This is a sample construction agreement between the City and County of Broomfield, Colorado, and an unnamed contractor for the Stoneybrook Drive Retaining Wall Replacement project (Project No. 24T0030). The project involves renovating a retaining wall located behind residential properties at 5524 and 5444 Stoneybrook Drive. The scope of work includes removing an existing wood retaining wall, installing new redi-block wall units, performing construction surveying, tree protection, grading and drainage work, excavation, pond water control, and associated site restoration. The contract has a completion timeline of 105 calendar days from the start date, with work hours restricted to Monday through Friday, 7 a.m. to 7 p.m., and limited Saturday work possible with pre-approval.
The contract requires the contractor to obtain a Class C contractor's license and a no-fee Public/Private Improvement (PPIP) permit. Performance and labor/material payment bonds are mandatory for contracts exceeding $50,000, and retainage will be withheld for contracts over $150,000. The contractor must maintain site cleanliness, minimize public impacts, and implement Best Management Practices for stormwater control. Insurance requirements and specific documentation are outlined, with the city retaining the right to terminate the contract with proper notice. The total contract price is not specified in the document, but payment will be made monthly based on completed work, with 95% of the contract price paid and 5% retained until final project acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Document Package.pdf | ||
| Bid Form.xlsx | XLSX spreadsheet | |
| Cattail Removal Specifications - Add Alternate.pdf | ||
| Project Plans.pdf | ||
| Project Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMPLE CONSTRUCTION AGREEMENT
FOR
STONEYBROOK DRIVE RETAINING WALL REPLACEMENT
PROJECT NO. 24T0030
1. PARTIES. The parties to this Construction Agreement (this “Agreement”) are the City and County of Broomfield, a Colorado municipal corporation and county, (the “City”) and , (the “Contractor”), collectively, the “Parties,” or individually, a
“Party.”
2. RECITALS. The Recitals to this Agreement are incorporated herein by this reference as though fully set forth within the body of this Agreement.
2.1. The City, seeking construction services for Redpoint Ridge Park Landscape
Renovation completed a competitive selection process by invitation to bid (ITB) issued on July 31, 2025.
2.2. The Contractor’s response to the above referenced ITB was determined to be of best value, responsible, responsive bidder to the City for the procurement of the services requested.
2.3. The Parties therefore desire to enter into a Construction Agreement for completion of the services further described herein.
3. TERMS AND CONDITIONS. In consideration of the mutual covenants and promises of the Parties contained herein, and other valuable consideration, the receipt and adequacy of which are hereby acknowledged, the Parties agree as follows:
3.1. Work. The Contractor agrees to furnish all necessary labor, materials, equipment, tools, and services necessary to perform in a workmanlike manner the work (hereinafter “Work”) described in the Scope of Work attached hereto as Exhibit A and incorporated by this reference.
3.1.1. Key Personnel. The Contractor’s key personnel shall include (i) the
[Project Executive - insert name]; (ii) the [Field Superintendent - insert name] and (iii) the [Project Manager - insert name]. The Contractor's obligation to provide adequate staffing is not limited to providing the key personnel, but is determined by the needs of the Project. The
Contractor shall not replace any of the key personnel without the City’s prior written approval, which shall not be unreasonably withheld. If any of the key personnel become unavailable to perform services in connection with this Agreement due to death, illness, discharge or resignation, then the Contractor shall promptly appoint a replacement acceptable to the City. The City shall be entitled to complete information on each such replacement, including a current resume of his or her qualifications and experience.
3.2. Contract Documents. The Contract Documents shall consist of the following:
3.2.1. This Agreement; and
3.2.2. The Scope of Work attached hereto as Exhibit A;
3.2.3. The Contractor’s Cost Proposal dated __________, 2025, attached hereto as Exhibit B; and
3.2.4. The ITB; and
3.2.5. The Construction Plans for Project No. 24T0030; and
3.2.6. The General Conditions attached hereto as Exhibit D; and
3.2.7. Any change orders and contract amendments, as applicable; and
3.2.8. Colorado Department of Transportation Standard Specifications for Road and Bridge Construction (2023), as amended; and
3.2.9. Project Specifications and Electrical Specifications for Project No. 24T0030;
and
3.2.10. The Insurance Requirements attached hereto as Exhibit C, all of which are incorporated by reference as though set forth in full herein, whether or not attached hereto and shall form an integral part of this
Contract. If there is any conflict between this Agreement and the other
Contract Documents, this Agreement shall control.
3.3. Access and Inspection. The City and its representatives shall at all times have access to the Work. The Contractor shall provide proper facilities for access to and for inspection of the Work for the purpose of determining compliance with this
Agreement and quality of workmanship and material. All materials, equipment and supplies used in the performance of the Work shall be subject to adequate inspection and testing in accordance with generally accepted standards. The City
Representative may order that portions of the Work be uncovered, exposed or made available for observation, inspection or testing at no additional cost. The
Contractor shall provide all labor, tools, materials, equipment and supplies necessary to comply with the request of the City Representative. If any portion of the Work is determined to be defective, the Contractor shall bear all costs involved to bring the Work into compliance with the Agreement, including without limitation the cost to replace any materials, to re-perform or to reconstruct. The
Contractor shall remove from the work site all work or materials rejected by the
City for failure to comply with the Contract whether incorporated in the Work or not at no additional cost to the City.
Construction Asset Replacement
Updated 8/26/2022
3.4. Site Clean-Up. On a daily basis, the Contractor shall maintain the work site free from accumulation of waste materials or rubbish caused by performance of the Work. The Contractor shall remove all rubbish, tools, construction equipment, machinery, and surplus material from the work site. If the
Contractor fails to maintain the work site in an appropriate condition, the City may, after notice to the Contractor, perform any necessary clean-up and charge the clean-up costs to the Contractor.
3.5. Protection of Property. All existing finishes, structures, utilities, services, roads, trees, shrubbery, etc. located on City property and adjacent property impacted by the Work shall be protected against damage or interrupted services at all times by the Contractor during the term of the Work. The
Contractor shall be responsible for repairing or replacing any and all property which is damaged by reason of the Contractor’s operation on the property to the satisfaction of the City within three (3) weeks of the notification of such damage, which may be extended with written approval of the City.
3.6. Utilities. The Contractor shall fully comply with the provisions of Article 1.5 of
Title 9 of the Colorado Revised Statutes including, but not limited to, providing notices to the notification association. Unless otherwise provided in the Scope of Work, the Contractor shall be responsible for communicating and coordinating with utilities, as necessary. The Contractor shall cooperate with utilities and the City as provided in this Agreement and as required by law. The
Contractor shall be responsible for determining the exact location of utilities that may interfere with construction of the Work by exploratory excavation sufficiently in advance of beginning construction in an area so that potential conflicts may be resolved. The Contractor will consider in the Contract Price all of the utility appurtenances within the project; and the Contractor shall not make a claim for delay or additional compensation due to any relocation operations by a utility.
3.7. Documents on Site. The Contractor shall maintain at the site for the City one electronic or hard copy of all drawings, specifications, addenda, change orders and other modifications, in good order and marked currently to record all changes made during construction. At the City’s option, the referenced record drawings will be reviewed monthly by the City for acceptability. If, in the judgment of the City, the Contractor fails or refuses to keep these documents current, the Contractor shall not be entitled to progress payments until it makes the necessary changes to the documents to make them current.
3.8. Differing Site Conditions. The Contractor acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and review of the
Contract Documents.
3.8.1. Contractor shall give immediate written notice to the City
Representative if it encounters a “Differing Site Condition,” defined as either:
3.8.1.1. Subsurface or latent physical conditions at the site which differ materially from those indicated in the Contract Documents; or
3.8.1.2. Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this Contract.
3.8.2. Contractor acknowledges that no request for a change order or modification in Contract Price resulting from a Differing Site Condition shall be allowed unless immediate written notice is provided and the conditions remain undisturbed until the City has the opportunity to investigate.
4. Completion Date. Within ten (10) calendar days of receipt of executed Agreement, the
Contractor shall provide the City acceptable bonds, if applicable, and certificates of insurance. A Notice to Proceed will be issued upon City approval of the bonding and insurance. The Contractor shall perform no Work until the City Representative issues a
Notice to Proceed.
The Contractor shall begin the Work on or before the fifth (5th) calendar day after receipt of the Notice to Proceed. The Notice to Proceed will stipulate the date on which the contract time count commences (the “Start Date”). The Contractor shall complete the Work and fulfill all of its other obligations within one hundred and five
(105) calendar days of the Start Date (the “Completion Date”). The time between the
Start Date and the Completion Date shall be known as the “Contract Time.”
All time limits are of the essence in this Agreement. The Contractor acknowledges that a notice to proceed will not be issued until the City has received acceptable certificates of insurance and bonds, if applicable.
5. CONTRACTOR’S PROJECT SCHEDULE. The Contractor shall submit a completion schedule for the Work (the “Project Schedule”) beginning with receipt of the signed
Agreement and concluding with Project Completion prior to the commencement of the
Work and shall coordinate on a daily basis with the City’s project manager. The Project
Schedule shall include all lead time for the order and delivery of equipment for the
Work. Schedule updating shall be done on a weekly basis, or more often as necessary
(each a “Schedule Update”). The revision shall indicate actual progress to date, changes resulting from change orders, and planned changes as necessary to complete the Work in accordance with the Contract Documents. All costs associated with the development and maintenance of the Project Schedule shall be borne by the
Contractor. Acceptance by the City of the Contractor’s Project Schedule does not relieve the Contractor of any of its responsibility whatsoever for the accuracy or feasibility of the Project Schedule, or of the Contractor’s ability to meet the Contract
Time, nor does such acceptance expressly or impliedly warrant, acknowledge or admit the reasonableness of the activities, duration, or cost loading of the Contractor’s
Project Schedule.
6. UNUSUALLY SEVERE WEATHER CONDITIONS.
6.1. It is expressly understood and agreed, by and between the Contractor and the
City, that the Contract Time for the completion of the Work is a reasonable time, taking into consideration the climatic and economic conditions and other factors prevailing in the locality of the Work. The Contract Time anticipates
“Normal” weather and climate conditions in and around the vicinity of the project site during the times of year that the construction will be carried out.
Extensions of time based upon weather conditions shall be granted only if the
Contractor demonstrates clearly that such conditions were “unusually severe,” would not have been reasonably anticipated, and that such conditions adversely affected the Contractor’s Work and thus required additional time to complete the Work.
6.2. The following specifies the procedure for the determination of time extensions for unusually severe weather. The listing below defines the anticipated number of calendar days lost to adverse weather for each month and is based upon
National Oceanic and Atmospheric Administration (NOAA) or similar data for the geographic location of the project.
ANTICIPATED CALENDAR DAYS LOST TO ADVERSE WEATHER CONDITIONS:
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL
7 5 4 3 3 2 2 2 2 3 3 7 43 day
6.3. The above schedule of anticipated adverse weather will constitute the base line for monthly (or portion thereof) weather time evaluations. Upon acknowledgement of the notice to proceed and continuing throughout the
Agreement on a monthly basis, actual adverse weather days and the impact of adverse weather days that delay the Work will be recorded on a day-to-day basis. It is assumed that the Work will be carried out Mondays through Fridays
(holidays excepted); however, non-standard work hours will be required as specified in the Statement of Work and as shown on the Project Schedule. The number of calendar days of delayed Work due to adverse weather or the impact thereof will then be compared to the monthly adverse weather schedule above.
6.4. An actual adverse weather day must prevent Work for 50 percent or more of the Contractor’s workday, delay Work critical to the timely completion of the
Project, and be documented by the Contractor. The Contractor shall notify the
City Representative in writing if work cannot proceed on a given date, within two calendar days of that date. The City will use the above written notification in determining the number of calendar days for which Work was delayed during each month.
6.5. At the end of each month if the number of calendar days for which Work was delayed due to adverse weather exceeds that shown in the above schedule a change order will be executed which increases the Contract Time.
6.6. The Contractor’s Project Schedule must reflect the above-anticipated adverse weather delays on all weather-dependent activities. While extension of time shall be granted for “unusually severe” weather or climate conditions, or the impact thereof, the City shall make no monetary compensation for any costs to the Contractor arising out of such delays. The Contractor shall comply with the portions of the Contract Documents relating to its Project Schedule and amendments thereto which result from the “unusually severe” weather condition.
7. PRICE AND PAYMENT. The City shall pay the Contractor for performance of the Work an amount not to exceed $_________ (the “Contract Price”) based upon the unit prices set forth on Contractor’s Cost Proposal attached hereto as Exhibit B and in accordance with the following schedule:
7.1. If the Contractor is satisfactorily performing the Agreement, the City shall make partial payments at the end of each calendar month or as soon thereafter as practicable of ninety-five percent (95%) of the Contract Price based on the calculated value of the Work completed (the “Partial Payments”) and shall retain five percent (5%) of the amount due to the Contractor (the “Retained
Amount”) until the Work is complete. If applicable, the Contractor shall make payments to its subcontractors in accordance with C.R.S. §24-91-103.
7.2. The City shall retain the Retained Amount until Final Acceptance (as defined in
Final Acceptance and Final Payment below). If the Contractor has completed the Work in a manner finally acceptable to the City, the City may authorize final payment from the Retained Amount upon written request by invoice of the Contractor (the “Final Payment”). Before the Final Payment is made, the
City and the Contractor, as applicable, shall comply with the Final Acceptance and Payment paragraph of this Agreement.
7.3. The Contractor shall, as soon as practicable after the end of each calendar month during performance of the Work, submit an itemized invoice for services performed, stating the percentage of the Work that has been completed and the type of services performed. Each invoice will also include an Application and Certificate of Payment form (AIA Document G702) or equivalent form approved by the City. The Contractor shall prepare the invoices at its sole cost and shall include sufficient detail to enable the City to verify the appropriateness of the invoice. Each invoice shall be subject to review and approval by the City Representative. The City shall not be required to pay disputed items until the dispute is resolved. Payment of any invoice shall not act as a waiver of the City’s right to recover in full any over-payment revealed by any subsequent audit or inspection. No air travel, car rental, entertainment, education expense, meals or similar or related costs shall be payable without prior written approval of the City. Incorrect payments to the
Contractor due to omission, error, fraud, or defalcation may be recovered from the Contractor by deduction from subsequent payments due the Contractor under this Contract or other contracts between City and Contractor.
7.4. Change Orders. The Contractor will do nothing to cause the Contract Price to increase without prior execution of a change order by the City. The City will issue no change order requiring additional compensable work to be performed, which work causes the aggregate amount payable under this Agreement to exceed the amount appropriated for this Agreement. Except as provided below and as provided in C.R.S. 24-91-103.6, the City shall have no duty or obligation whatsoever to compensate or to reimburse the Contractor for any additional work not specifically authorized as provided herein. In the event (i) the City requires additional compensable work to be performed by the Contractor prior to the execution or other finalization of a change order or contract amendment, and (ii) the Contractor has submitted to the City an estimate of the cost for the additional compensable work, then the City shall reimburse the
Contractor for the costs associated with such additional work on a periodic basis in accordance with the terms of this Agreement.
8. FINAL INSPECTION AND FINAL PAYMENT.
8.1. Final Inspection. The Contractor shall notify the City when the Work is complete and ready for final inspection by means of a letter of completion (the
“Letter of Completion”). Within ten (10) calendar days of the City’s receipt of the Letter of Completion, the City Representative shall make a final inspection to determine whether the Work has been completed in accordance with this
Agreement and shall submit a written list of any defects to the Contractor (the
“Punchlist”). The Contractor shall promptly correct all Punchlist items without additional cost to the City within ten (10) calendar days after receipt of the
Punchlist. If any Punchlist item cannot be corrected within ten (10) calendar days, the Contractor shall submit a letter to the City Representative for approval requesting an extension of time to complete such item (the “Request for Extension”). The Request for Extension must be received by the City
Representative within seven (7) calendar days of the Contractor’s receipt of the
Punchlist and shall include the Contractor’s justification for the request and a schedule for completion of the Punchlist item. The Contractor shall also deliver to the City, all statements to support state sales and use tax refunds and any as-built drawings. The Contractor shall provide the City with a letter of approval for contract closure from any surety furnishing bonds for the Work provided on AIA Form G707 (Consent of Surety Letter) or equivalent form.
8.2. Final Payment. Upon satisfactory completion of the Work, the City
Representative will provide the Contractor with a written acceptance of the
Work (the “Final Acceptance”). Payment shall not be made until the City
Representative has approved the payment and a notice of contractor’s settlement has been published in accordance with C.R.S. §38-26-107. The City shall condition publication and final settlement upon receipt of any duly executed approvals of the corporate surety or sureties issuing the bonds required hereunder. Such final settlement shall be advertised as provided by statute at least twice, the last publication appearing at least ten (10) days prior to the date of final settlement. On the date of final settlement (or such later date as may be permitted by statute if claims are asserted or litigation is commenced alleging nonpayment of funds due for labor, materials, supplies, etc.), payment and final settlement shall be made in full.
9. CONTRACTOR'S REPRESENTATIONS. In order to induce the City to enter into this
Agreement, the Contractor makes the following representations:
9.1. The Contractor has familiarized itself with the nature and extent of the
Agreement, Work, the locality, and with all local conditions and federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the Work. The Contractor acknowledges an obligation to comply with all applicable laws, including the Broomfield
Municipal Code, to respect property rights by working within the defined work limits or designated staging areas, and to work within the prescribed work hours. The Contractor acknowledges that use of air compression brakes ("jake brakes") within City limits is prohibited, unless otherwise posted by the City
Traffic Engineer.
9.2. Before submitting a proposal, the Contractor has become fully informed regarding the Work and any materials or equipment required, including the amount or quantity thereof. No adjustment or modification shall be allowed for any misunderstanding of the Work or of equipment or material requirements, or of the provisions contained in this Contract and in the other Contract
Documents.
9.3. Contractor has given the City written notice of any conflicts, errors or discrepancies that he has discovered in the Agreement and exhibits incorporated therein and the written resolution thereof by the City is acceptable to the Contractor.
10. NOTICE AND AUTHORIZED REPRESENTATIVES. Any notice required or permitted by this
Agreement shall be in writing and shall be sufficiently given for all purposes if sent by email to the authorized representative identified below. Such notice shall be deemed to have been given when the email was sent and received. The City may change its representative at any time by notice to the Contractor. The Contractor shall not replace the Contractor Representative unless: (a) the City requests a replacement, or
(b) the Contractor terminates the employment of the Contractor Representative and provides a satisfactory substitute. The City must approve a substitute Contractor
Representative, and, if no substitute is acceptable, the City may terminate this
Agreement. The Parties each designate an authorized representative as follows:
5.1 The City designates Elizabeth Racca-Johnson as the authorized representative of the City under this Agreement. Email address is elizabeth.johnson@broomfield.org.
5.2 The Contractor designates _______________________ as the authorized representative of the Contractor under this Agreement. Email address is
If the Contractor is alleging that the City is in breach of this Agreement or has violated any term of this Agreement, Legal Notice shall be made by making the notice above http://broomfield.org/ with a copy to citycountyattorney@broomfield.org.
Failure of City’s on-site representative to call to the attention of the Contractor any defective work or deviations from the Contract Documents shall not constitute acceptance of such work by the City or relieve the Contractor of its obligation to perform the Work in strict accordance with the Contract Documents.
11. TIME EXTENSIONS AND COMPENSATION FOR DELAY.
11.1. Remedy. If the Contractor is delayed or disrupted in the performance of the
Work, the Contractor’s exclusive remedy with respect to such delay or disruption shall be as stated in this Section.
11.2. Time Extensions. Evaluation of all time extension requests shall be based upon the latest updated project schedule submitted to the City by the Contractor.
11.3. Definitions. The following words shall have the meaning set forth below:
11.3.1. “Contractor Delay” is defined as delay on a particular date resulting from acts or omissions within the control of the Contractor or its subcontractors, agents or suppliers, including any delay within their joint control.
11.3.2. “No-Fault Delay” is defined as delay on a particular date resulting from events beyond the reasonable control of and without the fault or negligence of either the Contractor or the City or their agents, employees, contractors, subcontractors, sub-subcontractors or suppliers.
11.3.3. “Owner Delay” is defined as delay on a particular date resulting from acts or omissions within the control of the City, its agents, employees or contractors, including the City’s Representative.
11.3.4. “Concurrent Delay” is defined as the occurrence on a particular date of one or more instances of Owner Delay and Contractor Delay, Owner
Delay and No-Fault Delay or Contractor Delay and No-Fault Delay.
11.4. Completion Date Adjustment. An adjustment in the Completion Date for delay on a particular date shall be made under this subparagraph if any delay on such date is classified as either Owner, No-Fault or Concurrent Delay. The adjustment in the Completion Date shall only be in proportion to the amount of the delay, which is attributable to Owner, or No-Fault Delay. No adjustment in the Completion Date shall be allowed for the portion of the delay that is mailto:cityandcountyattorney@broomfield.org attributable to Contractor Delay, including but not limited to, that portion of a
Concurrent Delay which includes Contractor Delay.
11.5. Price Adjustment. An adjustment in the Contract Price for delay on a particular date shall be made under this subparagraph only if such delay is classified as either Owner Delay or Concurrent Delay when such Concurrent Delay includes
Owner Delay. The adjustment in the Contract Price shall only be in proportion to the portion of the delay costs, which is directly attributable to Owner Delay.
No adjustment in the Contract Price shall be made for the portion of the delay costs, which is attributable to Contractor Delay, or No-Fault Delay, or that portion of a Concurrent Delay which includes Contractor Delay or No-Fault
Delay or both.
11.6. Mitigation. An adjustment in Contract Price shall be made under this subparagraph only to the extent to which the Contractor can demonstrate that its time-related costs to complete the Work will be increased. The Contractor expressly acknowledges its obligation to minimize the cost impact of compensable delays. The Contractor shall, to the best of its ability, re-assign labor and equipment, commence unaffected portions of the Work, and otherwise minimize delay costs. In no event shall the City be liable for payment of delay costs, which could have been avoided or mitigated by any means reasonably available to the Contractor or for consequential damages.
11.7. Notification of Delay and Recovery. The Contractor shall notify the City as soon as practicable regarding the nature and starting date of a delay, and the activities affected, but in no case later than seven (7) calendar days after the event giving rise to the delay. In the case of a continuing delay, only one notification shall be necessary. Any claim for an extension of time for delay shall be made in writing to the City not more than ten (10) calendar days after the end of the delay; otherwise, such claim shall be waived. Recovery of delay costs shall be waived unless a request for a change order for delay costs is submitted within ten (10) calendar days after the end of the delay period. The
Contractor must also provide a cost and time impact analysis with any request for a change order for delay costs. The cost impact analysis shall contain all direct and indirect labor costs, all material and equipment expenses, any and all documented impact costs related to, and/or occasioned by the Work described therein, as well as all taxes (if applicable under the provisions of this
Contract), insurance and profit. Documentation supporting this cost impact analysis must be submitted at the time of the request for change order for delay costs.
12. DEFAULT AND DAMAGES. If the Contractor fails to comply with any provision of this
Agreement, the Contractor shall be liable for any and all damages, including without limitation, the cost of procuring similar supplies and services and all other costs and expenses incurred by the City because of such failure. If the Contractor fails or refuses to perform the Work on schedule, or to complete the Work in a timely and satisfactory manner, the City may terminate this Contract and the Contractor’s right to proceed hereunder. If the City terminates this Contract under this paragraph, the Contractor may, at the option of the City, be required to cease any or all Work provided for under this Contract and shall be liable for any additional cost to the City for services acceptable to the City from another contractor as well as any actual damages associated with such failure to perform. The cost to complete the Work or any portion thereof which remains unperformed at the time of such termination, together with any other damages, shall be deducted from any sum payable hereunder before final payment to the Contractor.
13. LIQUIDATED DAMAGES. Time is of the essence in completing the Work. Alternatively, and in lieu of actual damages for delay, in the event of delay in the completion of the
Work as specified beyond the Completion Date, it would be difficult to determine the exact amount of the loss or damages suffered by the City due to delays in completion of the Work. However, the City has attempted to forecast a reasonable daily amount as compensation for the damages incurred due to late completion caused by the
Contractor, based upon considerations which include, but are not limited to, public inconvenience and additional contract administration costs. Therefore, the Contractor will be liable to the City, as liquidated damages (and not as a penalty), in the amount of $500.00 for each and every calendar day beyond the Completion Date. The City reserves the right to deduct said liquidated damages from any amount due the
Contractor under this Agreement or, at its option, to collect such liquidated damages directly from the Contractor or its surety.
14. PERFORMANCE AND PAYMENT BONDS. In accordance with C.R.S. §38-26-105, if the
Contract Price exceeds $50,000, the Contractor shall furnish at its expense a separate performance bond and labor and materials bond, each for an amount not less than one hundred percent (100%) of the Contract Price. The bonds shall be issued by a qualified corporate surety licensed to transact business in Colorado. If at any time during performance of the Work the surety on the bonds shall be disqualified from doing business in Colorado, or shall become insolvent or otherwise impaired, the Contractor shall furnish bonds from an alternate surety acceptable to the City. The bonds shall remain in effect through Final Acceptance, and continuing in effect through completion of all warranty and guaranty work and shall be delivered to the City prior to the commencement of the Work. The Contractor shall secure an increase in the bonds in an amount equal to the cost of any additional work authorized pursuant to a duly executed change order or contract amendment.
15. COLORADO LABOR. If the Contract Price exceed $500,000, the Contractor shall employ not less than eighty percent of Colorado labor of each type or class of labor in the several classifications of skilled and common labor to perform the work under this
Agreement in accordance with the provisions of C.R.S. §8-17-101 et seq.
16. INDEPENDENT CONTRACTOR. The Contractor is an independent contractor as provided in C.R.S. § 8-40-202(2). The Contractor is not entitled to workers' compensation benefits and the Contractor is obligated to pay federal and state income tax on monies earned pursuant to this Agreement.
17. INDEMNIFICATION. The Contractor expressly agrees to indemnify, defend and hold harmless the City, its officers, employees and insurers from and against all claims, damages, losses, expenses and demands, including court costs, attorney’s fees and expenses, due to injuries, losses or damages arising out of, resulting from, or in any manner connected with the Contractor, its officers, employees, subcontractors or agents in connection with the performance of the services pursuant to this Agreement.
Except for workers’ compensation, disability benefits or other similar employee benefit claims, Contractor is not obligated to indemnify the City hereunder for that portion of any claims, damages, losses, demands, and expenses arising out of or resulting from any negligent act or omission of the City, or its agents and employees.
This indemnification is intended to comply with and be subject to C.R.S.
13-50.5-102(8), as amended from time to time. In the event that any such suit or action is brought against the City, the City will give timely notice thereof to the other
Party.
18. INSURANCE. To assure the City that the Contractor is always capable of fulfilling specified indemnification obligations, the Contractor shall purchase and maintain insurance of the kind and in the amounts required by the City, from an insurer with an
AM Best FSR rating of A- or higher as more particularly set forth on Exhibit C. Current proof of such insurance is attached at Exhibit C, incorporated by this reference.
However, proof of insurance attached as Exhibit C shall not be deemed to limit or define obligations of Contractor as provided elsewhere in this Agreement, and
Contractor should rely on its expertise to obtain additional insurance coverage needed for the City and Contractor in its performance hereunder.
19. APPROVAL OF SUBCONTRACTORS AND CONSULTANTS. The Contractor shall not employ any subcontractors or consultants without the prior written approval of the City
Representative. Prior to commencing any work, each subcontractor or consultant shall provide the appropriate insurance as required for the Contractor under this
Agreement. The Contractor shall be responsible for coordination of the work and the acts and omissions of its agents, employees, subcontractors, consultants and suppliers, and shall bind each to the terms of this Agreement so far as are applicable. This
Agreement is voidable by the City if subcontracted by the Contractor without the express written consent of the City.
20. WARRANTY.
20.1. Warranty Period. The Contractor warrants that it will perform the Work in a timely, accurate and complete manner in accordance with the provisions of this
Agreement. The Contractor warrants that the materials and/or workmanship will conform to the Contract Documents and that the materials used will be of good quality and new and that the Work shall be free from defects. The
Contractor shall guarantee the Work against defects in workmanship and materials for a period of 2 years (1 year for landscape and irrigation work), commencing on the date of final acceptance of the Work by the City
Representative (the “Warranty Period”). The Contractor shall also assign to the
City any longer term guarantee of materials used by the Contractor as may be provided by the manufacturer. The Contractor shall promptly replace any materials or re-perform any portion of the Work found to be defective within the Warranty Period in accordance with this Agreement and without expense to the City. The time allowed for such corrective action shall be mutually agreed upon by the City and the Contractor. If the Contractor fails to proceed promptly in accordance with these guarantees, the City reserves the right to place the
Contractor in default of its contractual obligations and may have the Work performed at the expense of the Contractor. This provision shall survive the completion of the Work and the termination of this Agreement. The above guarantee does not limit any claims that the City may otherwise have against the Contractor.
20.2. Warranty Verification. At least 60 calendar days prior to the expiration of the
Warranty Period, the City Representative shall have the option to make an inspection to determine whether the Work has been completed in accordance with this Agreement and may submit a written list of any defects to the
Contractor (the “Warranty Work”). In the event the City chooses this option, the Contractor shall promptly correct all Warranty Work without additional cost to the City within the Warranty Period. If any Warranty Work cannot be corrected within the Warranty Period, the Contractor shall submit a letter to the City Representative for approval requesting an extension of time to complete such item (the “Request for Extension of Warranty Work”). The
Request for Extension of Warranty Work must be received by the City
Representative within seven calendar days of the Contractor’s receipt of the
Warranty Work and shall include the Contractor’s justification for the request and a schedule for completion of the Warranty.
21. NO THIRD PARTY BENEFICIARIES. This Agreement is intended to describe the rights and responsibilities only as to the parties hereto. This Agreement is not intended and shall not be deemed to confer any rights on any person or entity not named as a party hereto.
22. FINANCIAL OBLIGATIONS OF THE CITY. All financial obligations of the City under this
Agreement are subject to appropriation, budgeting, and availability of funds to discharge such obligations. Nothing in this Agreement shall be deemed to pledge the
City’s credit or faith, directly or indirectly, to the Contractor. If funds for this
Agreement are not appropriated and budgeted in any year subsequent to the fiscal year of execution of this Agreement as determined by the City, this Agreement may be terminated by the City upon written notice to the Contractor. The City’s fiscal year is currently the calendar year.
23. EXHIBITS. All exhibits referred to in this Agreement are by reference incorporated herein for all purposes.
24. INTEGRATION AND AMENDMENT. This Agreement represents the entire agreement between the Parties and there are no oral or collateral agreements or understandings.
This Agreement may be amended only by an instrument in writing signed by the
Parties. For purposes of clarity, the terms and conditions of any Contractor invoice, Contractor timesheet, or other form, including but not limited to indemnification, limitation of liability, or cancellation fees, shall be void and of no effect against the
City notwithstanding any signatures on such form by a City employee. The
Contractor’s rights and obligations shall be solely governed by the terms and conditions of this Agreement.
25. SEVERABILITY. If any provision of this agreement as applied to either Party or to any circumstance shall be adjudged by a court to be void or unenforceable, the same shall in no way affect any other provision of this Agreement, the application of any such provision in any other circumstances, or the validity or enforceability of the
Agreement as a whole.
26. ADDITIONAL DOCUMENTS OR ACTION. The parties agree to execute any additional documents or take any additional action that is necessary to carry out this Agreement.
27. MINOR CHANGES. The Parties executing this Agreement are authorized to make nonsubstantive corrections to this Agreement and attached exhibits, if any, as they consider necessary.
28. DOCUMENTS. All drawings, analyses, plans, tests, maps, surveys, electronic files and written material of any kind generated in the performance of this Agreement or developed specifically for work performed under this Agreement shall remain the sole and exclusive property of the City, and the other Party shall not provide copies of any such material to anyone without the express written consent of the City.
29. RECORDS RETENTION. The Contractor shall maintain complete and accurate records of time spent and materials used for performance of the Work, together with any invoices, time cards, or other supporting data reasonably requested. All records, data and documentation shall be retained by the Contractor for a period of not less than three (3) years after completion of the Work, and shall be subject to review, inspection and copying by the CIty upon reasonable notice.
30. OFFICIALS NOT TO BENEFIT. No elected or employed member of City government shall directly or indirectly be paid or receive any share or part of this Agreement or any benefit that may arise therefrom. The Contractor warrants that it has not retained any entity or person, other than a bona fide employee working solely for the
Contractor, to solicit or secure this Agreement.
31. SALES TAX EXEMPTION. The Contractor and its subcontractors, consultants and suppliers will not be required to pay Colorado state sales and use taxes on property incorporated into the Work. The Contractor shall obtain a sales tax exemption permit from the State of Colorado Department of Revenue, if necessary, to obtain materials for the Work without the payment of Colorado state sales tax.
32. ASSIGNMENT. This Agreement shall not be assigned by either Party without the prior written consent of the other Party.
33. BINDING EFFECT. This Agreement shall inure to the benefit of and be binding upon the parties and their respective legal representatives, successors, heirs, and assigns, provided that nothing in this paragraph shall be construed to permit the assignment of this Agreement except as otherwise expressly authorized herein.
34. DAYS. If the day for any performance or event provided for herein is a Saturday, a
Sunday, a day on which national banks are not open for the regular transactions of business, or a legal holiday pursuant to C.R.S. § 24-11-101(1), such day shall be extended until the next day on which such banks and state offices are open for the transaction of business.
35. NO PRESUMPTION. The Parties to this Agreement and their attorneys have had a full opportunity to review and participate in the drafting of the final form of this
Agreement. Accordingly, this Agreement shall be construed without regard to any presumption or other rule of construction against the Party causing the Agreement to be drafted.
36. GOOD FAITH OF PARTIES. In the performance of this Agreement or in considering any requested approval, acceptance, or extension of time, the Parties agree that each will act in good faith and will not act unreasonably, arbitrarily, capriciously, or unreasonably withhold, condition, or delay any approval, acceptance, or extension of time required or requested pursuant to this Agreement.
37. WAIVER OF BREACH. This Agreement or any of its provisions may not be waived except in writing by a Party’s authorized representative. A waiver by any party to this
Agreement of the breach of any term or provision of this Agreement shall not operate or be construed as a waiver of any subsequent breach by either party.
38. GOVERNING LAW. This Agreement shall be governed by the laws of the State of
Colorado. Any claims or litigation arising under this Agreement will be brought by the
Parties solely in the District Court, Broomfield County, Colorado.
39. LAWS TO BE OBSERVED. The Contractor shall be cognizant of all federal and state laws and local ordinances and regulations that in any manner affect those engaged or employed in the work or which in any manner affect the conduct of the work, and of all such orders and decrees of bodies or tribunals having any jurisdiction or authority over the same, and shall at all times observe and comply with all such existing laws, ordinances, regulations and decrees, and shall protect and indemnify the City against any claim or liability arising from or based on the violations of any such law, ordinance, regulation, order or decree, whether by itself, its subcontractors, agents or employees. The Contractor shall procure all necessary approvals, licenses and permits at its own expense; provided, that, the Contractor will be able to receive no cost permits when such permits are issued by the City directly.
40. TERMINATION. The City reserves the right to terminate this Contract, in whole or in part, with or without cause by written notice to the Contractor. In the event of termination, the Contractor shall incur no additional expenses and shall perform no further Work for the City under this Agreement after the date of receipt of the notice of termination, unless otherwise specified by the City. The City shall pay the
Contractor for all work satisfactorily performed prior to receipt of the notice of termination and for other services required by the City to be completed prior to termination and satisfactorily performed.
41. SURVIVAL OF OBLIGATIONS. The obligations contained in this Agreement that are not fully performed as of termination shall survive termination and shall continue to bind the Parties until fully performed.
42. EXECUTION; ELECTRONIC SIGNATURES. This Agreement may be executed in counterparts, each of which shall be deemed an original and all of which shall constitute but one and the same instrument. This Agreement shall not be binding upon any Party hereto unless and until the Parties have executed this Agreement. The
Parties approve the use of electronic signatures for execution of this Agreement. All documents must be properly notarized, if applicable.
[The remainder of this page is intentionally left blank.]
This Agreement is executed by the Parties hereto in their respective names as of
__________________ ___, 2025.
THE CITY AND COUNTY OF BROOMFIELD,
a Colorado municipal corporation and county
Mayor
One DesCombes Drive
Broomfield, CO 80020
APPROVED AS TO FORM:
City and County Attorney’s Office
Notarization by both parties is only required when contracting with an individual. If an entity is a party to this agreement the notary block may be removed.
STATE OF COLORADO )
) ss.
COUNTY OF BROOMFIELD )
The foregoing instrument was acknowledged before me this _____ day of _______________
2023, by ___[insert name of person signing]________________ as [insert title of person signing] of the City and County of Broomfield.
WITNESS my hand and official seal.
(SEAL) ______________________________
Notary Public
CONTRACTOR:
_____________________[insert company name]
By: _____________________________________
Name:
Address:
Notarization by both parties is only required when contracting with an individual. If an entity is a party to this agreement the notary block may be removed.
STATE OF COLORADO )
) ss.
COUNTY OF _____________ )
The foregoing instrument was acknowledged before me this _____ day of _______________
2025, by [insert name of person signing] as [insert title of person signing] of
[insert name of company].
WITNESS my hand and official seal.
(SEAL) ______________________________
Notary Public
EXHIBIT A
SCOPE OF WORK
STONEYBROOK DRIVE RETAINING WALL REPLACEMENT
PROJECT NO. 24T0030
The City and County of Broomfield (Broomfield) has prepared plans and specifications to renovate Stoneybrook Drive Retaining Wall Replacement located directly behind the residential properties at 5524 and 5444 Stoneybrook Drive, Broomfield, Colorado.
The Work includes, but is not limited to, removing an existing wood retaining wall, installation of new wall units, construction surveying, tree protection, grading and drainage work, excavation, pond water control, and all labor and material necessary to complete the Work. All work shall be performed in a manner consistent with the
Stoneybrook Retaining Wall Replacement plans, project Specifications, Broomfield
Standards and Specifications, and all other applicable provisions associated with this project.
The Scope of Work also includes but is not limited to the following:
1. New redi-block retaining wall: A no-fee Building Permit is required.
2. Grading and Drainage: A no-fee Grading Permit is required.
3. Soil Excavation
4. Clearing and grubbing, including material export
5. Construction Surveying: Licensed survey engineer is required.
6. Material submittals and inspections
7. Site restoration of the surrounding / adjacent areas impacted by construction activities
8. Traffic Control and pedestrian detour signs. A condition of the required permits is an approved Traffic Control Plan consistent with the MUTCD.
9. Erosion Control. A condition of required permits is an approved Erosion
Control Plan
10. Pond water control as necessary for retaining wall installation.
11. Cattail Removal: If awarded.
Project General Notes.
1. Standards & Specifications. Work shall be performed in accordance with the project Specifications, project Electrical Specifications, and applicable sections of the latest 2022 Broomfield Standards and Specifications, and all other applicable provisions associated with this project.
https://drive.google.com/drive/folders/1F2zEBnuDD9ou8mTXXXm1RtjSiyVYT2lv
2. Licenses. The awarded Contractor must have or obtain a contractor’s license
(Class C, $50) with the City and County of Broomfield Building Department in order to obtain required permits.
3. Permitting. A City and County of Broomfield Public/Private Improvement (PPIP) will be required for the work. Contractor shall provide any other information required for approval of the permit. There will be no permit fees. See
Engineering Forms and Permits for more information.
4. Work Hours. Work hours are Monday through Friday, 7 a.m. to 7 p.m. Due to this area being closely surrounded by residential homes, contractor will comply to CCOB noise ordinance. Saturday work may be allowed for emergency purposes from 9 a.m. to 6 p.m. with a pre-approved Weekend/Holiday Work
Request form.
5. Bonding. A Bid Bond is required (for contracts in excess of $50,000). The awarded contractor will be required to provide a Performance Bond and a
Labor and Material Payment Bond for contracts in excess of $50,000.
6. Retainage. Retainage is required to be withheld for contracts in excess of
$150,000.
7. Other Expectations.
a. The site shall be maintained in a clean and tidy condition without miscellaneous debris, etc. left onsite. Stockpiled materials and equipment shall be neatly organized and in locations coordinated with
Broomfield’s CIP Construction Manager.
b. The Contractor shall be…