This document is Amendment No. 1 to Phase One of Solicitation for Offers (SFO) LI-14174, issued by Naval Facilities Engineering Command Pacific for administrative, warehouse, and storage space at Puget Sound Naval Shipyard & Intermediate Maintenance Facility in Washington. The amendment is dated February 10, 2025.

The amendment makes two key changes: (1) removes the requirement that a Phase 1 submittal must be received to be considered for follow-on phases, and (2) provides answers to three questions. The Q&A clarifies that occupancy timing will be specified in Phase 2, explains the difference between warehouse space (for storage/distribution) and industrial space (for manufacturing/production), and confirms that NAVFAC will consider acquisition-based leasing structures and build-to-suit proposals, with specific requirements to be detailed in Phase 2. Questions about the SFO must be submitted via email to the provided Navy contacts with "SFO LI-14174" in the subject line.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment No. 1 to Phase One

SOLICITATION FOR OFFERS

SFO LI-14174

Administrative, Warehouse and Storage Space Puget Sound Naval Shipyard & Intermediate Maintenance Facility, WASHINGTON

Naval Sea Systems Command (NAVSEASYSCOM)

10 February 2025

Prepared by:

Naval Facilities Engineering Command, Pacific

180 Main St Honolulu, HI 96818

Brandy L. Tallaksen Real Estate Contracting Officer (RECO)

Questions about this SFO must be addressed via electronic mail to the Real Estate Contracting Officer at the emails listed herein, and the Subject line should be marked “SFO LI-14174” Questions should be submitted by electronic mail to: jason.t.nanni.civ@us.navy.mil and zachary.t.schuhart2.civ@us.navy.mil.

SFO LI-14174

1. This Amendment No. 1 serves to remove the requirement that a Phase 1 submittal must be received in order to be considered for follow on Phases; and

2. Incorporates the follow Questions & Answers

Questions & Answers to Phase 1 SFO LI-14174:

Question 1: When does the DON want to occupy the space?

Answer 1: This information is not available in Phase 1, but will be available in Phase 2.

Question 2: What is the difference between warehouse and industrial?

Answer 2: Warehouses are primarily used for storage and distribution of goods, while industrial spaces are used for manufacturing, production, or processing. Phase 2 of the SFO will describe the Government’s requirements for industrial space.

Question 3: Is NAVFAC open to an acquisition-based leasing structure where Offerors acquire property(ies) to offer the same or build-to-suite (BTS) proposals? Is there any specific property criteria or preferences that should guide this acquisition strategy? What is the appropriate process for submitting a formal proposal for consideration?

Answer 3: Yes. Phase 2 will provide instructions to Offerors that describe the Government’s requirements which must be met for a formal proposal to be considered. Phase 2 will provide instructions for how to submit a formal proposal for consideration. Offerors are encouraged to submit a proposal in Phase 1.

3. All other terms and conditions of Phase 1 SFO LI-14174 remain unchanged:

2025-02-10T15:31:16-1000