This document is a Sample Application for Payment form for Pinellas County, Florida, designed for contractors to request payment for work performed on a county project. The form provides a standardized template for documenting payment details, including a change order summary, payment summary, and a release of claims section. It is intended to be used by contractors to certify that previous payments have been used to pay for materials and work, and to formally request the current payment due.
The form includes sections for tracking the original agreement amount, retainage percentage, total earned less retainage, and previous payments. It requires approval signatures from a consultant or design professional, a Pinellas County Engineering Project Manager, and the department director. The document serves as both an application for payment and a legal release, with the contractor waiving future claims against Pinellas County related to the performance of the agreement for the specified payment period.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX 3 - SAMPLE APPLICATION FOR PAYMENT
APPENDIX 3 – SAMPLE APPLICATION FOR PAYMENT
APPLICATION AND CERTIFICATE FOR PAYMENT
From (Contractor Name) Pinellas County Department
Payment Application Number Purchase Order Number
Payment Period From:
to
CHANGE ORDER SUMMARY PAYMENT SUMMARY
Change Order #
Date Approved
Additions Deductions Original Agreement Amount $
Retainage __________ %
Total Earned Less Retainage $
Less Previous Payments $
TOTAL
NET CHANGE Current Payment Due $
I certify that the payment requested is in APPLICATION FOR PAYMENT APPROVED BY:
accordance with the terms of the agreement dated _____________ and that previous Consultant or Design Professional/Engineer of Record payments have been used to pay obligations for materials supplied and work performed in conjunction with this project. In accordance
Pinellas County ________ (Dept) Engineering Project Manager with the contract documents and in consideration of _____________ ____ paid.
___________________ (“Contractor”) releases
Pinellas County Public Works and waives for itself and its subcontractors, materialmen, successors, and assigns, all claims demands, damages, costs and Director of ___________________ (Dept) expenses, whether in contract or in tort, against the Board of County Commissioners of Pinellas County, Florida, Ex Officio the governing Board of the Pinellas County (“County”) relating in any way to the performance of the agreement between contractors and owner, dated for the period from _________________ to
Contractor Date