SEED Project SOW - B101 Waterproofing by Handicap Ramp.pdf
PDF 141 KB Posted
- Attached to
- Amendment 1333ND222QNB190089-0001 - General Construction Multiple Award Indefinite Delivery/Indefinite Quantity (IDIQ) Contract. Federal contract opportunity
- Solicitation number
- 1333ND22QNB190089
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING 101 WATERPROOFING BY HANDICAP RAMP CONSTRUCTION
November 17, 2021
Statement of Work (SOW)
BACKGROUND
Building 101 on the NIST Gaithersburg campus was constructed in the mid 1960’s and includes administrative offices, conference, and dining facilities. During periods of rain, water leaks regularly occur in occupied basement areas on the northeast side of the building. Pressure injection grouting of concrete foundation walls has been tried as a remedial measure, but this has ultimately proven to be unsuccessful, and the water infiltration persists.
The areas of concern appear to coincide with the raised plinth areas enclosed by low retaining walls about three feet above the surrounding grade. Original construction drawings show a network of area drains connected to a storm sewer, stone drainage areas adjacent to the building and retaining walls, foundation drains along the main building walls, and grass in the remaining areas between the retaining walls and main building.
The original design has been compromised over time with addition of large trees and ornamental shrubs, and the removal of drainage stone at retaining walls. The drain systems for the raised area, retaining walls, and main building foundations have not been maintained; in some locations drains have been abandoned or removed.
In 2020 engineers McMullan & Associates completed construction documents including construction drawings and specifications to address remedial work necessary to address the water infiltration issues.
OBJECTIVES
Building 101 basement occupants, including DOC and NIST security offices, are regularly impacted by water infiltration during rain and snow events. In addition to the immediate safety concerns of puddling water, the continuing leaks are damaging the foundation walls and interior finishes.
This contract is intended to perform remedial work on existing retaining walls and footings, as well as the storm drain system and grading of landscape areas to alleviate existing water leaks which regularly occur in the B101 basement areas on the northeast side of the building.
SCOPE
Leak remediation modifications to exterior areas north and east of Building 101 to address water infiltration issues in areas below grade.
DELIVERY
Deliverable Description Quantity/Media Date Required
1 Contractor Limited Access Badge Applications
Completed forms Department of Commerce DN-52
Within 15 days of task order award
2 Contractor activity hazard analysis (job specific health and safety plan meeting COVID-19 requirements)
Electronic PDF submission
Within 15 days of task order award
3 Informational submittals for Temporary Facilities and Controls
Electronic PDF submission
Within 30 days of NTP
4 Submittal schedule Electronic PDF submission
Within 15 days of NTP
5 Key personnel assignments Electronic PDF submission
Within 15 days of NTP
GOVERNMENT FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION
None
SECURITY
All contract employees shall obtain badges for this contract. The badge type is a (Green) Site Card/ Personal Identification (PIV) Card. Contractor shall allow for up to 90 minutes to collect a badge (M-F 9AM to 12:00 PM).
NIST will not provide escort services to the contractor during the performance of this contract.
TRAVEL
Not applicable to this task order
SPECIAL MATERIAL REQUIREMENTS
OTHER UNIQUE REQUIREMENTS
PLACE OF PERFORMANCE
Gaithersburg, MD – Building 101
PERIOD OF PERFORMANCE
This Task Order will have a period of performance of 365 days from NTP.
END OF SOW
| BUILDING 101 WATERPROOFING BY HANDICAP RAMP CONSTRUCTION |
| BACKGROUND |
| OBJECTIVES |
| SCOPE |
| SECURITY |
| TRAVEL |
| SPECIAL MATERIAL REQUIREMENTS |
| OTHER UNIQUE REQUIREMENTS |
| PLACE OF PERFORMANCE |
| PERIOD OF PERFORMANCE |
File details come from the government source that posted it. Updated .