This is a Performance Bond template document for construction contracts in the Commonwealth of Massachusetts, applicable to the Sleepy Hollow Road Bridge Replacement Project in the Town of Richmond. The bond establishes a binding agreement between the contractor (Principal), a surety licensed by the State Division of Insurance, and the Town/City Owner. The bond guarantees that the Principal will faithfully perform all duties, undertakings, covenants, terms, conditions, and agreements of the Construction Contract during its original term and any extensions granted by the Owner. The bond amount is to be filled in by the parties and represents the penal sum in lawful U.S. currency. The Surety's obligation is triggered only after the Owner declares the Principal in default of the Construction Contract or determines that the Principal has failed, is unable, or is unwilling to execute work consistent with contract specifications.
Upon a declared Contractor Default, the Surety must promptly elect one of three remedial actions: arrange for the Principal to complete the work, arrange for an alternative contractor to complete the work, or reimburse the Owner for all costs and expenses incurred in performing and completing the work. The Surety's liability extends to correction of defective work, completion of the Construction Contract, additional design and professional services, legal costs including attorneys' fees, any additional work necessitated by the default, indemnification obligations, and liquidated or consequential damages as specified in the Construction Contract. The bond remains in full force regardless of changes, extensions, alterations, or additions to the Construction Contract terms, work scope, or specifications, and the Surety waives notice of any such modifications. Any legal proceedings arising under this Bond shall be instituted in a court of competent jurisdiction in the Commonwealth of Massachusetts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 00610
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS: That we ___________________________ (Name of Contractor) a ___________________________________________ hereinafter called “Principal” and (Corporation, Partnership, Joint Venture or Individual)
______________________________of ______________, State of ______________________ (Surety) (City & State)
_________________________ hereinafter called the "Surety" and licensed by the State Division of Insurance to do business under the laws of the Commonwealth of Massachusetts, are held and firmly bound to the City/Town of _______________, Massachusetts, hereinafter called "Owner", in the penal sum of ______________________________________________________ Dollars ($______________________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a certain contract with the Owner, dated the __________ day of _________________, 20___ (the “Construction Contract”), for the construction described as follows: ___________
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of the Construction Contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under the Construction Contract, and shall fully indemnify and save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the Surety’s obligation under this Bond shall arise after (1) the Owner has declared the Principal in default of the Construction Contract or any provision thereof or (2) has declared that the Principal has failed, or is otherwise unable or unwilling, to execute the work consistent with, and in conformance to, the Construction Contract (collectively referred to as a “Contractor Default”). The determination of a Contractor Default shall be made solely by the Owner. The Owner need not terminate the Construction Contract to declare a Contractor Default or to invoke its rights under this Bond.
When the Surety’s obligation under this Bond arises, the Surety, at its sole expense and at the consent and election of the Owner, shall promptly take one of the following steps: (1) arrange for the Principal to perform and complete the work of the Construction Contract: (2) arrange for a contractor other than the Principal to perform and complete the work of the Construction Contract; (3) reimburse the Owner, in a manner and at such time as the Owner shall decide, for all costs and expenses incurred by the Owner in performing and completing the work of the Construction Contract. Surety will keep Owner reasonably informed of the progress, status and results of any investigation of any claim of the Owner.
If the Surety does not proceed as provided in this Bond with due diligence and all deliberate speed, the Surety shall be deemed to be in default of this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner.
After the Surety’s obligation under this Bond arises, the Surety is obligated, to the limit of the amounts of this Bond, for (1) the correction of defective work and completion of the Construction Contract; (2) additional design, professional services, and legal costs, including attorneys’ fees, resulting from the Contractor Default or from the default of the Surety under this Bond; (3) any additional work beyond the Construction Contract made necessary by the Contractor Default or default of the Surety under this Bond; (4) indemnification obligation of the Principal, if any, as provided in the Construction Contract; and (5) liquidated damages as provided in the Construction Contract, or if none are so specified, actual and foreseeable consequential damages resulting from the Contractor Default or default of the Surety under this Bond.
Any proceeding, legal or equitable, under this Bond shall be instituted in any court of competent jurisdiction in the Commonwealth of Massachusetts.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Construction Contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Construction Contract or to the work or to the specifications.
IN WITNESS WHEREOF, this instrument is executed in _____ ( ) counterparts, each one of which shall be deemed an original, this the __________ day of ____________________, 20___.
ATTEST:
Principal
______________________________ By ______________________________ (Principal Secretary)
(Address-Zip Code)
______________________________ (SEAL)
Witness as to Principal
(Address-Zip Code)
ATTEST:
Surety
______________________________ By ______________________________ (Attorney-in-Fact)
(Address-Zip Code)
______________________________ (SEAL)