S02 - Exhibit 02c1 - 537-21-101 SOW Att - Contract Progress Report.pdf
PDF 520 KB Posted
- Attached to
- Z1DA--Rehabilitate Ogden Elevators Project # 537-21-101 Federal contract opportunity
- Solicitation number
- 36C25223B0023
About this file
This is a contract progress report template to be used for a project to rehabilitate elevators at the Ogden Veterans Affairs Medical Center. The template requires reporting of key project details including the contract and project numbers, award and start dates, descriptions of work completed, budgets, payments made, and status of labor, materials, and progress. It will be used to track performance on a contract awarded through solicitation number 36C25223B0023 by the Department of Veterans Affairs to rehabilitate elevators (Project #537-21-101) at their Veterans Integrated Service Network 12 facility. The selected contractor will be required to regularly submit progress reports using this template to allow the VA to monitor budget, payment, and completion metrics over the course of the elevator rehabilitation project.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT PROGRESS REPORT
LOCATION OF PROJECT
TO
Centra Texas Health Care System (CTVHCS) 1901 Memorial Drive Temple, TX 76504
1. PROJECT NO. 2. CONTRACT NO. 3. DATE CONTRACT AWARD 4. DATE NOTICE TO PROCEED RECEIVED
6. NAME AND ADDRESS OF CONTRACTOR 7. DESCRIPTION OF CONTRACT
12. EXTENDED CONTRACT COMPLETION DATE
ITEM
NO.
15.
VA FORM
JUN 2012 10-6001a
5. DATE CONST. STARTED
BRANCH OF WORK TOTAL VALUE VALUE OF WORK IN
PLACE-END LAST PERIOD
VALUE OF WORK INSTALLED
IN CURRENT PERIOD(A) (B)
(C) (D)
13. ESTIMATED COMPLETION DATE
OMB Approval No. 2900-0208 Estimated burden 12 minutes
16.
17.
18.
19.
20.
21.
22.
23.
14. DATE COMPLETED
8. ORIGINAL CONTRACT AMOUNT
9. SCHEDULED PERCENT COMPLETION
10. ACTUAL PERCENT COMPLETION
11. ORIGINAL CONTRACT COMPLETION DATE
REPORT FOR PERIOD ENDING
VA FORM
JUN 2012 10-6001a
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
SUPPLEMENTAL AGREEMENT - ADD
SUPPLEMENTAL AGREEMENT - DEDUCT
TOTAL $$$
CONTRACT FISCAL DATA
CHANGE ORDERS, SUPPLEMENTAL AGREEMENTS, AND TIME EXTENSIONS
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
55A.
55B.
55C.
55D.
56.
57.
58.
59.
60.
CURRENT CONTRACT AMOUNT (From Item 40, Col. B)
VALUE - UNUSED MATERIALS PAID FOR THIS PERIOD
RETAINAGE (Based on Item 45 less cost of bond premiums)
PAYMENT THIS PERIOD
TOTAL PAYMENT TO DATE (Item 47 plus 48)
CO CHANGE ORD., PREV. REPORTED, NO.
ISSUED THIS PERIOD
ISSUED THIS PERIOD
ISSUED THIS PERIOD
ISSUED THIS PERIOD
TO INCL.CO SUPPL. AGREE. PREV. REPORTED, SYM
TO
TO
TO
TO INCL.
INCL.
INCL.
INCL.
51. EQUIPMENT STATUS 52. MATERIALS STATUS 53A. WORK PROGRESS 53B. PROGRESS FACTOR 54. SUBMISSIONS OVERDUE
ITEM
NO.
61. REMARKS
62. SIGNATURE OF RESIDENT ENGINEER 63. DATE
ADDITIONS DEDUCTIONS
(C) (D) (E)
DATE
APPROVED
(B)
DAYS
EXTENSIONSYMBOLS
(A)
VALUE - CONTRACT NOT EARNED (Item 41 minus 45)
VALUE - WORK IN PLACE TO DATE (Item 40, Cols. C plus D)
VALUE - UNUSED MATERIALS PREVIOUSLY PAID FOR
EARNED TO DATE (Items 42 plus 43 plus 44)
TOTAL PREVIOUS PAYMENTS
FIELD SUPPL. AGREE. PREV. REPORTED, NO.
FIELD CHANGE ORD. PREV. REPORTED, SYM.
TIME EXTENS. PREV. REPORTED, NO.
VA FORM
JUN 2012 10-6001a
The Paperwork Reduction Act of 1995 requires us to notify you that this information collection is in accordance with the clearance requirements of section 3507 of the Paperwork Reduction Act of 1995. We may not conduct or sponsor, and you are not required to respond to, a collection of information unless it displays a valid OMB number. We anticipate that the time expended by all individuals who must complete this form will average 12 minutes. This includes the time it will take to read instructions, gather the necessary facts and fill out the form. If your firm does not already have a similar form, this is used to record the data necessary to assure the contractor provides sufficient labor and materials to accomplish the contract work. This form or a similar document is required to guarantee the performance of the work necessary to complete the project.
D:19970130153324Z
CONTRACT PROGRESS REPORT
CONTRACT PROGRESS REPORT
LOCATION OF PROJECT
LOCATION OF PROJECT
TO
TO
Centra Texas Health Care System (CTVHCS) 1901 Memorial Drive Temple, TX 76504 Centra Texas Health Care System (CTVHCS) 1901 Memorial Drive Temple, TX 76504
1. PROJECT NO.
1. PROJECT NO.
2. CONTRACT NO.
2. CONTRACT NO.
3. DATE CONTRACT AWARD
3. DATE CONTRACT AWARD
4. DATE NOTICE TO PROCEED RECEIVED
4. DATE NOTICE TO PROCEED RECEIVED
6. NAME AND ADDRESS OF CONTRACTOR
6. NAME AND ADDRESS OF CONTRACTOR
7. DESCRIPTION OF CONTRACT
7. DESCRIPTION OF CONTRACT
12. EXTENDED CONTRACT COMPLETION DATE
12. EXTENDED CONTRACT COMPLETION DATE
ITEM
NO.
15.
VA FORM
JUN 2012
10-6001a
5. DATE CONST. STARTED
5. DATE CONST. STARTED
BRANCH OF WORK
BRANCH OF WORK
TOTAL VALUE
TOTAL VALUE
VALUE OF WORK IN
PLACE-END LAST PERIOD
VALUE OF WORK IN
PLACE-END LAST PERIOD
VALUE OF WORK INSTALLED
IN CURRENT PERIOD
VALUE OF WORK INSTALLED
IN CURRENT PERIOD
(A) (B) (C) (D) \\iaimain\apps1\Pam_Ward\Logos\Formlogo.jpg Department of Veterans Affairs
13. ESTIMATED COMPLETION DATE
13. ESTIMATED COMPLETION DATE
OMB Approval No. 2900-0208 Estimated burden 12 minutes 16.
17.
18.
19.
20.
21.
22.
23.
14. DATE COMPLETED
14. DATE COMPLETED
8. ORIGINAL CONTRACT AMOUNT
8. ORIGINAL CONTRACT AMOUNT
9. SCHEDULED PERCENT COMPLETION
9. SCHEDULED PERCENT COMPLETION
10. ACTUAL PERCENT COMPLETION
10. ACTUAL PERCENT COMPLETION
11. ORIGINAL CONTRACT COMPLETION DATE
11. ORIGINAL CONTRACT COMPLETION DATE
REPORT FOR PERIOD ENDING
REPORT FOR PERIOD ENDING
VA FORM
JUN 2012
10-6001a 24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
SUPPLEMENTAL AGREEMENT - ADD
38. SUPPLEMENTAL AGREEMENT - ADD
SUPPLEMENTAL AGREEMENT - DEDUCT
39. SUPPLEMENTAL AGREEMENT - DEDUCT
TOTAL
40. TOTAL
CONTRACT FISCAL DATA
CHANGE ORDERS, SUPPLEMENTAL AGREEMENTS, AND TIME EXTENSIONS
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
55A.
55B.
55C.
55D.
56.
57.
58.
59.
60.
CURRENT CONTRACT AMOUNT (From Item 40, Col. B)
41. CURRENT CONTRACT AMOUNT (From Item 40, Col. B)
VALUE - UNUSED MATERIALS PAID FOR THIS PERIOD
44. VALUE - UNUSED MATERIALS PAID FOR THIS PERIOD
RETAINAGE (Based on Item 45 less cost of bond premiums)
46. RETAINAGE (Based on Item 45 less cost of bond premiums)
PAYMENT THIS PERIOD
48. PAYMENT THIS PERIOD
TOTAL PAYMENT TO DATE (Item 47 plus 48)
49. TOTAL PAYMENT TO DATE (Item 47 plus 48)
CO CHANGE ORD., PREV. REPORTED, NO.
55B. CO CHANGE ORD., PREV. REPORTED, NO.
ISSUED THIS PERIOD
57. ISSUED THIS PERIOD
ISSUED THIS PERIOD
58. ISSUED THIS PERIOD
ISSUED THIS PERIOD
59. ISSUED THIS PERIOD
ISSUED THIS PERIOD
60. ISSUED THIS PERIOD
TO
INCL.
CO SUPPL. AGREE. PREV. REPORTED, SYM
55A. CO SUPPL. AGREE. PREV. REPORTED, SYM
TO
TO
TO
TO
INCL.
INCL.
INCL.
INCL.
51. EQUIPMENT STATUS
51. EQUIPMENT STATUS
52. MATERIALS STATUS
52. MATERIALS STATUS
53A. WORK PROGRESS
53A. WORK PROGRESS
53B. PROGRESS FACTOR
53B. PROGRESS FACTOR
54. SUBMISSIONS OVERDUE
54. SUBMISSIONS OVERDUE
ITEM
NO.
61. REMARKS
61. REMARKS
62. SIGNATURE OF RESIDENT ENGINEER
62. SIGNATURE OF RESIDENT ENGINEER
63. DATE
63. DATE
ADDITIONS
ADDITIONS
DEDUCTIONS
DEDUCTIONS
(C) (D) (E)
DATE
APPROVED
DATE APPROVED
(B)
DAYS
EXTENSION
DAYS EXTENSION
SYMBOLS
(A) VALUE - CONTRACT NOT EARNED (Item 41 minus 45)
50. VALUE - CONTRACT NOT EARNED (Item 41 minus 45) VALUE - WORK IN PLACE TO DATE (Item 40, Cols. C plus D)
42. VALUE - WORK IN PLACE TO DATE (Item 40, Cols. C plus D)
VALUE - UNUSED MATERIALS PREVIOUSLY PAID FOR
43. VALUE - UNUSED MATERIALS PREVIOUSLY PAID FOR
EARNED TO DATE (Items 42 plus 43 plus 44)
45. EARNED TO DATE (Items 42 plus 43 plus 44)
TOTAL PREVIOUS PAYMENTS
47. TOTAL PREVIOUS PAYMENTS
FIELD SUPPL. AGREE. PREV. REPORTED, NO.
55C. FIELD SUPPL. AGREE. PREV. REPORTED, NO.
FIELD CHANGE ORD. PREV. REPORTED, SYM.
55D. FIELD CHANGE ORD. PREV. REPORTED, SYM.
TIME EXTENS. PREV. REPORTED, NO.
56. TIME EXTENS. PREV. REPORTED, NO.
VA FORM
JUN 2012
10-6001a The Paperwork Reduction Act of 1995 requires us to notify you that this information collection is in accordance with the clearance requirements of section 3507 of the Paperwork Reduction Act of 1995. We may not conduct or sponsor, and you are not required to respond to, a collection of information unless it displays a valid OMB number. We anticipate that the time expended by all individuals who must complete this form will average 12 minutes. This includes the time it will take to read instructions, gather the necessary facts and fill out the form. If your firm does not already have a similar form, this is used to record the data necessary to assure the contractor provides sufficient labor and materials to accomplish the contract work. This form or a similar document is required to guarantee the performance of the work necessary to complete the project.
| D40. TOTAL: |
| TextField2: |