PAD B100 B101 Elevator Interior Finsh Spec.docx

DOCX document 51 KB Posted

Attached to
Y1DA--NRM: 640-19-100 Replace and Modernize Elevators at Building 100 Federal contract opportunity
Solicitation number
36C26121R0044
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21

About this file

This document contains specifications for elevator cab interior finishes and flooring for the modernization of elevators in Buildings 100 and 101 at the VA Palo Alto Healthcare System. Key requirements include stainless steel, glass, and terrazzo tile materials. For the elevator walls, the specifications call for stainless steel panels in a seastone finish, stainless steel etched patterns, and lightweight glass panels. The handrails and ceiling are also to be made of stainless steel. The flooring material is specified as terrazzo tiles no less than 3/16 inches thick in an off-white field color with a gray accent color to match the hallway flooring. Installation is to comply with the manufacturers' instructions and applicable standards.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--NRM: 640-19-100 Replace and Modernize Elevators at Building 100, newest first.
File Type Posted
CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL.docx DOCX document
S02 - RFI FORM.docx DOCX document
SECTION 02 41 00 Demolition.docx DOCX document
138-18-28 Lock out Tag out.docx DOCX document
P07 Wage Determination CA20210018 03.05.21.pdf PDF
Addendum1-B100 B101_Elevator_Interior_Dwg.pdf PDF
SECTION 01 74 19 Construction Waste Management.docx DOCX document
SECTION 01 57 19 Temporary Environmental Controls.docx DOCX document
SECTION 01 35 36 Safety Requirements.docx DOCX document
SECTION 01 32 16 15 Project Schedule.docx DOCX document
138-17-19 WORKING ON ELECTRICAL DISTRIBUTION SYSTEMS.doc DOC document
S02 Price Breakdown by Division.docx DOCX document
014500 Quality Control.docx DOCX document
SECTION 01 33 32 Shop Drawings Product Data and Samples.docx DOCX document
SECTION 01 00 00 General Requirements Elevator Updated 03.01.21.rtf RTF text file
36C26121R0044.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAD B100 and B101 Elevator Upgrade Project Salient Characteristics for Elevator Cab Interior Finishes:

I. Ceiling:

· Satin stainless steel panels, and concealed access panel

· Six-panel suspended island design

· 6 LED downlights with all glass housing, color temperature: 3000K, CRI:80+, Lumens: minimum 450lm/ lamp

II. Wall panels: Forms + Surfaces LEVELe-106 Elevator Interiors, or equal

· Versatile panelized system with self-revealing extrusion channels, aluminum framed panels

· Extruded aluminum panel frame to have mitered corners in clear finish

· Panel inset consist of a decorative face material bonded to a fire-rated substrate

· The cab rear corners to have 90 degree angled reveals; front corners to have flat reveal strips

· The stainless steel base of no more than 4” to be fitted between the finish floor and the wall panels

· Wall panels below the handrail panels to have stainless steel in Seastone finish, or equal

· Rear wall panels above the handrail panels to have lightweight glass panel: Diamalite ViviSpectra Spectrum glass with custom image interlayer. The glass panel consists of one transparent lite of glass and reflective glass backer, both tempered. Configuration: Reflect, Finish: Standard and LumiLevel #1, or equal

· The two side wall panels above the handrail panels to have Stainless Steel Eco-Etch Patterns, panel pattern and color to be determined or equal

III. Handrail:

· 1-1/2” diameter tubular rail with tee standoffs join segment of Sextant rail, or equal

· Satin stainless steel finish

· Finial style: Cylinder, polished stainless steel finish

· Handrails to be mounted on handrail panels with pre- drilled holes

· 2 handrails on each 3 sides of the elevator cab, total 6 handrails in each elevator cab.

· The bottom handrails shall be mounted at 30” On Center AFF and the second handrail shall be mounted at 42” On Center AFF

IV. Flooring: Terrazzo Tiles

· Material: Homogenous terrazzo floor tile

· Tile thickness: No less than 3/16”

· Tile dimension: 24”x24” tile

· Critical Radiant Flux (ASTM E648) Class 1: 0.45 w/cm 2 or higher

· Static Coefficient (ASTM D2047) Slip Coefficient, minimum 0.80

· Smoke density (ASTM E662) Maximum specific optical density <450

· Antistatic Behavior (EN1815) Antistatic: less than 2 kilovolts (kV)

· Static load limit (ASTM F970) >1000psi

· Durometer Hardness (ASTM D2240) Shore A: >100

· Chemical Resistance (ASTM F925): Best, no change

· Finish: To match the hallway terrazzo flooring. Ground and polished to specified diamond grit finish

· Colors and pattern: An off-white field colors and a gray accent color to match the terrazzo flooring in the hallway. See Addendum 1 for the pattern layout.

· Adhesive: Mapei Ultrabond ECO 373 low emitting VOC adhesive, or equal

· Product Warranty- (20 years) warranty from time of final inspection to be free from manufacturing defects

Drawing of design intent for the elevator wall panels and ceiling.

PAD B100 Elevator Upgrade Project

SECTION 14 27 00 ELEVATOR CAB INTERIOR SYSTEMS

Part 1 GENERAL

1.1 Summary

A. Section Includes: Elevator cars and elevator car finishes for electric traction and hydraulic elevators. Pre-engineered elevator interior system including rear and side wall panels, handrail, bases, ceiling and lighting. Elevator interior system comes “ready to install” with fasteners, adhesives, and other materials required for a complete assembly. Fasteners shall be concealed type.

B. Related Sections:

1. Section 09 77 00 – Special Wall Surfacing
2. Section 05 75 00 – Decorative Formed Metal
3. Division 16 – Electrical. General requirements for electrical and lighting specified in thisSection.

1.2 References

A. ASTM E84 – Surface Burning Characteristics of Building Materials.

B. ASME A17.1 – Safety Code for Elevators and Escalators.

1.3 Submittals

A. Provide submittals in accordance with Section 01 30 50 and Section 14 21 23 – Submittal Procedures.

B. Submit manufacturer’s shop drawings, installation drawings, installation instructions and maintenance instructions.

C. Submit environmental impact data for all materials.

D. Submit samples no less than 6" x 6" for all specified material finishes.

E. Submit panel edge extrusion samples no less than 6” of specified finish.

F. Manufacturer information:

1. Provide overview literature describing manufacturer’s overall scope of products andmanufacturing capabilities.
2. Provide URL for manufacturer’s web site; web site must provide access to technical data,images and general product information.

1.4 Quality Assurance

A. Manufacturer Qualifications

1. Minimum 10 years experience in the manufacture of architectural surface materials.
2. Minimum 10 years experience in the fabrication of elevator cab interiors.
3. Provide reference list of at least 20 public space projects currently using elevator interiorsfabricated by the manufacturer.

B. Installer Qualifications

1. Minimum Five years of experience in the installation of elevators or elevator interiors.

1.5 Delivery, Storage and Handling

A. Deliver materials to installation site in manufacturer’s original packaging. Handle products in accordance with manufacturer’s instructions. Store in dry, secure location, protected against direct sunlight and excessive heat. Protect finished surfaces with strippable film.

1.6 Warranty

A. Provide manufacturer’s standard warranty.

1. Warranty terms: one year against defects in materials and workmanship.

Part 2 PRODUCT

2.1 Elevator Rear and Side Wall Panels

A. General

1. Provide interlocking grid panel system with inset panels mounted in extruded aluminumframes on fire-rated structural backer.
2. Panel configuration: Level e-106. See drawing for panel layout on p.2.
3. Provide inset panels in the finishes specified.
4. Weight per square foot: average 2.40 lbs to 3.04 lbs
5. Provide interlocking, self-revealing grid frame system comprising no more than five distinctextruded profiles, one to be used as the visible inset panel frame and one to be used as theconcealed frame mounting bracket.
6. Total thickness of installed grid frame and mounting bracket shall be no more than 1.125".

B. Inset Materials

1. Stainless Steel Panels
a. Material: Stainless Steel.
b. Finish: Seastone
c. Fire rating: Stainless Steel is inherently non-combustible and generally considered tobe NFPA and IBC Class A fire rated and UBC Class 1 fire rated.
d. Treatment: Provide Ceramiloc™ treatment, an invisible, protective treatmentthat significantly increases the fingerprint resistance and maintenance ease of stainlesssteel. Patented technology molecularly bonds nano-silica particles to thesurface of stainless steel.
2. Stainless Steel Eco-Etch Patterns Panel
a. Pattern and finish to be determined
b. Etched patterns to be applied using eco-friendly photolithographic bead blastingprocess
c. Fire rating: Stainless Steel is inherently non-combustible and generally considered tobe NFPA and IBC Class A fire rated and UBC Class 1 fire rated.
d. Treatment: Provide Ceramiloc™ treatment, an invisible, protective treatmentthat significantly increases the fingerprint resistance and maintenance ease of stainlesssteel. Patented technology molecularly bonds nano-silica particles to thesurface of stainless steel.
3. Lightweight Glass Panels
a. Material: Forms+Surfaces Diamalite Glass Panels: ViviSpectra Spectrum with customartwork, or equal
b. Fire rating: ViviSpectra Spectrum glass is Class A fire rated in accordance withASTMdesignation E84-09, standard test method of surface burning characteristicsof building materials. The foregoing test procedure is comparable to UL 723, ANSI/NFPANo. 255, and UBCNo. 8-1.

C. Base

1. Stainless Steel Panels
a. Material: Stainless Steel.
b. Finish: Forms+Surfaces Satin, or equal

D. Panel Frames and Reveals

1. Material: Extruded, anodized aluminum
2. Finish: Clear

2.2 Handrail

A. General

1. Provide (2) handrails on rear and side walls of single opening cars, total 6 handrails per car.
2. Style: Forms+Surfaces Sextant Series, Cylinder or equal
3. Material: Satin stainless steel
4. Finial and Tee Standoff: Polished stainless steel

2.3 Ceiling System

A. General

1. Provide Forms+Surfaces LEVELe Ceiling with inset panels mounted in extruded aluminumceiling frame on fire-rated polycarbonate backer and integral lighting system, or equal.
2. Provide removable exit hatch as per ASME A17.1 for emergency egress.

B. Ceiling Materials

1. Ceiling Inset Material
a. Material: Stainless Steel
b. Finish: Satin
2. Lighting
a. Configuration: Recessed low-voltage LED downlights. See drawing for lighting layouton p.2.
b. Color temperature: 3000-3500K

Part 3 EXECUTION

3.1 Preparation

A. Protect elevator finishes, fixtures and equipment from damage caused by work of this Section.

3.2 Installation

A. Do not make structural changes to elevator cab. Do not install work in a manner that interferes with the safe operation of elevator.

B. Install in accordance with elevator interior system manufacturer’s instructions.

3.3 Cleaning and Protection

A. Remove strippable film. Clean exposed surface in accordance with manufacturer’s instructions.

B. Protect exposed surfaces from damage by subsequent construction.

PAD B100 Elevator Upgrade Project

SECTION 09 66 16 TERRAZZO FLOOR TILE

PART 1 - GENERAL

1.1 DESCRIPTION:

A. This section specifies requirements for terrazzo tile for installation for elevator cab flooring.

1.2 RELATED WORK:

A. Color, Size, Thickness, Finish and Type: See Salient Characteristics of Flooring on p.1.

1.3 QUALITY ASSURANCE:

A.Approval by Contracting Officer Representative (COR) is required of products or service, or proposed manufacturer, suppliers and installers, and will be based upon submission by Contractor of certification that:
1.Manufacturer has manufactured terrazzo tile as one of his principal products for a minimum of five (5) years. Submit list of not less than five (5) installations. List is to include name of project, and owner and location of project. Submit manufacturer’s qualifications.
2.Installer has installed terrazzo tile for a minimum of five (5) years. Submit installer’s qualifications.

1.4 SUBMITTALS:

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Sustainable Design Submittals, as described below:

1. Postconsumer and pre-consumer recycled content as specified in PART 2 - PRODUCTS.

2. For flooring adhesive installation containing volatile organic compounds, provide documentation indicating applicable volatile organic compounds per volume as specified in PART 2 - PRODUCTS.

C.Flooring Manufacturer's Literature and Data: Printed pre-installation and installation instructions for conditions indicated.
D.Certificates: Indicating materials conform to specified requirements. Indicating flooring manufacturer's approval of underlayment, substrate preparation, adhesive finishes and cleaners.
E.Samples: Terrazzo Tile each color, size, finish, and type to be used.

F. Manufacturer’s qualifications including list of installations.

G. Installer’s qualifications.

H. Manufacturer’s warranty.

1.5 DELIVERY:

A. Deliver materials to job in manufacturer's original unopened containers, free of damage, with manufacturer's brand name marked thereon.

1.6 STORAGE:

A. Store materials in a protected area. That is kept dry and has a temperature not lower than 18 degrees C (65 degrees F) or higher than 27 degrees C (80 degrees F).

1.7 PROJECT CONDITIONS:

A. Do not install tiles until all other work that could cause damage to the finish flooring has been completed. Acclimate tiles and maintain spaces where tile is to be installed to a temperature of not less than 21 degrees C (70 degrees F) for at least 48 hours before, during and after the installation of tiles. A minimum temperature of 13 degrees C (55 degrees F) is to be maintained thereafter.

1.8 warranty:

A. Construction Warranty: Comply with FAR clause 52.246-21, “Warranty of Construction”.

1.9 APPLICABLE PUBLICATIONS:

A.The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by basic designation only.
B.ASTM International (ASTM):
C97/C97M-09Test Methods for Absorption and Bulk Specific Gravity of Dimension Stone
C109/C109M-13Compressive Strength of Hydraulic Cement Mortars
C501-84(R2009)Test Method for Relative Resistance to Wear of Unglazed Ceramic Tile by the Taber Abraser
E84-14Test Method for Surface Burning Characteristics of Building Materials
E90-09Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Element
E413-10Classification for Rating Sound Insulation
E492-09Standard Test Method for Laboratory Measurement of Impact Sound Transmission Through Floor-Ceiling Assemblies Using the Tapping Machine
E648-14cCritical Radiant Flux of Floor Covering Systems Using a Radiant Heat Energy Source
E989-06Standard Classification for Determination of Impact Insulation Class
F1869-11Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride
F2170-11Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in Situ Probes
C.Code of Federal Regulation (CFR):
40 CFR 59Determination of Volatile Matter Content, Water Content, Density Volume Solids, and Weight Solids of Surface Coating

D. Tile Council of North America (TCNA):

DCOF AcuTest-2012 Dynamic Coefficient of Friction Test

PART 2 - PRODUCTS

2.1 TERRAZZO TILE:

A. Provide terrazzo tile that is of color, size, thickness, finish and type as specified in Section 09 06 00, SCHEDULE FOR FINISHES. Tiles are to consist of marble, glass and stone chips embedded in a resilient polyester resin matrix. Chips sizes and gradation to match the terrazzo flooring in the hallway. Provide tile with the following properties.

1. Recycled Content of Terrazzo Products: Post-consumer content not less than 20%, pre-consumer content not less than 15%.

TERRAZZO TILE PROPERTIES

PROPERTY
TEST METHOD
VALUE
Static Load
ASTM F970

Less than or equal to 0.005” under 1000 lbs.

Residual Indentation
EN433
<0.2mm Pass
Shore Hardness
ASTM D2240
Shore Hardness Type A >100
Slip Resistance/ Coefficient of Friction
ASTM D2047 Slip Coefficient
0.80
Smoke Density
ASTM E662
Pass- max. 450 in the flaming and non-flaming mode
Critical Radiant Flux
ASTM E648
Class I

2.2 ADHESIVE:

A. Provide terrazzo tile manufacturer's standard product or a product recommended by the terrazzo tile manufacturer.

1. Adhesive to have a VOC content of 70 g/L or less when calculated according to 40 CFR 59, (EPA Method 24).

2.5 METAL EDGE STRIPS:

A. Extruded aluminum, butt-type, 38 mm (1-1/2 inches) wide with thickness to set top surface flush with top of tile and with bevel at exposed edge. Edge strips to have countersunk holes, within 12 mm (1/2 inch) of each end and spaced at no more than 203 mm (8 inches) on center for securement.

PART 3 - EXECUTION

3.1 GENERAL:

A. Provide terrazzo tile flooring on the (5) elevator floors as shown on the plan on Addendum 1. After becoming familiar with details of the work, verify dimensions in the field, and advise the COR of any discrepancy before performing the work.

3.2 INSTALLATION:

A.Install tile in accordance with the tile manufacturers approved installation instructions, except as specified herein. Lay design symmetrical about center lines of rooms. Joints are to be maximum 0.79 mm (1/32 inch) and in true alignment. Cut tile to fit snugly at pipes and other fixed vertical surfaces. Seal joints at pipes with silicone. Remove spots or smears of adhesive immediately. Make entire surfaces of finished tile floors smooth, straight, and free from bleeding adhesive, buckles, waves or projecting tile edges upon completion.
B.Metal Edge Strips: Secure strips with No. 10 aluminum alloy, counter sunk flathead machine screws with expansion sleeves. Provide metal edge strips, in one (1) piece, at any exposed edges of tile.
C.For tile pattern, see elevator cab floor plan on Addendum 1.

D. Lay flooring flush with threshold plate and base.

3.4 CLEANING:

A. Upon completion and after adhesive has cured, clean flooring in accordance with manufacturer's recommendations.

3.5 PROTECTION:

A. From the time of laying until acceptance, protect the flooring from damage. Replace damaged, loose, broken, or curled tiles. Except as necessary to install new tile, keep all traffic off new tile for at least 24 hours after installation.