Section 02103 - Split Rail Fence.doc

DOC document 33 KB Posted

Attached to
GAOA Echo Amphitheatre Rec Site Improvements: Phase II
Solicitation number
127EAX24R0005
Issued by

About this file

This document outlines specifications for a split rail fence installation project. The Forest Service is soliciting bids to install split rail fencing along trails at the GAOA Echo Amphitheatre Recreation Site in Carson National Forest, New Mexico as part of Phase II improvements. The split rail fencing will be constructed of treated Western Red Cedar and installed according to the standard detail sheet. Bidders must stake out the proposed fence alignment for approval before beginning construction. Payment will be made per linear foot of installed fencing, with concrete footings included in the base price. The solicitation number for this opportunity is 127EAX24R0005.

View the file

Other files

File Type Posted
Attachment 1 SOI.docx DOCX document
amendment 4.docx DOCX document
amendment 3.docx DOCX document
amendment 2.docx DOCX document
Amendment 2 Attachment 1.docx DOCX document
Amendment 1 Attachment 3.docx DOCX document
Amendment 1 Attachment 2.docx DOCX document
Amendment 1 Attachment 1.docx DOCX document
amendment 1.docx DOCX document
Section 00151 - Mobilization.docx DOCX document
Section 02100 - Timber Retaining Walls and Gravel Pad.doc DOC document
Section 02510 - Water Distribution.doc DOC document
Section 16400 - Underground Cable.doc DOC document
Wage determination.pdf PDF
ECHO Drawings.pdf PDF
Section 02316 - Excavation Trenching and Backfilling for Utility Systems.doc DOC document
127EAX24R0005.pdf PDF
Section 02101 - Road and Campsite Resurfacing.doc DOC document
Section 02102 - Clearing and Grubbing.doc DOC document
Section 02104 - General Recreation Site.doc DOC document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02103

split rail fence

PART 1 - GENERAL

1.1 SUMMARY

This work shall consist of installing split rail fencing on various intervals along the path leading up to the Amphitheater.

1.2 MEASUREMENT

A. Split rail fencing will be measured per linear foot.

B. The actual quantities will be paid for at the contract unit price for each pay item shown in the Schedule of items. Actual quantities are defined as the actual physical quantity of material needed to accomplish the work outlined in this section to deliver a product that is both safe and acceptable. If construction requires a higher quantity of material than what has been shown in the Schedule of items, contractor shall coordinate with the CO for approval prior to construction and/or purchasing and billing.

PART 2 – PRODUCTS

C. The split rail fencing shall be Treated Western Red Cedar or an approved equal.

D. Concrete for post footings shall be Quikrete High Strength Concrete Mix or an approved equal.

PART 3 – EXECUTION

1.3 split rail fence A. All debris, trees, stumps, roots, and other protruding vegetative material within the area of retaining wall, not DESIGNATED to remain, shall be cleared, grubbed, removed, and disposed of.

B. Contractor shall furnish and install Western Red Cedar Split Rail fencing in accordance with the standard detail on sheet X-19.

C. There are sections along the path where fencing may have a jog due to natural and/or manmade structures along the path. Contractor shall stake out their proposed alignment of the fencing and coordinate with COR for approval prior to construction.

PART 4 – MEASUREMENT & PAYMENT

4.1

MEASUREMENT & PAYMENT

A.

Payment for the split rail fence shall be per linear foot (LF).

B.

Concrete shall be incidental to the pay item for split rail fence.

END OF SECTION 02103