RFP No. SOL 294-17-000002 Amendment No. 3 Annex 1 Part B
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Implemented by AECOM
USAID/ West Bank & Gaza Architecture and Engineering Services
YATTA DISTRIBUTION NETWORK
REHABILITATION AND EXTENSION
PROJECT
BUILDING FOUNDATIONS IDIQ
18 January 2017
Pre Bid Meeting 9:30 – 10:15
• Procedures
• RFTOP Example Items
• Environmental and Technical Overview
Site Visit 12:30 – 14:30
AGENDA
• Nothing said or presented during the Pre-Bid Meeting or site visit shall be construed as a change to the RFP
• All questions shall be made in writing
– See RFP Section L5
PROCEDURES
Section Item
B.2 Contract Type B.3 Budget
Firm Fixed Unit Price Day works—$850,000
C.4 Requirements of Note Permits, CMC Field Offices Testing Labs, Safety Plan Traffic Control, other
D.2 Branding Strategy BIP Required Temporary & Permanent Project Signs (8 ea.)
F.2 Period of Performance 480 Calendar days from NTP
F.6 Liquidated Damages Daily Rate - $4,574
H.2 Key Personnel Task Order Manager Quality Control Manager Safety & Environmental Compliance Officer
RFTOP EXAMPLE ITEMS
REQUIREMENTS
• USAID Environmental Compliance Procedures
(22CFR216)
• Palestinian applicable laws
• Approved Environmental Review report
• Contractor’s MMP
OVERVIEW OF RESPONSIBILITIES
• Contractor: Implement, Mitigate and Monitor during all construction related activities
• CMC: Oversight
ENVIRONMENTAL COMPLIANCE (1)
CONTRACTOR REQUIREMENTS
Coordination with local authorities where required, including issues related to:
• Rights-of-way
Work located within narrow roads in villages through residential and school areas:
• Inform the public in advance about construction activities
• Implement dust and noise control practices
• Implement approved safety and traffic plans
ENVIRONMENTAL COMPLIANCE (2)
CONTRACTOR REQUIREMENTS (continued)
Private agricultural lands and open areas:
• Prohibit unapproved disposal or storage of construction materials and waste
• Protect existing vegetation and trees, and potentially present wild life in open areas
Utilities (above and underground):
• Identify and coordinate with appropriate authorities/owners
• Avoid any damage to existing utilities, including cesspits
ENVIRONMENTAL COMPLIANCE (3)
• Provide reliable, safe and affordable water supply and storage system for Yatta City and the nearby Beit Emra village
• Replace existing deteriorated distribution pipeline
• Provide water supply for unserved Areas (20,000 inhabitants) in Yatta City
OBJECTIVES OF PROJECT
WATER SUPPLY SOURCES
• PWA: Al-Reehya Well, Bani Naim Wells, Abu Al-Ashoush
Reservoir
• Mekorot pipeline
YATTA OVERVIEW MAP
SCHEMATIC FLOW DIAGRAM
PIPELINE ROUTES
• Work in commercial and residential areas
• Traffic and pedestrian movement
• Above ground and underground utilities
• Nearby agricultural lands and greenhouses
• Old stone walls (non-archaeological)
• Beit Emra—pipeline passes cliff cuts and near stone quarries
• Cesspits may exist within rights of way
SITE SPECIFIC CONCERNS
TRANSMISSION PIPELINE ROUTE
• At Grade
– 25.25 m inner diameter
– 10 m water height
• About 5 meter of soil will be replaced under the reservoir due to cavity in the ground
• Designated Site areas will be paved
• Inlet pipe 250 mm
• Outlet pipe 300 mm
KHALLET SALEEM RESERVOIR (5000 CM)
KHALLET SALEEM RESERVOIR (SITE PLAN)
KHALLET SALEEM RESERVOIR (SECTION)
• Residences in the vicinity
• Telecommunications towers
• Caves surrounding the proposed sites (not archeological)
• Open agricultural land (olive and almond)
SITE SPECIFIC CONCERNS—
KHALLET SALEEM RESERVOIR SITE
• At Grade
– 16.3 m inner diameter
– 5 m water height
• A small structure will be demolished by municipality
• Designated site areas will be paved
• Inlet pipe 300 mm
• Outlet pipe 300 mm
SCHOOLS RESERVOIR (1000 CM)
SCHOOLS RESERVOIR (SITE PLAN)
SCHOOLS RESERVOIR (SECTION)
• Construction activities located within school compound can not be conducted during school hours
• Mature Cypress and evergreen trees—to be relocated
• Nearby sanitation unit to be demolished by the municipality
• Nearby rainwater harvesting cistern
SCHOOLS RESERVOIR SITE
• Elevated
– 11.5 m x 11.5 m square
– 4.3 m water height
• Designated site areas and 125 m access road will be paved
• Inlet pipe 150 mm
• Outlet pipe 150 mm
BEIT EMRA RESERVOIR (500 CM)
BEIT EMRA RESERVOIR (SITE PLAN)
BEIT EMRA RESERVOIR (SECTION)
• Residences adjacent to the reservoir location
• Nearby olive tree orchards
• Unpaved access road with existing stone walls
• Electrical utilities within access road
BEIT EMRA RESERVOIR SITE
• Working Area: All components are located in Areas A and B
• ICA: NOL received from COGAT in the absence of JWC
• PWA Construction Permit: Obtained
PERMITS
SITE VISIT @ 12:30 IN THE MEETING POINT
Arrival Departure
Stop #1: Meeting Point (Start of project) 12:30 12:45
Stop #2: Schools Reservoir 13:00 13:15
Stop #3: Reehya Junction 13:25 13:35
Stop #4: Khallet Saleem Reservoir 13:45 14:00
Stop #5: Reehya Reservoir 14:20 14:30
SITE VISIT SCHEDULE
| YATTA DISTRIBUTION NETWORK REHABILITATION AND EXTENSION PROJECT��building foundations IDIQ |
| Agenda |
| Procedures |
| RFTOP EXAMPLE Items |
| ENVIRONMENTAL COMPLIANCE (1) |
| ENVIRONMENTAL COMPLIANCE (2) |
| ENVIRONMENTAL COMPLIANCE (3) |
| Objectives of Project |
| Yatta overview Map |
| Schematic Flow Diagram |
| Site Specific Concerns |
| Transmission Pipeline Route |
| Khallet Saleem Reservoir (5000 CM) |
| Khallet Saleem Reservoir (SITE PLAN) |
| Khallet Saleem Reservoir (SECTION) |
| Site Specific Concerns—�Khallet Saleem Reservoir Site |
| Schools Reservoir (1000 CM) |
| Schools Reservoir (SITE PLAN) |
| Schools Reservoir (SECTION) |
| Site Specific Concerns—�Schools Reservoir Site |
| Beit Emra Reservoir (500 CM) |
| Beit Emra Reservoir (SITE PLAN) |
| Beit Emra Reservoir (SECTION) |
| Site Specific Concerns—�Beit Emra Reservoir Site |
| Permits |
| Site Visit @ 12:30 in the Meeting Point |
| Site Visit Schedule |