Section F Deliveries or Performance.pdf

PDF 328 KB Posted

Attached to
Vertical Transportation Maintenance and Repair Services At Naval Station Great Lakes and Other Areas of Responsibility (AOR)
Solicitation number
N4008524R2584
Issued by

About this file

This document appears to be the Section F - Deliverables, Records, & Performance portion of a federal contract opportunity for Vertical Transportation Maintenance and Repair Services at Naval Station Great Lakes and other areas of responsibility.

The key details are: The contract requires the contractor to provide various deliverables such as plans, reports, certifications, inspection results, and other documentation on a recurring basis (e.g. monthly, annually) and upon request. These include items like an Accident Prevention Plan, Quality Management Plan, Critical Lift Plans, Crane Inspections, Safety Inspection Reports, and Hazardous Material Inventory Logs. The contractor must also provide information on system updates, installation, and modifications to existing or new Vertical Transportation Equipment (VTE) control panels. Submission requirements, distribution, frequency, and number of copies are specified for each deliverable. The overall federal contract opportunity is solicitation number N4008524R2584 for Vertical Transportation Maintenance and Repair Services, issued by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section F – 0200000 Management and Administration

Deliverables, Records, & Performance

Annex/ Spec Item

Form/ Attachment

Number/ Other

Resource

Deliverable Title/Description

Submission Requirements

Distribution

Submission Frequency

Submitted to

Number of Copies

0200000/ 2.2.1.2

Provided by Contractor

Request to Work Outside Government’s Regular

Working Hours

At least seven calendar days prior to requested day via email

KO, CS,

COR

1 each As specified

0200000/ 2.3.1

Provided by Contractor

Sign-in Sheets and Conference/Meeting

Minutes

Sign-in sheets and minutes for all contract meetings within two working days

COR 1 each Per occurrence

0200000/ 2.3.4

Provided by Contractor

Permits and Licenses

Before work commences and as requested by the KO, CS, or COR

COR, CS 1 each As specified

0200000/ 2.3.5

Provided by Contractor

Certificate of Insurance Within 15 calendar days after award.

COR, CS 1 each As specified

0200000/ 2.3.5.1

Provided by Contractor

Written Notice of Cancellation or Material

Change in Policy Coverage

At least 30 calendar days prior to cancellation or material change in policy coverage

KO, CS 1 each As specified

0200000/ 2.3.8

Provided by Contractor

Invoicing Electronically inputted into PIEE and emailed to COR and CS COR, CS 1 each Monthly

0200000/ 2.6.1

Provided by Contractor

Plan of Action and Milestones (POA&Ms)

As requested COR, CS 1 each As specified

0200000/ 2.6.1

Provided by Contractor

Cybersecurity Incident Per occurrence COR, CS 1 each As specified

0200000/ 2.6.5

Provided by Contractor

Notification of Difficulty In Scheduling Work Due to Government Controls

Per occurrence

KO, CS,

COR

1 each As specified

0200000/ 2.6.9.1

Provided by Contractor

Quality Management (QM) Plan

Within 15 calendar days after contact award and within seven calendar days of changes.

KO,

FSCM,

COR

1 each As specified

0200000/ 2.6.9.2

Provided by Contractor

Quality Inspection and Surveillance File

Within five working days of subsequent month

PAR,

COR, CS

1 each As specified

0200000/ 2.6.9.3

Provided by Contractor

Quality Inspection and Surveillance Report

First work day of each month

KO 1 each Monthly

0200000/ 2.7.1

Provided by Contractor

List of Key Personnel and Qualifications

Within 15 calendar days after contract award COR, CS 1 each As specified

0200000/ 2.7.1

Provided by Contractor

Organizational Chart Within 15 calendar days after contract award COR, CS 1 each As specified

0200000/ 2.7.2.6

Provided by Contractor

Proof of Legal Residency

Prior to being admitted to work site

COR, CS 1 each As specified

0200000/ 2.7.3

Provided by Contractor

Service Contract Reporting (SCR)

No later than 30 September (End of

Government fiscal year)

PAR,

COR, CS

1 each Annually

Annex/ Spec Item

Form/ Attachment

Number/ Other

Resource

Deliverable Title/Description

Submission Requirements

Distribution

Submission Frequency

Submitted to

Number of Copies

0200000/ 2.8.1

Provided by Contractor

Employee List Before commencement of work and as changes to employees occur COR, CS 1 each As specified

0200000/ 2.8.9

Provided by Contractor

List of Personnel Requiring Access To

Government IT, OT, and FRCS Systems

Before commencement of work and as changes to employees occur COR, CS 1 each

As specified (As applicable)

0200000/ 2.9.2

Provided by Contractor

Accident Prevention Plan

Within 15 calendar days after contract award and within seven calendar days of changes

COR, CS 1 each As specified

0200000/ 2.9.2

Provided by Contractor

Compliance Plans, Programs, and

Procedures

Together with the Accident Prevention

Plan and when changes occur

COR, CS, 1 each As specified

0200000/ 2.9.3

J-0200000-06 Activity Hazard

Analysis

Together with the Accident Prevention Plan and for changes

COR, CS 1 each As specified

0200000/ 2.9.4.3

Provided by Contractor

Confined Space Program

Activity/site specific procedures to comply with all regulatory standards

COR, CS 1 each As required

0200000/ 2.9.4.4

Provided by Contractor

Critical Lift Plan

Develop and complete a critical lift plan prior to performing any critical lifts

KO, COR,

CS, WHE

Program Manager

1 each As required

0200000/ 2.9.4.5

Provided by Contractor

Fall Prevention and Protection Plan

Site specific fall prevention and protection plan

COR, CS 1 each As required

0200000/ 2.9.4.7

J-0200000-10 Lock-Out/Tag-Out (LOTO) Periodic Inspection Form

Within five calendar days of completion/termination of the contract

COR, CS 1 each Annually

0200000/ 2.9.5

J-0200000- 11A

Contractor Lift Plan (Suspended Loads)

Entry Package

Submit the lift plan for review a minimum of five (5) working days prior to the scheduled lift

COR, CS,

WHE

Program Manager

1 each As required

0200000/ 2.9.5.1

Provided by Contractor

Crane Inspections and Testing

On site and readily available

COR, CS,

WHE

Program Manager

1 each As specified

0200000/ 2.9.5.2

J-0200000-11B Contractor Lift Plan

(Rigging Only) Entry Package

Submit the lift plan for review a minimum of five (5) working days prior to the scheduled lift

COR, CS,

WHE

Program Manager

1 each As required

0200000/ 2.9.5.3

Provided by Contractor

Crane Operator’s Certifications

Prior to performing any crane lifts

COR, CS,

WHE

Program Manager

1 each As required

Annex/ Spec Item

Form/ Attachment

Number/ Other

Resource

Deliverable Title/Description

Submission Requirements

Distribution

Submission Frequency

Submitted to

Number of Copies

0200000/ 2.9.6

J-0200000-12 NAVFAC Contractor

Incident Reporting System (CIRS)

Within five calendar days of accident

COR, CS,

KO

1 each As specified

0200000/ 2.9.6

J-0200000-13 OSHA 300 Forms Per occurrence

COR, CS,

KO

1 each As specified

0200000/ 2.9.6

J-0200000-14 Crane and Rigging Accident Report &

Instructions Per occurrence

COR, CS,

KO

1 each As specified

0200000/ 2.9.6

J-0200000-15 Crane and Rigging Gear

Near Miss Within 4 hours of event

COR, CS,

KO

1 each As specified

0200000/ 2.9.8

J-0200000-16 Monthly On-Site Labor

Report

Within five working days of subsequent month. Included with Quality Inspection

Report

PAR,

COR, CS

1 each Monthly

0200000/ 2.9.9

Provided by Contractor

OSHA Citation and Violations Corrective

Action Report

Within 48 hours after receiving a citation.

PAR,

COR, CS,

KO

1 each Per occurrence

0200000/ 2.9.10

Provided by Contractor

Contractor Safety Inspection and

Monitoring Report Upon Request

PAR,

COR, CS,

KO

1 each As specified

0200000/ 2.9.11

Provided by Contractor

Federal, State, County, City and Industry Safety

Certifications

Within 15 calendar days after award, and within seven calendar days of changes or expiration of current certifications

PAR,

COR, CS

1 each As specified

0200000/ 2.10.2.7

Provided by Contractor

Spill Reports

Notification as soon as possible but within 24 hours to KO, and reports within 48 hours of event

KO, PAR,

COR, CS

1 each As specified

0200000/ 2.10.2.8

J-0200000-18

Emergency Planning and Community Right-To- Know Act (EPCRA)

Report

Within 15 calendar days after award and within seven calendar days of changes

KO, PAR,

COR, CS

1 each As specified

0200000/ 2.10.2.8

J-0200000-18A Contractor Hazardous

Material Inventory Log

(EPRCA)

Within 15 calendar days after contract award and not less than 10 working days prior to planned use of hazardous material

KO, PAR,

COR, CS

1 each As specified

0200000/ 2.16

J-0200000-20 Self-Assessment

Checklist

Together with the Accident Prevention Plan and for changes.

At least 30 calendar days prior to start of contract performance

KO, PAR,

COR, CS

1 each Annually

Section F – 1502000 Management and Administration

Annex/ Spec Item

Form/ Attachment

Number/ Other

Resource

Deliverable Title/Description

Submission Requirements

Distribution

Submission Frequency

Submitted to

Number of Copies

1502000/ 2.2.1

Provided by Contractor

Certification, Training, and License

Within 15 days after contract award or as requested by the KO

COR, CS,

KO

1 each Once for initial submittal, then as requested

1502000/

Provided by Contractor

Information On System Updates, Installation or

Modifications to Existing or New VTE

Control Panels

Per occurrence

PAR, COR,

and

NAVFAC

VTE

Inspector

1 each As specified

1502000/ 3.1

Provided by Contractor

Service Order Summary Report

Included with monthly Quality Inspection and

Surveillance Report COR, CS 1 each Monthly

1502000/ 3.2

Provided by Contractor

Preventive Maintenance Program Plan

Within 30 calendar days after contract award

PAR, COR,

CS

1 each Annually

1502000/ 3.2.1

Provided by Contractor

Annual PM Work Schedule and first month’s Monthly PM Work/Plan Schedule

Within 30 calendar days of contract award and prior to first payment

PAR &

COR, and

NAVFAC

VTE

Inspector

1 each As specified

1502000/ 3.2.1

Provided by Contractor

Monthly PM Work/Plan Schedule

Five work days prior to the beginning of each month

PAR &

COR, and

NAVFAC

VTE

Inspector

1 each Monthly

1502000/

3.3 and 3.3.1

J-1502000-05 &

Inspection, Testing, and certification checksheet

Five work days prior to the beginning of each month

PAR &

COR, and

NAVFAC

VTE

Inspector

1 each Monthly

1502000/ 3.3.1

Provided by Contractor

Monthly Inspection, Testing, and

Certification Work Schedule

1st day of each month

PAR and

NAVFAC

VTE

Inspector

1 each Monthly