SECTION 02 41 00 Demolition.docx
DOCX document 21 KB Posted
- Attached to
- Y1DA--NRM: 640-19-100 Replace and Modernize Elevators at Building 100 Federal contract opportunity
- Solicitation number
- 36C26121R0044
About this file
This document contains specifications for selective demolition work related to the modernization of elevators in Building 100 at the VA Palo Alto Health Care System. The work includes completely demolishing and removing existing equipment and electrical systems, as well as cutting roof coverings and structural members to allow for removal of old equipment and installation of new systems. Upon completion, the site must be cleaned and left in a satisfactory condition. The related federal contract opportunity is solicitation number 36C26121R0044 for the modernization of elevators in Buildings 100 and 101 at the VA Palo Alto Healthcare System, to be awarded by the Department of Veterans Affairs Veterans Health Administration VISN 21. Selective demolition specifications require protecting facilities and occupants from hazards during removal work, preventing dust and debris spread, and ensuring structural support.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace and Modernize Elevators at Building 100 640-19-100 Palo Alto, Building 100, VA Palo Alto Health Care System Final Bid Document
02 41 00
SELECTIVE DEMOLITION
PART 1 GENERAL
1.1 DESCRIPTION:
This section specifies demolition and removal of portions of buildings, utilities, other structures and debris.
1.2 RELATED WORK:
A. Not Used.
1.3 PROTECTION:
| A. | Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures. Comply with requirements of GENERAL CONDITIONS Article, ACCIDENT PREVENTION. |
| B. | Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations. Comply with requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES AND IMPROVEMENTS. |
| E. | Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the work area daily. |
| F. | NOT USED: |
| G. | Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Medical Center; any damaged items shall be repaired or replaced as approved by the Contracting Officers Representative. The Contractor shall coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition or removal works. Repairs, reinforcement, or structural replacement must have Contracting Officers Representative’s approval. |
| H. | The work shall comply with the requirements of Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS. |
| I. | The work shall comply with the requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article 1.7 INFECTION PREVENTION MEASURES. |
1.4 UTILITY SERVICES:
| A. | NOT USED. |
| B. | NOT USED |
PART 2 - PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 DEMOLITION:
A. Completely demolish and remove equipment, electrical and associated materials.
B. Cut roof coverings, sheet metal and structural members as needed to provide an opening large enough to remove existing equipment and install new equipment.
C. Store removed roof section out of the way of lifting operations to ne reinstalled at the completion of the lifting operation(s).
3.2 CLEANUP:
On completion of work of each phase and after removal of all debris, leave site in clean condition satisfactory to Contracting Officers Representative. Cleanup shall include off the Medical Center disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.
07 92 00 - 1