This document contains a pricing schedule for a seed project under a multiple award task order contract to provide labor, materials, and equipment for facility improvements at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project number is 695-24-103 for fiscal year 2024 safety corrections, with a price range of $500,000 to $1,000,000. A lump sum base proposal is due along with adherence to a 315 calendar day completion schedule and approved work plans, submittals, and cost-loaded critical path method construction schedule. Additional scope details are defined in specifications and drawings, with off-hours and weekend work required for outages, shutdowns, and direct patient care areas. The related solicitation is number 36C25223R0071 for a multiple award task order contract at the Zablocki VA Medical Center through the Department of Veterans Affairs Veterans Health Administration VISN 12.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICING SCHEDULE (MATOC SEED PROJECT)

VA Project Number: 695-24-103: FY24TJC and Safety Corrections

Price Range: $500,000 to $1,000,000.

Base Proposal: Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project # 695-24-103: FY24TJC and Safety Corrections at the Clement J.

Zablocki VA Medical Center in Milwaukee, Wisconsin.

All work shall be completed within 315 calendar days after receiving Notice to Proceed.

Base Proposal LUMP SUM: _______________________________

NOTICE TO OFFERORS: Seed Project Award will be made to the lowest priced proposal from the successful MATOC award recipients.

NOTICE TO OFFERORS: At times, the contractor will be working in occupied buildings and the hospital. Work plans for VA review/approval are required before any work can begin associated with any of the tasks. Outages and shut-downs will need to take this information into account. Off-shift scheduling (nights/weekends) is required for outages, shutdowns, and work directly impacting patient care.

The contractor will be required to keep all other non-impacted roads, walks and entrances to grounds, parking, and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Submittals regarding staging of equipment, crane placement, storage of supplies, etc. are required. Off-hours and/or week-end deliveries of construction equipment or materials may be required.

NOTICE TO OFFERORS: An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.

NOTICE TO OFFERORS: Additional information regarding the general and specific scope of work is defined in the specifications and drawings. This PRICING SCHEDULE and STATEMENT OF WORK is in addition to and augments the specifications and drawings. ONLY ONE TASK ORDER AWARD WILL