide
SW Software
T&D Test and Development
TOAD Tool for Oracle Application Developers
TRN Training
UCMDB Universal Configuration Management Database
UFT Unified Functional Testing
UPK User Productivity Kit
VCE Virtual Computing Environment vCPU Virtual Central Processing Unit
VDI Virtual Desktop Infrastructure
VIP Virtual Internet Protocol
VM Virtual Machine
XML Extensible Markup Language
B-1
Appendix B: Consolidated Reference Documents This appendix lists other documents that are referenced, which are provided to complement required items.
Document # PWS Reference Document Title
4.1.4 Project Management Plan (PMP)
4.13.4 Configuration Management Plan
C-1
Appendix C: Reference Terms
Term Definition
Application Stack A set of servers (or OEs) and application(s) that provide the capabilities of the application(s) (i.e. HCM Web, Application, and Batch) to environments.
Converged System
A portfolio of system-based products from Hewlett-Packard (HP) that integrates preconfigured IT components into systems for virtualization, cloud computing, big data, collaboration, converged management, and client virtualization.
Enclave An environment or group of environments that support one or more phases of the SDLC (i.e., Development, Test, Support Tools, SDC, and PDC).
Environment A set of application stacks, databases, and configurations that meet a pre-defined requirement, and/or delivers a pre-defined capability (i.e. Core, Data Payroll, and Fit/Gap).
Site Hosting Data Center.
| 1 Introduction and Purpose |
| 1.1 Introduction |
| 1.2 Document Purpose |
| 1.3 Document Overview |
| 1.4 Reference Documents |
| 2 Background |
| 2.1 Legacy Systems and IPPS-A |
| 2.2 Data Centers |
| 3 Applications |
| 4 IPPS-A Environmental Design and Data Center Architectural Overview |
| 4.1 Hierarchical Framework |
| 4.1.1 Sites |
| 4.1.2 Zones |
| 4.1.3 Enclaves |
| 4.1.4 Application Stacks |
| 4.1.5 Environments |
| 4.2 Environmental Systems Management and Change Control |
| 4.2.1 Service-Level Agreements (SLAs) |
| 4.2.1.1 DISA |
| 4.3 Site High-Level Design |
| 4.3.1 IPPS-A Increment II SDC |
| 4.3.1.1 DISA DATA CENTER 2 Enclaves/Environments |
| 4.3.2 IPPS-A Increment II PDC |
| 4.3.2.1 IPPS-A Increment II Production Data Center Enclaves/Environments |
| 4.3.3 SuperCluster Capacity Planning |
| 4.3.4 Hardware and Software inventory |
| 5 IPPS-A Increment II Environment Prerequisites |
| 5.1 Data Center Remote Access |
| 5.2 Software Download Capability |
| Appendix A: Acronyms and Abbreviations |
| Appendix B: Consolidated Reference Documents |
| Appendix C: Reference Terms |
File details come from the government source that posted it. Updated .