Technical Questions and Answers SOL-CI-15-00021

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A Tab 1

ReferenceQuestionAnswer
11. Section 01 10 00 – Summary, 1.02, D.,2RFP states ….. Hazardous materials such as asbestos and lead paint may be encountered in performance of work under this contract. Asbestos reports are available for review.
Q: will the EPA provide those reports for preparation of bids?Removal of asbestos-containg materials, primarily pipe & pipe elbow insulation and flooring, has recently been completed in the main building, and no other ACM materials are known about. If ACM, lead paint, or other hazardous materials are encountered during construction, the contractor shall immediately bring it to the attention of EPA. There are no reports for the preparation of bids.
2Section 31 20 00 – Earth
Moving Part 1RFP REFERENCES, A. “Geotechnical Investigation Report, Phase 1A Laboratory Modernization, Western Ecology Building, EPA Facility, 200 SW 35th Street, Corvallis, Oregon”, Prepared by Kleinfelder, Inc., dated May 13, 2009.
Q: Will the EPA provide this report for preparation of bids?Report Attached.
3Site Visit Comment by facility Mgr.Drawing C300 shows a construction access between the Terf Building and the Annex Building. Our assumption was that the UPS trucks and owner deliveries would be made through this temp. access. During the site visit it was stated we needed to maintain access trough the construction site for the UPS / owner’s deliveries area and safety of employees at multiple. Will the EPA clarify the delivery routes and phasing plan to clarify what buildings need access?It is the intention to complete construction of Phase 1A with as little interruption of laboratory operations as feasible; however, it is recognized that construction activities must be accommodated. With that in mind, operations such as deliveries to the existing loading dock and employee pedestrian movement from the parking lot and adjacent buildings to the rear building entrance at the existing loading dock must be maintained for the time frame in which construction of Phase 1A is occurring, with intermittent closures allowed with prior approval from the PA Facility Manager / Site Represenetative. Detailed access routes and closure plans during the course of construciton shall be mutually agreed upon by the EPA Site Representative and the Contractor. (LS)
4Question about LEEDHas LEED been applied for on this project?The project is registered as a LEED NC 2009 project. The goal is Gold Certification at the end of all phases. (DB)
5Has the EPA already had environmental studies, and if so whether they have been approved.EPA has determined through its National Environmental Policy Act review and process that the project is eligible for a Categorical Exclusion according to the requirements of the appropriate sections of the Code of Federal Regulations. This process reviews, among other things, the effect of the project on the environment. EPA has also reviewed the requirements of the most recent Executive Orders concerning Climate Change Resiliency (EO 13693) and Floodplain Management (EO 13690) during the updating of the bid documents to ensure compliance with current federal requirements. (LS)
61. Specification section 01 91 13, 1.2, A1. Specification section 01 91 13, 1.2, A indicates the Commissioning Agent (CxA) is typically under contract with the owner or by the design team. Section 01 91 13 1.5 A indicates that the services of the Commissioning Agent are not included in this contract. Is the CxA on this project hired by the owner, design team, or is the GC to provide a third party CxA?The CxA is going to be procured by the government through the IDIQ with the design team. The contractor will not hire the CxA under this contract.
7LEED2. The project is to be LEED certified, and the LEED project checklist (p. 167 of the specifications) shows Enhanced commissioning (EA Cr. 3) as a source of points. In order for this credit to be achieved, it is necessary for the CxA to have reviewed the owners project requirements and basis of design prior to construction documents being issued. If the owner does not have a CxA, how will this review be accommodated to support the desired enhanced commissioning?A "Design Phase Commissioning Manual" was developed by the commissioning agent employed during design, which incorporated a review of owner requirements. A different commisisoning agent is being contracted with in order to provide construction phase commissioning.
8Specification section 01
91 13 1.73. Specification section 01 91 13 1.7 A has a table of marked systems that are to be commissioned. For LEED certification domestic hot water systems are required to be commission, but are not marked in the specification. Are domestic hot water systems to be commissioned?There are no domestic hot water systems that are a part of this phase of construction. There is domestic hot water piping in the scope, but no equipment to be commissioned.
94. Specification section 23 08 00, 3.3 F4. Specification section 23 08 00, 3.3 F indicates samples of FPT forms are provided as part of the “Design Phase Commissioning Manual”. Is this manual available for review to provided understanding of the test procedures and commitment required of the contractors?The "Design Phase Commissioning Manual" is being updated and will not be available to bidders. However, the contractor will be required to cooperate with the commissioning agenet as detailed in the specifications (01 91 13 - GENERAL COMMISSIONING REQUIREMENTS). Functional performance tests will test every element of the sequence of operations for all listed systems. Contractor shall use knowledge of the systems and the sequences identified in the drawings and specifications to estimate required effort.
10ATTACHMENT 1 STATEMENT OF WORK
Scope of Phase 1A1) Do you have any thing that lists what equipment will be installed and placed into service for this phase?

a. EF-L1 thru 4, will they be installed and placed in service under this phase? Will balancing be needed under this phase?

b. AHU-1 & 2 look to be installed but not placed in service, is this correct? Will the heating and cooling lines be hooked up and will they be balanced under this phase?

c. How much of the geothermal system will be built out? Will there be balancing needed?

d. Will the heat pumps installed under this phase?

e. Geothermal circulation pumps installed? Tested?a) yes. b) Correct, AHU-1 &2 are installed but not yet placed in service. Yes, balancing is needed under this phase. c) The complete borefield will be constructed at this time as well as all of the heat pumps. The loop is designed to be self-balancing. The pumps will be balanced on flow, but the individual circuits have balancing valves and will require balancing to evenly distribute the flow. d) The heat pumps will be installed as identified in the drawings. e.) The borefield circ. pumps will also be installed and tested.
1123 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC2) The TAB specifications request a “Pre-Construction” survey of all affected systems. Will this be limited to just the phase 1A scope or would all systems need to be completed under phase 1A?pre- construction TAB required on all mechanical systems under phase 1A.
12Specification 23 31 13 ‐ 10 of 13 section 3.8 , E.5specifications at division 23 section 3.8 calls for cleaning but referencing the old NADCA 1992. Does the EPA want this standard followed or use current standard 2013 ACR?The reference that will be enforced is the 2013 ACR standard for all duct cleaning. All existing ductwork shall be cleaned as part of this scope.
13Spec Section 230900Are there any requirements for the new DDC controls to integrate or interface with the existing Delta Control System? If so, can as-built control drawings be made available? If so, can the existing Delta System currently communicate using native BACnet IP or MSTP controllers or are they BACnet over ArcNet?Existing controls system and components to be replaced with new control system, components, and software.
14On MD113,On MD113, flag note 1 between Gridline D & E says that there are 7 exhaust fans typ. this side. There are actually 9 fans on this side, 2 of which are annotated by flag note 21. If you count the number of fans on the rest of the building annotated by flag note 1, they match the number listed even with several being annotated by flag note 21. Please confirm the total count for fans between gridline D & E is supposed to 9.Tag referenced should read "typical 9".
1523 11 13 part 2.1describes the fuel oil piping requirements as a rigid, secondarily contained piping system. We would like to propose a flexible double wall pipe system by OmegaFlex, which is designed for both above and under ground use. The primary pipe is a corrugated 316ss pipe with a UV stabilized Nylon 12 outer containment pipe. Please see attached brochure and advise if a 1” OmegaFlex pipe would be acceptable in lieu of the ¾” pipe system specified.No attachment received.
16Section 23 11 13 part 2.6DSection 23 11 13 part 2.6D calls for an interior ladder for the 2,000 gallon fuel tank specified in 23 13 00. Overall height of a 2,000 gallon ConVault tank is 5’ 3”. Please confirm if an interior ladder is required.Yes. Interior ladder required.
1723 13 00The tank specified in 23 13 00 is described as having an integral top-fill spill containment in part 1.7. As this tank is 5’ 3” tall, it is recommended to specify an external stair assembly for safe access to the fill point. Please confirm if an external stair assembly is required.Yes. External stair assembly required.
18Drawing P111 and section 23 11 13 part 2.8Drawing P111 and section 23 11 13 part 2.8 both indicate to provide a duplex pump arrangement for the fuel transfer to the day tank. No other information is given for the day tank itself. It is common for the duplex pump assembly to be factory-mounted on the day tank. Please clarify who is responsible to furnish the day tank, and if the duplex pumps are to be integrally factory-mounted of field installed by MC.Pump assembly is integral, factory mounted to day-tank system, furnished by electrical.
19Day tank capacity is not provided. Please advise the requested capacity.Reference electrical drawings and specifications.
20Fuel transfer pump capacity, voltage and horsepower are not provided. Please provide.Reference electrical drawings and specifications E401 and 26 32 13.
21Section 23 11 13 part 2.9Section 23 11 13 part 2.9 describes a fuel maintenance system, however the location of the system is not shown on the drawing sheets. Please confirm a fuel maintenance system is to be furnished and installed and, if so, where the system shall be mounted. Please confirm double wall piping is required for the fuel maintenance system.Coordinate with electrical. Double wall containment is required.
22221316 3.2 B/C above ground waste PVC is approved. D/E above ground vent PVC not listed. K Mentions PVC vent install. Is PVC acceptable for above ground ventingNo. PVC not allowed in the return air plenum.
23P112 indicated all roof drains and overflows on grid line G to terminate with a down spout nozzle. P11 does not show a below grade storm connection or storm riser. Are all roof drains to terminate with nozzles.No, there is also a trench drain connection- refer to P112 and civil.
24M121 has several circles with numbers in the middle, (FIT-100, FIT-001 Example)there is no legend or notes what these numbers mean or reference for?Refer to M605 Instrument List.
25Please confirm this project is on federal property and a building permit or city approval/inspection is not required.Confirmed. Project is on federal property and no local building permit or inspections will be required. However, the Government does require the contractor to conform to local jurisdiction and state building codes and requirements, where practical.
26Will there be any design build elements in the IDIQ?There are certain elements that will require delegated design including but not limited to the fire protection and fire alarm systems.
27Please confirm if permits and inspections from the local municipality will be required?Project is on a federal reservation and no local building permit or inspections will be required.
2801 50 00 1.11 talks about construction fencing. Do the temp fencing panels need to be set in the ground or set into a stand?It is preferred that temporary fencing will be installed in concrete blocks with two holes for fencing posts. Please coordinate with the EPA Site Representative before driving any fence posts in the ground.
29Please confirm who is paying Pacific Corp and Qwest for utility relocates as the drawings only state contractor to coordinate.Pacificorp and Caneturylink up-front charges are to be paid for by the contractor. We are currently coordinating with both utility companies to determine the charges so they can be included in the bids.
30Please provide the geo-technical report.Report Attached.
31Please confirm the depth of the water tableRefer to the geotechnical report.
32Anticipated the same level of design for the other projects.Question unclear.
33Will the design for the other task orders are provide by a third party A&E firm or in house?The design of future phases is intended to be completed by the same method the design for Phase 1A was completed, through a task order under an IDIQ contract with an A/E firm.
34Do they have a survey of existing ground conditions?As part of the project, the EPA contracted for a land survey, a thermal conductivity test and a geotechnical survey. We assume this question goes to the geotechnical survey. The report is attached.
35Will the existing loading dock be in use, if so how often will they need access?See response to Q3. It is expected that access to the existing loading dock and the pedestrian door into the building on the dock will be maintained, except for temporary closures as needed and coordinated through the EPA Site Representative.
36Will the phase three footprint area be available for locating job trailers?No.
37Please provide horizontal control locations for the NW and SW corners of the Phase Three addition for locating underground.NW: N=7807.69, E=9597.12; SW: N=7633.69, E-9597.12
38Sheet MD 113 note#4 indicates (2) condensing unit relocations for South & North penthouse. However, sheet M 113, note# 16 shows only (1) relocation at the South side. Where is the North condensing unit being relocated too?NW adjacent roof. (
39Sheet M 101 note#4 indicates 2” HPS/R lines. However sheet M121 note#2 indicates 2.5” HPS/R. Which size shall we assume?Refer to M101 and M121A for HPS/R information.
40Has the chemical reaction and safety consideration of mixing various different exhaust streams into a common header been assumed?As each phase of the laboratory renovation project is designed, the plans and specifications are rigorously reviewed by the appropriate experienced EPA personnel to help ensure for safe, healthy, secure and sustainable systems and facility areas. Manifolding of laboratory fume hood exhaust streams is one area that is carefully reviewed.
41Sheet M 600 Existing Chiller Schedule note#1 requires Eddy Current testing & baffle gasket replacements on the (2) existing centrifugal chillers.
a. Can this be done by a non-factory OEM agent?No.
b. What action plan is in place if an issue is determined to exist?Report findings to owner and engineer of record.
42Can we get a Revit file of the mechanical drawings?No.
43How long will the HVAC system (supply/exhaust) be allowed to shut down? Please define minimal downtime.To be determined by owner.
44Sheet M 111 note#15 indicates a building relief damper.
45Is relief damper barometric or mechanically/electrically actuated?Actuated.
46How and where does the relief damper ductwork terminate too?H-2
47Please clarify the nature / type(s) of laboratories that this contract will involve. For example, will work involve bio-medical laboratoriesLabs are research and analytical laboratories with biological and chemical functions in support of environmental research.
48Will the mechanical and plumbing will be coming out to bid, or has this already been awarded?The mechanical and plumbing will be bid by the general contractor as part of a single, complete project package.

Q&A Tab 2

Week of July 13, 2015
ReferenceQuestionAnswer
1A steel fab shop that does work in Oregon but does not belong to the organization AISC has asked the following request of your design team. The specifications the project is calling for the fabricator to be certified under the AISC – Certified Plant, Standard Category. This specification is usually a boiler plate inclusion by most design teams on Government projects. The requirement is usually waived especially on smaller projects such as this one. The certification will severely limit the number of fabricators that can/will submit proposals. Can the AISC certification can be waived? What is customary, is to have a 3rd party do the shop inspection of the in process steel, verify that the welders hold the proper credentials and that the means and methods to tract the heat numbers of the steel is in use.AISC Certified is required.
21. It is not clear how the structural metal studs joists are to be attached to the Steel Support beams. We have the reference on the drawing that states to use a stiffClip, how is the TSN StiffClip to be fastened to the Structural steel beam? 2. It is unclear on drawing 221/S302 if the note (N) Infill Stud Framing per G.S.N. is added in the 2’-4” wall height or is the intention to infill studs at all exterior walls of the penthouse framing? 3. If the existing walls of the penthouse are to receive infill studs, will the engineer provide the existing framing and cross bracing details to know how to locate track and studs? 4. Detail 228/S302 shows a 10” metal stud, where is this detail referencing?1. Attach stiffclip JH to steel support beams w/ (4) PAF. Connectors for Stiffclip CL's are shown in details. 2. Note referred to is on detail 223. All walls at penthouse to be new infill studs, at new wall height. 3. Infill wall is installed on top of lowest steel beam to underside of highest steel beam. cross bracing to match existing. 4. Between grids 8/8.5 along grid G as an example.
3Will the EPA verify the owner is providing and paying for the CxA? 1.2 Coordination A. Commissioning Team: The members of the commissioning team consist of the Commissioning Agent (CxA), the Owner’s Representative (PMT), the General Contractor (GC), Designers (A/E), the Mechanical Contractor (MC), the Electrical Contractor (EC), the TAB representative (TAB), the Controls Contractor (CC), the owner’s maintenance staff and any other installing subcontractors or suppliers of equipment. B. Management: 1. The CxA is typically under contract with the owner, but commissioning can also be provided under management by the design team.Owner will procure commissioning services under a separate contract.
4We received a call from the Submittal Exchange. They represent, the owner has pre-chosen them to provide services that coordinate between the owner/architect/contractor. They want to offer billing rates but not a guaranteed not to exceed price. We have no way to estimate the amount of time is allocated or needed. 1. Is the owner paying for the services of Submittal Exchange? 2. If not; for the purpose of bidding will the EPA establish an allowance for the contractors to include in their bids? 1.04 ELECTRONIC SUBMITTAL PROCEDURES A. Summary:1. Shop drawing and product data submittals, LEED submittals, requests for information (RFI’s), proposal requests, requests for change, construction schedules, change orders, field reports, meeting minutes, test reports, project record documents and closeout documents shall be transmitted to Government in electronic (PDF) format using a website service designed specifically for transmitting submittals between construction team members, as the basis of design. 2. Vendors: Subject to compliance with requirements, vendors that may be utilized for this service include, but are not limited to, the following: a. Submittal Exchange, www.submittalexchange.com1. The ower is not paying for this service. 2. The contractor shall include the cost of an electronic project management system for all of the items identified in Section 01 33 00 1.04.A.1. Submittal Exchange is approved, but many other vendors provide the same service. The contractor is free to utilize a vendor with the same basic functionality as Submittal Exchange to allow web based submittals and project communication.
Will the EPA provide an FTC (formation thermal conductivity) test report and or soils report?Yes. Reports attached.
The door schedule for the aluminum storefront door framing doesn’t seem to match the doors being called out. Pair of exterior storefront doors A119A framing is called out as hollow metal. Single door A119F seems to be correct. Single door A120A, not sure if this storefront door or a door provided by your hollow metal door supplier, the framing is called out as hollow metal. A120A might be storefront, Doors A119e and A120b appear to be hollow metal. This would be the half lite doors. Also drawn are 4” tall sills for the blast resistant storefront framing. No detail showing the product in this configuration is available. All of this information is on page A600 of the drawings, dated 5-15-2015. Clarification would be helpful. Also drawn are 4” tall sills for the blast resistant storefront framing. No detail showing the product in this configuration is available. All of this information is on page A600 of the drawings, dated 5-15-2015. Clarification would be helpful. Although not explicitly noted, the aluminum doors for the pairs and the single are drawn with mid panels on page A600. Are these indeed wanted or just a generically drawn door leaf? One exterior elevation of the single door shows without mid panels. See drawing A200, detail 3.Doors A119A, A119F, and A120A are aluminum as noted on the door schedule, remark 3 does not apply. Kawneer, the basis of design, has clarified they cannot provide the 4" high sill profile in the IR 501 series so the 2-3/4" profile is acceptable. Doors are to have the mid panels per A600.
Attachment 4 specifically calls submittal of key personnel for the project including Quality Control Manager. Phase 1A Specification section 01 45 00 discusses the QC System but does not specifically call out the requirement for a Quality Control Manager. Please confirm if a full-time, on-site Quality Control Manager, with no other duties assigned to him, is a requirement for this project?It is not required that a Quality Control Manager (QCM) be full-time or on-site full-time. The QCM position will be evaluated in terms of the requirements found in Attachment 4, and will be key in fully implementing the specified quality control system and QA/QC procedures. (LS)
Specification Section 01 81 13 – Sustainable Design and LEED Requirements. Please confirm the IDIQ/Phase 1A Contractor will not be responsible for paying USBGC/GBCI Project Registration or Certification Fees.Confirmed. Project has been registered. Fees for certification are not required as part of the Phase 1A bid.
Phase 1A Plans, Sheet E100 General Note C states “All Utility Company Charges For The Proposed New Service, Relocations, Demolition, Etc. For Electric And Telephone Utilities Shall Be Paid By The Contractor And Included In The Bid.” Since the EPA and Project Designers have obviously coordinated this design closely with the electric (Pacificorp) and telephone (Centurylink) and to ensure the EPA receives the best possible pricing possible on this project, we strongly suggest the EPA provided Allowances for these utility company fees. If this is not possible, please provide contact names, phone numbers, and email addresses for the correct points of contact at each of these firms so as ensure all offerors are being provided with the same information.Pacific Power has responded with:

- Upgrade to new service (and removal costs) = $43,000.00

- buy-out contract so no facilities charge = $12,600.00

- Accommodation work on SW Jefferson Way = $25,200.00 Pacific Power Total: $80,800

Pacific Power:

Kristi Wheeler Journeyman Estimator

541.967.6195 Office

kristi.wheeler@pacificorp.com

CenturyLink does not charge the customer in Corvallis for work in the publich right of way.

CenturyLink Total: $0

CenturyLink:

Kerry Pozder 541.259.7275 Kerry.Podzer@CenturyLink.com

Phase 1 Sheet C600, Detail 2 – Permeable Interlocking Concrete Pavers. What is the required epth of the Subbase Stone (ASTM No. 2). Cannot find this indicated on the documents.12 inches. The dimension is on the detail, but difficult to see through the hatching. Zoom in on the sub-base hatching.
Please confirm the Aggregate Base requirements for the Phase 1A building addition. There is a note referencing the geotechnical report but cannot find the geotechnical report either.Report attached.
Specification Section 31 10 00, Item 1.2 – list a “Geotechncial Investigation Report, Phase 1A Laboratory Modernization, Western Ecology Building, EPA Facility, 200 SW 35tth Street, Corvallis, Oregon”, Prepared by Kleinfelder, Inc., dated May 13, 2009. We cannot locate this document in the Solicitation documents. Please provide to all Offerors.Attached0
Phase 1 Sheet S302, Detail 223 – Penthouse Graming Section. 1 note states “(N) Infill Stud Framing Per G.S.N”. Please clarify. What is G.S.N? Does this apply to all of the penthouse areas that received new metal wall panels?GSN = General Structural Notes, sheets S001 & S002 (see abbreviation schedule). Yes, new penthouse wall studs for new wall panels.