S02. Drawings 09 29 20.pdf
PDF 7 MB Posted
- Attached to
- Add AHU Metering Federal contract opportunity
- Solicitation number
- 36C25021R0066_1
About this file
This solicitation is for an add AHU metering project at the Louis Stokes Cleveland VA Medical Center. The project scope involves adding metering to individual air handling units to implement energy conservation measures. The contractor must provide all labor, equipment, supplies, and supervision necessary for the project. The project magnitude is between $500,000 to $1 million. The NAICS code is 236220 with a business size standard of $39.5 million. The solicitation is a 100% set aside for service-disabled veteran-owned small businesses. Bids are due by May 10, 2021 at 3:30 PM EST and must be submitted electronically. Site visits will be conducted following social distancing guidelines. Requests for information must be submitted by the stated cutoff date and time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S02. Site Visit Information.pdf | ||
| S02. RFI Form.docx | DOCX document | |
| S02. Bid Opening Instructions.pdf | ||
| S02. Safety.docx | DOCX document | |
| S02. Solicitation 36C25021R0066.pdf | ||
| S02. VAMC Health Requirements.pdf | ||
| S02. Specifications 09 29 20.pdf | ||
| S02. Wage Determination.pdf | ||
| S02. Bid Item.pdf | ||
| S02. Calculation of Self-Performed and Sub-Contracted Work.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TITLE SHEET & DRAWING
INDEX
SITE KEY PLAN
NTS
10701 EAST BLVD. CLEVELAND, OH. 44106
DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER - WADE PARK
Cleveland Veterans Affairs
Medical Center
ADD AHU METERING
DRAWING INDEX
PROJECT NO. 541-21-205
GI-1 TITLE SHEET & DRAWING INDEX
MECHANICAL/HVAC
M-001 LEGEND AND ABBREVIATIONS
M-002 OVERALL AHU SUMMARY MATRIX
M-100 LEVEL A - OVERALL AHU PLAN
M-101 BASEMENT - OVERALL AHU PLAN
M-102 FIRST FLOOR - OVERALL AHU PLAN
M-103 SECOND FLOOR - OVERALL AHU PLAN
M-104 THIRD FLOOR - OVERALL AHU PLAN
M-105 FOURTH FLOOR - OVERALL AHU PLAN
M-106 FIFTH FLOOR - OVERALL AHU PLAN
M-107 SIXTH FLOOR - OVERALL AHU PLAN
M-108 SEVENTH FLOOR - OVERALL AHU PLAN
BID ISSUE SUBMISSION
9.29.20
CLEVELAND VAMC
NORTH
I. PROJECT LOCATION: CLEVELAND VETERANS AFFAIRS MEDICAL CENTER
10701 EAST BLVD.
CLEVELAND, OHIO
II. DESCRIPTION & USER GROUP CLASSIFICATION OF BLDG
A. NATURE OF PROJECT: ASSESSMENT/ADDITION OF METERING TO EXISTING AIR
HANDLERS AT THE MAIN MEDICAL CAMPUS
B. DESIGN CODES: 2018 NFPA LIFE SAFETY CODE 101, IBC 2018
C. USE GROUP: MIXED USE GROUPS IN HOSPITAL (I-2/S/B) - NO CHANGE
PROPOSED
D. CONSTRUCTION TYPE: TYPE I -332, IB - NON-COMBUSTIBLE, PROTECTED
FIRE RATED CONSTRUCTION (LSC A.8.2.1.2)
EXTERIOR BEARING WALLS 3 HRS
INTERIOR BEARING WALLS 3 HRS
STRUCTURAL COLUMNS 3 HRS (SUPPORTING > 1 FLOOR)
2 HRS (SUPPORTING 1 FLOOR ONLY)
2 HRS (SUPPORTING ROOF ONLY)
BEAMS, GIRDERS, TRUSSES 3 HRS (SUPPORTING > 1 FLOOR, COLS., OR BEARING
WALLS
2 HRS (ALL OTHERS)
FLOOR-CEILING ASSEMBLIES 2 HRS
ROOF-CEILING ASSEMBLIES 1
HRS
INTERIOR NON-BEARING WALLS 0 HRS
EXTERIOR NON-BEARING WALLS 0 HRS
WALL ASSEMBLIES
EXIT ACCESS CORRIDOR WALLS 0 HR SMOKE PARTITIONS
CODE INFORMATION
35% SCHEM. DESIGN SUBMISSION 6.4.20
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
F i l e
P a t h
P
M
FULLY SPRINKLERED
Louis Stokes Cleveland
VA Medical Center
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
Project Director
CJK DAKRevisions: Date:
1468 WEST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
E T
G
DE
I
RET
S
HCRA
I
KACZMAR
STANLEY
NO. 4988
T
E R
S
ATE
I
T C
J.
O
O
FO
H
GI-1
BID ISSUE SUBMISSION
9.29.20
65% DESIGN DEVELOPMENT SUBMISSION 7.7.20
M-601 AHU SCHEMATICS (CONFIG. A & B)
M-602 AHU SCHEMATICS (CONFIG. C & D)
M-603 AHU SCHEMATICS (CONFIG. E. & F)
M-604 AHU SCHEMATICS (CONFIG. G & H)
M-605 AHU SCHEMATICS (CONFIG. I & J)
M-606 AHU SCHEMATICS (CONFIG. K & L)
M-607 AHU SCHEMATICS (CONFIG. M & N)
M-608 AHU SCHEMATICS (CONFIG. O & P)
M-609 AHU SCHEMATICS (CONFIG. Q & R)
M-610 AHU SCHEMATICS (CONFIG. S & T)
M-611 AHU SCHEMATICS (CONFIG. U & V)
M-701 AHU ENLARGED PLANS - BASEMENT
M-702 AHU ENLARGED PLANS - FIRST FLOOR
M-703 AHU ENLARGED PLANS - SECOND FLOOR
M-704 AHU ENLARGED PLANS - THIRD FLOOR
M-705 AHU ENLARGED PLANS - FIFTH & SEVENTH
FLOOR
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
90% CDs SUBMISSION 7.31.20
E. PROJECT AREA: ALL AIR HANDLERS IN ENTIRE HOSPITAL
F. PROJECT AREA OCCUPANT LOAD: NOT APPLICABLE
G. FIRE PROTECTION: EXISTING BUILDING FULLY SPRINKLED AND
WILL REMAIN AS A PART OF THIS PROJECT.
FIRE PROTECTION SYSTEM DESIGN NOT IN
SCOPE OF WORK
100% CDs SUBMISSION 8.20.20
BID ISSUE SUBMISSION 9.29.20
AutoCAD SHX Text
EAST BLVD.
AutoCAD SHX Text
E. 105 ST.
AutoCAD SHX Text
EAST BLVD.
AutoCAD SHX Text
MAGNOLIA DR.
AutoCAD SHX Text
HAZEL DR.
AutoCAD SHX Text
E. 108 ST.
AutoCAD SHX Text
MT. SINAI DR.
AutoCAD SHX Text
MARTIN LUTHER KING DR.
NOTE: ALL SYMBOLS AND ABBREVIATIONS
ARE SUBJECT TO MODIFICATIONS
ON OTHER DRAWINGS.
ALL SYMBOLS OR ABBREVIATIONS
MIGHT NOT NECESSARILY BE USED ON
THIS PROJECT.
ABBREVIATIONS
AC - AIR COMPRESSOR OR AIR CONDITIONER
ACCU - AIR COOLED CONDENSING UNIT
AD - ACCESS DOOR OR AREA DRAIN
ADJ - ADJUSTABLE
AFF - ABOVE FINISHED FLOOR
AFG - ABOVE FINISHED GRADE
AFMS - AIR FLOW MEASURING STATION
ALT - ALTERNATE
AP - ACCESS PANEL
APPROX - APPROXIMATE
ARCH - ARCHITECT OR ARCHITECTURAL
ASSY - ASSEMBLY
ATC - AUTOMATIC TEMPERATURE CONTROL
(SYNONYMOUS W ITH BAS)
BAS - BUILD ING AUTOMATION SYSTEM
BDD - BACK DRAFT DAMPER
BFP - BACKFLOW PREVENTER
BLDG - BUILD ING
BOB - BOTTOM OF BEAM
BOD - BOTTOM OF DUCT
BOE - BOTTOM OF EQUIPMENT
BOF - BOTTOM OF FOOTING
BOG - BOTTOM OF GRILLE
BOP - BOTTOM OF PIPE
BOT - BOTTOM
BTU - BRITISH THERMAL UNIT
BTUH - BRITISH THERMAL UNIT PER HOUR
CBD - COUNTER BALANCED BACKDRAFT DAMPER
CC - COOLING COIL
C.C.L.A.T. - COILING COIL LEAVING AIR TEMPERATURE
CFCI - CONTRACTOR FURNISHED CONTRACTOR
INSTALLED
CFM - CUBIC FEET PER MINUTE
CHGR - CHILLED W ATER GLYCOL SOLUTION RETURN
CHGS - CHILLED W ATER GLYCOL SOLUTION SUPPLY
CHW - CHILLED W ATER
CHW S - CHILLED W ATER SUPPLY
CHW R - CHILLED W ATER RETURN
CLG - CEILING
CMU - CONCRETE MASONRY UNIT
CO - CLEAN OUT
CO2 - CARBON DIOXIDE
CONN - CONNECT OR CONNECTION
CONTR - CONTRACTOR
COR - CONTRACTING OFFICER'S REPRESENTATIVE
CT - CURRENT TRANSDUCER
CTR - CENTER
CU - COPPER
CW - COLD W ATER
CW R - CONDENSER W ATER RETURN
CW S - CONDENSER W ATER SUPPLY
D - DRAIN LINE
DB - DRY BULB
DDC - D IRECT D IGITAL CONTROLS
DI - DEIONIZED W ATER
DIA - D IAMETER
DIM - D IMENSION
DN - DOW N
DW G - DRAW ING
EA - EACH OR EXHAUST AIR
EAT - ENTERING AIR TEMPERATURE
EC - ELECTRICAL (DIVISION 26)
EJ - EXPANSION JOINT
ELEC - ELECTRICAL
ELEV - ELEVATOR
EQUIP - EQUIPMENT
ET - EXPANSION TANK
ETR - EXISTING TO REMAIN
EQS - EQUIPMENT SUPPLIER
EW T - ENTERING W ATER TEMPERATURE
EXH - EXHAUST
EXP - EXPANSION
EXT - EXTERIOR
EX - EXISTING
FD - FLOOR DRAIN
FF - FINISHED FLOOR ELEVATION
FLR - FLOOR
FOB - FLAT ON BOTTOM
FOF - FUEL OIL FLOW
FOG - FUEL OIL GAUGE
FOR - FUEL OIL RETURN
FOS - FUEL OIL SUPPLY
FOT - FLAT ON TOP
FPM - FEET PER MINUTE
FSC - FIRE SUPPRESSION (DIVISION 21)
FT - FEET
FTG - FOOTING
G - GAS OR NATURAL GAS
GA - GAUGE
GAL - GALLON
GALV - GALVANIZED
GC - GENERAL TRADES
GPM - GALLONS PER MINUTE
HB - HOSE BIBB
HC - HVAC (DIVISION 23)
H.C.L.A.T. - HEATING COIL LEAVING AIR TEMPERATURE
HD - HUB DRAIN
HG - REFRIGERANT HOT GAS
HP - HORSEPOW ER
HPC - H IGH PRESSURE CONDENSATE RETURN
HPS - H IGH PRESSURE STEAM SUPPLY
HR - HOUR
HT - HEAT TRACE
HTR - HEATER
HVAC - HEATING, VENTILATING, AND AIR CONDITIONING
HHW - HEATING HOT W ATER
HHW R - HEATING HOT W ATER RETURN
HHW S - HEATING HOT W ATER SUPPLY
ID - INSIDE DIAMETER
INV - INVERT ELEVATION
IN - INCHES
KEC - KITCHEN EQUIPMENT
L - LENGTH
LAT - LEAVING AIR TEMPERATURE
LAV - LAVATORY
LBS - POUNDS
LPC - LOW PRESSURE CONDENSATE RETURN
LPS - LOW PRESSURE STEAM SUPPLY
LW T - LEAVING W ATER TEMPERATURE
MAX - MAXIMUM
MDD - MOTORIZED DAMPER
MEZZ - MEZZANINE
MFR - MANUFACTURER
MH - MANHOLE
MIN - MIN IMUM OR MINUTE
MISC - MISCELLANEOUS
MTD - MOUNTED
MTG - MOUNTING
MPC - MEDIUM PRESSURE CONDENSATE
RETURN
MPS - MEDIUM PRESSURE STEAM SUPPLY
MU - W ATER MAKE-UP
N/C - NORMALLY CLOSED
NIC - NOT IN CONTRACT
N/O - NORMALLY OPEN
NOM - NOMINAL
NPT - NATIONAL PIPE THREAD
NTS - NOT TO SCALE
OA - OUTDOOR AIR
OBD - OPPOSED BLADE DAMPER
OD - OUTSIDE DIAMETER
OFCI - OW NER FURNISHED CONTRACTOR
INSTALLED
OFOI - OW NER FURNISHED O W NER INSTALLED
P - PROPANE GAS
PC - PLUMBING (DIVISION 22)
OR PUMPED CONDENSATE RETURN
PHC - PREHEAT COIL
PLBG - PLUMBING
PRESS - PRESSURE
PRV - PRESSURE REGULATING VALVE
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
PSIG - POUNDS PER SQUARE INCH GAUGE
RA - RETURN AIR
RAD - RADIUS
RCP - REFLECTED CEILING PLAN
RD - ROOF DRAIN
REC - RECESSED
REQD - REQUIRED
RI - ROUGH IN
RL - REFRIGERANT LIQUID
ROS - REVERSE OSMOSIS W ATER SUPPLY
ROR - REVERSE OSMOSIS W ATER RETURN
RPM - REVOLUTIONS PER MINUTE
RS - REFRIGERANT SUCTIO N
S - SPRINKLER (W ET)
SA - SUPPLY AIR
SAN - SANITARY OR SANITARY DRAIN
SCH - SCHEDULE
SCW - SOFT COLD W ATER
SHT - SHEET
SPEC - SPECIFICATIONS
SQ - SQUARE
SR - SUPPLY RISER
SRV - SAFETY RELIEF VALVE
SS - STAINLESS STEEL
STD - STANDARD
STM - STORM OR STORM DRAINAGE
STRUC - STRUCTURAL OR STRUCTURE
SUC - SITE UTILITY CONTRACTOR
TEMP - TEMPERATURE
TOB - TOP OF BEAM
TOD - TOP OF DUCT
TOE - TOP OF EQUIPMENT
TOF - TOP OF FOOTING
TOJ - TOP OF JOIST
TOP - TOP OF PIPE
TOS - TOP OF SLAB OR TOP OF STEEL
TYP - TYPICAL
UNO - UNLESS NOTED OTHERW ISE
V - VENT
VAC - VACUUM
VEL - VELO CITY
VIB - VALVE IN BOX
VOL - VOLUME
VTR - VENT THROUGH ROOF
VR - VENT RISER
W / - W ITH
W /O - W ITHOUT
W B - W ET BULB
W CO - W ALL CLEANOUT
GENERAL FLOOR PLAN NOTES
PLAN NOTE. APPLIES ONLY TO THE SHEET W HICH IT IS SHOW N UNLESS
NOTED OTHERW ISE.
DETAIL NOTE. APPLIES ONLY TO THE ASSOCIATED DETAIL.
A1
EQUIPMENT, DEVICE, OR PLUMBING FIXTURE MARK. LETTER DESIGNATIONS
REFER TO SCHEDULES.
H1 H1OR
EQUIPMENT REFERENCE. LETTER DESIGNATION VARIES. REFER TO
SCHEDULES.
H2
B
H2
RISER OR STACK NUMBER
DETAIL: B = DETAIL DESIGNATION
H2 = SHEET W HERE DETAIL IS LOCATED
SECTION: 1 = SECTION DESIGNATION
H2 = SHEET W HERE DETAIL IS LOCATED
A1 "UP TO" SYMBOL (ITEM ON FLOOR ABOVE)
APPROXIMATE DIMENSION ABOVE FIN ISHED FLOOR TO TOP OR BOTTOM OF
EQUIPMENT, UNLESS NOTED OTHERW ISE
10"
ELEV: 8' - 0"ELEV: 8' - 0"
TOD: 8' - 10"
BOD: 7' - 2"
20x20
20x20
APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO TOP OR BOTTOM OF
DUCTW ORK, UNLESS NOTED OTHERW ISE
APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO CENTERLINE OF PIPE,
UNLESS NOTED OTHERW ISE
DL-1
UC-X DOOR UNDERCUT. X = HEIGHT OF UNDERCUT IN INCHES; 0.75 INCH
UNDERCUT IF NO HEIGHT IS NOTED. COORDINATE W ITH GC.
DOOR LOUVER. 1 = SQUARE FEET OF LOUVER.
CONNECT TO EXISTING
HVAC PIPING DESIGNATIONS
CHILLED W ATER SUPPLY PIPECHS
CONDENSER W ATER SUPPLY PIPECW S
CONDENSER W ATER RETURN PIPECW R
DRAIN LINE. PITCH IN DIRECTION INDICATEDD
HEATING HOT W ATER SUPPLY PIPEHW S
HEATING HOT W ATER RETURN PIPEHW R
W ATER MAKE-UP PIPEMU
VENT PIPEV
REFRIGERANT LIQUID LINERL
REFRIGERANT SUCTION LINERS
EXPANSION TANK PIPEET
REFRIGERANT HOT GAS LINEHG
LOW PRESSURE CONDENSATE RETURN PIPELPC
LOW PRESSURE STEAM SUPPLY PIPELPS
MEDIUM PRESSURE CONDENSATE RETURN PIPEMPC
MEDIUM PRESSURE STEAM SUPPLY PIPEMPS
PUMPED CONDENSATE RETURN PIPEPC
HIGH PRESSURE CONDENSATE RETURN PIPEHPC
HIGH PRESSURE STEAM SUPPLY PIPEHPS
STEAM SUPPLY PIPE - NUMBER IND ICATES P.S.I.G.10
MISC SYMBOLS
DUCTWORK SYMBOLS
ROUND BRANCH DUCTW ORKCONICAL
FITTING
ACOUSTIC
FITTING
ACOUSTIC
FITTING
ADAD
D
R R
D
REC TANGULAR BR ANCH DUCTW ORK
SQUARE TEE W ITH TURNING VANES
NOTE: ALL SQUARE ELBOW S IN
RECTANGULAR AND ROUND / OVAL
DUCTW ORK SHALL BE PROVIDED W ITH
TURNING VANES. REFER TO
SPECIFICATIONS FOR ADDITIONAL DETAILS.
EXISTING DUCTW ORK TO REMOVED
RETURN AIR , RELIEF AIR, OR TRANSFER AIR
DUCTW ORK. (UP AND DOW N) RADIUSED
OR SQUARE W ITH TURNING VANES.
SUPPLY AIR OR OUTDOOR AIR DUCTW ORK.
(UP AND DOW N) RADIUSED OR SQUARE
W ITH TURNING VANES.
EXHAUST AIR DUCTW ORK. (UP AND DOW N)
RADIUSED OR SQUARE W ITH TURNING
VANES.
RECTANGULAR AND ROUND / OVAL
DUCTW ORK RISE / DROP W ITH 90° RADIUSED
OR SQUARE ELBOW S AND TURNING VANES.
RADIUS ELBOW
90° SQUARE ELBOW (W ITH TURNING VANES)
NOTE: ALL SQUARE ELBOW S IN
RECTANGULAR AND ROUND DUCTW ORK
SHALL BE PROVIDED W ITH TURNING VANES.
ACCESS DOOR OR PANEL
DUCTW ORK RISE IN DIRECTION OF AIR
FLOW
DUCTW ORK DROP IN DIRECTION OF AIR
FLOW
DUCTW ORK W ITH ACOUSTICAL LINER.
LISTED DUCT SIZES ARE INSIDE CLEAR
DIMENSIONS.
RECTANGULAR ROUND / OVAL
FLEXIBLE DUCTW ORK
FLEXIBLE CONNECTION
DUCTW ORK CONSTRUCTED OF SPECIAL
MATERIAL AS NOTED
DIRECTION OF PITCH
RECTANGULAR DUCTW ORK DIMENSIONS
(W x H)26x20
ROUND DUCTW ORK DIMENSIONS (DIA)26ø
OVAL DUCTW ORK DIMENSIONS (W x H)26x20 OV
DUCTWORK DEVICE SYMBOLS
W ALL OR DUCTW ORK MOUNTED AIR DEVICE. SG1 = DESIGNATION (REFER
TO AIR DEVICE SCHEDULE). 20x12 = DUCT CONNECTION SIZE (IN INCHES).
300 = REQUIRED CFM. 9'-0" = MOUNTING HEIGHT FROM FLOOR TO BOTTOM
OF GRILLE.
A3 10ø
MANUAL BALANCING DAMPER W ITH LOCKING DEVICE
BDD = BACK DRAFT DAMPER
CBD = COUNTER-BALANCED BACK DRAFT DAMPER
SD = SMOKE DAMPER
FS = COMBINATION FIRE - SMOKE DAMPER
MDD = MOTORIZED DAMPER
AFMS = AIR FLOW MEASURING STATION
DUCT MOUNTED SMOKE DETECTOR. COORDINATE LOCATION.
HUMIDITY SENSOR - DUCT MOUNTED
SG1
20x12
BOG : 9'-0"
XXX
A-D
XX
H
SD
SP
AIR DEVICE. A3 = DESIGNATION (REFER TO FLOOR PLANS AND AIR DEVICE
SCHEDULE FOR VARIOUS DESIGNATIONS).
10ø = NECK SIZE (IN INCHES). 300 = REQUIRED CFM. ALL AIR DEVICE
DISCHARGE 4-W AY UNLESS NOTED W ITH FLOW ARROW S. AIR DEVICE
SHOW N IS 2-W AY SIDE THROW . METHOD OF IDENTIFICATION ALSO APPLIES
TO OTHER CEILING MOUNTED AIR DEVICES.
FIRE DAMPER
A = TYPE (REFER TO FLOOR PLANS FOR VARIOUS TYPES)
D OR S = DYNAMIC OR STATIC
STATIC PRESSURE SENSOR - DUCT MOUNTED
C
CARBON DIOXIDE SENSOR - DUCT MOUNTED
S
TEMPERATURE SENSOR - DUCT MOUNTED
CHECK VALVE
T
P
FOB
FOT
SHUTOFF VALVE (REFER TO SPECIFICATIONS FOR
REQUIRED TYPE BASED ON APPLICATIONS)
CONCENTRIC PIPE REDUCER
ECCENTRIC PIPE REDUCER
PRESSURE GAUGE
TEMPERATURE GAUGE OR THERMOMETER
COMBINATION SHUTOFF AND BALANCING VALVE
(REFER TO SPECIFICATIONS FOR REQUIRED
TYPE BASED ON APPLICATIONS)
BALL VALVE
BUTTERFLY VALVE
GATE VALVE
VALVES AND FITTINGS
DOUBLE LINE SINGLE LINE
10"
TOE: 3' - 0"
BOE: 0' - 6"
GLYCOL W ATER SOLUTION RETURN PIPEGW R
GLYCOL W ATER SOLUTION SUPPLY PIPEGW S
CHILLED W ATER RETURN PIPECHR
SQUARE THROAT / RADIUS HEEL
FITTINGS NOT ACCEPTABLE
PIPING SYMBOLS
DOUBLE LINE SINGLE LINE
BOTTOM CONNECTION (45°)
BRANCH TEE CONNECTION (NOTE:
BULLHEAD TEE'S ARE NOT PERMITTED)
DIRECTION OF PITCH
DROP
ELBOW DOW N
ELBOW UP
EXISTING PIPE TO BE REMOVED
EXISTING PIPE TO REMAIN
FLOW DIRECTION DESIGNATION
PUMP
RISE
TOP CONNECTION (45°)
TOP CONNECTION (90°)
BOTTOM CONNECTION (90°)
DD
RR
PIPE RISER
RADIUS'D BRANCH
RADIUS'D TEE
EXISTING DUCTW ORK TO REMAIN
UNLESS NOTED OTHERW ISE ON DRAW INGS,
15° MAX FOR DIVERGING, 30° MAX FOR
CONVERGING TRANSITION
EMERGENCY SHUTOFF STATION. 46" MOUNTING HEIGHT UNLESS NOTED OTHERW ISE.
SPACE TEMPERATURE SENSOR / THERMOSTAT. W HEN W ALL MOUNTED, MOUNTING
HEIGHT 46" TO MEET ADA REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH
COORDINATE W ITH ARCHITECT.
T
DP
DIFFERENTIAL PRESSURE SENSOR. W HEN W ALL MOUNTED, MOUNTING HEIGHT 46" TO
MEET ADA REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH COORDINATE W ITH
ARCHITECT.
H
HUMIDITY SENSOR. W HEN W ALL MOUNTED, MOUNTING HEIGHT 46" TO MEET ADA
REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH COORDINATE W ITH ARCHITECT.
CARBON DIOXIDE SENSOR. W HEN W ALL MOUNTED, MOUNTING HEIGHT 46" TO MEET ADA
REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH COORDINATE W ITH ARCHITECT.
C
CO
CARBON MONOXIDE SENSOR. W HEN W ALL MOUNTED, MOUNTING HEIGHT 46" TO MEET
ADA REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH COORDINATE W ITH
ARCHITECT.
TEMPERATURE SENSOR. W HEN W ALL MOUNTED, MOUNTING HEIGHT 46" TO MEET ADA
REQUIREMENTS. W HEN MOUNTED NEXT TO W ALL SW ITCH COORDINATE W ITH
ARCHITECT.
S
S TEMPERATURE SENSOR MOUNTED IN CEILING PLENUM.
STATIC PRESSURE SENSOR.SP
STRAINER W ITH A BLOW DOW N VALVE AND HOSE
CONNECTION
DRAIN VALVE W ITH HOSE END CONNECTION
AUTOMATIC FLOW CONTROLLER W ITH P/T PLUG IN
AND OUT
EXPANSION JOINT
MANUAL AIR VENT
AUTOMATIC AIR VENT
PRESSURE REDUCING VALVE
2 PORT AUTOMATIC CONTROL VALVE
3 PORT AUTOMATIC CONTROL VALVE
QUICK OPENING MANUAL VALVE
VACUUM BREAKER
NEEDLE VALVE
PRESSURE AND TEMPERATURE TEST PLUG
VACUUM GAUGE W ITH STOP
END CAP
GLOBE VALVE
SHUTOFF VALVE AND BOX
SHUTOFF VALVE ON RISER
A
M
M
N
V
VB
SOLENOID VALVE
S
SAFETY RELIEF VALVE. FOR HYDRONIC SYSTEMS
PIPE DISCHARGE AIR GAPPED TO FLOOR DRAIN
UNLESS NOTED OTHERW ISE. FOR STEAM
SYSTEMS PIPE D ISCHARGE TO OUTDOORS.
W ATER METERM
PRESSURE G AUGE W ITH COCK AND SIPHON LOOP
BI-M ETALIC STEAM TRAP AND DRIP ASSEM BLY
THERMODYNAMIC STEAM TRAP AND DRIP
ASSEMBLY
INVERTED BUCKET STEAM TRAP AND DRIP
ASSEMBLY
FLOAT AND THERMOSTATIC STEAM TRAP AND
DRIP ASSEMBLY
TH ERM OSTATIC STEAM TRAP AND DRIP ASSEM BLY
BM
TD
IB
FT
TS
FLOW METER
F
UNION
CLEANOUT
STRAINER
AUTOMATIC PRESSURE INDEPENDENT CONTROL
VALVE
M
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:0
A
M
M-001
LEGEND & ABBREVIATIONS
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
HVAC SHEET LIST
SHEET NUMBER SHEET NAME
M-001 LEGEND & ABBREVIATIONS
M-002 OVERALL AHU SUMMARY MATRIX
M-100 LEVEL A - OVERALL AHU PLAN
M-101 BASEMENT - OVERALL AHU PLAN
M-102 FIRST FLOOR - OVERALL AHU PLAN
M-103 SECOND FLOOR - OVERALL AHU PLAN
M-104 THIRD FLOOR - OVERALL AHU PLAN
M-105 FOURTH FLOOR - OVERALL AHU PLAN
M-106 FIFTH FLOOR - OVERALL AHU PLAN
M-107 SIXTH FLOOR - OVERALL AHU PLAN
M-108 SEVENTH FLOOR - OVERALL AHU PLAN
M-601 AHU SCHEMATICS (CONFIG. A & B)
M-602 AHU SCHEMATICS (CONFIG. C & D)
M-603 AHU SCHEMATICS (CONFIG E & F)
M-604 AHU SCHEMATICS (CONFIG. G & H)
M-605 AHU SCHEMATICS (CONFIG. I & J)
M-606 AHU SCHEMATICS (CONFIG. K & L)
M-607 AHU SCHEMATICS (CONFIG. M & N)
M-608 AHU SCHEMATICS (CONFIG. O & P)
M-609 AHU SCHEMATICS (CONFIG. Q & R)
M-610 AHU SCHEMATICS (CONFIG. S & T)
M-611 AHU SCHEMATICS (CONFIG. U & V)
M-701 AHU ENLARGED PLANS - BASEMENT
M-702 AHU ENLARGED PLANS - FIRST FLOOR
M-703 AHU ENLARGED PLANS - SECOND FLOOR
M-704 AHU ENLARGED PLANS - THIRD FLOOR
M-705 AHU ENLARGED PLANS - FIFTH AND SEVENTH FLOOR
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
100% CDS SUBMISSION 08/20/20
BID ISSUE SUBMISSION 09/29/20
AHU SUMMARY
NOTES: BID ITEMS:
AHU TAG LOCATION SERVES LEVELS SERVED
AREA
SERVED (SF)
CONFIGURATION CONFIG SHEET
ENLARGED
PLAN SHEET
BID ITEM # NOTES
AC-6 PENTHOUSE 2-B-501 MRI, RADIOLOGY 1 6,710 A M-601 M-703 1
AC-14 2C129 LOBBY B, 1 9,300 R M-609 M-703 BID ITEM #3 1
AC-20 3RD FLOOR ROOF HEMO/ONCOLOGY 2 6,800 A M-601 M-704 1
AC-22 3RD FLOOR PENTHOUSE RADIATION THERAPY B 7,600 A M-601 M-704 1
AC-26 BF467 RESEARCH, ENVIRONMENTAL MANAGEMENT B, 1 22,500 C M-602 M-701 1
AC-28 BE260 RESEARCH (ANIMAL OR) B 1,060 B M-601 M-701 BID ITEM #2 1
AC-29 7TH FLOOR ROOFTOP BEDS SCI 6 21,800 Q M-609 M-705 1
AC-31 BE260 MICU 2 8,325 E M-603 M-701 1
AC-32 BE260 DIRECTOR'S SUITE, QUALITY MGMT., EDUCATION, SURGICAL, GERIATRICS 1 12,000 F M-603 M-701 1
AC-34 3RD FLOOR ROOF
RADIATION THERAPY, BEHAVIORAL HEALTH, PSYCHOSOCIAL REHAB AND
RECOVERY CENTER
B, 1, 2 17,960 A M-601 M-704 1
AC-35 BE260 RESEARCH FES, APT B 9,800 S M-610 M-701 BID ITEM #3 1
AC-51 BA109 AMBULATORY CARE SOUTH 1, 2 26,700 F M-603 M-701 1
AC-52 BA109 AMBULATORY CARE NORTH B, 1, 2 34,450 F M-603 M-701 1
AC-53 BA109 ATRIUM, CORRIDORS 1, 2 20,420 G M-604 M-701 1
AC-54 5TH FLOOR PAC200 EYE CLINIC, BEHAVIORAL HEALTH, AUDIOLOGY 3, 4 28,000 H M-604 M-705 1
AC-55 5TH FLOOR PAC302 BEHAVIORAL HEALTH, DENTAL, COMMON SPACE 3, 4, 5 21,275 H M-604 M-705 1
AC-56 PENTHOUSE 2F501B LOGISTICS, WAREHOUSE B, 1 26,940 J M-605 M-703 1
AC-57 PENTHOUSE 2F501C PATHOLOGY LABORATORIES 1 16,000 M M-607 M-703 1
AC-61 7TH FLOOR W PENTHOUSE PF104
CARES TOWER: PATIENT BEDS CLC, BLINDS REHAB, BEDS PSY RES
REHAB, REHAB MEDICINE, NUTRITION, CHAPEL, EDU., ENV. MGMT.,
INPATIENT PSYCHIATRY, SUBSTANCE ABUSE
A, B, 1, 2, 3, 4, 5, 6 105,800 K M-606 M-705 1
AC-62 7TH FLOOR W PENTHOUSE PF104
CARES TOWER: PATIENT BEDS CLC, PSY RES REHAB, REHAB MEDICINE,
INPATIENT PSYCHIATRY, SUBSTANCE ABUSE
A, B, 1, 2, 3, 4, 5, 6 108,720 K M-606 M-705 1
AC-63 1F191 COMMON SPACE B, 1 3,450 J M-605 M-702 BID ITEM #2 1
AC-64 7TH FLOOR W PENTHOUSE PF104 PENTHOUSE ELECTRICAL, ELEVATOR 7 2,600 T M-610 M-705 BID ITEM #2 1
AHU-E-0-1 2ND FLOOR PENTHOUSE 2B480A
CARDIOLOGY/NUCMED, ENGINEERING, ENG BIO-MED, MEDICAL SERVICE
ADMIN, ENV MANAGEMENT, CENTRALIZED STAFF FACILITIES, DIAGNOSTIC
IMG.,
B 49,500 H M-604 M-703 1
AHU-E-0-2 2ND FLOOR PENTHOUSE 2B480A NUTRITION, FOOD, ENG., PROSTHETICS, RESEARCH, ENV. MGMT. B 22,000 H M-604 M-703 1
AHU-E-0-3 2ND FLOOR PENTHOUSE 2B480A PHARMACY B 9,100 H M-604 M-703 1
AHU-E-1-1 2ND FLOOR PENTHOUSE 2B480A
SPEC. CARE, SURGICAL, RESEARCH, BEHAV. HEALTH, PRI. CARE, W.
HEALTH, SEC., ENG., H.C. ADMIN, HOME-BASED HEALTH, VSO VET ASSIST.
UNION, PATHOLOGY, VOL. SVC., ENV. MGMT., CANTEEN SVC.
1 57,700 H M-604 M-703 1
AHU-E-1-2 2ND FLOOR PENTHOUSE 2B480A CANTEEN SVC., NUTRITION, FOOD 1 22,175 H M-604 M-703 1
AHU-S-2-1 3RD FLOOR PENTHOUSE 3B162D SICU, DIGESTIVE ENDOSCOPY 2 19,000 H M-604 M-704 1
AHU-S-2-2 3RD FLOOR PENTHOUSE 3B162D SURGICAL 2 19,600 L M-606 M-704 1, 2
AHU-S-2-3 3RD FLOOR PENTHOUSE 3B162D SURGICAL 2 1,850 H M-604 M-704 BID ITEM #3 1
AHU-S-2-4 1C164 SURGICAL, STORAGE, OFFICE 2 3,850 U M-611 M-702 BID ITEM #3 1
AHU-S-2-5 3RD FLOOR S ROOFTOP SURGICAL, HYBRID ORS 2 3,775 V M-611 M-704 BID ITEM #3 1
AHU-W-0-1 2ND FLOOR PENTHOUSE 2E480A MORGUE, PATHOLOGY, ENG. SHOPS B 11,500 I M-605 M-703 1
AHU-W-0-2 2ND FLOOR PENTHOUSE 2E480A RESEARCH, COMMON, ENV. MGMT. B 14,050 I M-605 M-703 1
AHU-W-0-3 BD490 ENGINEERING SHOPS, COMMON SPACE B 17,750 N M-607 M-701 1
AHU-W-1-1 2ND FLOOR PENTHOUSE 2E480A
RETAIL, LIBRARY, NUTRITIONAL, FOOD, DIRECTOR'S SUITE, QUALITY
MGMT., PATHOLOGY, CANTEEN SVC., ENV. MGMT, MEDICAL SVC. ADMIN,
SPEC. CARE, INFECTIOUS DISEASE, VOL. SVC.
1 45,500 H M-604 M-703 1
AHU-W-1-2 2ND FLOOR PENTHOUSE 2E480A REC. HALL, ENV. MGMT., VOL. SVC., EDUCATION 1 5,000 D M-602 M-703 1
AHU-W-1-3 2ND FLOOR PENTHOUSE 2E480A CHAPEL 1 2,700 D M-602 M-703 1
RTU-65 2ND FLOOR W ROOFTOP PALMS CONNECTING CORRIDOR 1 2,600 P M-608 M-703 BID ITEM #2 1
RTU-66 2ND FLOOR W ROOFTOP CONNECTING CORRIDOR B 1,600 O M-608 M-703 BID ITEM #2 1
RTU-67 2ND FLOOR W ROOFTOP CONNECTING CORRIDOR 1 533 O M-608 M-703 BID ITEM #2 1
RTU-68 2ND FLOOR W ROOFTOP CONNECTING CORRIDOR 1 533 O M-608 M-703 BID ITEM #2 1
RTU-69 2ND FLOOR W ROOFTOP CONNECTING CORRIDOR 1 533 O M-608 M-703 BID ITEM #2 1
AI
AO
BI
BO
PI
OAT
MAT
RAT
SAT
CCAT
HCAT
OAHY
RAH
SAH
NC
NO
L
H
C
XX-01
LEGEND-
AUTOMATIC TEMPERATURE CONTROLS
CONTROL POINT - SEE POINTS SCHEDULE
ANALOG INPUT
ANALOG OUTPUT
BINARY INPUT
BINARY OUTPUT
PULSED INPUT
OUTSIDE AIR TEMPERATURE
MIXED AIR TEMPERATURE
RETURN AIR TEMPERATURE
SUPPLY AIR TEMPERATURE
COOLING COIL LEAVING AIR TEMPERATURE
HEATING COIL LEAVING AIR TEMPERATURE
OUTSIDE AIR HUMID ITY
RETURN AIR HUMIDITY
SUPPLY AIR HUMIDITY
NORMALLY CLOSED (CLOSES ON LOSS OF POW ER)
NORMALLY OPEN (OPENS ON LOSS OF POW ER)
LOW
HIGH
COMMON
2-W AY AUTOMATIC 2-POSITION CONTROL VALVE
3-W AY AUTOMATIC 2-POSITION CONTROL VALVE
2-W AY AUTOMATIC MODULATING CONTROL VALVE
3-W AY AUTOMATIC MODULATING CONTROL VALVE
DIFFERENTIAL PRESSURE SENSOR
DIFFERENTIAL PRESSURE SW ITCH
CARBON DIOXIDE SENSOR
CARBON MONOXIDE SENSOR
CURRENT SENSOR TRANSMITTER
ELECTRONIC TO PNEUMATIC TRANSDUCER
FLOW METER TRANSMITTER
HUMIDITY SENSOR
LEVEL CONTROLLER
LEVEL TRANSMITTER
PRESSURE SENSOR
STATIC PRESSURE SENSOR
TEMPERATURE SENSOR
W ATER FLOW SENSOR
W ATER LEVEL SENSOR
CURRENT SW ITCH
END SW ITCH
FLOW SW ITCH
HUMIDISTAT
OCCUPANCY SENSOR
PRESSURE SW ITCH, HIGH LIMIT
PRESSURE SW ITCH, LOW LIMIT
TEMPERATURE LOW LIMIT (FREEZE STAT)
ROOM THERMOSTAT
W ATER LEVEL SW ITCH
EMERGENCY SHUT-OFF STATION
AIR FLOW MEASURING STATION
VARIABLE FREQUENCY DRIVE (ADJUSTABLE FREQUENCY MOTOR CNRL)
MOTOR STARTER
CONTACTOR
LOCAL TEMPERATURE CONTROL PANEL
PRESSURE SAFETY - HIGH
PRESSURE SAFETY - LOW
SMOKE DETECTOR
DAMPER OR VALVE ACTUATOR - MODULATING
DAMPER OR VALVE ACTUATOR - 2-POSITION
RELAY
UVGI LIGHT
PUMP
FAN
COOLING COIL
HEATING COIL
HUMIDIFIER
FILTER
ENERGY RECOVERY W HEEL
OPPOSED BLADE CONTROL DAMPER
PARALLEL BLADE CONTROL DAMPER
SMOKE DAMPER
MIN OA / ECON DAMPER
DX COIL
W ALL MOUNTED DEVICE
DUCT INSERTION DEVICE
PIPE INSERTION OR IMMERSION DEVICE W ITH W ELL
AVERAGING SENSOR OR DEVICE
OUTDOOR SENSOR OR DEVICE, SHIELDED
FAN ARRAY, "X" FANS VERTICAL x "Y" FANS HORIZONTAL
M
M
M
M
DPH
L
DP
H
L
C
CO
CS
EPT
FM
H
LC
LT
P
SP
T
W F
W L
CS
ES
FS
H
OS
HL
P
LL
P
T
LL
T
W L
LEGEND-
AUTOMATIC TEMPERATURE CONTROLS
AFMS
VFD
MS
CON
TCP
SD
M
M
SD
X
X
X
X
X
X
X
X
X
X
R
M M
MINECON
R
UV
3 x 1X x Y
PSH
PSL
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:0
A
M
M-002
OVERALL AHU SUMMARY MATRIX
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
AIR HANDLING UNIT ENERGY USE INDEX (EUI) CALCULATIONS
A. CALCULATE AN EUI FOR EACH AIR HANDLING UNIT (AHU) SYSTEM AND THE AREA IT SERVES. THE AHU EUI W ILL ONLY CONSIDER THE MECHANICAL AND ELECTRICAL ENERGY CONSUMED BY THE CENTRAL AIR HANDLING UNITS. EUI IS EXPRESSED AS ENERGY PER SQUARE FOOT PER YEAR. IT’S CALCULATED BY DIVIDING THE TOTAL ENERGY CONSUMED IN ONE YEAR (MEASURED IN KBTU) BY THE TOTAL GROSS FLOOR AREA.
FIELD CONTROLLER SEQUENCES OF OPERATION: ALL FIELD CONTROLLER SCOPE IS TO BE PROVIDED BY THE CONTRACTOR.
REFER TO SPEC SECTION 23 09 23 PARAGRAPH 1.1.G FOR COORDINATION OF W ORK BETW EEN CONTRACTOR AND VA RETAINED, THIRD-PARTY MASTER
SYSTEM INTEGRATOR UNDER SEPARATE CONTRACT.
A. GENERAL SCOPE: MODIFY AND EXTEND THE EXISTING FIELD CONTROLLERS AS SHOW N IN THE CONTRACT DOCUMENTS. THE FIELD CONTROLLERS ARE TO
BE USED TO MONITOR REAL TIME ENERGY USAGE AND PROVIDE TIME-AVERAGED DATA FOR USE BY THE SUPERVISOR. THE TIME-AVERAGE FUNCTION IS TO ENSURE ACCURACY OF ENERGY CALCULATIONS W HILE REDUCING THE POLL FREQUENCY AND NETW ORK TRAFFIC TO A REASONABLE AMOUNT.
B. ELECTRICAL USAGE: FOR EACH ITEM BELOW , SCALE AND CALCULATE THE ANALOG INPUT AS REQUIRED TO THE UNITS OF KW . TIME AVERAGE THIS VALUE
OVER A 15-MINUTE PERIOD AND PROVIDE FOR USE BY THE SUPERVISOR.
1. FIXED SPEED MOTORS: MEASURE ELECTRICAL CURRENT VIA AN ANALOG CURRENT TRANSDUCER FOR FIXED SPEED MOTORS. CALCULATE THIS
CURRENT TO POW ER (KW ) USING THE MEASURED CURRENT AND NAMEPLATE LINE-TO-LINE VOLTAGE AND POW ER FACTOR AS FOLLOW S:
A. 3-PHASE MOTOR KW = 1.73 * VOLTS * AMPS * POW ER FACTOR / 1000
B. 1-PHASE MOTOR KW = VOLTS * AMPS * POW ER FACTOR / 1000
2. VARIABLE SPEED MOTORS: FOR MOTORS DRIVEN BY VARIABLE FREQUENCY DRIVES, RECONFIGURE THE EXISTING DRIVE TO OUTPUT POW ER USAGE
VIA AN ANALOG OUTPUT AND MONITOR AND AVERAGE BY THE DDC CONTROLLER.
C. W ATER SIDE UTILITY USAGE: FOR EACH ITEM BELOW , DIRECTLY CALCULATE THE UTILITY USAGE VIA A W ATER SIDE BTU METER AND INTEG RATE DIRECTLY
INTO THE TRIDIUM SYSTEM.
1. CHILLED W ATER USAGE (EXCEPT AC-20 AND AC-34): DIRECTLY CALCULATE ALL AHU CHILLED W ATER USAGE VIA W ATER SIDE BTU METERS AND
INTEGRATE DIRECTLY INTO THE TRIDIUM SYSTEM.
2. CHILLED W ATER USAGE (AC-20 AND AC-34): TIME-AVERAGE ALL CHILLED W ATER SENSORS AS SHOW N IN EACH CONFIGURATION MATRIX OVER A 15-
MINUTE PERIOD AND MAKE AVAILABLE FOR USE BY THE SUPERVISOR. THESE DATA INCLUDE SUPPLY AND RETURN W ATER TEMPERATURE AND FLOW .
3. HOT W ATER USAGE: DIRECTLY CALCULATE SELECT AHU’S HOT W ATER USAGE VIA W ATER SIDE BTU METERS AND INTEGRATE DIRECTLY INTO THE
TRIDIUM SYSTEM. SEE AHU CONFIGURATIONS TO IDENTIFY W HICH AHUS UTILIZE W ATER SIDE APPROACH FOR HOT W ATER METERING.
D. AIR SIDE STEAM AND HOT W ATER USAGE: FOR ALL AHU’S STEAM USAGE AND SELECT AHU’S HOT W ATER USAGE RATES, CALCULATE AT THE TRIDIUM
SUPERVISOR UTILIZING TIME-AVERAGED DATA FROM THE DDC CONTROLLERS. SEE AHU CONFIGURATIONS TO IDENTIFY W HICH AHUS UTILIZE AIR SIDE
APPROACH FOR HOT W ATER METERING.
1. TIME-AVERAGE ALL SENSORS AS SHOW N IN EACH CONFIGURATION MATRIX OVER A 15-MINUTE PERIOD AND MAKE AVAILABLE FOR USE BY THE
SUPERVISOR. THESE DATA INCLUDE, BUT ARE NOT LIMITED TO, TEMPERATURE, HUMIDITY, AND AIRFLOW .
SUPERVISOR SEQUENCE OF OPERATION: ALL SUPERVISOR SCOPE IS TO BE PROVIDED BY THE OWNER VIA A SEPARATE CONTRACT.
A. ANALYTICS FEATURE: FACILITATE ANALYTICAL FEATURES THRO UGH THE SUPERVISOR TO COMPARE UTILITY USAGE AGAINST A DEFINABLE BENCHMARK
PERIOD. VIA THE DASHBOARD, FACILITATE THIS ANALYTICAL FEATURE BY:
1. HAVING A USER DEFINED PERIOD (PER AHU SYSTEM) TO BENCHMARK PERFORMANCE (1-YEARS LENGTH)
2. TRACKING CUMULATIVE UTILITY USAGE FOR THE LAST CALENDAR YEAR
3. TRACKING CUMULATIVE USAGE ON A ROLLING 12-MONTH BASIS
4. MAINTAINING A TREND LOG OF EACH UTILITY-RATE SO THAT ANY PERIOD’S CUMULATIVE USAGE MAY BE CALCULATED EXTERNALLY
B. SUPERVISOR INTEGRATION: USE THE EXISTING N IAGARA SUPERVISOR FOR THE ENERGY DASHBOARD AND ANALYTICS. THE CALCULATION OF EACH UTILITY’S USAGE RATE W ILL BE COMPLETED AT THE AHU DDC CONTRO LLER OR BTU METER LEVEL AS SPECIFIED ABOVE. DETERMINE THE CUMULATIVE
USAGE FOR EACH ANALYTICAL PERIOD AT THE SUPERVISOR.
1. STOP CALCULATIONS AND GENERATE AND ALARM UPON A LOSS OF COMMUNICATION LONGER THAN 15 MINUTES. ADDITIONALLY, CUMULATE THE
TOTAL TIME DURATION OF VALID DATA SO THAT EACH ANALYTICAL PERIOD CAN BE NORMALIZED TO A YEAR’S LENGTH REGARDLESS OF DATA
COMMUNICATION FAILURES.
C. SUPERVISOR SEQUENCES OF OPERATION:
1. GENERAL SCOPE: FOR EACH AHU INTEGRATE ALL NEW DATA POINTS FOR ALL UTILITIES TO THE SUPERVISOR. UTILIZE THESE POINTS FOR
CALCULATIONS, MONITORING AND TRENDING PURPOSES. UTILIZE THE SUPERVISOR TO CALCULATE ENERGY USAGE AND TIME DURATION ACROSS THE VARIOUS ANALYTICAL TIME-PERIODS AS DESCRIBED IN THE ANALYTICS FEATURES SECTION. MAKE THESE CALCULATIONS FOR EACH INDIVIDUAL UTILITY AND PROVIDE A GRAND TOTAL. CALCULATE INDIVIDUAL UTILITIES IN THEIR MEASURED UNITS. USE THE TRADITIONAL UNIT OF KBTU/FT2 FOR
GRAND TOTALS. THE FOLLOW ING CONVERSIONS APPLY.
• MBTU X 1
• BTU X 0.001
• KW H X 3.14
2. ELECTRICAL USAGE: CALCULATE THE ELECTRICAL POW ER IN KW FOR EACH MOTOR AT THE AHU DDC CONTROLLER AND AVERAGE OVER A 15 MINUTE PERIOD. AT THE SUPERVISOR, CUMULATE THIS ELECTRICAL USAGE AS REQUIRED BY THE GENERAL SCOPE.
3. W ATER SIDE UTILITY USAGE
A. CHILLED W ATER USAGE (EXCEPT AC-20 AND AC-34): THE CHILLED W ATER UTILITY RATE IS CALCULATED BY EACH W ATER SIDE BTU METER. AT THE
SUPERVISOR, CUMULATE THIS CHILLED W ATER USAGE AS REQUIRED BY THE GENERAL SCOPE.
B. CHILLED W ATER USAGE (AC-20 AND AC-34): CALCULATE THE CHILLED W ATER ENERGY USAGE IN THE FOLLOW ING MANNER
a. AT THE DDC FIELD CONTROLLER, CALCULATE A ROLLING 15-MINUTE AVERAGE OF TEMPERATURE AND W ATER FLOW DATA. INTEGRATE INTO
TRIDIUM SYSTEM.
b. CALCULATE CHILLED W ATER ENERGY RATE (MBTU/HR) = 500 * GPM * (TOUT - TIN) / 1000
c. CUMULATE THIS USAGE AS REQUIRED BY THE GENERAL SCOPE.
C. HOT W ATER USAGE: THE HOT W ATER UTILITY RATE IS CALCULATED BY EACH W ATER SIDE BTU METER. AT THE SUPERVISOR, CUMULATE THIS HOT W ATER USAGE AS REQUIRED BY THE GENERAL SCOPE. SEE AHU CONFIGURATIONS TO IDENTIFY W HICH AHUS UTILIZE W ATER SIDE APPROACH
FOR HOT W ATER METERING.
4. AIR SIDE STEAM AND HOT W ATER USAGE: FOR ALL AHU’S STEAM USAGE AND SELECT AHU’S HOT W ATER USAGE, CALCULATE RATES AT THE TRIDIUM
SUPERVISOR UTILIZING TIME-AVERAGED DATA FROM THE DDC CONTROLLERS. SEE AHU CONFIGURATIONS TO IDENTIFY W HICH AHUS UTILIZE AIR SIDE
APPROACH FOR HOT W ATER METERING.
A. HEATING COIL: CALCULATE STEAM OR HOT W ATER HEATING COIL USAGE IN THE FOLLOW ING MANNER
a. AT THE DDC FIELD CONTROLLER, CALCULATE A ROLLING 15 MINUTE AVERAGE OF TEMPERATURE AND AIRFLOW DATA. INTEGRATE INTO THE
TRIDIUM SYSTEM.
b. CALCULATE THE STEAM ENERGY RATE (MBTU/HR) = 1.08 * CFM * (TOUT – TIN) / 1000
c. CUMULATE THIS USAGE AS REQUIRED BY THE GENERAL SCOPE.
B. HUMIDIFIER: CALCULATE STEAM HUMIDIFIER USAGE IN THE FOLLOW ING MANNER:
a. AT THE DDC FIELD CONTROLLER, CALCULATE A ROLLING 15 MINUTE AVERAGE OF TEMPERATURE, HUMIDITY, AND AIRFLOW DATA. INTEGRATE
INTO THE TRIDIUM SYSTEM.
b. CALCULATE W IN, THE INLET HUMIDITY RATIO, AND W OUT, THE OUTLET HUMIDITY RATIO. TO CALCULATE W :
• CALCULATE THE VAPOR PRESSURE USING THE DDC TEMPERATURE AND RELATIVE HUMIDITY DATA AND THE BUILT-IN PSYCHROMETRIC
FUNCTION BLOCK.
• THE HUMIDITY RATIO IS THEN CALCULATED AS W = 0.621945 * VAPOR PRESSURE / (14.35 – VAPOR PRESSURE)
c. CALCULATE THE STEAM ENERGY RATE (MBTU/HR) = 4760 * CFM * (W OUT – W IN) / 1000
d. LIM IT TO MINIMUM OF 0 BTU/HR
e. CUMULATE THIS USAGE AS REQUIRED BY THE GENERAL SCOPE.
UTILITY SERVICE INTERRUPTION REQUIREMENTS
A. NO UTILITY SERVICE SUCH AS W ATER, GAS, STEAM, ELECTRICITY, FIRE PROTECTION SYSTEMS AND COMMUNICATIONS SYSTEMS MAY BE INTERRUPTED W ITHOUT PRIOR APPROVAL OF COR. ELECTRICAL W ORK SHALL BE ACCOMPLISHED W ITH ALL AFFECTED CIRCUITS OR EQUIPMENT DE-ENERGIZED.
B. CONTRACTOR SHALL SUBMIT A REQUEST TO INTERRUPT ANY SUCH SERVICES TO COR, IN W RITING, 7 DAYS IN ADVANCE OF PROPOSED INTERRUPTION.
REQUEST SHALL STATE REASON, DATE, EXACT TIME OF, AND APPROXIMATE DURATION OF SUCH INTERRUPTION.
C. CONTRACTOR W ILL BE ADVISED (IN W RITING) OF APPROVAL OF REQUEST, OR OF W HICH OTHER DATE AND/OR TIME SUCH INTERRUPTION W ILL CAUSE LEAST INCONVENIENCE TO OPERATIONS OF MEDICAL CENTER. INTERRUPTION TIME APPROVED BY MEDICAL CENTER MAY OCCUR AT OTHER THAN
CONTRACTOR'S NORMAL W ORKING HOURS.
D. MAJOR INTERRUPTIONS OF ANY SYSTEM MUST BE REQUESTED, IN W RITING, AT LEAST 15 CALENDAR DAYS PRIOR TO THE DESIRED TIME AND SHALL BE
PERFORMED AS D IRECTED BY THE COR .
E. IN CASE OF A CONTRACT CONSTRUCTION EMERGENCY, SERVICE W ILL BE INTERRUPTED ON APPROVAL OF COR. SUCH APPROVAL W ILL BE CONFIRMED IN
W RITING AS SOON AS PRACTICAL.
PROJECT SEQUENCING
A. THE CONTRACTOR SHALL BE RESPONSIBLE FOR DEVELOPING A SEQUENCING PLAN FOR THE ORDER IN W HICH THE AIR HANDLERS IN THE PROJECT ARE ADDRESSED, AND SHALL SUBMIT SAME TO THE VA COR FOR REVIEW AND APPROVAL DURING THE PRE-CONSTRUCTION PHASE. IT IS NOT NECESSARILY A REQUIREMENT THAT THE AIR HANDLERS BE W ORKED ON ONE-BY-ONE IF THE CONTRACTOR OBTAINS APPROVAL FROM THE VA COR TO W ORK ON MULTIPLE AIR HANDLERS AT ONCE. REGARDLESS OF THE APPROACH TAKEN, TOTAL CONSTRUCTION TIMELINE SHALL NOT EXCEED THE DURATION
OUTLINED BELOW .
B. PROJECT SCHEDULE SHALL INDICATE THE STARTING DATE AND DURATION OF W ORK FOR EACH AIR HANDLING UNIT SYSTEM.
C. REFER TO 23 09 23 PARAGRAPH 1.1.G FOR COORDINATION OF W ORK BETW EEN CONTRACTOR AND VA RETAINED, THIRD-PARTY MASTER SYSTEM
INTEGRATOR UNDER SEPARATE CONTRACT.
CONSTRUCTION PHASING
FOR EACH UNIT, THE GENERAL PHASING OF W ORK SHALL BE:
A. DETERMINE EXACT UPGRADES THAT ARE TO BE PERFORMED ON AIR HANDLING UNIT AND ASSOCIATED CONTROLLER AS SPECIFIED IN UNIT'S SENSOR
CONFIGURATION MATRIX.
B. SCHEDULE SHUTDOW N OF UNIT.
C. PERFORM W ORK NOT REQUIRING UNIT SHUTDOW N, SUCH AS: AHU CONTROLLER UPGRADES, NEW CONDUIT AND W IRING BETW EEN CONTROLLER PANELS
AND SENSOR OR METER LOCATIONS. INSTALL ANY CHILLED W ATER METERING SENSORS AND METERS.
D. SHUTDOW N AIR HANDLING UNIT. EACH AHU SHALL BE OUT OF SERVICE NO LONGER THAN 4 HOURS.
E. PERFORM REMAIN ING SENSOR INSTALLATION.
F. PERFORM SENSOR TESTING AND CALIBRATION OF EXISTING AND NEW SENSORS AS DESCRIBED IN AIR HANDLING UNIT SENSOR CONFIGURATION MATRIX.
G. COMPLETE FIELD CONTROLLER AND PROGRAMMING W ORK.
H. RESTART UNIT.
I. COORDINATE W ITH THIRD-PARTY MASTER SYSTEM INTEGRATOR (PROVIDED UNDER SEPARATE CONTRACT) TO COMPLETE SUPERVISOR AND EUI
INTEGRATION W ORK.
CONSTRUCTION TIMELINE
THE SCOPE OF W ORK DESCRIBED IN THIS DRAW ING PACKAGE REPRESENTS A PROJECT THAT MUST BE UNDERTAKEN DURING FULL OCCUPANCY AND FUNCTIONALITY OF THE EXISTING HOSPITAL. THE PROPOSED DURATION PLAN IS AS FOLLOW S:
PRE-CONSTRUCTION: 60 DAYS
CONSTRUCTION: 365 DAYS* (NOTE: CONTRACTOR SHALL ALLOW 7 DAYS PER AIR HANDLER
FOR VA'S MASTER SYSTEM INTEGRATOR W ORK)
TOTAL TIMEFRAME: 425 DAYS
THE FOLLOW ING CONSTRUCTION SCHEDULE TIMEFRAMES SHALL APPLY TO THIS PROJECT:
CONSTRUCTION ACTIVITIES ARE PERMITTED TO OCCUR DURING REGULAR SHIFT HOURS, W HEN NO INTERRUPTION TO OPERATION RESULTS. CONTRACTORS, HOW EVER, SHALL NOT BE PERMITTED TO HAVE MATERIALS AND DELIVERIES DELIVERED OR TAKEN AW AY DURING REGULAR SHIFT HOURS, AND MUST
COORDINATE SUCH ACTIVITIES W ITH STAFF AND VA COR.
THE TIMEFRAMES IDENTIFIED ABOVE ARE IN REFERENCE TO NORMAL CONSTRUCTION ACTIVITIES AND, UNLESS APPROVED BY VA COR, SHALL NOT APPLY TO
W ORK SUCH AS:
• UTILITY SHUTDOW NS
• EXISTING MEP SYSTEM SHUTDOW NS
• W ORK IN PUBLIC CORRIDORS
• CUTTING OF FLOOR OPENINGS IN THE EXISTING BUILDING
• W ORK OUTSIDE OF TEMPORARY CONSTRUCTION PARTITIONED AREAS, INCLUDING ACCESS OF CEILING PLENUM SPACES IN FLOORS ABOVE OR BELOW
CONSTRUCTION AREAS, AND REPLACEMENT OF EXISTING FINISHES.
• CONSTRUCTION OF TEMPORARY CONSTRUCTION BARRIERS.
W ORK IDENTIFIED ABOVE SHALL OCCUR EITHER IN THE EVENING SHIFT OR ON W EEKENDS. ALL CONSTRUCTION ACTIVITIES AND SCHEDULES MUST BE REVIEW ED AND APPROVED BY VA COR. REFER TO SPEC DIVISION 01 FOR GENERAL PROJECT REQUIREMENTS.
1) PROVIDE ALL CLEANING, CALIBRATION, SENSORS, CONDUIT, W IRING, NEW CONTROL POINTS, AND PROGRAMMING AS REQUIRED FOR W ORK INDICATED ON AHU CONFIGURATION MATRICES, AND ENLARGED AHU PLANS. ALL NEW
CONTROL POINTS SHALL BE DISCOVERABLE BY THE TRIDIUM SYSTEM.
2) AS OF DESIGN, UNIT IS NOT YET IN SERVICE.
BID ITEM 1 (BASE BID): ALL W ORK INCLUDED W ITHIN CONSTRUCTION DOCUMENTS AND ASSOCIATED SPECIFICATIONS.
BID ITEM 2 (DEDUCT ALTERNATE 1): W ORK INCLUDES BID ITEM 1 (BASE BID), EXCEPT DELETE ALL W ORK ASSOCIATED W ITH AC-28, AC-63, AC-64, RTU-65, RTU-66, RTU-67, RTU-68, AND RTU-69 INCLUDING SENSORS, CONTROLS, PROGRAMMING, AND ELECTRICAL CONNECTIONS.
BID ITEM 3 (DEDUCT ALTERNATE 2): W ORK INCLUDES BID ITEM 2, EXCEPT ADDITIONALLY DELETE ALL W ORK ASSOCIATED W ITH AC-14, AC-35, AHU-S-2-3, AHU-S-2-4, AHU-S-2-5, INCLUDING SENSORS, CONTROLS, PROGRAMMING, AND ELECTRICAL CONNECTIONS.
GENERAL NOTES:
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
XX
X
X X
X
X
X
X
X
X XXX
X X X X X X X X X X X
X
X
X
XX
X
X
X
X X
FEC
FEC
FEC
FEC
UP
UP
UP
X
AC-61
AC-62
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:1
A
M
M-100
LEVEL A - OVERALL AHU PLAN
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
GENERAL NOTES
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
SCALE: 1/32" = 1'-0"
LEVEL A FLOOR PLAN
1N
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
Existing panel Existing panel Existing panel Existing panelExisting panel
UP
DN
DN
UP
UP
DN
B F C
B F C
16001600
B
B
B
A
AC-22
AC-26
AC-26
AC-28
AC-34
AC-52
AC-53
AC-52
AC-51
AC-31
AC-32
AC-56
AHU-E-0-1
AHU-E-0-2
AHU-E-0-3
AHU-W-0-1
AHU-W-0-2
AHU-W-0-3
AHU-W-0-3
AC-61
AC-62
M -701
AC-28
M -701
M -701
M -701
AC-63
AC-35
A C
-1
AC-35
RTU-66
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:1
A
M
M-101
BASEMENT - OVERALL AHU PLAN
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
BASEMENT FLOOR PLAN
GENERAL NOTES
N
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLER
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
AHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
C
B
A
G
FED
C
B A
FEC
U P
R
D O W N
R
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
STAIR D
PE1
STAIR B
STAIR A
STAIR 2
STAIR 3
STAIR 1
STAIR 2
STAIR 6
STAIR 5
STAIR 4
STAIR 13 STAIR 2
STAIR 9
STAIR 2
STAIR C
STAIR B
STAIR A
STAIR 11
STAIR A
STAIR 8
STAIR S3
STAIR S2
P3P2P1
STAIR S1
S3
S2
S1
PE8PE7
PE6PE5PE4PE3
SE2SE1
16001600
B
A B
B
B
C
AC-26
AC-34
AC-51
AC-52
AC-6
AC-32
AC-53
A C
-5
AC-57
AHU-E-1-1
AHU-E-1-2
AHU-W-1-1
A H
U -W
-1 -3
AHU-W-1-2
AC-61
AC-62
RTU-65
AHU-S-2-4
AC-63
AHU-63
M -702
M -702
AC-14
AHU-E-1-1
AHU-S-2-4
RTU-67-69
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:2
A
M
M-102
FIRST FLOOR - OVERALL AHU PLAN
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
FIRST FLOOR PLAN
GENERAL NOTES
N
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
CRASH CRASH
NIC NIC
AE113AW
B
HM
I M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000ECAE113AW
B
HM
I
M
SC
10.000000EC AE113AW
B
HM
I
M
SC
10.000000EC AE113AW
B
HM
I
M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000ECAE113AW
B
HM
I
M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000EC AE113AW
B
HM
I
M
SC
10.000000EC
AE113AW
B
HM
I
M
SC
10.000000EC
46-3618-38HM IM FS10.000000
3 6/18 M S
46-3618-38HMI MFS 10.000000
36/18
MS
46-3618-38HM IM FS10.000000
3 6/18 M S
46-3618-38HMI MFS 10.000000
36/18
MS
SA300ANMAUS10.000000
SA300ANMAUS10.000000
SA300ANMAUS10.000000SA300ANMAUS10.000000 SA300ANMAUS10.000000 SA300ANMAUS10.000000
SA300ANMAUS10.000000SA300ANMAUS10.000000
SA300ANMAUS10.000000
SA300ANMAUS10.000000 SA300ANMAUS10.000000
SA300ANMAUS10.000000
E3231.42HM
I
HEI170.000000U
E3231.42HM
I
HEI170.000000U
E3210.42WHM
I
HEI170.000000U
E3210.42WHM
I
HEI170.000000U
E6010. HMI HEI 162.000000U
E6010. HMI HEI 162.000000U
E6010. HMI HEI 162.000000U
E6010. HMI HEI 162.000000U
M 16-1522-FFHM IM ER10.000000M P
M 16-1522-FFHM IM ER10.000000M P
M 16-1528-BFHM IM ER10.000000M P M 16-1528-BFHM IM ER10.000000M P
M 16-1528-BFHM IM ER10.000000M P
M 16-1522-FFHM IM ER10.000000M P
M 16-1528-BFHM IM ER10.000000M P
M 16-1522-FFHM IM ER10.000000M P
26-4220-3NHM
I
M
ER
10.000000M F
26-4220-3NHM
I
M
ER
10.000000M F
2 1
..1.
H S
L-
H A
P
..1.
H S
L-
H A
P
H S L- 0 02 4
H A P
- J LE
..1.
H F
P-
H A
P
H S L- 0 04 2
H A P
. . 1 .
H S
R-
H A
P
. . 1 .
H S
R-
H A
P
HSL-0048
HAP HAP
HSL-0054
HSL-0030
HAP
H S R- 0 03 0
H A P
H S R- 0 03 0
H A P
H S L- 0 04 8
H A PH A P
H S L- 0 05 4
H S L- 0 03 0
H A P
HSL-0024
HAP
..1.
H S
L-
H A
P
..1.
H S
L-
H A
P
..1
J
LE
P D
M
H A
P
..1
J
LE
P D
M
H A
P
HSL-0042
HAP
HTTC-30
HAP
H S L- 0 02 4
H A P
- J LE
. . 1 .
H F
P-
H A
P
HSL-0048
HAP HAP
HSL-0054
HSL-0030
HAP
H S L- 0 04 8
H A PH A P
H S L- 0 05 4
H S L- 0 03 0
H A P
H S L- 0 04 2
H A P
ELEVATOR
D O W N
R
FEC
W
V
U
T
S
UP
DN
DN
UP
UP
DN
B F C
AC-34
AC-51
AC-52
AC-20
AC-6
AC-31
AC-53
AC-56
AC-57
AHU-E-0-3 AHU-E-0-2
AHU-E-1-1
AHU-E-0-1AHU-E-1-2
AHU-S-2-1
AHU-S-2-2
AHU-W-0-2 (LOWER)
AHU-W-0-1 (UPPER)
AHU-W-1-2 (LOWER)
AHU-W-1-3 (UPPER)
AHU-W-1-1
AC-61
AC-62
M -703
M -703
A H
U -S
-2 -3
RTU-68
RTU-66
RTU-69
M -703
RTU-67
AC-14
AHU-S-2-5
RTU-65
M -703
M -703
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:3
A
M
M-103
SECOND FLOOR - OVERALL AHU
PLANHEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
SECOND FLOOR PLAN
GENERAL NOTES
N
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
UPDN
UP DN
DN
UP
B F C
16001600
B
C
B
B
B
A
AC-34
AC-22
AC-20
AC-54
AC-55
AHU-S-2-1
AC-61
AC-62
AHU-S-2-2
M -704
M -704
M -704
AHU-S-2-5
AHU-S-2-3
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:3
A
M
M-104
THIRD FLOOR - OVERALL AHU
PLANHEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
THIRD FLOOR PLAN
GENERAL NOTES
N
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
FEC
B F C
16001600
B
C
B
B
B
A
AC-54
AC-55
AC-61
AC-62
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:4
A
M
M-105
FOURTH FLOOR - OVERALL AHU
PLANHEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
FOURTH FLOOR PLAN
GENERAL NOTES
N
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
16001600
B
A B
B
B
C AC-54
AC-55
AC-55
AC-61
AC-62
M -705
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a l_ jd z e ig le r.
rv t
/3
/2
:5
:4
A
M
M-106
FIFTH FLOOR - OVERALL AHU PLAN
HEAPY ENGINEERING
1422 EUCLID AVE STE 1162
CLEVELAND, OH 44115
216-862-5846
ADD AHU METERING
10701 EAST BLVD. CLEVELAND, OHIO
541-21-205
CAMPUS
09/29/2020 MGW JDZ
BID ISSUE SUBMISSION
FULLY SPRINKLERED
2020-05088
01528
SCALE: 1/32" = 1'-0"
FIFTH FLOOR PLAN
GENERAL NOTES
N
A. AIR HANDLER SHAPE, SIZE, AND LOCATION IS APPROXIMATE AND
FOR REFERENCE ONLY.
B. SHOW N AHU SERVICE AREA IS APPROXIMATE AND FOR REFERENCE
ONLY.
C. ALL EXISTING AIR HANDLER MECHANICAL ROOMS ARE ENCLOSED IN
1 HR RATED FIRE BARRIERS. CONTRACTOR SHALL FIRESTOP ALL
NEW THRU-W ALL PENETRATIONS.
DASHED BOUNDARY INDICATES APPROXIMATE
AREA SERVED BY TAGGED AIR HANDLERAHU TAG
Revisions: Date:
35% SCHEM. DESIGN SUBMISSION 06/04/20
65% DESIGN DEVELOPMENT 07/07/20
90% CDS SUBMISSION 07/31/20
X
6A107C
STAIR 4
STAIR 3
STAIR 5
STAIR 8
STAIR 9
SE1 SE2
PE3 PE4 PE5 PE6
PE7 PE8
STAIR S1
S1
S2
S3
STAIR S2
STAIR S3
P1 P2 P3
16001600
B
A B
B
B
C
AC-61
AC-62
AC-29
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Departm ent of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ENGINEER OF RECORD STAMPARCHITECT
321 4 5 6 7 8 9 10
1468 W EST 9TH STREET #400
CLEVELAND, OH 44113
P. 216.687.1555 F. 216.687.1558
PROJECT NO.
STATE COA FIRM NO.
D a y d a ta
\H e a p y D o c u m e n ts \j d z e ig le r\ M y D o c u m e n ts
\2
-0
-M E
-C e n tr a…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .