The document is a Project Specifications file for the Stoneybrook Drive Retaining Wall Replacement project, issued by the City and County of Broomfield (CCOB) with Project No. 24T0030. The project involves replacing an existing retaining wall, including comprehensive site work such as earthwork, grading, wall subgrade stabilization, seeding, and site restoration. The contractor will be responsible for obtaining various permits including Public Private Improvement Permit (PPIP), Grading Permit, Over-Excavation Permit, and Building Permit. Environmental considerations include an assessment noting red-winged black birds in the area, with construction expected to begin after a 20-day environmental clearance. The project requires careful coordination with residential surroundings, compliance with noise ordinances, and maintaining a clean work environment.
The contract includes 17 primary bid items and an add alternate for cattail removal, with payment structures ranging from lump sum to unit price per cubic yard or acre. Mobilization is capped at 5% of the base bid total, and the contract references the latest City and County of Broomfield 2022 Standards and Specifications and 2023 CDOT Standard Specifications. Bid items cover a comprehensive range of work including site access and staging, traffic control, construction surveying, wall removal and excavation, earthwork, wall construction, seeding, and site restoration. A force account allowance is included for additional work requiring prior approval. The specifications emphasize that actual field-measured quantities will govern final payment, and the contractor is expected to verify quantities and secure all necessary materials and permits.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Document Package.pdf | ||
| Bid Form.xlsx | XLSX spreadsheet | |
| Project Plans.pdf | ||
| Cattail Removal Specifications - Add Alternate.pdf | ||
| Sample Construction Agreement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SPECIFICATIONS
Stoneybrook Drive Retaining Wall Replacement Project No. 24T0030
GENERAL INFORMATION
PERMITS
● Public Private Improvement Permit (PPIP) The City and County of Broomfield (CCOB) Project Manager will initiate a PPIP, however, the Contractor is responsible for preparing and providing all the information and documents required by the PPIP, including but not limited to a Traffic Control plan and Erosion Control plan. This permit is a no-fee permit to the Contractor. The Contractor shall have this permit approved and ready to begin work upon a Notice to Proceed.
● Grading Permit A no-fee grading permit is required by the Contractor. The Contractor shall have this permit approved and ready to begin work prior to any grading work.
● Over-Excavation Permit A no-fee over-excavation permit is required by the Contractor. The Contractor shall have this permit approved and ready to begin work prior to excavation work.
● Building Permit A no-fee building permit is required by the Contractor. The Contractor shall have this permit approved and ready to begin work prior to construction of the new retaining wall.
COORDINATION
Environmental: An environmental assessment has been performed during the design phase for this project. Red-winged black birds have been identified to be within the area. However, it has been noted that they migrate out of the area around September and should be clear by construction start. CCOB will obtain a second 20-day letter for the construction phase, to confirm no further environmental impacts. Construction is expected to begin within the 20-day environmental clearance.
Seeding Work: Seeding is expected to be completed within the contract working days.
However, the project may run into the season with inclement weather and inappropriate seeding season or lack of availability of seeds. The contractor is responsible for securing all the materials needed for each phase of work. If the seeding cannot be accomplished within the contract time due to the seasonal constraints, Contractor may submit a revised seeding work schedule for CCOB’s review and approval. The planting and seeding may be a delayed item of work at no additional cost to the City.
Community Impacts: The park is surrounded by residential homes. Contractor is expected to comply with all CCOB noise ordinance and maintain a neat, clean and dust-free environment.
Contractor shall secure all equipment during and outside work hours. The Contractor shall not enter from the residential properties. The contractor is required to obtain right of entry
Specifications https://broomfield.org/DocumentCenter/View/1408/Public-Private-Improvement-Permit-Fillable-Right-of-Way-Permit-4-15-20?bidId=
Project No. 24T0030 permission from the residents if emergency access is needed. This right of entry must be coordinated with CCOB Engineer.
Cattail Removal and Disposal - Add Alternate: If awarded, this work will be coordinated with the general contractor under the Stoneybrook Drive Retaining Wall Replacement Work. It is the responsibility of the general contractor to coordinate the work schedule and site access with the cattail subcontractor. Refer to the Cattail Removal Specifications for further description and requirements of this work.
(End of Section - General Information)
MEASUREMENTS AND PAYMENTS
PART 1 - GENERAL SCOPE OF CONTRACT SUM
1) The Contract Sum for performance of the Work under Contract Documents, or under any Bid item, Allowance, Alternate, or Optional shall include full compensation for all Work required under the Contract Documents, including without limitation, all labor, materials, taxes, transport, handling, storage, supervision, administration, and all other items necessary for the satisfactory completion of the Work, whether or not expressly specified or indicated, incidental work and unexpected expenses, and all terms, conditions, requirements and limitations outlined in the Contract Documents, Redpoint Ridge Park Landscape Renovations, project Specifications, latest City and County of Broomfield 2022 Standards and Specifications and related 2023 CDOT Standard Specifications.
2) Contract Sum may be expressed as lump sum, unit price, guaranteed maximum price, allowance, or combination thereof.
3) Unless otherwise noted, estimated quantities on the bid schedule are believed to be accurate; however, the Contractor should verify the quantities as it relate to ordering sufficient material and scheduling work. Actual field-measured quantities, complete in place, not the quantities listed in the bid schedule, will govern final payment.
UNIT PRICE ITEMS
1) Quantity of Work to be paid for under any item for which a unit price is fixed in Contract Documents shall be determined by Owner based on, so far as practicable, actual number of units satisfactorily completed, as determined by Owner and certified by Contractor, within prescribed or ordered limits, and no payment will be made for Work unsatisfactorily performed or done outside of limits.
Project No. 24T0030
2) Unit Prices shall apply to Work covered by unit prices so long as actual quantities performed on the Project are not less than 75 percent or greater than 125 percent of the estimated quantities bid or otherwise stated in the Contract Documents. If actual quantities exceed these parameters, then the unit price shall be adjusted by an amount to reflect the Contractor’s incremental cost differential resulting from increased or decreased economies of scale.
LUMP SUM ITEMS
1) When the estimated quantity for a specific portion of Work is not indicated and/or Work is designated as lump sum, payment will be on a lump sum basis for Work satisfactorily completed in accordance with Contract Documents.
2) Payment for lump sum Work, or items of Work subject to a lump sum (e.g. without limitation, change order work), shall be made based on satisfactory completion of such Work or work item, earned in progressive stages in accordance with the Contract Documents, up to but not exceeding the Contractor’s percentage completion of the Work or item.
3) Lump sum items shall be paid based upon the approved Schedule of Values, which shall be used to measure progressive payments based upon satisfactory progress towards completion of the item.
PART 2 - BID ITEM DESCRIPTIONS
Unless specifically indicated in this section, full compensation for conforming to the requirements is included in the contract prices paid for the various items of work involved, and no additional compensation will be allowed therefor. The term “Detail” used in this section shall refer to the specific detail drawings shown on the plans.
Bid Item No. 1 - “Mobilization (Not to Exceed 5% of Base Bid total)” Mobilization shall be paid by lump sum (LS). Payments for the lump sum item shall be determined based on the percentage of the bid item work completed as determined by the CCOB Engineer at the time the progress payment is prepared, and no additional compensation shall be made. This includes securing a City and County of Broomfield Public and Private Improvements permit by the Contractor before the start of work. The contract price paid for Mobilization shall include, but not limited to, obtaining a building permit, excavation and cut/fill plans withgrading permit and over-excavation permit, including all preparatory work and operations necessary for personnel, equipment, supplies, and incidentals to the project site, as shown on the plans, these project Specifications, latest CCOB 2022 Standards and Specifications, Section 626, "Mobilization," of the 2023 CDOT Standard Specifications, and as directed by the CCOB Engineer. Mobilization shall not exceed 5% of the contract amount for each lot. Payment for Traffic Control, Erosion Control and Provisions of Site Access and Staging Areas, shall be paid separately under their respective bid items under “Traffic Control”, “Erosion
Control”, “Provisions of Site Access and Staging Areas”, and no additional compensation will be allowed therefore.
Bid Item No. 2 - “Provision of Site Access and Staging Areas” Bid price for Provision of Site Access and Staging Areas shall be paid by lump sum (LS). This work includes preparation for equipment site access and staging areas. The work shall include but is not limited to, installing a temporary equipment access path/road to the work area, preparing for equipment staging, dewatering, or cofferdams as necessary to access wall work, including but not limited to all material, labo,r and equipment involved in providing site access and staging areas ready for the wall work. Payments for the lump sum item shall be determined based on the percentage of the bid item work completed as determined by the CCOB Engineer at the time the progress payment is prepared, and no additional compensation shall be made.
Bid Item No. 3 - “Traffic Control” Bid price for Traffic Control shall be paid by lump sum (LS). This work includes traffic and pedestrian handling on-site and off-site. The work shall include, but is not limited to, preparation and submittal of a traffic control and pedestrian handling plan to CCOB for review and approval, as part of the PPIP permit process. Payments for the lump sum item shall be determined based on the percentage of the bid item work completed as determined by the CCOB Engineer at the time the progress payment is prepared, and no additional compensation shall be made.
Bid Item No. 4 – “Construction Surveying” Bid price for Construction Surveying shall be paid by lump sum (LS). Payments for the lump sum item shall be determined based on the percentage of the bid item work reflecting the completed survey, as determined by the CCOB Engineer, at the time the progress payment is prepared, and no additional compensation shall be made. The contract price paid for Construction Surveying shall include, but not limited to, performing vertical and horizontal survey work and other incidentals performed by a licensed professional surveyor, staking and layout, verification and necessary adjustments as it relates to existing field conditions, verification and location of existing utilities in a horizontal and vertical plan, other detailed survey, in order to complete the construction of the work as shown on the plans, as specified in Section 625, “Construction Surveying”, of the 2023 CDOT Standard Specifications, these project Specifications, and no additional compensation will be allowed therefore.
Bid Item No. 5 - “Erosion Control” Bid price for Erosion Control shall be paid by lump sum (LS). This work includes the implementation of control measures to prevent soil loss at or adjacent to the construction site and the implementation of Best Management Practices (BMP). An Erosion Control plan shall be submitted to CCOB as part of the PPIP permit process. The work shall include labor, materials, equipment, and material storage, incidentals to complete the work as shown on the approved Erosion Control plan. Payments for the lump sum item shall be determined based on the
Project No. 24T0030 percentage of the bid item work completed as determined by the CCOB Engineer at the time the progress payment is prepared, and no additional compensation shall be made. Payment for any dewatering or cofferdams shall be paid separately under the lump sum bid item for “Provision of Site Access and Staging Areas”, and no additional compensation shall be made.
Bid Item No. 6 - “Tree Protection” Bid price for Tree Protection shall be paid by unit price per each (EA). This work includes the implementation of protection measures for each tree affected by the construction site. No trees shall be removed unless specified on the plans or directed by the Engineer. The work involved in tree protection, throughout the work, shall include labor, materials, chain link fence around each tree, equipment, and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation shall be made.
Bid Item No. 7 - “Clearing and Grubbing” Bid price for Clearing and Grubbing shall be paid by lump sum (LS). The work involved shall include labor, material, equipment and incidentals to complete the work, including disposal of all materials involved in clearing and grubbing, as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standard and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation shall be made.
Bid Item No. 8 - “Existing Wall Removal and Excavation for Proposed Wall” Bid price for Existing Wall Removal and Excavation for Proposed Wall shall be paid by lump sum (LS). The work involved shall include labor, material, equipment and incidentals to complete the work, in and removal and disposal of the existing wood wall and removal of existing soil to make room for the proposed wall, any temporary trench protection needed, as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standard and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. Dipsoal of the existing soils shall be paid separately under the bid item unit price for “Earthwork (Export)” and no additional compensation shall be made.
Bid Item No. 9 - “Earthwork (On-Site Grading)” Bid price for Earthwork (On-Site Grading) shall be paid by unit price per cubic yard (CY) and shall include labor, material, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed, therefore. The work for construction surveying to determine the cut or fill shall be paid separately under the lump sum bid price for “Construction Surveying”. Export material, if needed, shall be paid separately, under the unit bid price for “Earthwork (Export)l” and no additional compensation shall be made.
Bid Item No. 10 - “Earthwork - Export” Bid price for Earthwork - Export shall be paid by unit price per cubic yard (CY) and shall include labor, material, equipment and incidentals to complete the removal of excess dirt from the site, as shown on the plans, its Detail, latest City and County of Broomfield Standard Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB CM. No additional compensation will be allowed therefore. The cost for temporary storage of export material on site shall be paid separately, under the bid item for “Erosion Control” and no additional compensation shall be made .
Bid Item No. 11 - “Earthwork (Fine Grading)” Bid price for Earthwork (Fine-Grading) shall be paid by the unit price per square foot (SF) and shall include labor, material, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed therefore. The work for construction surveying to determine the cut or fill shall be paid separately under the lump sum bid price for “Construction Surveying”, and no additional compensation shall be made.
Bid Item No. 12 - “Retaining Wall Subgrade Stabilization” Bid price for Retaining Wall Subgrade Stabilization shall be paid by lumps sum (LS) and shall include labor, material, material testing, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed therefore. The work for construction surveying to determine the cut or fill shall be paid separately under the lump sum bid price for “Construction Surveying”, and no additional compensation shall be made.
Bid Item No. 13 - “New Retaining Wall, Fill Material and Wall Drain” Bid price for New Retaining Wall, Fill Material and Wall Drain shall be paid by lumps sum (LS) and shall include labor, material, material testing, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed therefore. The work for construction surveying to determine the cut or fill shall be paid separately under the lump sum bid price for “Construction Surveying”, and no additional compensation shall be made.
Bid Item No. 14 - “Seeding” Bid price for Seeding shall be paid by the unit price per acre (AC) and shall include labor, material, equipment and incidentals to install the seeding at the top of the wall and adjacent areas impacted by the construction work, as shown on the plans, its Detail, latest City and
County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed therefore. The work for seeding may be a delayed item of work and no additional compensation shall be made for the delay of this work to the Spring Season.
Bid Item No. 15 - “Site Restoration” Bid price for Site Restoration shall be paid by lumps sum (LS) for work involved in general cleanup, removal of excess debris, repair of damaged irrigation impacted by the work outside the access area and staging areas, cleanup of adjacent properties as needed, removal of all surveying markers and erosion control measures not needed, watering and maintenance of landscape and irrigation prior to the completion and acceptance of the punch list work items, and shall include labor, material, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. No additional compensation will be allowed therefore.
Bid Item No. 16 - “Site Restoration of Site Access and Staging Area” Bid price for Site Restoration of Site Access and Staging Area shall be paid by lumps sum (LS) for work involved in removing all temporary access materials and equipment from the staging areas, including removal of any dewatering or cofferdam equipment, repairing damaged irrigation systems impacted by the site access and staging areas. The work involved shall include labor, material, equipment and incidentals to complete the work as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standards and Specifications, 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer.
No additional compensation will be allowed therefore.
Bid Item No. 17 - “Force Account” Bid price for Force Account is an allowance and shall be paid by lump sum (LS) and for the actual work performed. The work under this item shall require prior approval and shall include labor, material, equipment and incidentals, complete and in place, as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standard and Specifications, Section 109.04 of the 2023 CDOT Standard Specifications, these project Specifications, and as directed by the CCOB Engineer. Actual work performed shall be paid and no additional compensation will be allowed.
Add Alternates: Alt Bid Items - “Cattail Removal and Disposal” Bid price for Cattail Removal and Disposal shall be paid by lump sum (LS) for the work involved in removal of the cattails, mobilization, cleanup, site access, permits, coordination with the Stoneybrook Retaining Wall work schedule and its PPIP permit, proper disposal of the cattails to an appropriate disposal site, reseeding in the pond, preparing for the access to the cattails, and shall include labor, material, equipment and incidentals, complete and in place, as shown on the plans, its Detail, latest City and County of Broomfield 2022 Standard and Specifications, Cattail Specifications, these project Specifications, and as directed by the CCOB Engineer.
Actual work performed shall be paid and no additional compensation will be allowed.
(End of Section - Measurements and Payments)
-The remainder of this page is intentionally left blank-
GENERAL INFORMATION
| PERMITS |
| COORDINATION |