S02 - Exhibit 02c2 - 537-21-101 SOW Att - Contractor Production Report.pdf

PDF 87 KB Posted

Attached to
Z1DA--Rehabilitate Ogden Elevators Project # 537-21-101 Federal contract opportunity
Solicitation number
36C25223B0023
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

This document is a contractor production report template to be used for federal construction contracts. The template requires contractors to provide daily reports with details such as weather conditions, work completed, safety inspections conducted, equipment used, labor hours by trade, materials received and incorporated into the project. Contractors must track cumulative labor hours and submit supporting documentation for any safety incidents, inspections of cranes and other equipment. The purpose of the daily reports is to ensure contractors are providing sufficient resources to complete the contract work according to the project schedule and meeting all safety requirements.

The related federal contract opportunity is a solicitation from the Department of Veterans Affairs to rehabilitate elevator systems at the Ogden facility for $537-21-101. Offerors will be required to provide construction services and meet the specifications in the solicitation document.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Rehabilitate Ogden Elevators Project # 537-21-101, newest first.
File Type Posted
36C25223B0023 0003.docx DOCX document
S04 - Pre-Bid Site Visit Sign-in Sheet_7102023.pdf PDF
S02 - 537-21-101 Wage Determination_7.19.23.pdf PDF
36C25223B0023 0002.docx DOCX document
S02 - Exhibit 02b1_537-21-101 - SOW Ex - SOC Floor Plan 1 of 2 U.pdf PDF
S02 - Exhibit 02b1_537-21-101 - SOW Ex - SOC Floor Plan 2 of 2 U.pdf PDF
36C25223B0023 0001.docx DOCX document
S02 - Exhibit 01b1 537-21-101 Specifications Vol 1of 2 IFBC 06072023 U.pdf PDF
S02 - Exhibit 01a 537-21-101 Construction Drawings IFBC 06072023 U.pdf PDF
S02 - Exhibit 01b2 537-21-101 Specifications Vol 2 of 2 IFBC 06072023 U.pdf PDF
S02 - Exhibit 02c1 - 537-21-101 SOW Att - Contract Progress Report.pdf PDF
S02 - Exhibit 02b1_537-21-101 - SOW Ex - SOC Floor Plan 2 of 2.pdf PDF
S02 - Exhibit 01b2 537-21-101 Specifications Vol 2 of 2 IFBC 06072023.pdf PDF
36C25223B0023_1.docx DOCX document
S02 - Ex 02c3 - 537-21-101 SOW Att - Subcontractor Payment Summary.xlsx XLSX spreadsheet
S02 - 537-21-101 Wage Determination_6.14.23.pdf PDF
S02 - Exhibit 02b2 - 537-21-101 SOW Ex - Asbestos Survey Report.pdf PDF
S02 - Exhibit 02b1_537-21-101 - SOW Ex - SOC Floor Plan 1 of 2.pdf PDF
S02 - Exhibit 01b1 537-21-101 Specifications Vol 1of 2 IFBC 06072023.pdf PDF
S02 - Exhibit 01a 537-21-101 Construction Drawings IFBC 06072023.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB No.: 2900-0208 Exp. Date: Mar 31. 2022 Respondent Burden: 24 Minutes

CONTRACTOR PRODUCTION REPORT

(Attach additional sheets if necessary)

DATE

CONTRACT NUMBER TITLE AND LOCATION (Title and Location of Construction Contract) REPORT NUMBER

CONTRACTOR SUPERINTENDENT

AM WEATHER (Weather data, include precipitation & winds) PM WEATHER (Weather data, include precipitation & winds) MAX TEMP (F) MIN TEMP (F)

WORK PERFORMED TODAY

SCHEDULE ACTIVITY NO. WORK LOCATION AND DESCRIPTION EMPLOYER NUMBER TRADE HOURS

JOB SAFETY

WAS A JOB SAFETY MEETING HELD THIS DATE?

(If YES, attach copy of the meeting minutes) YES NO

WERE THERE ANY LOST TIME ACCIDENTS THIS DATE?

(If YES, attach copy of completed OSHA report) YES NO

WAS CRANE/MANLIFT/TRENCHING/SCAFFOLD/HV ELEC/HIGH WORK/HAZMAT

WORK DONE? (If YES, attach statement or checklist showing inspection performed)

YES NO

TOTAL WORK HOURS ON JOB SITE, THIS

DATE, INCL CON'T SHEETS

CUMULATIVE TOTAL OF WORK HOURS

FROM PREVIOUS REPORT

TOTAL WORK HOURS FROM START OF

CONSTRUCTION

SCHEDULE

ACTIVITY NO.

LIST ANY SAFETY ACTION TAKEN TODAY/SAFETY

INSPECTION CONDUCTED

(Include any safety topic covered during the safety meeting)

SAFETY REQUIREMENTS

HAVE BEEN MET

EQUIPMENT/MATERIAL RECEIVED TODAY TO BE INCORPORATED IN JOB (Indicate a schedule activity number) SCHEDULE ACTIVITY NO. SUBMITTAL NUMBER DESCRIPTION OF EQUIPMENT/MATERIAL RECEIVED

CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY, INDICATE

HOURS USED AND SCHEDULE ACTIVITY NUMBER

SCHEDULE ACTIVITY NO. OWNER DESCRIPTION OF CONSTRUCTION EQUIPMENT USED TODAY (Include Make and Model)

SCHEDULE ACTIVITY NO. REMARKS

CONTRACTOR/SUPERINTENDENT DATE REPORT PREPARED

The Paperwork Reduction Act of 1995 requires us to notify you that this information collection is in accordance with the clearance requirements of section 3507 of the Paperwork Reduction Act of 1995. We may not conduct or sponsor, and you are not required to respond to , a collection of information unless it displays a valid OMB number. We anticipate that the time expended by all individuals who must complete this form will be average 24 minutes. This includes the time it will take to read instructions, gather the necessary facts and fill out the form. If your firm does not already have a similar form, this is used to record the data necessary to assure the contractor provides sufficient labor and materials to accomplish the contract work. This form or a similar document is required to guarantee the performance of the work necessary to complete the project.

VA FORM

JUL 2018 10101

OMB No.: 2900-0208 Exp. Date: Mar 31. 2022 Respondent Burden: 24 Minutes O M B No.: 2900-0208 Exp. Date: Mar 31. 2022 Respondent Burden: 24 Minutes Department of Veterans Affairs LOGO

CONTRACTOR PRODUCTION REPORT

(Attach additional sheets if necessary)

CONTRACTOR PRODUCTION REPORT

(Attach additional sheets if necessary)

DATE

CONTRACT NUMBER

TITLE AND LOCATION (Title and Location of Construction Contract)

REPORT NUMBER

CONTRACTOR

SUPERINTENDENT

AM WEATHER (Weather data, include precipitation & winds) PM WEATHER (Weather data, include precipitation & winds)

MAX TEMP (F)

MIN TEMP (F)

WORK PERFORMED TODAY

SCHEDULE ACTIVITY NO.

WORK LOCATION AND DESCRIPTION

EMPLOYER

NUMBER

TRADE

HOURS

JOB SAFETY

WAS A JOB SAFETY MEETING HELD THIS DATE?

(If YES, attach copy of the meeting minutes)

WERE THERE ANY LOST TIME ACCIDENTS THIS DATE?

(If YES, attach copy of completed OSHA report)

WAS CRANE/MANLIFT/TRENCHING/SCAFFOLD/HV ELEC/HIGH WORK/HAZMAT

WORK DONE? (If YES, attach statement or checklist showing inspection performed)

TOTAL WORK HOURS ON JOB SITE, THIS

DATE, INCL CON'T SHEETS

CUMULATIVE TOTAL OF WORK HOURS

FROM PREVIOUS REPORT

TOTAL WORK HOURS FROM START OF

CONSTRUCTION

SCHEDULE

ACTIVITY NO.

LIST ANY SAFETY ACTION TAKEN TODAY/SAFETY

INSPECTION CONDUCTED

(Include any safety topic covered during the safety meeting) EQUIPMENT/MATERIAL RECEIVED TODAY TO BE INCORPORATED IN JOB (Indicate a schedule activity number)

SCHEDULE ACTIVITY NO.

SUBMITTAL NUMBER

DESCRIPTION OF EQUIPMENT/MATERIAL RECEIVED

CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY, INDICATE

HOURS USED AND SCHEDULE ACTIVITY NUMBER

SCHEDULE ACTIVITY NO.

OWNER

DESCRIPTION OF CONSTRUCTION EQUIPMENT USED TODAY (Include Make and Model)

SCHEDULE ACTIVITY NO.

REMARKS

CONTRACTOR/SUPERINTENDENT

DATE REPORT PREPARED

The Paperwork Reduction Act of 1995 requires us to notify you that this information collection is in accordance with the clearance requirements of section 3507 of the Paperwork Reduction Act of 1995. We may not conduct or sponsor, and you are not required to respond to , a collection of information unless it displays a valid OMB number. We anticipate that the time expended by all individuals who must complete this form will be average 24 minutes. This includes the time it will take to read instructions, gather the necessary facts and fill out the form. If your firm does not already have a similar form, this is used to record the data necessary to assure the contractor provides sufficient labor and materials to accomplish the contract work. This form or a similar document is required to guarantee the performance of the work necessary to complete the project.

VA FORMJUL 2018

V A Form 1 0 1 0 1, JULY 2018 10101 C:\Program Files\Adobe\Form Designer\Forms\Adobe.xft\VA3918.xft David Wachter April 2015 5.0

OA&MM

VA3918

{CF3222A7-20FA-11D4-ABC1-00D0B71D6ABB}

PDFForms.xml Spelling Checker;{224F7DEA-B7C1-11D3-AB40-00902712A5C9};PLSSpeller.cab Intra-Agency Transfer Request David Wachter VA Form 3918

JULY 2018

10101, CONTRACTOR, PRODUCTION, CONSTRUCTION

Missie Vaccaro-Palomaki VA Form 10101, CONTRACTOR PRODUCTION REPORT Rafael Taylor/Sterai Payne/Karen Bruce (003A2A)

DATE REPORT PREPARED

The Paperwork Reduction Act of 1995 requires us to notify you that this information collection is in accordance with the clearance requirements of section 3507 of the Paperwork Reduction Act of 1995. We may not conduct or sponsor, and you are not required to respond to , a collection of information unless it displays a valid O M B number. We anticipate that the time expended by all individuals who must complete this form will be average 24 minutes. This includes the time it will take to read instructions, gather the necessary facts and fill out the form. If your firm does not already have a similar form, this is used to record the data necessary to assure the contractor provides sufficient labor and materials to accomplish the contract work. This form or a similar document is required to guarantee the performance of the work necessary to complete the project.:

CONTRACTOR/SUPERINTENDENT:
SCHEDULE ACTIVITY NUMBER, line 4 of 4:
OWNER, line 4 of 4:
REMARKS, line 4 of 4:
SCHEDULE ACTIVITY NUMBER, LINE 4 OF 5:
WORK LOCATION AND DESCRIPTION, LINE 4 OF 5:
HOURS, LINE 4 OF 5:
SCHEDULE ACTIVITY NUMBER, LINE 5 OF 5:
WORK LOCATION AND DESCRIPTION, LINE 5 OF 5:
HOURS, LINE 5 OF 5:
SAFETY REQUIREMENTS

HAVE BEEN MET "YES" CHECK BOX.: 0

SAFETY REQUIREMENTS

HAVE BEEN MET "YES" CHECK BOX.: 0

SAFETY REQUIREMENTS

HAVE BEEN MET "YES" CHECK BOX.: 0

SAFETY REQUIREMENTS

HAVE BEEN MET "YES" CHECK BOX.: 0

"NO" CHECK BOX.: 0
"NO" CHECK BOX.: 0
"NO" CHECK BOX.: 0
TOTAL WORK HOURS ON JOB SITE, THIS

DATE, INCL CON'T SHEETS:

CUMULATIVE TOTAL OF WORK HOURS

FROM PREVIOUS REPORT:

TOTAL WORK HOURS FROM START OF

CONSTRUCTION (Auto calculated field):

File details come from the government source that posted it. Updated .