Section 00151 - Mobilization.docx
DOCX document 15 KB Posted
- Solicitation number
- 127EAX24R0005
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains a Section 00151 mobilization specification for a construction contract and details for a related federal solicitation. The specification outlines payment terms for mobilizing personnel, equipment, materials, and permits to the project site, including reimbursing bond premiums according to FAR 52.232-5 and paying 50% of the mobilization line item when 5% of the original contract amount is earned from other pay items, and the remaining 50% when 10% is earned. The related solicitation is for Phase II improvements to the GAOA Echo Amphitheatre recreation site in the Carson National Forest in New Mexico, issued by the USDA Forest Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 SOI.docx | DOCX document | |
| amendment 4.docx | DOCX document | |
| amendment 3.docx | DOCX document | |
| amendment 2.docx | DOCX document | |
| Amendment 2 Attachment 1.docx | DOCX document | |
| Amendment 1 Attachment 3.docx | DOCX document | |
| Amendment 1 Attachment 2.docx | DOCX document | |
| Amendment 1 Attachment 1.docx | DOCX document | |
| amendment 1.docx | DOCX document | |
| Section 02100 - Timber Retaining Walls and Gravel Pad.doc | DOC document | |
| Section 02510 - Water Distribution.doc | DOC document | |
| Section 16400 - Underground Cable.doc | DOC document | |
| Wage determination.pdf | ||
| ECHO Drawings.pdf | ||
| Section 02316 - Excavation Trenching and Backfilling for Utility Systems.doc | DOC document | |
| 127EAX24R0005.pdf | ||
| Section 02101 - Road and Campsite Resurfacing.doc | DOC document | |
| Section 02102 - Clearing and Grubbing.doc | DOC document | |
| Section 02104 - General Recreation Site.doc | DOC document | |
| Section 02103 - Split Rail Fence.doc | DOC document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 00151. — MOBILIZATION
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds.
Payment
151.02 The accepted quantities will be paid at the contract price per unit of measurement for the Section 151 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.
Progress payments for mobilization by the lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from pay items (not including mobilization), 50 percent of the mobilization pay item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from pay items (not including mobilization), 100 percent of the mobilization pay item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization pay item in excess of 10 percent of the original contract amount will be paid after final acceptance.