This is a Schedule of Items for a federal service contract issued by the Superior National Forest Supervisor's Office for snowplowing services at the warehouse facility.

The contract covers snow removal services at the warehouse site under a base period running from award through August 31, 2027, with four option years extending through August 31, 2031. The schedule of items is identical across all contract periods and includes three line items: (1) snow removal cost for snowfall of 7 inches or less per event, priced per each (EA) with an estimated quantity of 15; (2) snow removal hourly rate for snowfall exceeding 7 inches per event, priced per hour (HR) with an estimated quantity of 15; and (3) hourly rate for excess snow removal at the warehouse site, priced per hour with an estimated quantity of 15. All services include sanding and salting per attached specifications. The document provides the requisition number 723354 and establishes the pricing structure for both the base period and the four option years, though specific unit prices and totals are blank, indicating this is a pricing schedule to be completed by offerors during the solicitation process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NUMBER

DESCRIPTION

PAY

UNIT

EST

QTY

Unit Price Total

Snow removal cost for 7” or less of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

EA 15

Snow removal hourly rate for over 7” of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

HR 15

0003 Hourly rate for excess snow removal at warehouse site HR 15

ITEM

NUMBER

DESCRIPTION

PAY

UNIT

EST

QTY

Unit Price Total

Snow removal cost for 7” or less of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

EA 15

Snow removal hourly rate for over 7” of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

HR 15

1003 Hourly rate for excess snow removal at warehouse site HR 15

Period of Performance Base Period: Upon award - 8/31/2027

Period of Performance Option Year 1: 9/01/2027 - 8/31/2028

SCHEDULE OF ITEMS

Superior National Forest Supervisor's Office

PROJECT TITLE: Snowplowing SO Warehouse

WORKPLAN ACQUISITION PLAN/REQUISITION NO: 723354

ITEM

NUMBER

DESCRIPTION

PAY

UNIT

EST

QTY

Unit Price Total

Snow removal cost for 7” or less of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

EA 15

Snow removal hourly rate for over 7” of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

HR 15

2003 Hourly rate for excess snow removal at warehouse site HR 15

ITEM

NUMBER

DESCRIPTION

PAY

UNIT

EST

QTY

Unit Price Total

Snow removal cost for 7” or less of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

EA 15

Snow removal hourly rate for over 7” of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

HR 15

3003 Hourly rate for excess snow removal at warehouse site HR 15

ITEM

NUMBER

DESCRIPTION

PAY

UNIT

EST

QTY

Unit Price Total

Snow removal cost for 7” or less of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

EA 15

Snow removal hourly rate for over 7” of snowfall, per event, at the warehouse site to include sanding/salting, per attached specifications.

HR 15

4003 Hourly rate for excess snow removal at warehouse site HR 15

EA - EACH, HR - HOUR

Period of Performance Option Year 2: 9/01/2028 - 8/31/2029

Period of Performance Option Year 3: 9/01/2029 - 8/31/2030

Period of Performance Option Year 4: 9/01/2030 - 8/31/2031