This is a Request for Proposal (RFP) for construction services at Grand Teton National Park for the Mormon Row Cultural Landscape Improvements—Phase IV project. The National Park Service seeks a Service-Disabled Veteran-Owned Small Business (SDVOSB) to complete landscape repairs and improvements at Mormon Row, a historic cultural site located approximately two miles east of Moose, Wyoming. Work includes repairing and resurfacing trails and viewing areas to meet ABA accessibility standards, installing wayfinding and interpretive signage, constructing a new off-street parking area for approximately 50 cars on nearly 2 acres, constructing new and improved pedestrian pathways, installing raised road crosswalks, fencing, vault toilets, and site furnishings. The work must maintain sensitivity to the historic character of the Mormon Row Historic District and comply with preservation and environmental standards while keeping Mormon Row Road open to visitors during construction.

The solicitation number is 140P1426R0002, with proposals due by March 30, 2026, at 3:00 PM local time. The contract is for a firm-fixed-price award with a performance period of 180 calendar days after Notice to Proceed, with construction beginning after July 1, 2026, and completion required by November 15, 2026. The estimated project magnitude is between $1,000,000 and $5,000,000. The NAICS code is 237310 (Highway, Street, and Bridge Construction) with a small business size standard of $45 million. A bid guarantee of 20 percent of the bid price and performance and payment bonds are required within 10 days of award. Proposals must be submitted electronically in two separate volumes (non-price technical proposal and price proposal) via email to molly_lynam@nps.gov. Evaluation will be based on past performance, project experience, key personnel experience, schedule, safety, and price, with non-price factors combined being approximately equally important to price. Davis Bacon wage rates apply.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140P1426R0002

NPS, IMR - Northern Rockies MABO PO Box 168 Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190 molly_lynam@nps.gov

0044034462

PIR

Molly Lynam molly_lynam@nps.gov

02/27/2026

03/30/2026

10 180

FAR 52.211-10

Grand Teton National Park (GRTE) Mormon Row Cultural Landscape Improvements - Phase IV - PMIS 228830

PROJECT DESCRIPTION: Project work consists of providing all labor, materials, tools and other equipment necessary to complete the Grand Teton National Park Mormon Row Cultural Landscape Improvements - Phase

IV - PMIS 228830. Additional information is provided in the solicitation, specifications, supporting documents and other pertinent attachments.

Mormon Row is a significant cultural landscape located roughly 2 miles east of Moose, WY that attracts park visitors for its historic resources and spectacular mountain views. In 2026, construction at Mormon

Row will focus on landscape repairs and improvements designed to enhance visitor access, safety, and understanding of this historic site. Work will involve repairing and resurfacing trails and viewing areas to meet ABA accessibility standards, installing clear wayfinding and interpretive signage, and constructing a new off-street parking area for approximately 50 cars on nearly 2 acres. Work will also involve new and improved pedestrian pathways, raised road crosswalk, fencing, vault toilets and site furnishings to better manage visitor access and their activities. All work will be completed with sensitivity to the historic character of the Mormon Row Historic District and in compliance with

Continued...

1 61

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

NPS, IMR - Northern Rockies MABO PO Box 168 Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190

PIR

Molly Lynam

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

preservation and environmental standards.

Mormon Row Road will remain open to visitors during this construction so work tasks along the nearly ¾ mile work corridor must be thoughtfully sequenced to support public access.

Specifications and other supporting documents are attached and incorporated herein. Refer to

SECTION J.

SET-ASIDE TYPE: This procurement is being solicited as a Service-Disabled Veteran-Owned

Small Business (SDVOSB) - Set-Aside.

NAICS CODE: 237310, Highway, Street, and Bridge

Construction with a small business size standard of $45M.

MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between

$1,000,000 and $5,000,000.

DURATION: See FAR 52.211-10.

SITE VISIT: See FAR 52.236-27 for additional information.

WAGE RATES: Davis Bacon wage rates apply and are included as part of this solicitation package.

SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and

Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.

INSTRUCTIONS FOR SUBMITTING OFFER: Refer to

Section L and M. The contractor agrees that they will follow the plans and specifications provided. Offers must be provided electronically.

QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to

Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than ten (10) calendar days prior to the offer due date.

Delivery: 180 Days After Notice to Proceed

Delivery Location Code: 0011283244

NPS, Grand Teton NP

Headquarters Warehouse

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

103 Headquarters Loop Road

Moose WY 83012-0170 US

Period of Performance: 06/01/2026 to

11/30/2026

00010 See Section B - Bid Schedule

Product/Service Code: Z2LZ

Product/Service Description: REPAIR OR

ALTERATION

OF PARKING FACILITIES

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 5 of 61

TABLE OF CONTENT

Part I – The Schedule SECTION A – Solicitation/Contract Form 52.252-2 – Clauses Incorporated by Reference (Feb 1998) SECTION B – Bid Schedule

SPECIAL CLAUSE: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS 10

SECTION C – Specifications/Drawings SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance 52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996) SECTION F - Deliveries or Performance 52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 -- Suspension of Work (Apr 1984) SECTION G - Contract Administration Data 1452.201-70 Authorities and Delegations (Sep 2011) DOI AAAP-0050 V3 Notice to Contractors - Contractor Performance Assessment Reporting System (December 2015) Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021) Construction Contract Administration SECTION H - Special Contract Requirements SECTION I - Contract Clauses 52.252-2 – Clauses Incorporated by Reference (Feb 1998) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) .20 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.211-18 Variation in Estimated Quantity (Apr 1984) 52.215-2 Audit and Records- Negotiations (Jun 2020) 52.215-8 Order of Precedence -- Uniform Contract Format (Oct 1997) 52.219-8 Utilization of Small Business Concerns (Jan 2025) 52.219-27 Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024) 52.219-28 Post-Award Small Business Program Rerepresentation (Jan 2025) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 6 of 61

52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers With Disabilities (Jun 2020) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employee Eligibility Verification (Jan 2025) 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-23 Sustainable Products and Services (May 2024) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance- Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021) (DEVIATION May 2023) 52.228-12 Prospective Subcontractor Request for Bonds (May 2014) 52.228-15 Performance and Payment Bonds- Construction (Jun 2020) (DEVIATION May 2023) 52.229-3 Federal, State, and Local Taxes (Feb 2013) 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation (Jun 2020) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-16 Progress Payments (Nov 2021) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach Of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 21 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 7 of 61

52.236-13 Accident Prevention (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-16 Quantity Surveys (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) 52.242-13 Bankruptcy (July 1995) 52.243-4 Changes (Jun 2007) 52.244-5 Competition in Subcontracting (Dec 1996) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Jan 2025) 52.245-1 Government Property (Sep 2021) 52.245-9 Use and Charges (Apr 2012) 52.246-21 Warranty of Construction (Mar 1994) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - (ALT I) (Sept 1996) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)

CLAUSES INCORPORATED BY FULL TEXT

1452.203-70 -- Restrictions on Endorsements (Jul 1996) 1452.204-70 -- Release of Claims (Jul 1996) 1452.228-70 -- Liability Insurance—Department of the Interior (Jul 1996) 52.204-21 – Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) 52.204-28 Federal Acquisition Supply Chain Security Act Orders – Federal Supply Schedules, Government Acquisition Contracts, and Multi-Agency Contracts (Dec 2023) 52.204-30 Federal Acquisition Supply Chain Security Act Orders – Prohibition (Dec 2023) 52.219-14 Limitations on Subcontracting (Oct 2022)(DEVIATION Oct 2022) 52.225-9 -- Buy American–Construction Materials (Oct 2022) 52.232-18 Availability of Funds (Apr 1984) 52.252-6 – Authorized Deviations in Clauses (Nov 2020) Part III – List of Documents, Exhibits, and Other Attachments SECTION J – List of Attachments Part IV – Representations and Instructions SECTION K - Representations, Certifications, and Other Statements of Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.203-18 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements - Representation (Jan 2017) 52.204-17 Ownership of Control of Offeror (Aug 2020) 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications (Jun 2020)

PROVISIONS INCORPORATED BY FULL TEXT

52.201-1 Acquisition 360: Voluntary Survey (Sep 2023) 52.204-8 -- Annual Representations and Certifications (Jan 2025) 52.204-24 Representation Regarding Certain Telecommunication and Video Surveillance Services or Equipment (Nov 2021) 52.204-26 Covered Telecommunications Equipment or Services-Representation (Oct 2020) 52.204-29 Federal Acquisition Supply Chain Security Act Orders – Representation and Disclosures (Dec 2023) 52.209-7 – Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements – Certification (Nov 2021) 52.222-23 -- Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.236-28 -- Preparation of Proposals – Construction (Oct 1997) 52.252-5 – Authorized Deviations in Provisions (Nov 2020) SECTION L - Instructions, Conditions, and Notices to Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.204-7 System for Award Management (Nov 2024)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 8 of 61

52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.211-6 Brand Name or Equal (Aug 1999) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.215-1 -- Instructions to Offerors-Competitive Acquisition (Nov 2021)

PROVISIONS INCORPORATED BY FULL TEXT

52.211-3 -- Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (Jun 1988) 52.216-1 – Type of Contract (Apr 1984) 52.222-5 -- Construction Wage Rate Requirements—Secondary Site of the Work (May 2014) 52.225-10 -- Notice of Buy American Requirement--Construction Materials (May 2014) 52.228-1 Bid Guarantee (Sep 1996) 52.233-2 Service of Protest Department of the Interior (Sep 2006) (DEVIATION) (Jul 1996) 52.236-27 – Site Visit (Construction) (Feb 1995) 1452.215-71 -- Use and Disclosure of Proposal Information - Department of the Interior (Apr 1984)

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR RESPONDENTS

SECTION M - EVALUATION FACTORS FOR AWARD

52.217-5 Evaluation of Options (July 1990)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 9 of 61

Part I – The Schedule

SECTION A – Solicitation/Contract Form

52.252-2 – Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov

(End of Section A) http://www.acquisition.gov/

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 10 of 61

SECTION B – Bid Schedule

Proposal pricing shall be provided in accordance with Section L and is incorporated herein. The contractor must furnish an itemized breakdown. Contractor shall use the Bid Schedule below.

Contract Line Item Number (CLIN) & Option Number

Contract Line Item Title QTY Unit of Measure

Unit Price Total Price

CLIN 1 - BASE Visitor Parking Area (including traffic counter and loops and empty conduit)

1 Lump Sum $ $

CLIN 2 – BASE* South Mormon Row Road Detached Trail Accessibility Improvements - RAP

1 Lump Sum $ $

CLIN 3 – Option A Trails, Pedestrian Bridges and Gravel & Concrete NPS Employee Parking

1 Lump Sum $ $

CLIN 4 – Option B Native Soil Trails 1 Lump Sum $ $ CLIN 5 – Option C* South Mormon Row Road

Detached Trail Accessibility Improvements

– Porous Pavement

1 Lump Sum $ $

CLIN 6 – Option D Waysides, Wayfinding, Site Furnishings, Shade Shelter, Fencing

1 Lump Sum $ $

CLIN 7 – Option E Revegetation 1 Lump Sum $ $

TOTAL BASE & OPTION PRICE (CLINS 1 -7)

The Government will calculate total evaluated price as the sum of the base items (CLINs 1 & 2) plus all options (CLINs 3-7). If CLIN 5 is exercised, CLIN 2 will be removed and replaced by CLIN 5.

* If funding is available and CLIN 5 is exercised, CLIN 2 will not be performed. Reference Plan Sheet L3.7 which states, “BASE BID: 1. FOR BIDDING PURPOSES, ASSUME REPAIR OF 20% OF EX RAP TRAIL IN PLACE.

CONTRACTOR TO STAKE LOCATIONS WITH CONTRACTING OFFICER. RE: DETAIL 2/L6.1.

2. ENTIRE TRAIL TO MEET US ACCESS BOARD ACCESSIBILITY STANDARDS UPON COMPLETION.

BID OPTION: 1. REMOVE AND REHABILITATE THE ENTIRE LENGTH OF EXISTING RAP TRAIL IN PLACE WITH FILTERPAVE TRAIL MATERIAL, RE: SPECIFICATION. STAKE CENTERLINE OF TRAIL FOR CONTRACTING OFFICER APPROVAL. PROPOSED TRAIL WIDTH TO BE 6'-0". RE: DETAIL 1/L6.1.

2. ENTIRE TRAIL TO MEET US ACCESS BOARD ACCESSIBILITY STANDARDS UPON COMPLETION.”

This project is currently subject to availability of funds. See FAR 52.232-18 for additional information.

SPECIAL CLAUSE: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS

The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 60 days after contract award. Performance of added line item tasks shall be at the price negotiated in the contract Schedule. (End of clause)

(End of Section B)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 11 of 61

SECTION C – Specifications/Drawings

Project work consists of providing all labor, materials, tools and other equipment necessary to complete the Grand Teton National Park Mormon Row Cultural Landscape Improvements - Phase IV - PMIS 228830. Additional information is provided in the solicitation, specifications, supporting documents and other pertinent attachments.

Mormon Row is a significant cultural landscape located roughly 2 miles east of Moose, WY that attracts park visitors for its historic resources and spectacular mountain views. In 2026, construction at Mormon Row will focus on landscape repairs and improvements designed to enhance visitor access, safety, and understanding of this historic site. Work will involve repairing and resurfacing trails and viewing areas to meet ABA accessibility standards, installing clear wayfinding and interpretive signage, and constructing a new off-street parking area for approximately 50 cars on nearly 2 acres. Work will also involve new and improved pedestrian pathways, raised road crosswalk, fencing, vault toilets and site furnishings to better manage visitor access and their activities. All work will be completed with sensitivity to the historic character of the Mormon Row Historic District and in compliance with preservation and environmental standards. Mormon Row Road will remain open to visitors during this construction so work tasks along the nearly ¾ mile work corridor must be thoughtfully sequenced to support public access.

Specifications and other supporting documents are attached and incorporated herein. Refer to SECTION J.

(End of Section C)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 12 of 61

SECTION D - Packaging and Marking

No clauses included

(End of Section D)

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 13 of 61

SECTION E - Inspection and Acceptance

52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph

(i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 14 of 61

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of Clause)

SECTION F - Deliveries or Performance

Work shall be completed by skilled personnel per industry standards and manufacturer specifications.

52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

52.236-15 Schedules for Construction Contracts (Apr 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

(End of clause)

52.242-14 -- Suspension of Work (Apr 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 15 of 61

Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.

However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed—

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

(End of clause)

SECTION G - Contract Administration Data

(a) Contact Information:

Contracting Officer (CO):

Molly Lynam, molly_lynam@nps.gov

Contracting Officer’s Representative (COR):

TBD

(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.

(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.

(d) Any request for contract changes/modifications shall be submitted to the CO.

(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items.

All field changes must be approved by the CO prior to execution.

(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.

FINAL PAYMENT

Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.

AVAILABILITY OF UTILITIES SERVICES

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 16 of 61

Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.

UTILITIES CONSERVATION

The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.

OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS

The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.

INTERIM AND FINAL INSPECTIONS

1. Prior to covering, enclosing, or hiding any of type work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.

2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.

3. The final inspection will be onsite with the Contractor, the Contracting Officer’s Representative, and Contract Specialist/Contracting Officer (when possible).

1452.201-70 Authorities and Delegations (Sep 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

The COR for this contract will be:

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 17 of 61 consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.

(End of Local Clause)

DOI AAAP-0050 V3 Notice to Contractors - Contractor Performance Assessment Reporting System (December 2015)

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in CPARS for Government use in evaluating past performance as part of a source selection action.

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in CPARS marked as “Pending” with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 18 of 61 than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of Notice)

Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

The contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR) and Contract Specialist (CS) a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the NPS CS and the contractor. If the COR recommends acceptance, the contractor shall submit a copy of the final version of the checklist and the Invoice Package to the NPS through IPP.

1. Completed copy of the COR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)

2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments)

3. Completed copy of the Limitations on Subcontracting Report

4. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts

5. A copy of the current construction schedule (refer to project specification section 013216)

6. A copy of the current Schedule of Values. (refer to project specification section 013216)

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.

Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.

(End of Section G) https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov https://www.doi.gov/pam/acquisition/policy/constructioncontract

140P1426R0002 GRTE Mormon Row Phase IV - PMIS 228830 Page 19 of 61

SECTION H - Special Contract Requirements

KEY PERSONNEL (Contractor shall complete section (a) listing Key Personnel per their technical proposal)

(a) The Contractor shall list the Key Personnel assigned to the resultant contract:

Project Manager:

Site Superintendent:

On-site Quality Control Supervisor:

On-site Safety Supervisor:

(b) During the first 60 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 60-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.

Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.

(End of clause)

GREEN PROCUREMENT

To the extent that the construction services provided by the Contractor require provision of any of the types of products listed at https://sftool.gov/greenprocurement, the Contractor is expected to provide the green type of product unless that type of product is not available competitively within a reasonable time,…