About this file
This is a Request for Proposal (RFP) for a Facilities Maintenance Indefinite Delivery/Indefinite Quantity (IDIQ) contract for the Savannah River Site, issued by the USDA Forest Service. The solicitation seeks up to four multiple-award firm fixed-price contracts for facility construction, maintenance, and repair projects at the Savannah River Forest Station in New Ellenton, South Carolina. The contract period is from November 1, 2025, to October 31, 2030, with a base period of one year and four one-year option periods.
Key requirements include performing facility construction, maintenance, and repair work across the Savannah River Site, with projects potentially involving renovation of buildings, restrooms, pavilions, docks, and administrative facilities. Offerors must demonstrate bonding capacity of at least $250,000 per project and $1 million aggregate, provide a technical approach for managing multiple concurrent projects, submit five relevant construction project experiences, and include past performance documentation. The solicitation will evaluate proposals using a best value trade-off process, with technical factors being approximately equal in importance to price. Proposals are due October 20, 2025, at 12:00 pm EST, with two seed projects (Building 760-G Interior Repair and Intrusive Plant Management) used to evaluate pricing.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.12445225R0045 Project: Savannah River Site Facilities Maintenance IDIQ
Table of Contents
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATION
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
F.2 OTHER REQUIREMENTS
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
G.2 OTHER REQUIREMENTS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES ................................................................................................................... …. 10
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF
OFFERORS OR RESPONDENTS
K.1 PROVISIONS
K.2
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
Reference attachment (J) and (K) for seed project schedule of items.
B.2 SCHEDULE NOTES
a) Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with (IAW) the terms and conditions of this contract.
b) One award will be made from this solicitation; contractors must submit pricing for all items.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
The scope of work for this contract includes a broad range of Facility Construction, Maintenance, & Repair projects. The Contractor must furnish all labor, supervision, materials, equipment, transportation, and incidentals to perform work in accordance with all terms, specifications, conditions, and provisions of this solicitation, resultant contract and associated Task Order statements of work (SOWs).
Construction-trade projects may include but are not limited to; new construction or renovation work on buildings, restrooms, pavilions, docks/piers, and administrative buildings on Savannah River Site.
C.2 PROJECT LOCATION
The work site is located on the Savannah River Site at the following address:
Savannah River Site 1-Mile Inside Aiken Barricade New Ellenton, SC 29809
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
The magnitude of construction will be determined for each project at the task order level.
C.4 TECHNICAL SPECIFICATIONS
All work must be performed in compliance with the most recent International Building Code (IBC), Uniform Plumbing Code (UPC), International Mechanical Code (IMC), National Electric Code (NEC), National Fire Protection Association (NFPA), the International Fire Code (IFC), United States Nuclear Regulatory Commission (NRC) (when applicable), the Occupational Safety and Health Administration (OSHA) regulations, and South Carolina Department of Health and Environmental Control (SC DHEC) Code that regulates water quality including drinking water, onsite septic systems, and surface water management.
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 CLAUSES
FAR 52.246-12 Inspection of Construction (AUG 1996) FAR 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
F.1 CLAUSES
FAR 52.211-13 Time Extensions (SEP 2000) FAR 52.211-18 Variation in Estimated Quantity (APR 1984) FAR 52.236-15 Schedules for Construction Contracts (APR 1984) FAR 52.242-14 Suspension of Work (APR 1984)
FAR 52.211.10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the specified completion date for each task order. The time stated for completion shall include final cleanup of the premises.
FAR 52.211-12 Liquidated Damages—Construction (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount specified in the task order award for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
F.2 OTHER REQUIREMENTS
The Contracting Officer may issue orders to suspend or stop the work wholly or in part for such period of time as deemed necessary because of:
(1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project trails which causes otherwise suitable soils to be muddy or unsuitable; or
(2) Failure of the Contractor to comply with specifications, such as but not limited to, placing of asphalts or concrete at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, or FAR 52.242-15, Stop- Work Order and shall not qualify for an equitable adjustment.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
FAR 52.216-32 Task-Order and Delivery-Order Ombudsman (Sep 2019) (Inserted “Chief, Compliance and Oversight Branch” Sm.fs.pps_cando@usda.gov” in paragraph(a)) AGAR 452.204-70 Modification for Contract Closeout
AGAR 452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held before work begins, after the date of contract award. The conference will be held at a location to be determined as agreed upon.
G.2 OTHER REQUIREMENTS
Task Orders – Request for Quote (RFQ) Procedures
a) A Task Order is a contractual instrument issued by an authorized and warranted government Contracting Officer to order work for the government.
b) As the need exists for performance under the terms of this Contract any warranted Forest Service Contracting Officer may solicit quotes and issue task orders against this contract.
c) Additional specifications may be provided with each RFQ.
d) RFQs will be transmitted primarily via e-mail.
e) RFQs may include evaluation criteria (ie: past performance, technical approach, etc.) which will require the submission of a technical proposal. All RFQs shall specify the method for award determination and indicate the required response documentation.
f) Upon the receipt of an RFQ from the Government, the Contractor shall respond as specified.
g) Contract holders will receive fair opportunity to be considered for each RFQ unless one of the exceptions in FAR subpart 16.505(b)(2) applies.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
Minimum Insurance Coverage Requirements
Pursuant to FAR clause FAR 52.228-5, Insurance-Work on a Government Installation paragraph (a), Contractors shall present evidence and maintain, as a minimum, the amounts of insurance coverage indicated below:
(1) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they must be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(2) General Liability. The Contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
(3) Automobile Liability. The Contractor must have automobile liability insurance written on a comprehensive form of policy. The policy must provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(4) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor must have aircraft public and passenger liability insurance. Coverage must be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury.
Coverage for passenger injury must be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
9PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR): https://www.acquisition.gov/browse/index/far (Clauses are located at FAR part 52 and begin with 52)
Department of Agriculture Acquisition Regulation (AGAR):https://www.acquisition.gov/agar (Clauses are located at AGAR part 452 and begin with 452)
Deviations to clauses may be viewed at: USDA FAR Class Deviations
FAR 52.202-1 Definitions (JUN 2020) FAR 52.203-3 Gratuities (APR 1984) FAR 52.203-5 Covenant against Contingent Fees (MAY 2014) FAR 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) FAR 52.203-7 Anti-Kickback Procedures (JUN 2020) FAR 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY
2014) FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) FAR 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) FAR 52.203-13 Contractor Code of Business Ethics and Conduct (NOV 2021) FAR 52.203-14 Display of Hotline Poster(s) (NOV 2021) FAR 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower Guidance to contractor employees) FAR 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
(JAN 2017)
FAR 52.204-2 Security Requirements (MAR 2021) Alternate II (APR 1984) FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-15 Service Contract Reporting Requirements for Indefinite Delivery Contracts (OCT 2016) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) FAR 52.204-21 Basic Safeguarding of Covered Contractor Information Sysrems (NOV 2021) FAR 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab Covered Entities (DEC 2023) FAR 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance
Services or Equipment (NOV 2021) FAR 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) FAR 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec 2023) FAR 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment, or Voluntarily Excluded (JAN 2025) FAR 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT
2018) FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) FAR 52.210-1 Market Research (NOV 2021) (DEVIATION JUNE 2025)
FAR 52.215-2 Audit and Records -- Negotiation (JUN 2020) FAR 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) FAR 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) FAR 52.219-8 Utilization of Small Business Concerns (JAN 2025) FAR 52.219-9 Small Business Subcontracting Plan (JAN 2025) FAR 52.219-14 Limitations on Subcontracting (OCT 2022)
☐ By the end of the base term of the contract and then by the end of each subsequent option period; or
☒ By the end of the performance period for each order issued under the contract.
FAR 52.219-16 Liquidated Damages --Subcontracting Plan (SEP 2021)
FAR 52.219-28 Postaward Small Business Program Rerepresentation (JAN 2025) FAR 52.222-3 Convict Labor (JUN 2003) FAR 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) FAR 52.222-6 Construction Wage Rate Requirement (AUG 2018) FAR 52.222-7 Withholding of Funds (MAY 2014) FAR 52.222-8 Payrolls and Basic Records (JUL 2021) FAR 52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025) FAR 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) FAR 52.222-11 Subcontracts (Labor Standards) (MAY 2014) FAR 52.222-12 Contract Termination - Debarment (MAY 2014) FAR 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
FAR 52.222-14 Disputes Concerning Labor Standards (FEB 1988) FAR 52.222-15 Certification of Eligibility (MAY 2014) FAR 52.222-35 Equal Opportunity for Veterans (JUN 2020) FAR 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) FAR 52.222-37 Employment Reports on Veterans (JUN 2020) FAR 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) FAR 52.222-50 Combating Trafficking in Persons (NOV 2021) FAR 52.222-54 Employment Eligibility Verification (JAN 2025) FAR 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN 2022) FAR 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (MAY
2024) (DEVIATION FEB 2025)
FAR 52.223-3 Hazardous Material Identification and Material Safety Data (FEB 2021)- Alternate l
(JULY 1995)
FAR 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) FAR 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons
(MAY 2024)
FAR 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air
Conditioners (MAY 2024) FAR 52.223-20 Aerosols (MAY 2024) FAR 52.223-21 Foams (MAY 2024) FAR 52.223-23 Sustainable Products & Services (MAY 2024) (DEVIATION FEB 2025) FAR 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) FAR 52.226-7 Drug-Free Workplace (MAY 2024) FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (MAY 2024) FAR 52.227-1 Authorization and Consent (JUN 2020) FAR 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) FAR 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) FAR 52.228-2 Additional Bond Security (OCT 1997) FAR 52.228-5 Insurance – Work on a Government Installation (JAN 1997)
FAR 52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY 2023) FAR 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) FAR 52.228-14 Irrevocable Letter of Credit (NOV 2014) FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION MAY 2023) FAR 52.229-3 Federal, State, and Local Taxes (FEB 2013) FAR 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) FAR 52.232-17 Interest (MAY 2014) FAR 52.232-23 Assignment of Claims (MAY 2014) FAR 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) FAR 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) FAR 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) FAR 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) FAR 52.233-3 Protest after Award (AUG 1996) FAR 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) FAR 52.236-2 Differing Site Conditions (APR 1984) FAR 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) FAR 52.236-5 Material and Workmanship (APR 1984) FAR 52.236-6 Superintendence by the Contractor (APR 1984) FAR 52.236-7 Permits and Responsibilities (NOV 1991) FAR 52.236-8 Other Contracts (APR 1984) FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
FAR 52.236-10 Operations and Storage Areas (APR 1984) FAR 52.236-11 Use and Possession Prior to Completion (APR 1984) FAR 52.236-12 Cleaning Up (APR 1984) FAR 52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) FAR 52.236-14 Availability and Use of Utility Services (APR 1984) FAR 52.236-17 Layout of Work (APR 1984) FAR 52.236-21 Specifications and Drawings for Construction (FEB 1997) Alternate I (APR 1984) Alternate II (APR 1984) FAR 52.236-26 Preconstruction Conference (FEB 1995) FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American
Security Drone Act-Covered Foreign Entities (NOV 2024) FAR 52.242-5 Payments to Small Business Subcontractors (JAN 2017) FAR 52.242-13 Bankruptcy (JUL 1995) FAR 52.243-4 Changes (JUN 2007) FAR 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2025)
(DEVIATION FEB 2025)
FAR 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) FAR 52.245-9 Use and Charges (APR 2012) FAR 52.246-21 Warranty of Construction (MAR 1994) Alternate I (MAR 1994) FAR 52.248-3 Value Engineering – Construction (OCT 2020) FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)-Alternate I
(SEP 1996)
FAR 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements) (APR 2012) FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) FAR 52.253-1 Computer Generated Forms (JAN 1991) AGAR 452.236-70 Emergency Response, Fire Suppression, and Liability
FAR 52.216-18 Ordering (AUG 2020)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from 1 November 2025 through 31 October 2030.
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) A delivery order or task order is considered “issued” when—
(1) If sent by mail (includes transmittal by U.S. mail or private delivery service), the Government deposits the order in the mail;
(2) If sent by fax, the Government transmits the order to the Contractor's fax number; or
(3) If sent electronically, the Government either—
(i) Posts a copy of the delivery order or task order to a Government document access system, and notice is sent to the Contractor; or
(ii) Distributes the delivery order or task order via email to the Contractor's email address.
(d) Orders may be issued by methods other than those enumerated in this clause only if authorized in the contract.
FAR 52.216-19 Order Limitations (Oct 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $2,000.00, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract. The Government is not obligated to award any task orders beyond the guaranteed minimum amount of $1,000.00.
(b) Maximum order. The Contractor is not obligated to honor—
(1) Any order for a single item in excess of $1,000,000.00;
(2) Any order for a combination of items in excess of $1,000,000.00; or
(3) A series of orders from the same ordering office within (5) five days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection FAR 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within (3) days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
FAR 52.216-22 Indefinite Quantity (Oct 1995)
(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”
(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after one year after the ordering period ends of this contract.
(End of clause)
FAR 52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days.
FAR 52.217-9 Option to Extend the Term of the Contract (Mar 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 7 days;
provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 5 (years).
FAR 52.225-9 Buy American Act-Construction Materials (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.
supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
(End of clause)
FAR 52.225-11 Buy American Act-Construction Materials under Trade Agreements (NOV 2023)
(a) Definitions. As used in this clause—
Caribbean Basin country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2
(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.
supply chain resiliency. The list of critical items is at FAR 25.105.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, North Macedonia, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Saint Maarten, or Trinidad and Tobago).
"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Free Trade Agreement country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
Least developed country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(4)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(4)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or…