Carville RFP amendment 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend6.doc | DOC document | |
| Amend5.doc | DOC document | |
| Amend4.doc | DOC document | |
| TAR_Roustabout.PDF | ||
| Amend3.doc | DOC document | |
| J-20_OMS-10 04302008.pdf | ||
| J-22_CDSS Plan 2008.doc | DOC document | |
| Amend1.doc | DOC document | |
| Pre-Prop Conf Powerpoint 611.ppt | PPT presentation | |
| J-20_CTT-10 04302008.pdf | ||
| J-15_DavisBacon LA3.txt | TXT text file | |
| J-12_Square Foot table.doc | DOC document | |
| J-17_National Staff Compensation Report.xls | XLS spreadsheet | |
| J-8_Entergy3.5.08.xls | XLS spreadsheet | |
| J-13_EPMS Report with cost.pdf | ||
| J-20_MSO 20 04302008.pdf | ||
| J-14_Site Plan.jpg | JPG image | |
| J-13_EPMS Report.pdf | ||
| J-23_Inventory-Vehicles.htm | HTM file | |
| J-20_MPO35 04302008.pdf | ||
| J-16_SCA_05-2231.txt | TXT text file | |
| Carville-RFP.doc | DOC document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
June 30, 2008
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
6. ISSUED BY
CODE
U.S. DEPARTMENT OF LABOR
Office of the Asst. Secy for Admin. & Mgmt.
Unit of JOB CORPS Support 525 S. Griffin Street RM 707 Dallas, Texas 75202
7. ADMINISTERED BY (If other than Item 6)
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
9A. AMENDMENT OF SOLICITATION NO.
S09F6LA009
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended X is not extended
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning ________ copies of the amendment; (b) by acknowledging receipt of this amendment on each copy of the offer submitted; or (c) by separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATE (If required) Job Corps
13.
THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| () |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A. |
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office)ADVANCE \x48 SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
Basic Contract, Clause 52.243-2
D. OTHER (Specify type of modification and authority) Section G.
E. IMPORTANT: Contractor_ X _is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment provides answers to questions raised from the Pre-proposal conference of June 11, 2008 Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Linda Bynum, Contracting Officer – OASAM 972-850-4423
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
| 15C. Date Signed |
| 16B. UNITED STATES OF AMERICA |
BY _____________________________________________
(Signature of Contracting Officer) 16C.Date Signed
6/30/2008
NSN 7540-01-152-8070
30-105
STANDARD FORM 30
Prescribed by GSA
FAR (48 CFR) 53.243
S09F6LA009
Amendment# 2
1) Re: RFP C.2
States that the Job Corps site is leased from the LANG. Will the National Guard then be responsible for center security?
Answer: NO Will the LANG be responsible for the upkeep of the grounds?
Answer: NO
(2) Re: RFP C.3
States that youth screened for the Carville Job Corps Center shall come from Louisiana. There are several OA contracts in the state. How will the "Zone of Influence" of each be determined as well as the distribution of prospects from the National Call Center?
Answer: Zone of influence will be:
Beauregard Parish
Evangeline Parish
Allen Parish
Saint Landry Parish Calcasieu Parish
Acadia Parish Cameron Parish
Lafayette Parish
Jefferson Davis Parish
Saint Martin Parish
West and East Feliciana Parish
Vermillion Parish
Pointe Coupe Parish
Iberia Parish
Saint Helena Parish
Saint Mary Parish
Tangipahoa Parish
Assumption Parish Washington Parish
Saint James Parish West & East Baton Rouge Parish
Saint John Parish
Livingston Parish
Saint Charles Parish Iberville Parish
Lafourche Parish Ascension Parish
Terrebonne Parish
(3) Re: RFP Attachment J-18
Is this a historically poor performing center?
Answer: NO
(4) Re: RFP Section L.7.B.3.b.1
Please confirm that the government is requesting only relevant projects, not all projects that are currently operated or have been operated within the past three years.
Answer: Only relevant projects should be included.
(5) Re: RFP Section L.7.B.4
Is it acceptable to provide the Subcontracting Plan Summary Sheet on CDs and/or jump drives?
Answer: Yes, it is acceptable but must also be provided in written format.
S09F6LA009
Amendment# 2
(6) Re: RFP Section L.7
L.7.A (General) of the RFP requests that one electronic copy of the complete proposal (all parts) be placed on a CD or flash drive. In addition, throughout Section L.7 of the RFP, there are separate requests for copies of individual files on CD or flash drive or floppy disks. Please confirm that by providing the one copy of all files on a CD or flash drive as required in Section L.7.A (General), the Offeror has satisfied all requirements that appear throughout Section L.7 for CD or flash drive or floppy drive copies of individual files.
Answer: There should be one CD or flash drive with Section G and one CD or flash drive which includes the entire proposal.
(7) Re: RFP Section L.7.B.5
Please clarify whether offerors are to complete the 2 pages of Section B of the
RFP and, if so, where should those pages be placed in the Cost Justification proposal?
Answer: Yes; place them with the other Business Management Data.
8) Questions regarding the current contract:
Where is the current OA/CTS Staff located?
What is the proposed zone of influence? Are Arrivals and CTS Placement for Baton Rouge area only or for the whole state?
Is there availability of GSA vehicles for the OA/CTS component?
Who is the current Physician on center?
Who is the current Dentist on center?
Who is the current Mental Health consultant on center?
Where are the current ACT students enrolled? Is it possible to get a copy of the latest Student Satisfaction Survey? Answer: The above questions do not relate to this solicitation, and therefore will not be provided.
(9) Is there a new TAR associated with the American Petroleum Institute Field Operator Assistant CTT offering?
Answer: NO
(10) Is there availability of GSA vehicles for the OA/CTS component? Answer: Yes. These are detailed on the property listing provided with Amendment 1.
(11) What is the relationship with the National Guard? Answer: All relationships are in the RFP.
(12) The arrival totals will be corrected on page 3 of the RFP to read 366. Answer: The Contractor shall provide Outreach and Admissions services in the state of Louisiana and shall ensure the arrival of a minimum of 366 students into the Carville Job Corps Center annually for 149 resident male students and 217 resident female students.