S02 - ATTACHMENT L - Bay Pines VAMC Construction Schedule.pdf
PDF 5 MB Posted
- Attached to
- Q702--Bay Pines IOT&A (VA-22-00030354)
- Solicitation number
- 36C77622Q0238
About this file
This is a request for quotation (RFQ) from the Department of Veterans Affairs Office of Information Service Center seeking quotations for Q702--Bay Pines IOT&A (VA-22-00030354). The RFQ requires quotations for information technology assessment and authorization (IOT&A) services at the Bay Pines VA Medical Center. Quotations are due by April 18, 2022. The award date is anticipated for May 2, 2022. Pricing is to be quoted as firm-fixed price. The period of performance is from the award date through September 30, 2022. The place of performance is the Bay Pines VA Medical Center. The RFQ identifies the incumbent contractor as Iron Bow Technologies. The RFQ seeks IOT&A services to assess and authorize IT systems and assets at the medical center in accordance with NIST and VA requirements.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Remaining Duration
Schedule % Complete
Start Finish Total Float
11 438 413 1.06% 01-Feb-22 A 17-Oct-23 -13
PREDuct116 Prepare & Submit Structural Modifications Pre-demo Work Riser 15 15 0% 01-Feb-22 A 21-Mar-22 -14
PREDuct134 Approve Structural Modificationsr Pre-demo Work Riser 20 20 0% 22-Mar-22 18-Apr-22 -14
PREDuct150 Procure/Manufacture Steel for new Slab Penetrations for Pre-Demo Riser 15 15 0% 19-Apr-22 09-May-22 -14
PREDuct158 Cut, Reinforce and Grout new Slab Penetrations for Pre-Demo Shafts 8 8 0% 10-May-22 19-May-22 -14
PREDuct160 Install New fire dampers at New floor Penetrations @ Pre-Demo Shaft North 6 6 100% 28-Feb-22 A 27-May-22 -14
PREDuct162 Install Duct down through entire Building @ Pre-Demo Shaft North 8 8 0% 31-May-22 09-Jun-22 -14
PREDuct168 Frame Shaft Walls @ Pre-Demo Shaft North 3 3 0% 10-Jun-22 14-Jun-22 -14
PREDuct172 Install Shaft wall Dampers @ Pre-Demo Shaft North 3 3 0% 15-Jun-22 17-Jun-22 -14
PREDuct174 Complete and test Mechanical Duct @ Pre-Demo Shaft North 3 3 0% 20-Jun-22 22-Jun-22 -14
PREDuct180 Insulate Mechanical Supply Duct @ Pre-Demo Shaft North 6 6 0% 23-Jun-22 30-Jun-22 -14
PREDuct186 Install Shaft Wall Liner @ Pre-Demo Shaft North 3 3 0% 01-Jul-22 06-Jul-22 -14
PREDuct192 Rough-in In-wall Electrical @ Pre-Demo Shaft North 2 2 0% 07-Jul-22 08-Jul-22 -14
PREDuct194 Hang and Finish Dry-wall @ Pre-Demo Shaft North 3 3 0% 11-Jul-22 13-Jul-22 -14
PREDuct200 Fire Caulk & Seal Dry-wall @ Pre-Demo Shaft North 2 2 0% 14-Jul-22 15-Jul-22 -14
PREDuct202 Connect North Risers to existing Risers [attic] and existing HVAC [1st floor North] 4 4 0% 16-Jul-22 24-Jul-22 -6
PREDuct206 Connect South Risers to existing Risers (attic) and existing HVAC [1st floor South] 4 4 0% 24-Jul-22 06-Aug-22 -6
PREDuct208 Demoilsh Old Existing Exhaust Duct [All Floors] 5 5 0% 08-Aug-22 12-Aug-22 -13
.5N.592 DW - Hang 1 SIDE @ 5th Flr North 10 10 0% 15-Aug-22 26-Aug-22 -13
.5N.598 DW - Install Insulation @ 5th Flr North 3 3 0% 29-Aug-22 31-Aug-22 -13
.5N.5040 DW - Hang 2-SIDE @ 5th Flr North 10 10 0% 01-Sep-22 15-Sep-22 -13
.5N.596 DW - Frame Hard Ceilings & Soffits & Furr-Outs @ 5th Flr North 5 5 0% 16-Sep-22 22-Sep-22 -13
.5N.5982 ELE - Rough-In Electrical at Hard Ceilings@ 5th Flr North 10 10 0% 23-Sep-22 06-Oct-22 -13
.5N.5280 DW - Hang Hard Ceilings @ 5th Flr North 6 6 0% 07-Oct-22 14-Oct-22 -13
.5N.5300 DW - Finish Drywall (Mud & Tape) @ 5th Flr North 10 10 0% 17-Oct-22 28-Oct-22 -13
.5N.5340 DW - Touch Up Drywall @ 5th Flr North 2 2 0% 31-Oct-22 01-Nov-22 -13
.5N.5380 PNT - Prime and First Coat Paint @ 5th Flr North 4 4 0% 02-Nov-22 07-Nov-22 -13
.5N.5320 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr North 7 7 0% 08-Nov-22 17-Nov-22 -13
.5S.5700 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr South 7 7 0% 18-Nov-22 30-Nov-22 -13
.5L.5320 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr Lobby 7 7 0% 01-Dec-22 09-Dec-22 -13
.4N.4325 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr North 7 7 0% 12-Dec-22 20-Dec-22 -13
.4N.4350 ELE - Install Lighting Support @ 4th Flr North 3 3 0% 21-Dec-22 27-Dec-22 -13
.4N.4385 ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr North 12 12 0% 28-Dec-22 16-Jan-23 -13
.4N.4405 ACT - Install Ceiling Tiles @ 4th Flr North 8 8 0% 17-Jan-23 26-Jan-23 -13
.4S.4430 ACT - Install Ceiling Tiles @ 4th Flr South 8 8 0% 27-Jan-23 07-Feb-23 -13
.4L.5700 ACT - Install Ceiling Tiles @ 4th Flr Lobby 4 4 0% 08-Feb-23 13-Feb-23 -13
.3N.3410 ACT - Install Ceiling Tiles @ 3rd Flr North 8 8 0% 14-Feb-23 23-Feb-23 -13
.3S.3410 ACT - Install Ceiling Tiles @ 3rd Flr South 8 8 0% 24-Feb-23 07-Mar-23 -13
.3L.3340 ACT - Install Ceiling Tiles @ 3rd Flr Lobby 4 4 0% 08-Mar-23 13-Mar-23 -13
.2N.2410 ACT - Install Ceiling Tiles @ 2nd Flr North 8 8 0% 14-Mar-23 23-Mar-23 -13
.2S.2410 ACT - Install Ceiling Tiles @ 2nd Flr South 8 8 0% 24-Mar-23 04-Apr-23 -13
.2W.2410 ACT - Install Ceiling Tiles @ 2nd Flr West W. 8 8 0% 05-Apr-23 14-Apr-23 -13
.2C.2410 ACT - Install Ceiling Tiles @ 2nd Flr Central W. 8 8 0% 17-Apr-23 26-Apr-23 -13
.2C.2415 Flr - Prep & Install Flooring @ 2nd Flr Central W. 14 14 0% 27-Apr-23 16-May-23 -13
.2C.2440 Flr - Install Base @ 2nd Flr Central W. 5 5 0% 17-May-23 23-May-23 -13
.2C.2445 PNT - Final Coat Paint @ 2nd Flr Central W. 5 5 0% 24-May-23 31-May-23 -13
.2C.2450 ELE - Install Electrical Trim @ 2nd Flr Central W. 4 4 0% 01-Jun-23 06-Jun-23 -13
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
17-Oct-23, 1
Prepare & Submit Structural Modifications Pre-demo Work Riser
Approve Structural Modificationsr Pre-demo Work Riser
Procure/Manufacture Steel for new Slab Penetrations for Pre-Demo Riser
Cut, Reinforce and Grout new Slab Penetrations for Pre-Demo Shafts
Install New fire dampers at New floor Penetrations @ Pre-Demo Shaft North
Install Duct down through entire Building @ Pre-Demo Shaft North
Frame Shaft Walls @ Pre-Demo Shaft North
Install Shaft wall Dampers @ Pre-Demo Shaft North
Complete and test Mechanical Duct @ Pre-Demo Shaft North
Insulate Mechanical Supply Duct @ Pre-Demo Shaft North
Install Shaft Wall Liner @ Pre-Demo Shaft North
Rough-in In-wall Electrical @ Pre-Demo Shaft North
Hang and Finish Dry-wall @ Pre-Demo Shaft North
Fire Caulk & Seal Dry-wall @ Pre-Demo Shaft North
Connect North Risers to existing Risers [attic] and existing HVAC [1st floor North]
Connect South Risers to existing Risers (attic) and existing HVAC [1st floor South]
Demoilsh Old Existing Exhaust Duct [All Floors]
DW - Hang 1 SIDE @ 5th Flr North
DW - Install Insulation @ 5th Flr North
DW - Hang 2-SIDE @ 5th Flr North
DW - Frame Hard Ceilings & Soffits & Furr-Outs @ 5th Flr North
ELE - Rough-In Electrical at Hard Ceilings@ 5th Flr North
DW - Hang Hard Ceilings @ 5th Flr North
DW - Finish Drywall (Mud & Tape) @ 5th Flr North
DW - Touch Up Drywall @ 5th Flr North
PNT - Prime and First Coat Paint @ 5th Flr North
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr North
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr South
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 5th Flr Lobby
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr North
ELE - Install Lighting Support @ 4th Flr North
ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr North
ACT - Install Ceiling Tiles @ 4th Flr North
ACT - Install Ceiling Tiles @ 4th Flr South
ACT - Install Ceiling Tiles @ 4th Flr Lobby
ACT - Install Ceiling Tiles @ 3rd Flr North
ACT - Install Ceiling Tiles @ 3rd Flr South
ACT - Install Ceiling Tiles @ 3rd Flr Lobby
ACT - Install Ceiling Tiles @ 2nd Flr North
ACT - Install Ceiling Tiles @ 2nd Flr South
ACT - Install Ceiling Tiles @ 2nd Flr West W.
ACT - Install Ceiling Tiles @ 2nd Flr Central W.
Flr - Prep & Install Flooring @ 2nd Flr Central W.
Flr - Install Base @ 2nd Flr Central W.
PNT - Final Coat Paint @ 2nd Flr Central W.
ELE - Install Electrical Trim @ 2nd Flr Central W.
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:30
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 1 of 63 TASK filter: All Activities
© Oracle Corporation
Remaining Duration
Schedule % Complete
Start Finish Total Float
.2C.2460 Punch Area @ 2nd Flr Central W. 6 6 0% 07-Jun-23 14-Jun-23 -13
.2C.2470 Remove Trash Chute and repair area @ Building 11 11 0% 07-Jun-23 21-Jun-23 -13
.2.210 AHJ - Inspections @ 2nd Flr 5 5 0% 22-Jun-23 28-Jun-23 -13
.SITE.2000 Demo Existing Site & Landscaping @ Port Cochere 3 3 0% 29-Jun-23 05-Jul-23 -13
.SITE.2010 Rough Grade @ Port Cochere 3 3 0% 06-Jul-23 10-Jul-23 -13
.SITE.2020 Complete Foundation Layout @ Port Cochere 1 1 0% 11-Jul-23 11-Jul-23 -13
.SITE.2030 Foundation Excavation @ Port Cochere 3 3 0% 12-Jul-23 14-Jul-23 -13
.SITE.2040 Form Footing & Pier Foundation @ Port Cochere 5 5 0% 17-Jul-23 21-Jul-23 -13
.SITE.2060 Foundation Reinforcement & Anchor Bolts @ Port Cochere 5 5 0% 24-Jul-23 28-Jul-23 -13
.SITE.2080 Inspect Foundatin Reinforcement & Anchor Bolts @ Port Cochere 1 1 0% 31-Jul-23 31-Jul-23 -13
.SITE.2090 Pour & Cure Foundations & Footings [inc. Bollards] @ Port Cochere 4 4 0% 01-Aug-23 04-Aug-23 -13
.SITE.2100 Form & Reinforce Site Walls @ Port Cochere 8 8 0% 07-Aug-23 16-Aug-23 -13
.SITE.2130 Inspect Site Walls @ Port Cochere 1 1 0% 17-Aug-23 17-Aug-23 -13
.SITE.2140 Pour & Cure Walls @ Port Cochere 4 4 0% 18-Aug-23 23-Aug-23 -13
.SITE.2160 Backfill, Compaction & Finegrade For Walkways, Sidewalks & Stairs @ Port Cochere 5 5 0% 24-Aug-23 30-Aug-23 -13
.SITE.2180 Form & Reinforce Walkways & Stairs @ Port Cochere 10 10 0% 31-Aug-23 13-Sep-23 -13
.SITE.2200 Pour & Cure Walkways & Stairs @ Port Cochere 5 5 0% 14-Sep-23 20-Sep-23 -13
.SITE.2220 Install Railings @ Port Cochere 4 4 0% 21-Sep-23 26-Sep-23 -13
.SITE.2230 Punch Sitework 10 10 0% 27-Sep-23 10-Oct-23 -13
COMPLETION Work Complete [Target 9/28/2023] 0 0 0% 17-Oct-23* -13
DEMOB Complete Final Acceptance Inspection, Demob and Closeout as required for Final Completion5 5 0% 11-Oct-23 17-Oct-23 -13
22 198 198 0% 01-Mar-22 09-Dec-22 -13
BIM00 Coordinate BIM Development [Verify Scope] 20 20 0% 01-Mar-22 28-Mar-22 -13
BIM000 Develop BIM Model of Building Geometry 10 10 0% 29-Mar-22 11-Apr-22 -13
BIM5000 Populate BIM Model for 5th Floor System Rooms 10 10 0% 12-Apr-22 25-Apr-22 -13
BIM5002 Populate BIM Model for Balance of 5th Floor 8 8 0% 26-Apr-22 05-May-22 -13
BIM0000 Populate BIM Model @ Crawlspace 10 10 0% 06-May-22 19-May-22 -13
BIM4030 Populate BIM Model for 3rd and 4th Floor System Rooms 10 10 0% 20-May-22 03-Jun-22 -13
BIM4032 Populate BIM Model for Balance of 3rd and 4th Floor 12 12 0% 06-Jun-22 21-Jun-22 -13
.4N.4055 MEC - Install M echanical Duct Trunk Lines @ 4th Flr North 15 15 0% 22-Jun-22 13-Jul-22 -13
.4N.4075 MEC -Rough-in Branch / Med & Low Pressure Duct @ 4th Flr North 15 15 0% 14-Jul-22 03-Aug-22 -13
.4N.4125 ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 4th Flr North 15 15 0% 04-Aug-22 24-Aug-22 -13
.4N.4190 ELE - Rough-in Lighting Conduit @ 4th Flr North 15 15 0% 25-Aug-22 15-Sep-22 -13
.4N.4210 FSP - Rough-in Fire Sprinkler Mains @ 4th Flr North 10 10 0% 16-Sep-22 29-Sep-22 -13
.4N.4245 FSP - Rough-in Fire Sprinkler Branch Lines @ 4th Flr North 8 8 0% 30-Sep-22 11-Oct-22 -13
.4N.4270 LV - Install Low Voltage Supports @ 4th Flr North 3 3 0% 12-Oct-22 14-Oct-22 -13
.4N.4275 LV - Install Cable Trays @ 4th Flr North 5 5 0% 17-Oct-22 21-Oct-22 -13
.4N.4285 LV - Pull Telecom / Data @ 4th Flr North 10 10 0% 24-Oct-22 04-Nov-22 -13
.4N.4300 DW - Hang Hard Ceilings @ 4th Flr North 6 6 0% 07-Nov-22 15-Nov-22 -13
.4N.4305 DW - Finish Drywall (Mud & Tape) @ 4th Flr North 10 10 0% 16-Nov-22 01-Dec-22 -13
.4N.4310 DW - Touch Up Drywall @ 4th Flr North 2 2 0% 02-Dec-22 05-Dec-22 -13
.4N.4320 PNT - Prime and First Coat Paint @ 4th Flr North 4 4 0% 06-Dec-22 09-Dec-22 -13
33 10 10 0% 23-Sep-22 06-Oct-22 -13
.5N.5984 MEC -Rough-in Mechanical at Hard Ceilings @ 5th Flr North 10 10 0% 23-Sep-22 06-Oct-22 -13
44 35 35 0% 17-Apr-23 05-Jun-23 -12
.2W.2415 Flr - Prep & Install Flooring @ 2nd Flr West W. 15 15 0% 17-Apr-23 05-May-23 -12
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
Punch Area @ 2nd Flr Central W.
Remove Trash Chute and repair area @ Building
AHJ - Inspections @ 2nd Flr
Demo Existing Site & Landscaping @ Port Cochere
Rough Grade @ Port Cochere
Complete Foundation Layout @ Port Cochere
Foundation Excavation @ Port Cochere
Form Footing & Pier Foundation @ Port Cochere
Foundation Reinforcement & Anchor Bolts @ Port Cochere
Inspect Foundatin Reinforcement & Anchor Bolts @ Port Cochere
Pour & Cure Foundations & Footings [inc. Bollards] @ Port Cochere
Form & Reinforce Site Walls @ Port Cochere
Inspect Site Walls @ Port Cochere
Pour & Cure Walls @ Port Cochere
Backfill, Compaction & Finegrade For Walkways, Sidewalks & Stairs @ Port Cochere
Form & Reinforce Walkways & Stairs @ Port Cochere
Pour & Cure Walkways & Stairs @ Port Cochere
Install Railings @ Port Cochere
Punch Sitework
Work Complete [Target 9/28/2023], Complete Final Acceptance Inspection, Demob and Closeout as required for Final Completion
09-Dec-22, 2
Coordinate BIM Development [Verify Scope]
Develop BIM Model of Building Geometry
Populate BIM Model for 5th Floor System Rooms
Populate BIM Model for Balance of 5th Floor
Populate BIM Model @ Crawlspace
Populate BIM Model for 3rd and 4th Floor System Rooms
Populate BIM Model for Balance of 3rd and 4th Floor
MEC - Install M echanical Duct Trunk Lines @ 4th Flr North
MEC -Rough-in Branch / Med & Low Pressure Duct @ 4th Flr North
ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 4th Flr North
ELE - Rough-in Lighting Conduit @ 4th Flr North
FSP - Rough-in Fire Sprinkler Mains @ 4th Flr North
FSP - Rough-in Fire Sprinkler Branch Lines @ 4th Flr North
LV - Install Low Voltage Supports @ 4th Flr North
LV - Install Cable Trays @ 4th Flr North
LV - Pull Telecom / Data @ 4th Flr North
DW - Hang Hard Ceilings @ 4th Flr North
DW - Finish Drywall (Mud & Tape) @ 4th Flr North
DW - Touch Up Drywall @ 4th Flr North
PNT - Prime and First Coat Paint @ 4th Flr North
06-Oct-22, 3
MEC -Rough-in Mechanical at Hard Ceilings @ 5th Flr North
05-Jun-23, 4
Flr - Prep & Install Flooring @ 2nd Flr West W.
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:30
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 2 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
.2W.2440 Flr - Install Base @ 2nd Flr West W. 5 5 0% 08-May-23 12-May-23 -12
.2W.2445 PNT - Final Coat Paint @ 2nd Flr West W. 5 5 0% 15-May-23 19-May-23 -12
.2W.2450 ELE - Install Electrical Trim @ 2nd Flr West W. 4 4 0% 22-May-23 25-May-23 -12
.2W.2460 Punch Area @ 2nd Flr West W. 6 6 0% 26-May-23 05-Jun-23 -12
55 22 22 0% 21-Dec-22 25-Jan-23 -12
.4S.4350 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr South 7 7 0% 21-Dec-22 04-Jan-23 -12
.4S.4375 ELE - Install Lighting Support @ 4th Flr South 3 3 0% 05-Jan-23 09-Jan-23 -12
.4S.4410 ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr South 12 12 0% 10-Jan-23 25-Jan-23 -12
66 35 35 0% 18-Nov-22 13-Jan-23 -12
.5N.5400 ELE - Install Lighting Support @ 5th Flr North 3 3 0% 18-Nov-22 22-Nov-22 -12
.5N.5500 ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr North 12 12 0% 23-Nov-22 12-Dec-22 -12
.5N.5700 ACT - Install Ceiling Tiles @ 5th Flr North 8 8 0% 13-Dec-22 22-Dec-22 -12
.5S.5860 ACT - Install Ceiling Tiles @ 5th Flr South 8 8 0% 27-Dec-22 09-Jan-23 -12
.5L.5700 ACT - Install Ceiling Tiles @ 5th Flr Lobby 4 4 0% 10-Jan-23 13-Jan-23 -12
77 22 22 0% 17-Oct-22 16-Nov-22 -12
.5S.5650 DW - Hang Hard Ceilings @ 5th Flr South 6 6 0% 17-Oct-22 24-Oct-22 -12
.5S.5660 DW - Finish Drywall (Mud & Tape) @ 5th Flr South 10 10 0% 25-Oct-22 07-Nov-22 -12
.5S.5670 DW - Touch Up Drywall @ 5th Flr South 2 2 0% 08-Nov-22 09-Nov-22 -12
.5S.5690 PNT - Prime and First Coat Paint @ 5th Flr South 4 4 0% 10-Nov-22 16-Nov-22 -12
88 3 3 0% 01-Jun-23 05-Jun-23 -12
.2C.5870 Install Accoustical Wall Panels @ 2nd Flr Central W. 3 3 0% 01-Jun-23 05-Jun-23 -12
99 22 22 0% 05-Jan-23 03-Feb-23 -11
.4L.5320 ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr Lobby 7 7 0% 05-Jan-23 13-Jan-23 -11
.4L.5400 ELE - Install Lighting Support @ 4th Flr Lobby 3 3 0% 16-Jan-23 18-Jan-23 -11
.4L.5500 ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr Lobby 12 12 0% 19-Jan-23 03-Feb-23 -11
1010 15 15 0% 01-Dec-22 21-Dec-22 -11
.5S.5750 ELE - Install Lighting Support @ 5th Flr South 3 3 0% 01-Dec-22 05-Dec-22 -11
.5S.5820 ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr South 12 12 0% 06-Dec-22 21-Dec-22 -11
1111 22 22 0% 16-Nov-22 19-Dec-22 -11
.4S.4325 DW - Hang Hard Ceilings @ 4th Flr South 6 6 0% 16-Nov-22 23-Nov-22 -11
.4S.4330 DW - Finish Drywall (Mud & Tape) @ 4th Flr South 10 10 0% 28-Nov-22 09-Dec-22 -11
.4S.4335 DW - Touch Up Drywall @ 4th Flr South 2 2 0% 12-Dec-22 13-Dec-22 -11
.4S.4345 PNT - Prime and First Coat Paint @ 4th Flr South 4 4 0% 14-Dec-22 19-Dec-22 -11
1212 2 2 0% 01-Jun-23 02-Jun-23 -11
.2C.2455 SIGN - Install Room ID / Signage @ 2nd Flr Central W. 2 2 0% 01-Jun-23 02-Jun-23 -11
1313 34 34 0% 07-Aug-23 21-Sep-23 -10
.SITE.2110 Set Precast Columns @ Port Cochere 5 5 0% 07-Aug-23 11-Aug-23 -10
.SITE.2120 Place Precast Concrete Caps @ Port Cochere 5 5 0% 14-Aug-23 18-Aug-23 -10
.SITE.2150 Assemble Pre-Cast Canopy Elements [Girder, Joists, Planks] @ Port Cochere 9 9 0% 21-Aug-23 31-Aug-23 -10
.SITE.2190 FRPC Toping Slab @ Port Cochere 9 9 0% 01-Sep-23 13-Sep-23 -10
.SITE.2210 Install Insulation and Roof Membrane @ Port Cochere 6 6 0% 14-Sep-23 21-Sep-23 -10
1414 44 44 0% 24-Jul-23 21-Sep-23 -10
.SITE.2070 Rough-In Underground Electrical @ Port Cochere 3 3 0% 24-Jul-23 26-Jul-23 -10
SITE.1140 Rough-in Site Electrical [inc light pole foundations as required] @ South Site 10 10 0% 27-Jul-23 09-Aug-23 -10
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
Flr - Install Base @ 2nd Flr West W.
PNT - Final Coat Paint @ 2nd Flr West W.
ELE - Install Electrical Trim @ 2nd Flr West W.
Punch Area @ 2nd Flr West W.
25-Jan-23, 5
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr South
ELE - Install Lighting Support @ 4th Flr South
ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr South
13-Jan-23, 6
ELE - Install Lighting Support @ 5th Flr North
ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr North
ACT - Install Ceiling Tiles @ 5th Flr North
ACT - Install Ceiling Tiles @ 5th Flr South
ACT - Install Ceiling Tiles @ 5th Flr Lobby
16-Nov-22, 7
DW - Hang Hard Ceilings @ 5th Flr South
DW - Finish Drywall (Mud & Tape) @ 5th Flr South
DW - Touch Up Drywall @ 5th Flr South
PNT - Prime and First Coat Paint @ 5th Flr South
05-Jun-23, 8
Install Accoustical Wall Panels @ 2nd Flr Central W.
03-Feb-23, 9
ACT - Install Ceiling Hangers, Wall Angles, Grid, Detail @ 4th Flr Lobby
ELE - Install Lighting Support @ 4th Flr Lobby
ELE - Install Lighting Fixtures & Whips / Flex @ 4th Flr Lobby
21-Dec-22, 10
ELE - Install Lighting Support @ 5th Flr South
ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr South
19-Dec-22, 11
DW - Hang Hard Ceilings @ 4th Flr South
DW - Finish Drywall (Mud & Tape) @ 4th Flr South
DW - Touch Up Drywall @ 4th Flr South
PNT - Prime and First Coat Paint @ 4th Flr South
02-Jun-23, 12
SIGN - Install Room ID / Signage @ 2nd Flr Central W.
21-Sep-23, 13
Set Precast Columns @ Port Cochere
Place Precast Concrete Caps @ Port Cochere
Assemble Pre-Cast Canopy Elements [Girder, Joists, Planks] @ Port Cochere
FRPC Toping Slab @ Port Cochere
Install Insulation and Roof Membrane @ Port Cochere
21-Sep-23, 14
Rough-In Underground Electrical @ Port Cochere
Rough-in Site Electrical [inc light pole foundations as required] @ South Site
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:30
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 3 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
SITE.1260 Rough-in Site Electrical [inc light pole foundations as required] @ North Site 10 10 0% 10-Aug-23 23-Aug-23 -10
SITE.1360 Rough-in Site Electrical [inc light pole foundations as required] @ Center Site 5 5 0% 24-Aug-23 30-Aug-23 -10
SITE.1080 Install and Trim Light Poles and Electrical Devices @ Site 8 8 0% 31-Aug-23 11-Sep-23 -10
SITE.1120 Complete Final Landscaping/Irrigation 8 8 0% 12-Sep-23 21-Sep-23 -10
1515 75 75 0% 08-Feb-23 23-May-23 -10
.4S.4440 Flr - Prep & Install Flooring @ 4th Flr South 15 15 0% 08-Feb-23 28-Feb-23 -10
.4S.4465 Flr - Install Base @ 4th Flr South 5 5 0% 01-Mar-23 07-Mar-23 -10
.4S.4470 PNT - Final Coat Paint @ 4th Flr South 5 5 0% 08-Mar-23 14-Mar-23 -10
.4S.4475 ELE - Install Electrical Trim @ 4th Flr South 4 4 0% 15-Mar-23 20-Mar-23 -10
.4S.4485 Punch Area @ 4th Flr South 6 6 0% 21-Mar-23 28-Mar-23 -10
.4L.5920 Punch Area @ 4th Flr Lobby 8 8 0% 29-Mar-23 07-Apr-23 -10
.3N.3460 Punch Area @ 3rd Flr North 6 6 0% 10-Apr-23 17-Apr-23 -10
.3S.3460 Punch Area @ 3rd Flr South 6 6 0% 18-Apr-23 25-Apr-23 -10
.3L.3385 Punch Area @ 3rd Flr Lobby 8 8 0% 26-Apr-23 05-May-23 -10
.2N.2460 Punch Area @ 2nd Flr North 6 6 0% 08-May-23 15-May-23 -10
.2S.2460 Punch Area @ 2nd Flr South 6 6 0% 16-May-23 23-May-23 -10
1616 29 29 0% 05-Apr-23 15-May-23 -10
.2S.2415 Flr - Prep & Install Flooring @ 2nd Flr South 15 15 0% 05-Apr-23 25-Apr-23 -10
.2S.2440 Flr - Install Base @ 2nd Flr South 5 5 0% 26-Apr-23 02-May-23 -10
.2S.2445 PNT - Final Coat Paint @ 2nd Flr South 5 5 0% 03-May-23 09-May-23 -10
.2S.2450 ELE - Install Electrical Trim @ 2nd Flr South 4 4 0% 10-May-23 15-May-23 -10
1717 29 29 0% 08-Mar-23 17-Apr-23 -10
.3S.3415 Flr - Prep & Install Flooring @ 3rd Flr South 15 15 0% 08-Mar-23 28-Mar-23 -10
.3S.3440 Flr - Install Base @ 3rd Flr South 5 5 0% 29-Mar-23 04-Apr-23 -10
.3S.3445 PNT - Final Coat Paint @ 3rd Flr South 5 5 0% 05-Apr-23 11-Apr-23 -10
.3S.3450 ELE - Install Electrical Trim @ 3rd Flr South 4 4 0% 12-Apr-23 17-Apr-23 -10
1818 15 15 0% 12-Dec-22 05-Jan-23 -10
.5L.5400 ELE - Install Lighting Support @ 5th Flr Lobby 3 3 0% 12-Dec-22 14-Dec-22 -10
.5L.5500 ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr Lobby 12 12 0% 15-Dec-22 05-Jan-23 -10
1919 241 188 10.31% 28-Oct-21 A 23-Nov-22 -10
PRE1010 Verification of Existing MEP / Testing by Subcontractors 5 5 0% 01-Mar-22 07-Mar-22 -10
MILE200 Basic Enabling Tasks Complete 0 0 0% 07-Mar-22 -10
PRECON404 Install Heat Detectors & Fire Extinguishers / Life Safety Prep Floors 2 - 5 5 4 100% 28-Oct-21 A 11-Mar-22 -10
PRE1050 Identify and Preserve Temp Lighting / Safe-off Utilities Floors 2 - 5 10 3 100% 10-Feb-22 A 16-Mar-22 -10
.6.5990 DEMO - Verify 'Make Safe' @ 6th Floor 1 1 0% 17-Mar-22 17-Mar-22 -10
.6.6000 DEMO - Pre Abatement Demolition @ 6th Floor 2 2 100% 10-Jan-22 A 21-Mar-22 -10
.5.504 DEMO - Pre Abatement Demolition @ 5th Flr North & Lobby 4 4 0% 05-Jan-22 A 25-Mar-22 -10
.5.506 DEMO - ACM & Lead Abatement @ 5th Flr North & Lobby 2 2 0% 27-Jan-22 A 29-Mar-22 -10
.5.508 DEMO - Post Abatement Demolition @ 5th Flr North & Lobby 11 11 0% 14-Feb-22 A 13-Apr-22 -10
.5N.510 Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 5th Flr North2 2 0% 14-Apr-22 15-Apr-22 -10
.5N.512 DW - Layout Area Framing @ 5th Flr North 4 4 0% 18-Apr-22 21-Apr-22 -10
.5N.514 DW - Frame Priority Walls @ 5th Flr North 3 3 0% 22-Apr-22 26-Apr-22 -10
.5S.5060 DW - Layout Area Framing @ 5th Flr South 4 4 0% 27-Apr-22 02-May-22 -10
.5S.5070 DW - Frame Priority Walls @ 5th Flr South 3 3 0% 03-May-22 05-May-22 -10
.5L.512 DW - Layout Area Framing @ 5th Flr Lobby 2 2 0% 06-May-22 09-May-22 -10
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
Rough-in Site Electrical [inc light pole foundations as required] @ North Site
Rough-in Site Electrical [inc light pole foundations as required] @ Center Site
Install and Trim Light Poles and Electrical Devices @ Site
Complete Final Landscaping/Irrigation
23-May-23, 15
Flr - Prep & Install Flooring @ 4th Flr South
Flr - Install Base @ 4th Flr South
PNT - Final Coat Paint @ 4th Flr South
ELE - Install Electrical Trim @ 4th Flr South
Punch Area @ 4th Flr South
Punch Area @ 4th Flr Lobby
Punch Area @ 3rd Flr North
Punch Area @ 3rd Flr South
Punch Area @ 3rd Flr Lobby
Punch Area @ 2nd Flr North
Punch Area @ 2nd Flr South
15-May-23, 16
Flr - Prep & Install Flooring @ 2nd Flr South
Flr - Install Base @ 2nd Flr South
PNT - Final Coat Paint @ 2nd Flr South
ELE - Install Electrical Trim @ 2nd Flr South
17-Apr-23, 17
Flr - Prep & Install Flooring @ 3rd Flr South
Flr - Install Base @ 3rd Flr South
PNT - Final Coat Paint @ 3rd Flr South
ELE - Install Electrical Trim @ 3rd Flr South
05-Jan-23, 18
ELE - Install Lighting Support @ 5th Flr Lobby
ELE - Install Lighting Fixtures & Whips / Flex @ 5th Flr Lobby
23-Nov-22, 19
Verification of Existing MEP / Testing by Subcontractors
Basic Enabling Tasks Complete, Install Heat Detectors & Fire Extinguishers / Life Safety Prep Floors 2 - 5
Identify and Preserve Temp Lighting / Safe-off Utilities Floors 2 - 5
DEMO - Verify 'Make Safe' @ 6th Floor
DEMO - Pre Abatement Demolition @ 6th Floor
DEMO - Pre Abatement Demolition @ 5th Flr North & Lobby
DEMO - ACM & Lead Abatement @ 5th Flr North & Lobby
DEMO - Post Abatement Demolition @ 5th Flr North & Lobby
Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 5th Flr North
DW - Layout Area Framing @ 5th Flr North
DW - Frame Priority Walls @ 5th Flr North
DW - Layout Area Framing @ 5th Flr South
DW - Frame Priority Walls @ 5th Flr South
DW - Layout Area Framing @ 5th Flr Lobby
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:30
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 4 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
.5L.528 DW - Frame and Top-Out / 1-Side Walls @ 5th Flr Lobby 6 6 0% 10-May-22 17-May-22 -10
.5L.534 MEC - Install Mechanical Duct In Risers [Inc Floor Dampers] @ 5th Flr Lobby 4 4 0% 18-May-22 23-May-22 -10
.5L.542 MEC -Rough-in Branch / Med & Low Pressure Duct @ 5th Flr Lobby 6 6 0% 24-May-22 01-Jun-22 -10
.5L.562 ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 5th Flr Lobby 8 8 0% 02-Jun-22 13-Jun-22 -10
.5L.590 ELE - Rough-in Lighting Conduit @ 5th Flr Lobby 10 10 0% 14-Jun-22 27-Jun-22 -10
.5L.5000 FSP - Rough-in Fire Sprinkler Mains @ 5th Flr Lobby 8 8 0% 28-Jun-22 08-Jul-22 -10
.5L.5140 FSP - Rough-in Fire Sprinkler Branch Lines @ 5th Flr Lobby 8 8 0% 11-Jul-22 20-Jul-22 -10
.5L.5180 LV - Install Low Voltage Supports @ 5th Flr Lobby 3 3 0% 21-Jul-22 25-Jul-22 -10
.5L.5200 LV - Install Cable Tray (as applicable) @ 5th Flr Lobby 5 5 0% 26-Jul-22 01-Aug-22 -10
.5L.5220 LV - Pull Telecom / Data @ 5th Flr Lobby 10 10 0% 02-Aug-22 15-Aug-22 -10
.5L.5976 DW - Hang Hard Ceilings @ 5th Flr Lobby 8 8 0% 16-Aug-22 25-Aug-22 -10
.5L.5300 DW - Finish Drywall (Mud & Tape) @ 5th Flr Lobby 10 10 0% 26-Aug-22 09-Sep-22 -10
.5L.5340 DW - Touch Up Drywall @ 5th Flr Lobby 5 5 0% 12-Sep-22 16-Sep-22 -10
.5L.5984 Flr - Install Terrazzo Flooring @ 5th Flr Lobby 15 15 0% 19-Sep-22 07-Oct-22 -10
.5L.5360 TILE - Install Tile Flooring and Walls @ 5th Flr Lobby 15 15 0% 10-Oct-22 28-Oct-22 -10
.5L.5280 MILL - Blocking and Faux Wood Beams/Purlins @ 5th Flr Lobby 17 17 0% 31-Oct-22 23-Nov-22 -10
2020 0 0 0% 18-Apr-22 18-Apr-22 -10
MILE210 Start Interior Renovations 0 0 0% 18-Apr-22 -10
2121 2 2 0% 22-May-23 23-May-23 -10
.2W.2455 SIGN - Install Room ID / Signage @ 2nd Flr West W. 2 2 0% 22-May-23 23-May-23 -10
2222 37 37 0% 29-Jun-23 22-Aug-23 -9
SITE.1000 Demo Existing Site & Landscaping @ South Site 5 5 0% 29-Jun-23 07-Jul-23 -9
SITE.1005 Survey & Layout @ South Site 3 3 0% 10-Jul-23 12-Jul-23 -9
SITE.1010 Complete Rough Grade @ South Site 5 5 0% 13-Jul-23 19-Jul-23 -9
SITE.1190 Demo Existing Site & Landscaping @ North Site 5 5 0% 20-Jul-23 26-Jul-23 -9
SITE.1200 Survey & Layout @ North Site 3 3 0% 27-Jul-23 31-Jul-23 -9
SITE.1210 Complete Rough Grade @ North Site 5 5 0% 01-Aug-23 07-Aug-23 -9
SITE.1290 Demo Existing Site & Landscaping @ Center Site 4 4 0% 08-Aug-23 11-Aug-23 -9
SITE.1300 Survey & Layout @ Center Site 2 2 0% 14-Aug-23 15-Aug-23 -9
SITE.1310 Complete Rough Grade @ Center Site 5 5 0% 16-Aug-23 22-Aug-23 -9
2323 49 49 0% 10-Jan-23 17-Mar-23 -9
.5S.5880 Flr - Prep & Install Flooring @ 5th Flr South 15 15 0% 10-Jan-23 30-Jan-23 -9
.5S.5930 Flr - Install Base @ 5th Flr South 5 5 0% 31-Jan-23 06-Feb-23 -9
.5S.5940 PNT - Final Coat Paint @ 5th Flr South 5 5 0% 07-Feb-23 13-Feb-23 -9
.5S.5950 ELE - Install Electrical Trim @ 5th Flr South 4 4 0% 14-Feb-23 17-Feb-23 -9
.5S.5970 Punch Area @ 5th Flr South 6 6 0% 20-Feb-23 27-Feb-23 -9
.5L.5920 Punch Area @ 5th Flr Lobby 8 8 0% 28-Feb-23 09-Mar-23 -9
.4N.4460 Punch Area @ 4th Flr North 6 6 0% 10-Mar-23 17-Mar-23 -9
2424 13 13 0% 16-Jan-23 01-Feb-23 -9
.4L.5420 MEC -Install Flex / Grills / Registers [diffusers and returns] @ 4th Flr Lobby 5 5 0% 16-Jan-23 20-Jan-23 -9
.4L.5440 FSP - Fire Sprinkler Drop Head & Trim-Out @ 4th Flr Lobby 8 8 0% 23-Jan-23 01-Feb-23 -9
2525 111 111 0% 26-Apr-22 30-Sep-22 -9
A1530 Procure Ductwork [First Areas] 15 15 0% 26-Apr-22 16-May-22 -9
.5N.534 MEC - Install M echanical Duct Trunk Lines @ 5th Flr North 15 15 0% 17-May-22 07-Jun-22 -9
.5N.542 MEC -Rough-in Branch / Med & Low Pressure Duct @ 5th Flr North 15 15 0% 08-Jun-22 28-Jun-22 -9
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
DW - Frame and Top-Out / 1-Side Walls @ 5th Flr Lobby
MEC - Install Mechanical Duct In Risers [Inc Floor Dampers] @ 5th Flr Lobby
MEC -Rough-in Branch / Med & Low Pressure Duct @ 5th Flr Lobby
ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 5th Flr Lobby
ELE - Rough-in Lighting Conduit @ 5th Flr Lobby
FSP - Rough-in Fire Sprinkler Mains @ 5th Flr Lobby
FSP - Rough-in Fire Sprinkler Branch Lines @ 5th Flr Lobby
LV - Install Low Voltage Supports @ 5th Flr Lobby
LV - Install Cable Tray (as applicable) @ 5th Flr Lobby
LV - Pull Telecom / Data @ 5th Flr Lobby
DW - Hang Hard Ceilings @ 5th Flr Lobby
DW - Finish Drywall (Mud & Tape) @ 5th Flr Lobby
DW - Touch Up Drywall @ 5th Flr Lobby
Flr - Install Terrazzo Flooring @ 5th Flr Lobby
TILE - Install Tile Flooring and Walls @ 5th Flr Lobby
MILL - Blocking and Faux Wood Beams/Purlins @ 5th Flr Lobby
18-Apr-22, 20
Start Interior Renovations, 18-Apr-22
23-May-23, 21
SIGN - Install Room ID / Signage @ 2nd Flr West W.
22-Aug-23, 22
Demo Existing Site & Landscaping @ South Site
Survey & Layout @ South Site
Complete Rough Grade @ South Site
Demo Existing Site & Landscaping @ North Site
Survey & Layout @ North Site
Complete Rough Grade @ North Site
Demo Existing Site & Landscaping @ Center Site
Survey & Layout @ Center Site
Complete Rough Grade @ Center Site
17-Mar-23, 23
Flr - Prep & Install Flooring @ 5th Flr South
Flr - Install Base @ 5th Flr South
PNT - Final Coat Paint @ 5th Flr South
ELE - Install Electrical Trim @ 5th Flr South
Punch Area @ 5th Flr South
Punch Area @ 5th Flr Lobby
Punch Area @ 4th Flr North
01-Feb-23, 24
MEC -Install Flex / Grills / Registers [diffusers and returns] @ 4th Flr Lobby
FSP - Fire Sprinkler Drop Head & Trim-Out @ 4th Flr Lobby
30-Sep-22, 25
Procure Ductwork [First Areas]
MEC - Install M echanical Duct Trunk Lines @ 5th Flr North
MEC -Rough-in Branch / Med & Low Pressure Duct @ 5th Flr North
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:31
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 5 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
.5N.562 ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 5th Flr North 15 15 0% 29-Jun-22 20-Jul-22 -9
.5N.590 ELE - Rough-in Lighting Conduit @ 5th Flr North 15 15 0% 21-Jul-22 10-Aug-22 -9
.5N.5000 FSP - Rough-in Fire Sprinkler Mains @ 5th Flr North 10 10 0% 11-Aug-22 24-Aug-22 -9
.5N.5140 FSP - Rough-in Fire Sprinkler Branch Lines @ 5th Flr North 8 8 0% 25-Aug-22 06-Sep-22 -9
.5N.5180 LV - Install Low Voltage Supports @ 5th Flr North 3 3 0% 07-Sep-22 09-Sep-22 -9
.5N.5200 LV - Install Cable Trays @ 5th Flr North 5 5 0% 12-Sep-22 16-Sep-22 -9
.5N.5220 LV - Pull Telecom / Data @ 5th Flr North 10 10 0% 19-Sep-22 30-Sep-22 -9
2626 50 14 0% 30-Jan-22 A 18-Mar-22 -9
.5.502 DEMO - Verify 'Make Safe' @ 5th Flr North & Lobby 1 0 0% 24-Feb-22 A 26-Feb-22 A
PRECON512 Install Temp Communication Systems 15 14 100% 30-Jan-22 A 18-Mar-22 -9
2727 1 1 0% 24-Jul-23 24-Jul-23 -9
.SITE.2050 Survey & Inspect Footing & Pier Foundation Forming @ Port Cochere 1 1 0% 24-Jul-23 24-Jul-23 -9
2828 10 10 0% 17-May-23 31-May-23 -9
.2C.2435 EQP - Install Floor Mounted Medical Equipment @ 2nd Flr Central W. 10 10 0% 17-May-23 31-May-23 -9
2929 29 29 0% 08-Aug-23 15-Sep-23 -8
SITE.1230 Road Compaction & Subbase/Base @ North Site 6 6 0% 08-Aug-23 15-Aug-23 -8
SITE.1250 Install Curb & Gutter S @ North Site 9 9 0% 16-Aug-23 28-Aug-23 -8
SITE.1270 Install Side Walks (exc Port Cochere) @ North Site 8 8 0% 29-Aug-23 07-Sep-23 -8
SITE.1370 Install Side Walks @ Center Site 6 6 0% 08-Sep-23 15-Sep-23 -8
3030 29 29 0% 24-Mar-23 03-May-23 -8
.2N.2415 Flr - Prep & Install Flooring @ 2nd Flr North 15 15 0% 24-Mar-23 13-Apr-23 -8
.2N.2440 Flr - Install Base @ 2nd Flr North 5 5 0% 14-Apr-23 20-Apr-23 -8
.2N.2445 PNT - Final Coat Paint @ 2nd Flr North 5 5 0% 21-Apr-23 27-Apr-23 -8
.2N.2450 ELE - Install Electrical Trim @ 2nd Flr North 4 4 0% 28-Apr-23 03-May-23 -8
3131 29 29 0% 24-Feb-23 05-Apr-23 -8
.3N.3415 Flr - Prep & Install Flooring @ 3rd Flr North 15 15 0% 24-Feb-23 16-Mar-23 -8
.3N.3440 Flr - Install Base @ 3rd Flr North 5 5 0% 17-Mar-23 23-Mar-23 -8
.3N.3445 PNT - Final Coat Paint @ 3rd Flr North 5 5 0% 24-Mar-23 30-Mar-23 -8
.3N.3450 ELE - Install Electrical Trim @ 3rd Flr North 4 4 0% 31-Mar-23 05-Apr-23 -8
3232 29 29 0% 27-Jan-23 08-Mar-23 -8
.4N.4415 Flr - Prep & Install Flooring @ 4th Flr North 15 15 0% 27-Jan-23 16-Feb-23 -8
.4N.4440 Flr - Install Base @ 4th Flr North 5 5 0% 17-Feb-23 23-Feb-23 -8
.4N.4445 PNT - Final Coat Paint @ 4th Flr North 5 5 0% 24-Feb-23 02-Mar-23 -8
.4N.4450 ELE - Install Electrical Trim @ 4th Flr North 4 4 0% 03-Mar-23 08-Mar-23 -8
3333 10 10 0% 07-Jul-22 20-Jul-22 -8
PREDuct190 Install Shaft Wall Liner @ Pre-Demo Shaft South 3 3 0% 07-Jul-22 11-Jul-22 -8
PREDuct196 Rough-in In-wall Electrical @ Pre-Demo Shaft South 2 2 0% 12-Jul-22 13-Jul-22 -8
PREDuct198 Hang and Finish Dry-wall @ Pre-Demo Shaft South 3 3 0% 14-Jul-22 18-Jul-22 -8
PREDuct204 Fire Caulk & Seal Dry-wall @ Pre-Demo Shaft South 2 2 0% 19-Jul-22 20-Jul-22 -8
3434 2 2 0% 10-May-23 11-May-23 -8
.2S.2455 SIGN - Install Room ID / Signage @ 2nd Flr South 2 2 0% 10-May-23 11-May-23 -8
3535 2 2 0% 12-Apr-23 13-Apr-23 -8
.3S.3455 SIGN - Install Room ID / Signage @ 3rd Flr South 2 2 0% 12-Apr-23 13-Apr-23 -8
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 5th Flr North
ELE - Rough-in Lighting Conduit @ 5th Flr North
FSP - Rough-in Fire Sprinkler Mains @ 5th Flr North
FSP - Rough-in Fire Sprinkler Branch Lines @ 5th Flr North
LV - Install Low Voltage Supports @ 5th Flr North
LV - Install Cable Trays @ 5th Flr North
LV - Pull Telecom / Data @ 5th Flr North
18-Mar-22, 26
DEMO - Verify 'Make Safe' @ 5th Flr North & Lobby
Install Temp Communication Systems
24-Jul-23, 27
Survey & Inspect Footing & Pier Foundation Forming @ Port Cochere
31-May-23, 28
EQP - Install Floor Mounted Medical Equipment @ 2nd Flr Central W.
15-Sep-23, 29
Road Compaction & Subbase/Base @ North Site
Install Curb & Gutter S @ North Site
Install Side Walks (exc Port Cochere) @ North Site
Install Side Walks @ Center Site
03-May-23, 30
Flr - Prep & Install Flooring @ 2nd Flr North
Flr - Install Base @ 2nd Flr North
PNT - Final Coat Paint @ 2nd Flr North
ELE - Install Electrical Trim @ 2nd Flr North
05-Apr-23, 31
Flr - Prep & Install Flooring @ 3rd Flr North
Flr - Install Base @ 3rd Flr North
PNT - Final Coat Paint @ 3rd Flr North
ELE - Install Electrical Trim @ 3rd Flr North
08-Mar-23, 32
Flr - Prep & Install Flooring @ 4th Flr North
Flr - Install Base @ 4th Flr North
PNT - Final Coat Paint @ 4th Flr North
ELE - Install Electrical Trim @ 4th Flr North
20-Jul-22, 33
Install Shaft Wall Liner @ Pre-Demo Shaft South
Rough-in In-wall Electrical @ Pre-Demo Shaft South
Hang and Finish Dry-wall @ Pre-Demo Shaft South
Fire Caulk & Seal Dry-wall @ Pre-Demo Shaft South
11-May-23, 34
SIGN - Install Room ID / Signage @ 2nd Flr South
13-Apr-23, 35
SIGN - Install Room ID / Signage @ 3rd Flr South
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:31
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 6 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
3636 2 2 0% 15-Mar-23 16-Mar-23 -8
.4S.4480 SIGN - Install Room ID / Signage @ 4th Flr South 2 2 0% 15-Mar-23 16-Mar-23 -8
3737 10 10 0% 08-May-23 19-May-23 -8
.2W.2435 EQP - Install Floor Mounted Medical Equipment @ 2nd Flr West W. 10 10 0% 08-May-23 19-May-23 -8
3838 35 35 0% 27-Dec-22 15-Feb-23 -7
.5N.5780 Flr - Prep & Install Flooring @ 5th Flr North 15 15 0% 27-Dec-22 18-Jan-23 -7
.5N.5640 Flr - Install Base @ 5th Flr North 5 5 0% 19-Jan-23 25-Jan-23 -7
.5N.5860 PNT - Final Coat Paint @ 5th Flr North 5 5 0% 26-Jan-23 01-Feb-23 -7
.5N.5880 ELE - Install Electrical Trim @ 5th Flr North 4 4 0% 02-Feb-23 07-Feb-23 -7
.5N.5920 Punch Area @ 5th Flr North 6 6 0% 08-Feb-23 15-Feb-23 -7
3939 187 176 0% 17-Jan-22 A 27-Dec-22 -7
.4406 DEMO - ACM & Lead Abatement @ 4th Flr 3 0 0% 11-Feb-22 A 16-Feb-22 A
.4404 DEMO - Pre Abatement Demolition @ 4th Flr 7 6 0% 17-Jan-22 A 21-Apr-22 -7
.4408 DEMO - Post Abatement Demolition @ 4th 15 15 0% 22-Apr-22 12-May-22 -7
.4N.4000 Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 4th Flr North2 2 0% 13-May-22 16-May-22 -7
.4N.4005 DW - Layout Area Framing @ 4th Flr North 4 4 0% 17-May-22 20-May-22 -7
.4N.4010 DW - Frame Priority Walls @ 4th Flr North 3 3 0% 23-May-22 25-May-22 -7
.4S.4030 DW - Layout Area Framing @ 4th Flr South 4 4 0% 26-May-22 01-Jun-22 -7
.4S.4035 DW - Frame Priority Walls @ 4th Flr South 3 3 0% 02-Jun-22 06-Jun-22 -7
.4L.512 DW - Layout Area Framing @ 4th Flr Lobby 2 2 0% 07-Jun-22 08-Jun-22 -7
.4L.528 DW - Frame and Top-Out / 1-Side Walls @ 4th Flr Lobby 6 6 0% 09-Jun-22 16-Jun-22 -7
.4L.534 MEC - Install Mechanical Duct In Risers [Inc Floor Dampers] @ 4th Flr Lobby 4 4 0% 17-Jun-22 22-Jun-22 -7
.4L.542 MEC -Rough-in Branch / Med & Low Pressure Duct @ 4th Flr Lobby 6 6 0% 23-Jun-22 30-Jun-22 -7
.4L.562 ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 4th Flr Lobby 8 8 0% 01-Jul-22 13-Jul-22 -7
.4L.590 ELE - Rough-in Lighting Conduit @ 4th Flr Lobby 10 10 0% 14-Jul-22 27-Jul-22 -7
.4L.5000 FSP - Rough-in Fire Sprinkler Mains @ 4th Flr Lobby 8 8 0% 28-Jul-22 08-Aug-22 -7
.4L.5140 FSP - Rough-in Fire Sprinkler Branch Lines @ 4th Flr Lobby 8 8 0% 09-Aug-22 18-Aug-22 -7
.4L.5180 LV - Install Low Voltage Supports @ 4th Flr Lobby 3 3 0% 19-Aug-22 23-Aug-22 -7
.4L.5200 LV - Install Cable Tray (as applicable) @ 4th Flr Lobby 5 5 0% 24-Aug-22 30-Aug-22 -7
.4L.5220 LV - Pull Telecom / Data @ 4th Flr Lobby 10 10 0% 31-Aug-22 14-Sep-22 -7
.4L.5976 DW - Hang Hard Ceilings @ 4th Flr Lobby 8 8 0% 15-Sep-22 26-Sep-22 -7
.4L.5300 DW - Finish Drywall (Mud & Tape) @ 4th Flr Lobby 10 10 0% 27-Sep-22 10-Oct-22 -7
.4L.5340 DW - Touch Up Drywall @ 4th Flr Lobby 5 5 0% 11-Oct-22 17-Oct-22 -7
.4L.5984 Flr - Install Terrazzo Flooring @ 4th Flr Lobby 15 15 0% 18-Oct-22 07-Nov-22 -7
.4L.5360 TILE - Install Tile Flooring and Walls @ 4th Flr Lobby 15 15 0% 08-Nov-22 01-Dec-22 -7
.4L.5280 MILL - Blocking and Faux Wood Beams/Purlins @ 4th Flr Lobby 16 16 0% 02-Dec-22 27-Dec-22 -7
4040 18 18 0% 10-Jun-22 06-Jul-22 -7
PREDuct166 Install Duct down through entire Building @ Pre-Demo Shaft South 8 8 0% 10-Jun-22 21-Jun-22 -7
PREDuct178 Install Attic Duct and New Duct Fans @ Pre-Demo Shaft South 8 8 0% 22-Jun-22 01-Jul-22 -7
PREDuct188 Energize Pre-Demolition Mech Work [Attic Fans] 2 2 0% 05-Jul-22 06-Jul-22 -7
4141 9 9 0% 22-Jun-22 05-Jul-22 -7
PREDuct176 Frame Shaft Walls @ Pre-Demo Shaft South 3 3 0% 22-Jun-22 24-Jun-22 -7
PREDuct182 Install Shaft wall Dampers @ Pre-Demo Shaft South 3 3 0% 27-Jun-22 29-Jun-22 -7
PREDuct184 Complete and test Mechanical Duct @ Pre-Demo Shaft South 3 3 0% 30-Jun-22 05-Jul-22 -7
4242 8 8 0% 10-Jun-22 21-Jun-22 -7
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
16-Mar-23, 36
SIGN - Install Room ID / Signage @ 4th Flr South
19-May-23, 37
EQP - Install Floor Mounted Medical Equipment @ 2nd Flr West W.
15-Feb-23, 38
Flr - Prep & Install Flooring @ 5th Flr North
Flr - Install Base @ 5th Flr North
PNT - Final Coat Paint @ 5th Flr North
ELE - Install Electrical Trim @ 5th Flr North
Punch Area @ 5th Flr North
27-Dec-22, 39
DEMO - ACM & Lead Abatement @ 4th Flr
DEMO - Pre Abatement Demolition @ 4th Flr
DEMO - Post Abatement Demolition @ 4th
Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 4th Flr North
DW - Layout Area Framing @ 4th Flr North
DW - Frame Priority Walls @ 4th Flr North
DW - Layout Area Framing @ 4th Flr South
DW - Frame Priority Walls @ 4th Flr South
DW - Layout Area Framing @ 4th Flr Lobby
DW - Frame and Top-Out / 1-Side Walls @ 4th Flr Lobby
MEC - Install Mechanical Duct In Risers [Inc Floor Dampers] @ 4th Flr Lobby
MEC -Rough-in Branch / Med & Low Pressure Duct @ 4th Flr Lobby
ELE - Rough-in Overhead Electrical Conduit - Power & LV @ 4th Flr Lobby
ELE - Rough-in Lighting Conduit @ 4th Flr Lobby
FSP - Rough-in Fire Sprinkler Mains @ 4th Flr Lobby
FSP - Rough-in Fire Sprinkler Branch Lines @ 4th Flr Lobby
LV - Install Low Voltage Supports @ 4th Flr Lobby
LV - Install Cable Tray (as applicable) @ 4th Flr Lobby
LV - Pull Telecom / Data @ 4th Flr Lobby
DW - Hang Hard Ceilings @ 4th Flr Lobby
DW - Finish Drywall (Mud & Tape) @ 4th Flr Lobby
DW - Touch Up Drywall @ 4th Flr Lobby
Flr - Install Terrazzo Flooring @ 4th Flr Lobby
TILE - Install Tile Flooring and Walls @ 4th Flr Lobby
MILL - Blocking and Faux Wood Beams/Purlins @ 4th Flr Lobby
06-Jul-22, 40
Install Duct down through entire Building @ Pre-Demo Shaft South
Install Attic Duct and New Duct Fans @ Pre-Demo Shaft South
Energize Pre-Demolition Mech Work [Attic Fans]
05-Jul-22, 41
Frame Shaft Walls @ Pre-Demo Shaft South
Install Shaft wall Dampers @ Pre-Demo Shaft South
Complete and test Mechanical Duct @ Pre-Demo Shaft South
21-Jun-22, 42
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:31
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 7 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
PREDuct170 Install Attic Duct and New Duct Fans @ Pre-Demo Shaft North 8 8 0% 10-Jun-22 21-Jun-22 -7
4343 3 3 0% 10-May-22 12-May-22 -7
.5L.531 STL - Cut, Reinforce and Grout new Slab Penetration for Mechanical Shafts @ 5th Flr Lobby 3 3 0% 10-May-22 12-May-22 -7
4444 3 3 0% 01-Aug-23 03-Aug-23 -7
SITE.1060 Remove Jobsite Trailers @ Center Site 3 3 0% 01-Aug-23 03-Aug-23 -7
4545 2 2 0% 14-Feb-23 15-Feb-23 -7
.5S.5960 SIGN - Install Room ID / Signage @ 5th Flr South 2 2 0% 14-Feb-23 15-Feb-23 -7
4646 3 3 0% 10-May-22 12-May-22 -7
.5L.516 MEC - Install Mechanical Hangers / Support / Sleeves @ 5th Flr Lobby 3 3 0% 10-May-22 12-May-22 -7
4747 10 10 0% 05-Jan-23 18-Jan-23 -7
.4S.4390 LV - Install LV Devices - OH @ 4th Flr South 10 10 0% 05-Jan-23 18-Jan-23 -7
4848 8 8 0% 21-Dec-22 05-Jan-23 -6
.4N.4360 FSP - Fire Sprinkler Drop Head & Trim-Out @ 4th Flr North 8 8 0% 21-Dec-22 05-Jan-23 -6
4949 2 2 0% 23-May-22 24-May-22 -6
.4S.4025 Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 4th Flr South2 2 0% 23-May-22 24-May-22 -6
5050 1 1 0% 21-Mar-22 21-Mar-22 -6
.5.5FSP Temporary Upright Fire Sprinklers @ 5th Floor 1 1 0% 21-Mar-22 21-Mar-22 -6
No Float Path No Float Path 504 401 9.4% 11-Jan-21 A 29-Sep-23 12
DEM100 DEMO - Existing Conditions Documentation / Verification 10 0 100% 28-Sep-21 A 28-Sep-21 A
NTP NTP - Notice to Proceed 0 0 100% 28-Sep-21 A
PRE1000 Document Existing Conditions 5 0 100% 28-Sep-21 A 28-Sep-21 A
.BUY1010 Buyout Electrical 10 0 100% 28-Sep-21 A 28-Sep-21 A
.BUY1000 Buyout Demolition 20 0 100% 28-Sep-21 A 28-Sep-21 A
A1600 Buyout Drywall/Framing (general) 10 0 100% 28-Sep-21 A 28-Sep-21 A
PRECON1000 TRIRIGA CPMS Access 5 0 100% 28-Sep-21 A 29-Sep-21 A
.BUY1020 Buyout Grease Exhaust Duct [as required] 20 0 100% 28-Sep-21 A 30-Sep-21 A
.BUY1040 Buyout Mechanical/HVAC 20 0 100% 28-Sep-21 A 30-Sep-21 A
.BUY1050 Buyout Plumber 20 0 100% 28-Sep-21 A 30-Sep-21 A
PRECON1050 Submittal Register 10 0 100% 28-Sep-21 A 01-Oct-21 A
PRECON1040 Site Safefty Plan 20 0 100% 28-Sep-21 A 13-Oct-21 A
SITE1030 Perform Utility Locates 2 0 100% 04-Oct-21 A 13-Oct-21 A
PRECON100 Construct Temp Sidewalk, Site Structures and Crosswalk Striping @ Bldg 23 10 0 100% 08-Oct-21 A 15-Oct-21 A
PRECON1070 Accident Prevention Plan (APP) 15 0 100% 14-Oct-21 A 25-Oct-21 A
PRECON1160 Site Safefty Plan Approval 20 0 100% 25-Aug-21 A 25-Oct-21 A
PRECON1060 Environmental Plan 15 0 100% 25-Aug-21 A 25-Oct-21 A
MOB ECRM - General Contractor - Mobilization 20 0 100% 28-Sep-21 A 25-Oct-21 A
SITE1010 Install Site Fencing / Gates 3 0 100% 26-Oct-21 A 27-Oct-21 A
PRECON1080 CQC Plan 30 0 100% 26-Oct-21 A 28-Oct-21 A
A1590 Buyout Hollow Metal Doors and Frames 20 0 100% 28-Sep-21 A 01-Nov-21 A
PRECON504 Prepare & Submit [as required] for Temp Comm Systems 5 0 100% 26-Oct-21 A 01-Nov-21 A
DEM105 DEMO - Site-Walk / Photo Spec. 10 0 100% 28-Sep-21 A 08-Nov-21 A
SITE1040 Install Silt Fence 1 0 100% 04-Nov-21 A 08-Nov-21 A
SITE1050 Install Tree Barricade/Protection 4 0 100% 08-Nov-21 A 09-Nov-21 A
SITE1070 Clear & Grub For Trailers 3 0 100% 09-Nov-21 A 12-Nov-21 A
Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul Aug S Oct N D Jan F
Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023Qtr 1, 2024
Install Attic Duct and New Duct Fans @ Pre-Demo Shaft North
12-May-22, 43
STL - Cut, Reinforce and Grout new Slab Penetration for Mechanical Shafts @ 5th Flr Lobby
03-Aug-23, 44
Remove Jobsite Trailers @ Center Site
15-Feb-23, 45
SIGN - Install Room ID / Signage @ 5th Flr South
12-May-22, 46
MEC - Install Mechanical Hangers / Support / Sleeves @ 5th Flr Lobby
18-Jan-23, 47
LV - Install LV Devices - OH @ 4th Flr South
05-Jan-23, 48
FSP - Fire Sprinkler Drop Head & Trim-Out @ 4th Flr North
24-May-22, 49
Area Mobilization for Construction, Verify Work Plan/ Pre-Install Meeting, Shops etc.@ 4th Flr South
21-Mar-22, 50
Temporary Upright Fire Sprinklers @ 5th Floor
29-Sep-23, No Float Path
DEMO - Existing Conditions Documentation / Verification
NTP - Notice to Proceed, 28-Sep-21 A
Document Existing Conditions
Buyout Electrical
Buyout Demolition
Buyout Drywall/Framing (general)
TRIRIGA CPMS Access
Buyout Grease Exhaust Duct [as required]
Buyout Mechanical/HVAC
Buyout Plumber
Submittal Register
Site Safefty Plan
Perform Utility Locates
Construct Temp Sidewalk, Site Structures and Crosswalk Striping @ Bldg 23
Accident Prevention Plan (APP)
Site Safefty Plan Approval
Environmental Plan
ECRM - General Contractor - Mobilization
Install Site Fencing / Gates
CQC Plan
Buyout Hollow Metal Doors and Frames
Prepare & Submit [as required] for Temp Comm Systems
DEMO - Site-Walk / Photo Spec.
Install Silt Fence
Install Tree Barricade/Protection
Clear & Grub For Trailers
Bay Pines VAMC Improvements 3/1 Update Typical 17-Mar-22 12:31
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 8 of 63 TASK filter: All Activities
Remaining Duration
Schedule % Complete
Start Finish Total Float
SITE1090 Rough-in/Install Trailer Utilities 5 0 100% 09-Nov-21 A 12-Nov-21 A
SITE1080 Complete Rough Grade For Trailers 5 0 100% 12-Nov-21 A 16-Nov-21 A
SITE1100 Spread Gravel Base for Trailers 2 0 100% 16-Nov-21 A 17-Nov-21 A
A2090 Prepare & Submit Remainder of Plumbing (pipes, insulation, etc) 20 0 100% 16-Nov-21 A 19-Nov-21 A
A1870 Round 1 (Early) Submittals Substantially Complete 0 0 100% 23-Nov-21 A
SITE1110 Set Trailers 2 0 100% 22-Nov-21 A 24-Nov-21 A
DEM115 DEMO - Demolition License / Permits Notice 5 0 100% 28-Sep-21 A 01-Dec-21 A
PRE ELEC800 Prepare and Submit Temp SB Generator Submittals 20 0 100% 28-Sep-21 A 02-Dec-21 A
A1270 Prepare and Submit Lead Removal Plan 10 0 100% 01-Dec-21 A 02-Dec-21 A
PRECON506 Approve Temp Communication Systems 20 0 100% 02-Nov-21 A 02-Dec-21 A
A1350 Prepare and Submit Electrical (General) 20 0 100% 06-Dec-21 A 07-Dec-21 A
PRECON202 Prepare and Submit Temp Power Electrical Submittals 20 0 100% 12-Oct-21 A 08-Dec-21 A
SITE1120 Connect Trailer Utilities 5 0 100% 03-Dec-21 A 08-Dec-21 A
A2330 Prepare & Submit HVAC Fans 20 0 100% 24-Nov-21 A 08-Dec-21 A
DEM090 DEMO - Demolition [General] Workplan Development 20 0 100% 20-Dec-21 A 20-Dec-21 A
PRECON1180 Submittal Register Approval 20 0 100% 01-Oct-21 A 22-Dec-21 A
PREPipe110 Prepare & Submit Abatement Work Plan @ Crawl Space & 1st Flr 20 0 100% 28-Sep-21 A 23-Dec-21 A
A1450 Approve Electrical (General) Submittal 20 0 100% 07-Dec-21 A 27-Dec-21 A
PREDuct102 Prepare & Submit Ductwork & Mech Eq. Submittals for Pre-demo Work 15 0 100% 28-Sep-21 A 30-Dec-21 A
PREDuct104 Prepare & Submit Mechanical Dampers Submittals for Pre-demo Work 15 0 100% 28-Sep-21 A 30-Dec-21 A
A1370 Approve Lead Removal Plan Submittal 20 0 100% 02-Dec-21 A 30-Dec-21 A
PRE ELEC802 Approve Temp SB Generator Submittals 30 0 100% 02-Dec-21 A 03-Jan-22 A
.SBP.1000 Prepare and Submit New SB Generator Submittals 20 0 100% 01-Jan-22 A 03-Jan-22 A
A2210 Prepare & Submit Vacuum Systems 20 0 100% 15-Nov-21 A 03-Jan-22 A
PRECON502 Prepare Initial Communications Workplan for Pre-Demolition Work 15 0 100% 26-Oct-21 A 04-Jan-22 A
PREPipe100 Prepare & Submit CHW & HHW Submittals for Pre-demo Work @ Crawl Space & 1st Flr 15 0 100% 28-Sep-21 A 04-Jan-22 A
PREPipe106 Prepare & Submit MP Steam Piping Submittals for Pre-demo Work @ Crawl Space & 1st Flr15 0 100% 28-Sep-21 A 04-Jan-22 A
PREPipe108 Prepare & Submit HHW Steam Converter 1-Hx for Pre-demo Work @ Crawl Space & 1st Flr15 0 100% 28-Sep-21 A 04-Jan-22 A
PRECON700 Prepare & Submit Replacement Grease Exhaust Duct Workplan for Pre-demo Work 20 0 100% 28-Sep-21 A 04-Jan-22 A
A1340 Prepare and Submit HVAC (General) 20 0 100% 27-Dec-21 A 04-Jan-22 A
A2120 Prepare & Submit Domestic Water Pumps 20 0 100% 22-Nov-21 A 04-Jan-22 A
A2270 Prepare & Submit Remainder of Mechanical (piping, insulation, ) 20 0 100% 22-Dec-21…