This is a Request for Quotation (RFQ) for repair of fire suppression deficiencies at Yosemite National Park in California. The solicitation number is 140P8526Q0110, issued August 17, 2026, with offers due September 3, 2026, at 2:00 PM local time. The National Park Service (NPS), Pacific West Region, is the contracting agency, with Tim Modjeski serving as the Contracting Officer.

The contractor must perform comprehensive fire suppression system repairs at approximately 40 parkwide locations across multiple districts (El Portal, Yosemite Valley, Wawona, and Mather), including field review of deficiencies, required repairs, replacement of recalled or outdated components, and annual or 5-year interval testing and inspections to achieve passing inspection reports. All work must be completed within 120 calendar days following receipt of notice to proceed, with performance commencing within 10 days of notification. The contract requires performance and payment bonds equal to 100 percent of the contract price. This is a 100 percent Total Small Business Set-Aside under NAICS code 238290 (small business size standard: $22,000,000 in average annual receipts). Davis-Bacon wage rates apply for Mariposa County, California. Award will be made on a firm fixed-price basis using simplified acquisition procedures, evaluated on price, prior experience (three to five relevant projects within the past five years), and proposed project schedule. A bid guarantee of 20 percent of total proposal price or $3,000,000 (whichever is less) is required. Contractors must provide a site-specific safety and health plan, designate key personnel (superintendent and project manager), maintain liability insurance at $100,000 per person/$500,000 per occurrence/$100,000 property damage, and submit invoices electronically through the Treasury's Invoice Processing Platform (IPP). Buy American requirements apply to construction materials, and contractors are prohibited from using All-Terrain Vehicles (ATVs) on National Park Service lands.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140P8526Q0110

NPS, PWR - SF/SEA MABO

333 Bush Street Suite 500 San Francisco CA 94104 timothy_modjeski@ios.doi.gov

PPO

Timothy Modjeski 3038199916

08/17/2026

09/03/2026

10 120 Clause F.1

Repair Fire Suppression Deficiencies at Parkwide Yosemite Locations

YOSE has a need for repair of fire system deficiencies identified during the annual inspection and testing. After repairs are made to the systems, interval testing and inspections (annual or 5-year) will be performed to achieve a passing report for the fire suppression systems. The Contractor shall provide all mobilization, labor, supervision, materials, equipment, transportation, site rehabilitation, clean-up, and demobilization. All work shall be completed in strict accordance with the Statement of

Work.

1 28

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

DOI, NPS, PWR - SF/SEA MABO

333 Bush Street Suite 500 San Francisco CA 94104

PPO

Timothy Modjeski

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P8526Q0110

00010 HISTORIC HOUSING SYSTEM REPAIRS

Product/Service Code: Z1FA

Product/Service Description: MAINTENANCE OF

FAMILY HOUSING FACILITIES

00020 HOUSING SYSTEM REPAIRS

Product/Service Code: Z1FA

Product/Service Description: MAINTENANCE OF

FAMILY HOUSING FACILITIES

RFQ 140P8526Q0110 Page 4 of 28

GENERAL INFORMATION:

This is a COMBINED SYNOPSIS / SOLICITATION for commercial items prepared in accordance with the format in the Federal Acquisition Regulations (FAR) Subpart 12.6, as supplemented with additional information included in this notice. The National Park Service contemplates award of a firm fixed price contract as a result of this combined synopsis/solicitation to the vendor. This announcement constitutes the only solicitation issued as Request for Quotation (RFQ) 140P8526Q0110. A WRITTEN SOLICITATION WILL NOT BE ISSUED. FAR clauses and provisions enclosed within this RFQ are those in effect through Federal Acquisition Circular (FAC) 2026-01 and the Revolutionary FAR Overhaul updates currently enacted by DOI Deviations and are available in full text through Internet access at http:// www.acquisition.gov/far/.

NOTE: System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Point of Contact:

Name: Tim Modjeski Email: timothy_modjeski@ios.doi.gov Telephone: (303)819-9916

This acquisition is for Repair Fire Suppression Deficiencies at Parkwide Yosemite Locations in support of Yosemite National Park, CA.

This is a 100% Total Small Business Set-Aside. The North American Industry Classification System (NAICS) code is 238290. The small business size standard is $22,000,000 in average annual receipts.

Solicitation documents can also be found at

140P8526Q0110 - Repair Fire Suppression Deficiencies at Parkwide Yosemite Locations - Documents - 140P8526Q0110 - All Documents http://www.acquisition.gov/far/ https://doimspp.sharepoint.com/sites/nps-pwr-140P8526Q0106/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2Fnps%2Dpwr%2D140P8526Q0106%2FShared%20Documents%2F140P8526Q0110&viewid=de248ae0%2Df918%2D4254%2Da276%2D37c3ebefae02 https://doimspp.sharepoint.com/sites/nps-pwr-140P8526Q0106/Shared%20Documents/Forms/AllItems.aspx?id=%2Fsites%2Fnps%2Dpwr%2D140P8526Q0106%2FShared%20Documents%2F140P8526Q0110&viewid=de248ae0%2Df918%2D4254%2Da276%2D37c3ebefae02

RFQ 140P8526Q0110 Page 5 of 28

Award Selection Process:

Award will be made to the offeror that provides the best value to the government using simplified procedures (FAR Part 12.201). In accordance with FAR Part 12.203(c), the evaluation will be conducted by a comparative evaluation of offerors. This solicitation is not stating nor required to state the relative importance assigned to each evaluation factor and/or sub factor (FAR 12.203(c)(2)).

1. Price.

2. Prior experiences: The Government will evaluate the firm’s prior experience to determine its ability to best meet the Government’s requirement.

3. Project schedule: The Government will evaluate the Offeror’s proposed schedule to determine the likelihood of completing all required inspections, repairs, and testing across all 40 locations within the required 120-day period of performance.

RFQ 140P8526Q0110 Page 6 of 28

INSTRUCTIONS TO OFFERORS:

Quotes must be in accordance with and in the order detailed in this section. Failure to submit quotes according to the instructions provided within the solicitation may result in the respondent’s quote not being considered for award.

All interested parties shall be registered in the System for Award Management or SAM at time an offer or quotation is submitted. The offerors shall submit a quote to the contracting specialist by email to timothy.modjeski@ios.doi.gov.

Contractor questions shall submitted by email to timothy.modjeski@ios.doi.gov no later than August 27, 2026.

Offerors shall submit the following information in its entirety:

a) Checklist for quote submittal:

• This page of the solicitation completed as the first page in the package

• Signed acknowledgement of SF1442

• All amendments acknowledged using one of the methods set forth in Box 11 of the SF-30, if applicable

• Completed Provisions (as applicable)

• Completed clause H.2

• Completed Price Schedule

• Three to five prior experiences of projects in similar size and scope within the past five years to include:

o Brief description of project o Point of contact information

• Proposed schedule. The proposed schedule shall logically account for field review of deficiencies, required repairs (varied by location), replacement of recalled or outdated components, and testing and inspections (annual and 5-year interval) within the required 120-day period of performance.

• Bid Bond

b) Contractor Core Data:

Offerors Name: _________________________________________________________________________________

Offerors Address: _______________________________________________________________________________

Offerors Unique Entity Identifier (UEI): ______________________________________________________________

Offerors POC: __________________________________________________________________________________

Offerors Phone/Email: ___________________________________________________________________________ mailto:timothy.modjeski@ios.doi.gov mailto:timothy.modjeski@ios.doi.gov

RFQ 140P8526Q0110 Page 7 of 28

Clauses Section

F.1 Commencement, Prosecution, and Completion of Work

The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, prosecute the work diligently, and complete the entire work ready for use not later than 120 days following receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

G.1 – Contract Administration

The Contracting Officer's Representative (COR) for this contract will be:

Carrie Toepper Supervisory Facility Operations Specialist Yosemite National Park

(209) 379-1089 Carrie_Toepper@nps.gov

The Contract Specialist for this contract will be:

Tim Modjeski Contracting Officer Department of the Interior ConOps West / Yosemite MABO

(303) 819-9916 Timothy_Modjeski@ios.doi.gov

The Contracting Officer for this contract will be:

Tim Modjeski Contracting Officer Department of the Interior ConOps West / Yosemite MABO

(303) 819-9916 Timothy_Modjeski@ios.doi.gov

G.2 – CORRESPONDENCE

Copies of all correspondence and written notices between the Contracting Officer’s Representative and the Contractor shall be sent to the cognizant Contract Specialist at the address below, or by email. All correspondence sent by email shall state the contract number in the subject line of the email.

mailto:Carrie_Toepper@nps.gov

RFQ 140P8526Q0110 Page 8 of 28

Contract Specialist responsible for administering this contract:

Tim Modjeski Contracting Officer

(303) 819-9916 Timothy_Modjeski@ios.doi.gov (End of Clause)

G.3 – Appointment of Contractor Representative/Superintendent

Prior to the commencement of work under this contract, the Contractor shall provide the Contracting Officer with the name and telephone number of at least one responsible individual who will be available on a daily basis to respond to operational problems and/or emergencies. In the event the contract involves more than one subcontractor, the designated site superintendent shall be a W-2 employee of the prime contractor. The Contractor agrees that notice to the designated representative shall constitute notice to the Contractor and further agrees to be bound by any commitments or representations made by such representative.

(End of Clause)

G.4 –1452.201-70 – Authorities and Delegations (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority.

The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the

RFQ 140P8526Q0110 Page 9 of 28

COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of Clause)

G.5 – 1452.204-70 – Release of Claims – Department of the Interior (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of Clause)

G.6 – Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at:

https://www.doi.gov/pam/acquisition/policy/constructioncontract.

(End of clause)

G.7 – Notice to Contractors – Contractor Performance Assessment Reporting System

In accordance with DOI and NPS policy, past performance evaluations may be prepared for this acquisition. For more information see the Contractor Performance Assessment Reporting System (CPARS), available online at https://cpars.gov/.

https://www.doi.gov/pam/acquisition/policy/constructioncontract https://cpars.gov/

RFQ 140P8526Q0110 Page 10 of 28

H.1 – SITE SPECIFIC SAFETY AND HEALTH PLAN

A site-specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site-specific plan. The site-specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site-specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site-specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.

As work proceeds, the site-specific safety and health plan shall be adapted to new situations and new conditions. Changes and modifications to the accepted site-specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office.

Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.

Prior to submittal to the COR, the site-specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site-specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site-specific safety and health plan for review and approval by the safety office.

Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.

H.2 – KEY PERSONNEL

(a) The Contractor shall assign to this contract the following key personnel:

Superintendent: ____________________________________________

Project Manager: ___________________________________________

(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 10 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90 day period, the

RFQ 140P8526Q0110 Page 11 of 28

Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 10 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 10 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.

H.3 – SEASONAL SHUTDOWN

It is recognized that seasonal climatic conditions regularly occur in some of the National Park Service areas that restrict and, in some cases, prohibit normal construction activities. The actual timing of a seasonal shutdown will be determined by mutual agreement between the Contractor and the Contracting Officer. The Contractor shall give the Contracting Officer at least two weeks’ notice prior to the anticipated resumption of work. The actual date that work is resumed is subject to the approval of the Contracting Officer. The amount of time during a seasonal shutdown is taken into consideration when the completion time as stated in the Contract is determined. Therefore, the contract time will not be extended due to seasonal shutdowns.

H.4 – Wage Rates

Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section J). The project is located in Mariposa County, California.

(End of Clause)

H.5 – Workers Compensation

The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of Section 3700 of the Labor Code of the State of California. Evidence of coverage is required before commencement of project work.

(End of Clause)

I.1 ARCHEOLOGICAL FINDINGS

(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for

RFQ 140P8526Q0110 Page 12 of 28

Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.

I.2 CONDUCT OF OPERATIONS

At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.

I.4 CONSTRUCTION CONTRACT ADMINISTRATION

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at:

https://www.doi.gov/pam/acquisition/policy/constructioncontract.

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety

FAR 52.225-9 Buy American–Construction Materials OCT 2022 https://www.doi.gov/pam/acquisition/policy/constructioncontract https://www.acquisition.gov/far/part-2#FAR_2_101

RFQ 140P8526Q0110 Page 13 of 28 systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as https://www.acquisition.gov/far/part-25#FAR_25_105

RFQ 140P8526Q0110 Page 14 of 28 foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None.

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505

RFQ 140P8526Q0110 Page 15 of 28

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at

FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

RFQ 140P8526Q0110 Page 16 of 28

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price (dollars) * Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material

RFQ 140P8526Q0110 Page 17 of 28

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

(End of Clause)

(a) Definitions. As used in this clause-

Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance bonds ( Standard Form 25), except that a seal is not required. The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds ( Standard Form 25A), except that a seal is not required. The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

FAR 52.228-

15 Performance and Payment Bonds-Construction

JUN 2020

(DEVIATION

MAY 2023)

https://www.acquisition.gov/far/subpart-28.1#FAR_28_102_1 https://www.gsa.gov/forms-library/performance-bond https://www.gsa.gov/forms-library/payment-bond

RFQ 140P8526Q0110 Page 18 of 28

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection ( 40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

(End of clause)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

FAR 52.246-

12 Inspection of Construction AUG 1996 http://www.fms.treas.gov/c570/ http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3

RFQ 140P8526Q0110 Page 19 of 28

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of Clause)

RFQ 140P8526Q0110 Page 20 of 28

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://www.acquisition.gov/far/ https://www.acquisition.gov/diar https://www.acquisition.gov/caac-letters https://www.acquisition.gov/far-overhaul

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Department of Interior Regulation (48 CFR, Chapter 14) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

(End of clause)

52.212-4 Contract Terms and Conditions – Commercial Products and Commercial Services (DEVIATION) (Nov 2023)

52.203-17 Contractor Employee Whistleblower Rights (NOV 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-13 System for Award Management—Maintenance (Oct 2018) (DEVIATION Mar 2026)

52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JAN 2025)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.219-6 Notice of Total Small Business Set-Aside (DEVIATION JAN 2026)

52.219-33 Nonmanufacturer Rule (Sept 2021) (DEVIATION Jan 2026)

52.222-3 Convict Labor (Jun 2003)

52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination-Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations ( MAY 2014)

FAR 52.252-2 Clauses Incorporated by Reference FEB 1998

FAR 52.252-6 Authorized Deviation in Clauses NOV 2020 http://www.acquisition.gov/far/ https://www.acquisition.gov/diar https://www.acquisition.gov/caac-letters https://www.acquisition.gov/far-overhaul

RFQ 140P8526Q0110 Page 21 of 28

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Mar 2026)

52.222-35 Equal Opportunity for Veterans (Jun 2020)

52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

52.222-37 Employment Reports on Veterans (JUN 2020)

52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014)

52.222-50 Combating Trafficking in Persons (Oct 2025)

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

52.223-23 Sustainable Products and Services (May 2024)

52.225-1 Buy American-Supplies (Oct 2022)

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024)

52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Individual Surety—Pledges of Assets (FEB 2021) (DEVIATION May 2023) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014)

52.232-23 Assignment of Claims (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer—System for Award Management (Oct 2018)

52.232-36 Payment by Third Party (May 2014)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)

52.233-3 Protest After Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions (APR 1984) (DEVIATION JAN 2026)

52.236-5 Material and Workmanship (APR 1984) (DEVIATION JAN 2026)

52.236-6 Superintendence by the Contractor (APR 1984) (DEVIATION JAN 2026)

52.236-7 Permits and Responsibilities (NOV 1991) (DEVIATION JAN 2026)

52.240-91 Security Prohibitions and Exclusions (DEVIATION Mar 2026)

52.243-5 Changes and Changed Conditions (APR 1984)

52.244-6 Subcontracts for Commercial Products and Commercial Services (APR 2026) (DEVIATION

APR 2026)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984)

RFQ 140P8526Q0110 Page 22 of 28

(a) Definitions. As used in this clause—

Program participation means membership or participation in, or access or admission to: training, mentoring, or leadership development programs; educational opportunities; clubs; associations; or similar opportunities that are sponsored…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .