This is a Request for Proposal (RFP) for replacing surveillance cameras at Shenandoah National Park in Virginia. The National Park Service seeks a small business contractor to remove existing cameras and install new NDAA-compliant, Milestone-compatible outdoor security cameras at four entrance stations (located at Mile 1, Mile 31, Mile 65, and Mile 105 along Skyline Drive). The contract includes two optional line items for additional camera installations at the Byrd Visitor Center and Dickey Ridge Visitor Center. The base contract includes 40 cameras, camera mounts, weatherproof housings, conduit, wiring, network switches, and associated labor for electrical and IT integration, with a performance period of 90 calendar days from notice to proceed.
The solicitation is a small business set-aside with an estimated project value between $100,000 and $250,000 under NAICS code 238210 (Electrical Contractors). The contract will be awarded using a best value source selection process with a Lowest Price Technically Acceptable evaluation method. Contractors must submit technical and past performance information demonstrating capability to perform the work, along with a completed bid schedule. An organized site visit is scheduled for December 18, 2025, at the Front Royal Entrance Station. Wage rates will be determined by Davis-Bacon wage determinations for the North, Central, and South Districts of Virginia.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4226Q0001_Amd_0003.pdf | ||
| 140P4226Q0001_Q_and_A_II_0003.docx | DOCX document | |
| Revised_Statement_of_Work_0002.docx | DOCX document | |
| Sol_140P4226Q0001_Amd_0002.pdf | ||
| 140P4226Q0001_Q_and_A_0002.docx | DOCX document | |
| Sol_140P4226Q0001_Amd_0001.pdf | ||
| Photos_of_existing_camera_locations_0001.pdf | ||
| B08_Attachment_007_Wage_Determination_-_WD_VA20250014_-_South_District.pdf | ||
| B08_Attachment_006_Wage_Determination_-_WD_VA20250168_-_North_District.pdf | ||
| Subcontracting_Percentage_Worksheet.docx | DOCX document | |
| B08_Attachment_005_Wage_Determination_-_WD_VA20250008_-_Central_District.pdf | ||
| B08_Attachment_003_Bid_Schedule.docx | DOCX document | |
| Statement_of_Work.docx | DOCX document | |
| Shenandoah_NP_Map.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0044016401
DOI, NPS, NERO & NER SOUTH MABO
National Park Service
Northeast Regional Contracting South/Philadelphia MABO
PNC
1234 Market Street, 20th Floor
Philadelphia PA 19107
Deborah Coles 5406770325
PMIS 253478
12/12/2025
140P4226Q0001
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Attachment 001: Scope of Work, 14 pages
Attachment 002: Shenandoah NP Map, 1 page
Attachment 003: Bid Schedule, 3 pages
Attachment 004: Subcontractor Percentage Worksheet, 2 pages
Attachment 005: Wage Determination, WD VA20250008 dated 9/19/2025, North District, 5 pages
Attachment 006: Wage Determination, WD VA20250168 dated 9/19/2025, Central
District, 7 pages
Attachment 007: Wage Determination, WD VA20250014 dated 9/19/2025, South District, 6 pages
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 90 calendar days and complete it within ________________ ________________ calendar days after receiving
Clause 52.211-10
01/12/2026
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
DOI, NPS, NERO & NER SOUTH MABO
National Park Service
Northeast Regional Contracting South/Philadelphia MABO
PNC
1234 Market Street, 20th Floor
Philadelphia PA 19107
Deborah Coles
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 56
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P4226Q0001
Replace surveillance cameras at various locations throughout Shenandoah National Park (SHEN) in
Virginia
PROCURMENT TYPE: The Government anticipates awarding a single firm-fixed price contract to meet this requirement. This firm-fixed price contract will be awarded using best value as the source selection process in accordance with FAR
Part 13. Accordingly, we are requesting you review the information within the solicitation and attachments.
SET-ASIDE TYPE: This is small business set-aside acquisition. All responsible sources may submit an offer for consideration in accordance with these and other terms and conditions of the anticipated solicitation.
NAICS CODE: 238210; Electrical Contractors and
Other Wiring Installation Contractors, size standard of $19M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between
$100,000.00 and $250,000.00.
WAGE RATES: Davis Bacon General Wage Decision
Number: VA20250008, VA20250168, and VA20250014.
Construction Type: Building
DURATION: The contract performance period is expected to be 90 calendar days from notice to proceed; the period of performance is negotiable.
SITE VISIT: An organized site visit has been scheduled for Thursday, December 18, 2025 at
10:00 AM ET. Point of contact: Russell Griswold, email: russell_griswold@nps.gov; Debbie Coles, email: debbie_coles@nps.gov. See provision
52.236-27 site visit for further details
Delivery: 90 Days After Notice to Proceed
Delivery Location Code: 0011282874
NPS, Shenandoah National Park
Headquarters
3655 US HWY 211 East
Luray VA 22835 US
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 56
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P4226Q0001
Period of Performance: 01/19/2026 to 04/30/2026
00010 Remove and install surveillance cameras at entrance stations at Shenandoah National Park in
Virginia as described in the attached Scope of
Work.
Product/Service Code: 7J20
Product/Service Description: IT AND TELECOM -
SECURITY AND COMPLIANCE PRODUCTS (HARDWARE AND
PERPETUAL LICENSE SOFTWARE)
00020 Optional Activity 1: Install one surveillance camera at the Byrd Visitor Center as described in the attached Scope of Work
(Option Line Item)
Anticipated Exercise Date 30
Product/Service Code: 7J20
Product/Service Description: IT AND TELECOM -
SECURITY AND COMPLIANCE PRODUCTS (HARDWARE AND
PERPETUAL LICENSE SOFTWARE)
00030 Optional Activity 2: Install two surveillance cameras at Dickey Ridge Visitor Center as described in the attached Scope of Work
(Option Line Item)
Anticipated Exercise Date 30
Product/Service Code: 7J20
Product/Service Description: IT AND TELECOM -
SECURITY AND COMPLIANCE PRODUCTS (HARDWARE AND
PERPETUAL LICENSE SOFTWARE)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation No.
140P4226Q0001
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 5 of 50
TABLE OF CONTENTS
PART I - THE SCHEDULE
SECTION A- SOLICITATION/ CONTRACT FORM
SECTION B - BID SCHEDULE
SECTION C - SPECIFICATIONS/ DRAWINGS
SECTION D - PACKAGING AND MARKING
SECTION E- INSPECTION AND ACCEPTANCE
SECTION F - DELIVERIES OR PERFORMANCE
SECTION G-CONTRACT ADMINISTRATION DATA
SECTION H-SPECIAL CONTRACT REQUIREMENTS
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
PART Ill - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J - LIST OF ATTACHMENTS
PART IV- REPRESENTATIONS AND INSTRUCTIONS
SECTION K- REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS
OF OFFERORS
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
SECTION M - EVALUATION FACTORS FOR AWARD
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 6 of 50
PART I - THE SCHEDULE
SECTION A - SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF-1442)- pages 1- 4 of this package
52.252-2 - Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov http://www.acquisition.gov/
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 7 of 50
SECTION B - BID SCHEDULE
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars.
Refer to section "H" of this solicitation for additional information regarding contract options.
BASE CLIN 001
Item Unit Quantity Unit Cost Total Cost
Removal of existing cameras and wiring at four entrance stations LS 4
NDAA-compliant security cameras (outdoor, Milestone-compatible) EA 40
Camera mounts and weatherproof housings EA 40
Conduit and wiring (CAT6 & powers) LF 800
Network switches and PoE injectors EA 4
Labor (electrical & IT integration) HR 223
Testing and Commissioning LS 4
Training for park staff LS 1
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 8 of 50
Option CLIN 1 – Byrd Visitor Center
Item Unit Quantity Unit Cost Total Cost Camera EA 1
Mounts and weatherproofing EA 1
Wiring and Network Equipment EA 1
Labor/Installation HR 7
Testing & Commissioning LS 1
Option CLIN 2 – Dickey Ridge Visitor Center
Item Unit Quantity Unit Cost Total Cost Camera (including denio of existing)
EA 2
Mounts and weatherproofing EA 2
Wiring and Network Equipment
EA 1
Labor/Installation HR 7
Testing & Commissioning LS 1
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 9 of 50
SECTION C - SPECIFICATIONS/DRAWINGS
The work of this contract is for the replacement of surveillance cameras at four entrance stations.
Project Location: Shenandoah National Park in Virginia. The physical location of the facilities is from North to South at Mile 1, Mile 31, Mile 65 and Mile 105 along Skyline Drive. Two Line-Item Options will be two Visitor Centers which are located at Mile 5 and Mile 50. See attachment 002 – Shenandoah National Park Map
Project Description:
The work will involve the removal of existing cameras, wiring, and conduit at six designated locations throughout the park. Following the removal, new cameras, wiring, and necessary conduit will be installed.
Additionally, the project will include network programming to integrate the new cameras into the park's communications system, enabling remote monitoring capabilities. This upgrade will enhance surveillance efficiency and improve the park's overall security infrastructure.
The requirement incudes two optional line items
Specifications and drawings are attached and incorporated herein by reference. Refer to section J.
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 10 of 50
SECTION D - PACKAGING AND MARKING
No clauses included
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 11 of 50
SECTION E - INSPECTION AND ACCEPTANCE
52.246-12 Inspection of Construction (Aug 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 12 of 50
SECTION F - DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days (negotiable) after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 11/1/2025. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.242-14 SUSPENSION OF WORK (APR 1984)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 13 of 50
SECTION G - CONTRACT ADMINISTRATION DATA
(a) Contact Information:
Contracting Officer administrating the Contract:
Deborah Coles Contracting Officer National Park Service ConOps East, PA MABO Telephone No. (540)677-0325 Email: Debbie_Coles@nps.gov
(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.
(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.
(d) Any request for contract changes/modifications shall be submitted to the CO.
(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items. All field changes must be approved by the CO prior to execution.
(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.
FINAL PAYMENT
Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.
AVAILABILITY OF UTILITIES SERVICES
Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.
UTILITIES CONSERVATION
The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.
OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS
The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.
mailto:Debbie_Coles@nps.gov
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 14 of 50
INTERIM AND FINAL INSPECTIONS
1. Prior to covering, enclosing, or hiding any type of work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative to perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.
2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.
3. The final inspection will be onsite with the Contractor, the Contracting Officer's Representative, and Contract Specialist/Contracting Officer (when possible).
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 15 of 50
1452.204-70 RELEASE OF CLAIMS-DEPARTMENT OF THE INTERIOR (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (Dl-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.g
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at_https://www.cpars.g
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting "Accept the Ratings and Close the Evaluation".
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as "Pending" with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
http://www.cpars.g/ http://www.cpars.g/
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 16 of 50
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS-INTERNET PAYMENT PLATFORM (APR 2013) Payment requests must be submitted electronically through the U.S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is:_https://www.ipp.g
The contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service's (NPS) Contracting Officer's Representative (COR) a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to the contractor. If the COR recommends acceptance, the contractor shall submit a copy of the final version of the COR's checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the COR's final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments)
3. Completed copy of the Limitations on Subcontracting Report (Include if acquisition is being set-aside and clause 52.219-14 is included)
4. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
5. A copy of the current construction schedule
6. A copy of the current Schedule of Values.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Clause) Construction Contract Administration Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
http://www.ipp.g/ mailto:ippgroup@bos.frb.org mailto:ippgroup@bos.frb.org mailto:ippgroup@bos.frb.org http://www.doi.gov/pam/acquisition/policy/constructioncontract mailto:ippgroup@bos.frb.org
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 17 of 50
SECTION H - SPECIAL CONTRACT REQUIREMENTS
SPECIAL REQUIREMENT 1: OPTION FOR ADDITIONAL SERVICES-SEPARATELY PRICED LINE ITEMS
The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 60 days after contract award. Performance of added line-item tasks shall be at the price negotiated in the contract Schedule.
(End of clause)
SPECIAL REQUIREMENT 2: PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
1. The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
2. If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
3. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
4. The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
SPECIAL REQUIREMENT 3: NOTIFICATION OF SUBCONTRACTING
The contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The written notification shall be provided on Standard Form 1413 and must include as a minimum:
(a) Prime Contract Number and Subcontract Number (if applicable)
(b) The name and address of the Prime Contractor.
(c) The name and address of the subcontractor.
(d) The date upon which the subcontract was entered into and its duration.
(e) A detailed description of the work being subcontracted.
(f) Project Name and Location of Work.
(g) Identify the names of any intermediate subcontractors (if applicable)
(h) Must be signed by both Prime Contractor and Subcontractor
(End of Notice)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 18 of 50
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR "52.252-2 CLAUSES INCORPORATED BY REFERENCE" in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause's full text.
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY
(MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS (NOV 2023)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR
STATEMENTS (JAN 2017)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JUN 2020)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR
PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (DEC 2023)
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES AND EQUIPMENT (NOV 2021)
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUNE 2023)
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUB-CONTRACTING WITH CONTRACTOR'S
DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT, VOLUNTARILY EXCLUDED (JAN 2025)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT
2018) 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.215-2 AUDIT AND RECORDS-NEGOTIATIONS (JUN 2020)
52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997)
52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED
COST OR PRICING DATA-MODIFICATIONS (NOV 2021) ALT IV (OCT 2010)
52.219-3 NOTICE OF HUBZONE SET-ASIDE OR SOLE-SOURCE AWARD (OCT 2022)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 19 of 50
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2022)
52.219-28 POST AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS-OVERTIME COMPENSATION (MAR 2018)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION - DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIRMENTS AND RELATED REGULATIONS
(MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-26 EQUAL OPPORTUNITY (SEP 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APRIL 2015)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2025)
52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 14026 (JAN 2022)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION
(MAY 2024)(DEVIATION FEB 2025)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (JUN 2020)
52.224-1 PRIVACY ACT NOTIFICATION (APR 1984)
52.224-2 PRIVACY ACT (APR 1984)
52.224-3 PRIVACY TRAINING (JAN 2017)
52.225-9 BUY AMERICAN-CONSTRUCTION MATERIALS (OCT 2022)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.226-7 DRUG-FREE WORKPLACE (MAY 2024)
52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (MAY 2024)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN 2020)
52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA - SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 20 of 50
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.229-12 TAX ON CERTAIN FOREIGN PROCUREMENTS (FEB 2021)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-16 PROGRESS PAYMENTS (NOV 2021)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER-SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS CONTRACTORS (MAR 2023)
52.233-1 DISPUTES (MAY 2014)-ALTERNATE 1 (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
52.236-10
IMPROVEMENTS (APR 1984)
OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.240-1 PROHIBITION ON UNMANNED AIRCRAFT SYSTEMS MANUFACTURED OR ASSEMBLED
BY AMERICAN SECURITY DRONE ACT-COVERED FOREIGN ENTITIES (NOV 2024)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING - CONSTRUCTION (OCT 2020)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012), ALT 1 (SEP
1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
CLAUSES INCORPORATED BY FULL TEXT
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government or is considered by the Government to be superior to other products or services. This
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 21 of 50 restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
(End of clause)
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR 1984)
For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-2(d)), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.
(End of clause)
1452.228-70 LIABILITY INSURANCE. (JUL 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$100,000 each person* $500,000 each occurrence* $1,000,000 property damage*
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
(End of clause)
1452.236-70 Prohibition Against Use of Lead-based Paint.
Prohibition Against Use of Lead-Based Paint - Department of the Interior (JUL 1996)
Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.
(End of clause)
52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022) (DEVIATION OCT 2022)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that-
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to-
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 22 of 50
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are-
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F);
or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are-
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:
(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.
(i) The following services may be excluded from the 50 percent limitation:
(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (238210), Electrical Contractors and Other Wiring Installation Contractors.
(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.
(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded.
(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause - [Contracting Officer check as appropriate.] _X_ By the end of the base term of the contract and then by the end of each subsequent option period; or _ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
Document Title PARK PMIS 253478 - SHEN Replace Surveillance Cameras Page 23 of 50
(1) In a joint venture comprised of a small business protege and its mentor approved by the Small Business Administration, the small business protege shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protege in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
52.228-11 INDIVIDUAL SURETY-PLEDGE OF ASSETS (FEB 2021)(DEVIATION MAY 2023)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond--
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, except that the words "being duly sworn, depose and say" on the Standard Form 28 are replaced with the word "affirm" and the Standard Form 28 is not required to be sworn and notarized in block 12.
(b) The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained-
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds…
This is the start of the file's text. The full file is on GovTribe.