S02_Attachment - 876CM3025 Salisbury NC Annex II Bid Set Specs_Bk01.pdf

PDF 19 MB Posted

Attached to
Salisbury National Cemetery Public Restroom Renovation and Columbarium Cemetery Expansion
Solicitation number
36C78625R0014
Issued by

About this file

This file contains project specifications and a geotechnical investigation report for the Salisbury National Cemetery Annex II Project (876CM3025) in Salisbury, North Carolina. The specifications detail requirements for an expansion of the existing cemetery, including new construction of buildings, columbarium units, memorial walls, burial crypts, roadways, and associated site improvements.

The geotechnical report, prepared by SUMMIT Engineering in August 2023, analyzed 18 soil test borings and 6 asphalt cores at the 30-acre site. Key findings include the presence of alluvial soils, existing fill soils, and residual soils with varying stability. The report recommends shallow foundation systems with an allowable bearing pressure of 2,000 psf, minimum foundation depths of 12 inches below grade, and specific pavement sections for light duty (9.5 inches total thickness) and heavy duty (10 inches total thickness) applications. Special construction considerations are noted for areas with unstable soils, including potential need for undercutting and stabilization. The site is classified as Seismic Site Class E. The specifications indicate a bid set date of July 26, 2024, though actual solicitation release is scheduled for February 22, 2025.

View the file

Other files

File Type Posted
S02_Attachment - RFI Answers 5.02.2025.docx DOCX document
36C78625R0014 Amendment 0007.pdf PDF
36C78625R0014 Amendment 0006.pdf PDF
S02_Attachment - RFI Answers 4.27.2025.docx DOCX document
36C78625R0014 Amendment 0005.pdf PDF
S02_Attachment - RFI Answers updated 4.17.2025.docx DOCX document
S02_Attachment - Wage Determination 1.03.2025 Bldg.pdf PDF
S02_Attachment - Wage Determination 1.03.2025 Heavy.pdf PDF
S02_Attachment - RFI Answers.docx DOCX document
S02_Attachment - ASI 1 Part 3.pdf PDF
S02_Attachment - ASI 1 Part 1.pdf PDF
36C78625R0014 Amendment 0004.pdf PDF
S02_Attachment - Substitution Request Responses.pdf PDF
S02_Attachment - ASI 1 Part 2.pdf PDF
S02_Attachment - Full Text Added Terms and Conditions.docx DOCX document
S02_Attachment - Site Visit Attendance Roster.pdf PDF
36C78625R0014 Amendment 0003.pdf PDF
36C78625R0014 Amendment 0002.pdf PDF
36C78625R0014 Amendment 0001.pdf PDF
S02_Attachment - Wage Determination - Heavy.pdf PDF
S02_Attachment - Wage Determination - Building.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET DRAWINGS_Bk01.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC Bid Set Specs_Bk01.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II Bid Set Specs_Bk02.pdf PDF
S02_Attachment - Project Sample Template.docx DOCX document
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk01.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk03.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET Haz Mat Report.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk02.pdf PDF
S02_Attachment - Standard Form 1413.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET DRAWINGS_Bk05.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk04.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk05.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk06.pdf PDF
S02_Attachment - Approved Permits.pdf PDF
S02_36C78625R0014.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET DRAWINGS_Bk04.pdf PDF
S02_Attachment - Limitations on Subcontracting Cert.docx DOCX document
S02_Attachment - Statement of Work.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC Bid Set Specs_Bk02.pdf PDF
S02_Attachment - Past Performance Questionnaire.docx DOCX document
S02_Attachment - 876CM3025 Salibury NC Annex II BID SET Geotech Report.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET DRAWINGS_Bk02.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET Geotech Report.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Annex II BID SET DRAWINGS-Bk07.pdf PDF
S02_Attachment - Davis-Bacon Act Poster.pdf PDF
S02_Attachment - 876CM3025 Salisbury NC Seasonal High Water Table Test Results.pdf PDF
S02_Attachment - 876CM3024 Salisbury NC BID SET DRAWINGS_Bk03.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SALISBURY NATIONAL CEMETERY

SALISBURY, NORTH CAROLINA

ANNEX II

PROJECT 876CM3025

PROJECT SPECIFICATIONS

BID SET

July 26, 2024

PREPARED BY:

ARCHITECT:

ARCHITURA CORPORATION

9880 WESTPOINT DR. SUITE 400, INDIANAPOLIS, IN 46256-3384

LANDSCAPE ARCHITECT:

PASHEK + MTR, LTD.

619 E. OHIO ST., PITTSBURGH, PA 15212

CIVIL/STRUCTURAL ENGINEER:

KCI TECHNOLOGIES

936 RIDGEBROOK RD., SPARKS, MD 21152

MEP ENGINEER:

ARIUM|AE

5537 TWIN KNOLLS ROAD, SUITE 435

COLUMBIA, MARYLAND 21045

IRRIGATION DESIGNER:

AQUA ENGINEERING, INC.

3944 JFK Parkway, Unit 12C

Fort Collins, CO 80525-3089

Salisbury National Cemetery Annex II Project 876CM3025

Bid Set

TABLE OF CONTENTS

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

NCA MASTER SPECIFICATIONS

Section 00 01 10

DIVISION 01 - GENERAL REQUIREMENTS Author

01 00 02 General Requirements (Minor NCA Projects) PMTR

01 32 17 Network Analysis Schedules (Microsoft Project Gantt

Chart)

PMTR

01 33 23 Shop Drawings, Product Data, and Samples PMTR

01 42 19 Reference Standards PMTR

01 45 29 Testing Laboratory Services KCI

01 57 19 Temporary Environmental Controls KCI

01 74 19 Construction Waste Management PMTR

01 81 13 Sustainable Construction Requirements PMTR

DIVISION 02 – EXISTING CONDITIONS

02 41 10 Demolition and Site Clearing PMTR

02 85 00 Geotechnical Report Summit

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete KCI

03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn

Crypt)

PMTR

03 48 24 Precast Concrete Columbarium Units PMTR

03 48 26 Precast Concrete Memorial Wall Units PMTR

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring – Site Walls PMTR

04 20 00 Unit Masonry Architura

04 20 10 Unit Masonry – Site Walls PMTR

04 73 00 Columbarium Niche Covers PMTR

04 73 10 Memorial Wall Markers PMTR

DIVISION 05 – METALS

05 50 00 Metal Fabrications Architura

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry Architura

06 17 53 Shop Fabricated Wood Trusses Architura

06 20 00 Finish Carpentry Architura

00 01 10-2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation Architura

07 41 13 Standing Seam Metal Roofing Architura

07 46 46 Fiber-Cement Siding Architura

07 60 00 Flashing and Sheet Metal Architura

07 71 00 Roof Specialties Architura

07 92 00 Joint Sealants Architura

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames Architura

08 14 00 Interior Wood Doors Architura

08 31 13 Access Doors and Frames Architura

08 41 13 Aluminum Framed Entrances and Storefronts Architura

08 71 00 Door Hardware Architura

08 80 00 Glazing Architura

DIVISION 09 – FINISHES

09 29 00 Gypsum Board Architura

09 30 13 Tiling Architura

09 51 00 Acoustical Ceiling Architura

09 65 13 Resilient Base and Accessories Architura

09 91 00 Painting Architura

09 97 23 Concrete Stain for Precast Culvert PMTR

DIVISION 10 – SPECIALTIES

10 14 00 Exterior Signage PMTR

10 14 05 Architectural Signage Architura

10 21 13 Toilet Compartments Architura

10 28 00 Toilet and Bath Accessories Architura

10 44 16 Fire Extinguishers Architura

10 75 00 Flagpoles PMTR

DIVISION 13 - SPECIAL CONSTRUCTION

13 14 19 Metal Building Systems Architura

13 34 17 Pavilion Architura

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing Arium

22 05 23 General-Duty Valves for Plumbing Piping Arium

22 08 00 Commissioning of Plumbing Systems Arium

22 11 00 Facility Water Distribution Arium

22 13 00 Facility Sanitary Sewerage Arium

22 33 00 Electric Domestic Water Heaters Arium

22 40 00 Plumbing Fixtures Arium

00 01 10-3

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC Arium

23 05 93 Testing, Adjusting, and Balancing for HVAC Arium

23 07 11 HVAC Insulation Arium

23 08 00 Commissioning of HVAC Systems Arium

23 23 00 Refrigerant Piping Arium

23 34 00 HVAC Fans Arium

23 81 43 Air-Source Unitary Heat Pumps Arium

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations Arium

26 05 19 Low-Voltage Electrical Power Conductors and Cables Arium

26 05 26 Grounding and Bonding for Electrical Systems Arium

26 05 33 Raceway and Boxes for Electrical Systems Arium

26 05 41 Underground Electrical Construction Arium

26 24 16 Panelboards Arium

26 27 26 Wiring Devices Arium

26 29 21 Enclosed Switches and Circuit Breakers Arium

26 41 00 Facility Lightning Protection Arium

26 51 00 Interior Lighting Arium

26 56 00 Exterior Lighting Arium

DIVISION 27 – COMMUNICATIONS

27 05 26 Grounding and Bonding for Communications Systems Arium

27 05 33 Conduits and Backboxes for Communications Systems Arium

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 08 00 Commissioning of Electronic Safety and Security

Systems

Arium

28 20 00 Video Surveillance Arium

DIVISION 31 – EARTHWORK

31 20 00 Earth Moving KCI

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements PMTR

32 12 16 Asphalt Paving PMTR

32 17 23 Pavement Markings PMTR

32 31 13 Chain Link Fences and Gates PMTR

32 31 19 Decorative Metal Fences and Gates PMTR

32 33 00 Site Furnishings PMTR

32 84 00 Planting Irrigation AEI

32 90 00 Planting PMTR

00 01 10-4

DIVISION 33 – UTILITIES

33 10 00 Water Utilities KCI

33 30 00 Sanitary Sewerage Utilities KCI

33 40 00 Storm Sewer Utilities KCI

33 41 13 Foundation Drainage KCI

Signature - 1

Lead Consultant/Architect:

Architura Corporation

Landscape Architect:

Pashek+MTR

Civil Engineer:

KCI Technologies

MEP Engineer:

Arium AE

Irrigation Engineer:

Aqua Engineering

Structural Engineer:

KCI Technologies

NETWORK ANALYSIS SCHEDULE

01 32 17-1

SECTION 01 32 17

NETWORK ANALYSIS SCHEDULES

(MICROSOFT PROJECT GANTT CHART)

PART 1 - GENERAL

1.1 DESCRIPTION:

A. The Contractor shall develop a Microsoft Project 2021 Gantt Chart (bar chart) schedule demonstrating fulfillment of the contract requirements.

The Contractor shall keep the network up to date in accordance with the requirements of this section. The Contractor shall utilize the plan for scheduling, coordinating and monitoring work under this contract

(including all activities of subcontractors, equipment vendors and suppliers). The Gantt Chart will be utilized to satisfy time applications.

1.2 CONTRACTOR’S REPRESENTATIVE:

A. The Contractor shall designate an in-house representative who will be responsible to prepare the schedule, review the schedule and report progress of the project to the Contracting Officer's Representative.

B. The Contractor's in-house representative shall be given authority to act on behalf of the Contractor in fulfilling the requirements of this specification section. Such authority shall not be interrupted throughout the duration of the project.

1.3 COMPUTER PRODUCED SCHEDULES:

A. The contractor shall provide to VA monthly computer processing of all computer produced schedules generated from monthly project updates. The

Contractor shall provide to VA two (2) copies of the updated Microsoft

Project Gantt Chart and an electronic copy of this data. This must be submitted with and substantively support the contractor’s monthly payment request.

B. The Contractor is responsible for the correctness and timeliness of the computer-produced reports. The Contractor is also responsible for the accurate and timely submittal of the updated project schedule.

C. VA shall report errors in computer-produced reports to the Contractor’s representative within ten (10) calendar days from receipt of reports.

The Contractor shall reprocess the Gantt Chart and associated CDs, when requested by the Contracting Officers Representative, to correct errors that affect the schedule for the project.

01 32 17-2

1.4 THE COMPLETE PROJECT GANTT CHART SUBMITTAL:

A. The Complete Project Microsoft Project Gantt Chart will contain work activities/events as necessary to fully detail the project schedule.

B. Within ten (10) calendar days after receipt of the Notice to Proceed, the Contractor shall submit for the Contracting Officer's review, a

Microsoft Project Gantt Chart and a CD. Each activity/event on the

Gantt Chart schedule shall contain as a minimum, but not limited to, activity/event description, duration, start dates and finish dates.

Activity constraints, not required by the contract, will not be accepted. Logic events (non-work) will be permitted where necessary to reflect proper sequence among work events but must have zero duration.

C. The complete working Gantt Chart shall reflect the Contractor's approach to scheduling the complete project. The final Gantt Chart in its original form shall contain no contract changes or delays that may have been incurred during the final Gantt Chart development period. It shall reflect the Contractors “AS BID” or “DAY 1” schedule. Changes and /or delays shall be entered at the first monthly update after the final Gantt Chart has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT

COMPLETION.

D. Within ten (10) calendar days after receipt of the complete project

Gantt Chart, the Contracting Officer or his representative, will do one or both of the following:

1. Notify the Contractor concerning his actions, opinions, and objections.

2. Schedule a meeting with the Contractor at, or near the job site, for joint review, correction or adjustment of the proposed plan. Within ten (10) calendar days after the joint review, the Contractor shall revise and shall submit two (2) copies of the revised Gantt Chart and a revised CD as specified to the Contracting Officer. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.

1.5 WORK ACTIVITY/EVENT AND COST DATA INFORMATION:

A. The Contractor shall not be required to “cost load” the computerized

Microsoft Project Gantt Chart. As part of this submission, the

01 32 17-3

Contractor shall provide a separate Schedule of Costs on AIA document

G703. This Schedule of Costs shall reflect and contain all the same activities/events identified on the Gantt Chart.

B. The Contractor and the Contracting Officer shall use this Schedule of

Costs for monthly payment purposes as referenced in the General

Conditions of this agreement.

C. The Contractor and Contracting Officer shall agree on percentages for monthly work accomplished. The cumulative total amount of all cost loaded activities/events (including alternates) shall equal the total contract price.

D. Prorate overhead, profit and general conditions on all work activities/events for the entire project. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.

1.6 GANTT CHART REQUIREMENTS:

A. Show on the Gantt Chart the sequence and interdependence of work activities/events required for complete performance of all items of work. In preparing the Gantt Chart, the Contractor shall:

1. Show the following on each work activity/event:

a. Concise description of the work represented by the activity/event.

b. Duration (in workdays.)

2. Show activities/events as:

a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.

b. Contracting Officer Representative's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.

c. Interruption of VA Cemetery utilities, delivery of Government furnished equipment, project phasing and any other specification requirements.

d. Test, balance and adjust various systems and pieces of equipment.

3. Break up the work into activities/events of durations no longer than thirty (30) workdays each, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the Contracting Officer may approve the

01 32 17-4 showing of a longer duration. [The duration for VA approval of any required submittal, shop drawing, or other submittals shall not be less than ten (10) workdays.] The construction time as determined by the Gantt Chart schedule from start to finish for any sub-phase, phase or the entire project shall not exceed the total contract duration. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion.

Activities/events labeled "start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable.

4. Exterior Label Information: Provide the following information on an external label attached to each diskette(s):

a. VA project number and project location.

b. Name and telephone number of a point of contact, preferably the person who created the CD

c. The CD number and total number of CDs in the set

d. The project data status date.

1.7 PAYMENT TO THE CONTRACTOR:

A. Monthly, the contractor shall submit the Gantt Chart updated for remaining activity durations and a Schedule of Costs updated for costs.

AIA application and certification for payment documents G702 and G703 will be used. The payment request should reflect and be in accordance with the provisions of the following Article, PAYMENT AND PROGRESS

REPORTING, as the basis upon which progress payments will be made pursuant to Article, PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section GENERAL CONDITIONS. The Contractor is entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated Schedule of Costs unless, in special situations, the Contracting Officer permits an exception to this requirement. Monthly payment requests shall include: two (2) copies of the updated Microsoft Project Gantt Chart, a listing of all project schedule changes, and associated data, made at the update. These must be submitted with and substantively support the contractor’s monthly application and certificate for payment request documents.

B. When the Contractor fails or refuses to furnish to the Contracting

Officer the information and the associated updated Gantt Chart data, which, in the sole judgment of the Contracting Officer, are necessary

01 32 17-5 for validating the monthly progress payment, the Contractor shall not be deemed to have provided supporting schedule data upon which progress payment may be reasonably determined.

1.8 PAYMENT AND PROGRESS REPORTING:

A. Monthly job site progress meetings shall be held on dates mutually agreed to by the Contracting Officer (or Contracting Officer's

Representative) and the Contractor. Presence of subcontractors during the progress meeting is optional unless required by the Contracting

Officer (or Contracting Officer's Representative). Job progress will be reviewed to verify:

1. Actual start and/or finish dates for updated/completed activities/events.

2. Remaining duration, required to complete each activity/event started, or scheduled to start, but not completed.

3. Time and cost data for change orders, and supplemental agreements that are to be incorporated into the Gantt Chart.

4. Percentage for completed and partially completed activities/events.

5. Logic and duration revisions required by this section of the specifications.

6. Activity/event duration and percent complete shall be updated independently.

B. The Contractor shall submit a narrative report as a part of his monthly review and update, in a form agreed upon by the Contracting Officer.

The narrative report shall include a description of problem areas;

current and anticipated delaying factors and their estimated impact on performance of other activities/events and completion dates; and an explanation of corrective action taken or proposed. This report is in addition to the daily reports pursuant to the provisions of Article, DAILY REPORT OF WORKERS AND MATERIALS in the GENERAL CONDITIONS.

C. As part of the monthly jobsite progress meeting, the General

Contractor, specifically requested subcontractors and the Contracting

Officers Representative shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary actions required to maintain project schedule during the reporting period.

01 32 17-6

1.9 RESPONSIBILITY FOR COMPLETION:

A. Whenever it becomes apparent from the monthly progress review meeting or the monthly computer-produced Gantt Chart schedule that phasing or contract completion dates will not be met, the Contractor shall execute some or all of the following remedial actions:

1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.

2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.

3. Reschedule the work in conformance with the specification requirements.

B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the Contracting Officer for the proposed schedule changes. If such actions are approved, the revisions shall be incorporated by the Contractor into the Gantt Chart before the next update, at no additional cost to the Government.

1.10 CHANGES TO GANTT CHART SCHEDULE:

A. Within ten (10) calendar days after VA acceptance and approval of any updated computer-produced schedule, the Contractor shall submit a revised Gantt Chart, the associated CDs, and a list of any activity/event changes including predecessors and successors for any of the following reasons:

1. Delay in completion of any activity/event or group of activities/events, which indicate an extension of the project completion by twenty (20) working days or 10 percent of the remaining project duration, whichever is less. Such delays which may be involved with contract changes, strikes, unusual weather, and other delays will not relieve the Contractor from the requirements specified unless the conditions are shown on the Gantt Chart as the direct cause for delaying the project beyond the acceptable limits.

2. Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the work necessary.

3. The schedule does not represent the actual prosecution and progress of the project.

01 32 17-7

4. When there is, or has been, a substantial revision to the activity/event costs of the network diagram regardless of the cause for these revisions.

B. Revisions made under this paragraph, which affect the previously approved computer-produced schedules for Government furnished equipment, contract phase(s) and sub phase(s), utilities furnished by the Government to the Contractor, or any other previously contracted item, must be furnished in writing to the Contracting Officer for approval.

C. Contracting Officer's approval for the revised Gantt Chart and all relevant data is contingent upon compliance with all other paragraphs of this section and any other previous agreements by the Contracting

Officer or the Contracting Officer’s Representative.

D. The cost of revisions to the Gantt Chart resulting from contract changes will be included in the cost of the change.

E. The cost of revisions to the Gantt Chart not resulting from contract changes is the responsibility of the Contractor.

1.11 ADJUSTMENT OF CONTRACT COMPLETION:

A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, Gantt

Chart data and supporting evidence as the Contracting Officer may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract.

Submission of proof based on revised activity/event logic, durations

(in workdays) and costs is obligatory to any approvals.

B. The Contracting Officer's determination as to the total number of days of contract extension will be based upon the current computer-produced

Gantt Chart schedule for the time period when the change took place and all other relevant information. The Contracting Officer will, within thirty (30) calendar days after receipt of such justification and supporting evidence, advise the Contractor in writing of his decision on the matter.

C. The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in accordance with the provisions specified under Article, CHANGES, in the Section, GENERAL

CONDITIONS. The Contractor shall include, as a part of each change

01 32 17-8 order proposal, a sketch showing all revisions, duration (in workdays) changes, and cost changes, for work in question and its relationship to other activities on the approved network diagram.

D. All delays due to non-work activities/events such as RFI’s, WEATHER, STRIKES, and similar non-work activities/events shall be analyzed on a month-by-month basis.

- - - E N D - - -

July 26, 2024

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 33 23 - 1

SECTION 01 33 23

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

1-1. Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(FAR 52.236-21) and, SPECIAL NOTES (VAAR 852.236-91), in GENERAL

CONDITIONS.

1-2. For the purposes of this contract, samples (including laboratory samples to be tested, test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as

SUBMITTALS.

1-3. Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:

A. Satisfactory written evidence is presented to, and approved by

Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;

B. Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;

C. Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.

1-4. Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract - required items. Delays attributable to untimely and rejected submittals (including any laboratory samples to be tested) will not serve as a basis for extending contract time for completion.

1-5. Submittals will be reviewed for compliance with contract requirements by Architect-Engineer, and action thereon will be taken by COR on behalf of the Contracting Officer.

1-6. Upon receipt of submittals, Architect-Engineer will assign a file number thereto. Contractor, in any subsequent correspondence, shall

July 26, 2024

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 33 23 - 2 refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.

1-7. The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant to request therefor by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES

(FAR 52.243-4) and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the

GENERAL CONDITIONS.

1-8. Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs and Architect-Engineer. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The

Contracting Officer and Architect- Engineer assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.

1-9. Submittals must be submitted by Contractor only and shipped prepaid.

Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.

A. Submit samples required by Section 09 06 00, SCHEDULE FOR FINISHES, in quadruplicate. Submit other samples in single units unless otherwise specified. Submit shop drawings, schedules, manufacturers' literature and data, and certificates in quadruplicate, except where a greater number is specified.

B. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via e-mail (or if a sample, via first class mail) and shall contain the list of items, name of Cemetery, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers

(and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification

Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.

July 26, 2024

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 33 23 - 3

1. A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.

2. Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Cemetery, name of Contractor, manufacturer, brand, contract number and ASTM or

Federal Specification Number as applicable and location(s) on project.

3. Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by

Contractor.

C. In addition to complying with the applicable requirements specified in preceding Article 1.9, samples which are required to have Laboratory

Tests (those preceded by symbol "LT" under the separate sections of the specification shall be tested, at the expense of Contractor, in a commercial laboratory approved by Contracting Officer.

1. Laboratory shall furnish Contracting Officer with a certificate stating that it is fully equipped and qualified to perform intended work, is fully acquainted with specification requirements and intended use of materials and is an independent establishment in no way connected with organization of Contractor or with manufacturer or supplier of materials to be tested.

2. Certificates shall also set forth a list of comparable projects upon which laboratory has performed similar functions during past five years.

3. Samples and laboratory tests shall be sent directly to approved commercial testing laboratory.

4. Contractor shall send a copy of transmittal letter to both COR and to Architect-Engineer simultaneously with submission of material to a commercial testing laboratory.

5. Laboratory test reports shall be sent directly to COR for appropriate action.

6. Laboratory reports shall list contract specification test requirements and a comparative list of the laboratory test results.

When tests show that the material meets specification requirements, the laboratory shall so certify on test report.

July 26, 2024

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 33 23 - 4

7. Laboratory test reports shall also include a recommendation for approval or disapproval of tested item.

D. If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.

E. Approved samples will be kept on file by the COR at the site until completion of contract, at which time such samples will be delivered to

Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.

F. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. These drawings and schedules shall be stamped and signed by Contractor certifying to such check.

1. For each drawing required, submit one legible photographic paper or vellum reproducible.

2. Reproducible shall be full size.

3. Each drawing shall have marked thereon, proper descriptive title, including Cemetery location, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and

Specification Section Number.

4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.

5. Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.

6. One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.

7. When work is directly related and involves more than one trade, shop drawings shall be submitted to Architect-Engineer under one cover.

July 26, 2024

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

01 33 23 - 5

1-10. Shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted for approval to Architect-Engineer via e-mail.

1-11. At the time of transmittal to the Architect-Engineer, the Contractor shall also send a copy of the complete submittal directly to the COR.

1-12. Samples (except laboratory samples) for approval shall be delivered to the job site trailer for review by the COR and Architect-Engineer.

Photos of the samples shall be submitted digitally as a submittal.

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 1

SECTION 01 42 19

REFERENCE STANDARDS

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the availability and source of references and standards specified in the project manual under paragraphs APPLICABLE

PUBLICATIONS and/or shown on the drawings.

1.2 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS FPMR PART 101-29

(FAR 52.211-1) (AUG 1998)

A. The GSA Index of Federal Specifications, Standards and Commercial Item

Descriptions, FPMR Part 101-29 and copies of specifications, standards, and commercial item descriptions cited in the solicitation may be obtained for a fee by submitting a request to – GSA Federal Supply

Service, Specifications Section, Suite 8100, 470 East L’Enfant Plaza, SW, Washington, DC 20407, Telephone (202) 619-8925, Facsimile (202)

619-8978.

B. If the General Services Administration, Department of Agriculture, or

Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

1.3 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN THE GSA

INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS

(FAR 52.211-4) (JUN 1988)

A. The specifications and standards cited in this solicitation can be examined at the following location:

United States Department of Veteran Affairs

Technical Information Library https://www.cfm.va.gov/til/

1.4 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL

SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (FAR 52.211-3)

(JUN 1988)

A. The specifications cited in this solicitation may be obtained from the associations or organizations listed below.

AA Aluminum Association, Inc.

http://www.aluminum.org

AABC Associated Air Balance Council http://www.aabchq.com https://www.cfm.va.gov/til/ http://www.aabchq.com/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 2

AADM American Association of Automatic Door Manufacturers http://www.aaadm.com

AATC American Association of Textile Chemists and Colorist http://www.aatcc.org

AAMA American Architectural Manufacturer's Association http://www.aamanet.org

AAN American Nursery and Landscape Association http://www.anla.org

AASHTO American Association of State Highway and Transportation

Officials http://www.transportation.org/Pages/default.aspx

ACGIH American Conference of Governmental Industrial Hygienists http://www.acgih.org

ACI American Concrete Institute http://www.aci-int.net

ACPA American Concrete Pipe Association http://www.concrete-pipe.org

ACPPA American Concrete Pressure Pipe Association http://www.acppa.org

ADA American with Disabilities Act http://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-ada-standards/background/adaag

ADC Air Diffusion Council http://flexibleduct.org

AGA American Gas Association http://www.aga.org

AGC Associated General Contractors of America http://www.agc.org

AHA American Hardboard Association http://www.domensino.com/AHA/

AIHA American National Standards Institute/American Industrial Hygiene

Association http://www.aiha.org/Pages/default.aspx

AISC American Institute of Steel Construction http://www.aisc.org

AISI American Iron and Steel Institute http://www.steel.org http://www.aatcc.org/ http://www.agc.org/ http://www.hardboard.org/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 3

AITC American Institute of Timber Construction http://www.aitc-glulam.org

ALI Automotive Lift Institute http://www.autolift.org/

AMCA Air Movement and Control Association http://www.amca.org/

ANLA American Nursery & Landscape Association http://www.anla.org

ANSI American National Standards Institute, Inc.

http://www.ansi.org

APA Architectural Precast Association http://www.archprecast.org/

APA The Engineered Wood Association http://www.apawood.org

ARI Air-Conditioning and Refrigeration Institute http://www.lightindustries.com/ARI/

ARMA Asphalt Roofing Manufacturers Association http://www.asphaltroofing.org/

ASAE American Society of Agricultural Engineers http://www.asabe.org

ASCE American Society of Civil Engineers http://www.asce.org

ASHRAE American Society of Heating, Refrigerating, and

Air-Conditioning Engineers http://www.ashrae.org

ASME American Society of Mechanical Engineers http://www.asme.org

ASSE American Society of Sanitary Engineering http://www.asse-plumbing.org

ASTM American Society for Testing and Materials http://www.astm.org

AWI Architectural Woodwork Institute http://www.awinet.org

AWS American Welding Society http://www.aws.org

AWPA American Wood Protection Association http://www.awpa.com http://www.archprecast.org/ http://www.aws.org/ http://www.awpa.com/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 4

AWWA American Water Works Association http://www.awwa.org

BHMA Builders Hardware Manufacturers Association http://www.buildershardware.com

BIA The Brick Industry Association http://www.bia.org

CAGI Compressed Air and Gas Institute http://www.cagi.org

CARB California Environmental Protection Agency Air Resources Board http://arb.ca.gov/hompage.html/

CFR Code of Federal Regulations http://www.gpo.gov/fdsys/browse/collectionCfr.action?collectionCo de=CFR

CGA Compressed Gas Association, Inc.

http://www.cganet.com

CID Commercial Item Description http://www.gsa.gov/portal/content/100847

CISCA Ceilings and Interior Systems Construction Association http://www.cisca.org

CISPI Cast Iron Soil Pipe Institute http://www.cispi.org

CLFMI Chain Link Fence Manufacturers Institute http://www.chainlinkinfo.org

CPA Composite Panel Association http://www.compositepanel.org/

CRA California Redwood Association http://www.calredwood.org

CRI Carpet and Rug Institute http://www.carpet-rug.com

CRRC Cool Roof Rating System http://coolroofs.org/

CRSI Concrete Reinforcing Steel Institute http://www.crsi.org

CSI Cast Stone Institute http://www.caststone.org

DASMA Door and Access Systems Manufacturers Association http://www.dasma.com/ http://arb.ca.gov/hompage.html/ http://www.calredwood.org/ http://www.carpet-rug.com/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 5

DHI Door and Hardware Institute http://www.dhi.org

DOE U.S. Department of Energy http://www.energy.gov/

EEI Edison Electric Institute http://www.eei.org

EGSA Electrical Generating Systems Association http://www.egsa.org

EIMA Exterior Insulation Manufacturers Association http://www.eima.com/

EPA Environmental Protection Agency http://www.epa.gov

ETL ETL Testing Laboratories, Inc.

http://www.envirotestinglabs.com/

FCC Federal Communications Commission http://www.fcc.gov

FHA Federal Highway Administration http://www.fhwa.dot.gov/

FM FM Global http://www.fmglobal.com

FPS The Forest Products Society http://www.forestprod.org

FSC Forest Stewardship Council http://www.fscus.org

GA Gypsum Association http://www.gypsum.org

GANA Glass Association of North America http://www.glasswebsite.com

GBI Green Building Initiative http://www.thegbi.org/

GS Green Seal http://www.greenseal.org

GSA General Services Administration http://www.gsa.gov

HI Hydraulic Institute http://www.pumps.org

HPVA Hardwood Plywood & Veneer Association http://www.hpva.org http://www.dhi.org/ http://www.fmglobal.com/ http://www.fscus.org/ http://www.gypsum.org/ http://www.glasswebsite.com/ http://www.thegbi.org/ http://www.greenseal.org/ http://www.hpva.org/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 6

ICC The International Code Council http://www.iccsafe.org/Pages/default.aspx

ICEA Insulated Cable Engineers Association Inc.

http://www.icea.net

IEEE Institute of Electrical and Electronics Engineers http://www.ieee.org\

IGMA Insulating Glass Manufacturers Alliance http://www.igmaonline.org

ITS Intertek Training Services http://www.intertek.com/

MBMA Metal Buildings Manufacturers Association http://www.mbma.com

MHI Material Handling Industry of America http://www.mhi.org/

MIA Marble Institute of America http://www.marble-institute.com/

MIC Masonry Industry Council

MPI Master Painters Institute http://www.mpi.net/

MSJC Masonry Standards Joint Committee http://www.masonrysociety.org/msjc/

NAAMM National Association of Architectural Metal Manufacturers http://www.naamm.org

NAPHCC Plumbing-Heating-Cooling Contractors Association http://www.phccweb.org/

NBS National Bureau of Standards

See - NIST

NEC National Electric Code

See - NFPA National Fire Protection Association

NEMA National Electrical Manufacturers Association http://www.nema.org

NFPA National Fire Protection Association http://www.nfpa.org

NFRC National Fenestration Rating Council http://www.nfrc.org/

NHLA National Hardwood Lumber Association http://www.natlhardwood.org

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 7

NIH National Institute of Health http://www.nih.gov

NIOSH The National Institute for Occupational Safety and Health http://www.cdc.gov/niosh/

NIST National Institute of Standards and Technology http://www.nist.gov

NLMA Northeastern Lumber Manufacturers Association, Inc.

http://www.nelma.org

NPA National Particleboard Association

18928 Premiere Court

Gaithersburg, MD 20879

(301) 670-0604

NPCA National Precast Concrete Association http://www.precast.org

NRCA National Roofing Contractors Association http://www.nrca.net

NSF National Sanitation Foundation http://www.nsf.org

NSF NSF International http://www.nsf.org/

NTMA National Terrazzo and Mosaic Association http://ntma.com/

NWWDA Window and Door Manufacturers Association http://www.nwwda.org

OSHA Occupational Safety and Health Administration

Department of Labor http://www.osha.gov

PCA Portland Cement Association http://www.cement.org/

PCI Precast Prestressed Concrete Institute http://www.pci.org

PPI The Plastic Pipe Institute http://www.plasticpipe.org

PEI Porcelain Enamel Institute, Inc.

http://www.porcelainenamel.com

PTI Post-Tensioning Institute http://www.post-tensioning.org http://www.nrca.net/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 8

RCSC Research Council of Structural Connections http://www.boltcouncil.org/

RFCI The Resilient Floor Covering Institute http://www.rfci.com

RIS Redwood Inspection Service

See - CRA

RMA Rubber Manufacturers Association, Inc.

http://www.rma.org

SCAQMD South Coast Air Quality Management District http://www.aqmd.gov

SCMA Southern Cypress Manufacturers Association http://www.cypressinfo.org

SDI Steel Deck Institute http://www.sdi.org

SDI Steel Door Institute http://www.steeldoor.org

SEI Structural Engineering Institute http://www.asce.org/SEI/

SJI Steel Joist Institute http://www.steeljoist.org

SMACNA Sheet Metal and Air-Conditioning Contractors

National Association, Inc.

http://www.smacna.org

SPRI Single Ply Roofing Industry http://www.spri.org

SSPC The Society for Protective Coatings http://www.sspc.org

STI Steel Tank Institute http://www.steeltank.com

SWI Steel Window Institute http://www.steelwindows.com

SWRI Sealant Waterproofing and Restoration Institute http://www.swrionline.org/

TCNA Tile Council of North America, Inc.

http://www.tileusa.com

TPI Truss Plate Institute, Inc.

http://www.tpinst.org/ http://www.rma.org/ http://www.aqmd.gov/ http://www.sdi.org/ http://www.smacna.org/ http://www.spri.org/

July 26, 2024

REFERENCE STANDARDS

01 42 19 - 9

UL Underwriters' Laboratories Incorporated http://www.ul.com

ULC Underwriters' Laboratories of Canada http://www.ulc.ca

USDA U.S. Department of Agriculture http://www.usda.gov

USGBC U.S. Green Building Council http://www.usgbc.org

WCLIB West Coast Lumber Inspection Bureau http://www.wclib.org/

WDMA Window and Door Manufacturers Association https://www.wdma.com/

WH Warnock Hersey http://www.intertek.com/marks/wh/

WRCLA Western Red Cedar Lumber Association http://www.wrcla.org/

WWPA Western Wood Products Association http://www2.wwpa.org/

- - - E N D - - -http://www.ulc.ca/ http://www.usda.gov/ http://www.usgbc.org/

TESTING LABORATORY SERVICES

01 45 29 - 1

SECTION 01 45 29

TESTING LABORATORY SERVICES

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies materials testing activities and inspection services required during project construction to be provided by a

Testing Laboratory retained and paid for by Contractor. Refer to

Section 01 00 02, GENERAL REQUIREMENTS, for additional information.

1.2 RELATED DOCUMENTS

A. Section 01 00 02, GENERAL REQUIREMENTS.

1.3 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as otherwise shown or specified.

B. American Association of State Highway and Transportation Officials

(AASHTO):

T27-11(18) Sieve Analysis of Fine and Coarse Aggregates

T96-02(R2006) Resistance to Degradation of Small-Size Coarse

Aggregate by Abrasion and Impact in the Los

Angeles Machine

T99-10 The Moisture-Density Relations of Soils Using a

2.5 Kg (5.5 lb.) Rammer and a 305 mm (12 in.)

Drop

T104-99(R2007) Soundness of Aggregate by Use of Sodium Sulfate or Magnesium Sulfate

T180-10 Moisture-Density Relations of Soils using a

4.54 kg (10 lb.) Rammer and a 457 mm (18 in.)

Drop

T191-02(R2006) Density of Soil In-Place by the Sand-Cone

Method

C. American Society for Testing and Materials (ASTM):

01 45 29 - 2

A325-13 Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

A370-22 Definitions for Mechanical Testing of Steel

Products

A490-14 Heat Treated Steel Structural Bolts, 150 ksi

Minimum Tensile Strength

C31/C31M-22 Making and Curing Concrete Test Specimens in the Field

C33/C33M-18 Concrete Aggregates

C39/C39M-21 Compressive Strength of Cylindrical Concrete

Specimens

C109/C109M-21 Compressive Strength of Hydraulic Cement

Mortars

C138/C138M-17a Unit Weight, Yield, and Air Content

(Gravimetric) of Concrete

C140-22C Sampling and Testing Concrete Masonry Units and

Related Units

C143/C143M-20 Slump of Hydraulic Cement Concrete

C172/C172M-17 Sampling Freshly Mixed Concrete

C173/C173M-16 Air Content of freshly Mixed Concrete by the

Volumetric Method

C780-20 Pre-construction and Construction Evaluation of

Mortars for Plain and Reinforced Unit Masonry

C1019-20 Sampling and Testing Grout

C1064/C1064M-17 Freshly Mixed Hydraulic Cement Concrete

C1077-17 Agencies Testing Concrete and Concrete

Aggregates for Use in Construction and Criteria for Laboratory Evaluation

C1314-23 Compressive Strength of Masonry Prisms

01 45 29 - 3

C1364-23 Architectural Cast Stone

D698-R21 Laboratory Compaction Characteristics of Soil

Using Standard Effort

D1143/D1143M-20 Deep Foundations Under Static Axial Compressive

Load

D1188-15 Bulk Specific Gravity and Density of Compacted

Bituminous Mixtures Using Paraffin-Coated

Specimens

D1556-15E01 Density and Unit Weight of Soil in Place by the

Sand-Cone Method

D1557-12R21 Laboratory Compaction Characteristics of Soil

Using Modified Effort

D2166M-16 Unconfined Compressive Strength of Cohesive

Soil

D2167-15 Density and Unit Weight of Soil in Place by the

Rubber Balloon Method

D2216-19 Laboratory Determination of Water (Moisture)

Content of Soil and Rock by Mass

D2974-20E01 Moisture, Ash, and Organic Matter of Peat and

Other Organic Soils

D3666-16 Minimum Requirements for Agencies Testing and

Inspection Bituminous Paving Materials

D3740-19 Minimum Requirements for Agencies Engaged in

Testing and/or Inspection of Soil and Rock

E94M-22 Radiographic Examination

E164-19 Contact Ultrasonic Testing of Weldments

E329-21 Agencies Engaged in Construction Inspection, Testing, or Special Inspection

E543-21 Agencies Performing Nondestructive Testing

01 45 29 - 4

E709-21 Guide for Magnetic Particle Testing

E1155-20 Determining FF Floor Flatness and FL Floor

Levelness Numbers

D. American Welding Society (AWS):

D1.1-07 Structural Welding Code-Steel

1.4 REQUIREMENTS

A. Accreditation Requirements: Testing Laboratory retained and paid for by

Contractor must be accredited by one or more of the National Voluntary

Laboratory Accreditation Program (NVLAP) programs acceptable in the geographic region for the project. Furnish to the RE/COR a copy of the

Certificate of Accreditation and Scope of Accreditation. For testing laboratories that have not yet obtained accreditation by a NVLAP program, submit an acknowledgement letter from one of the laboratory accreditation authorities indicating that the application for accreditation has been received and the accreditation process has started, and submit to the RE/COR for approval, certified statements, signed by an official of the testing laboratory attesting that the proposed laboratory, meets or conforms to the ASTM standards listed below as appropriate to the testing field.

1. Laboratories engaged in testing of construction materials must meet the requirements of ASTM E329.

2. Laboratories engaged in testing of concrete and concrete aggregates must meet the requirements of ASTM C1077.

3. Laboratories engaged in testing of bituminous paving materials must meet the requirements of ASTM D3666.

4. Laboratories engaged in testing of soil and rock, as used in engineering design and construction, must meet the requirements of

ASTM D3740.

5. Laboratories engaged in inspection and testing of steel, stainless steel, and related alloys will be evaluated according to ASTM A880.

6. Laboratories engaged in non-destructive testing (NDT) must meet the requirements of ASTM E543.

01 45 29 - 5

7. Laboratories engaged in Hazardous Materials Testing must meet the requirements of OSHA and EPA.

B. Inspection and Testing: Testing laboratory to inspect materials and workmanship and perform tests described herein and additional tests requested by RE/COR. When it appears materials furnished, or work performed by Contractor fail to meet construction contract requirements, Testing Laboratory must direct attention of RE/COR to such failure.

C. Written Reports: Testing laboratory to submit test reports to RE/COR and Contractor within 24 hours after each test is completed unless other arrangements are agreed to in writing by the RE/COR. Submit reports of tests that fail to meet construction contract requirements on colored paper.

D. Verbal Reports: Give verbal notification to RE/COR immediately of any irregularity.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 EARTHWORK

A. General: The Testing Laboratory is to provide qualified personnel, materials, equipment, and transportation as required to perform the services identified/required herein, within the agreed to schedule and/or time frame. The work to be performed is as identified herein including, but not be limited to, the following:

1. Observe fill and subgrades during proof-rolling to evaluate suitability of surface material to receive fill or base course.

Provide recommendations to the RE/COR regarding suitability or unsuitability of areas where proof-rolling was observed. Where unsuitable results are observed, witness excavation of unsuitable material and recommend to RE/COR extent of removal and replacement of unsuitable materials and observe proof-rolling of replaced areas until satisfactory results are obtained.

2. Provide part time observation of fill placement and compaction and field density testing in building areas and provide part time

01 45 29 - 6 observation of fill placement and compaction and field density testing in pavement areas to verify that earthwork compaction obtained is in accordance with contract documents.

3. Provide supervised geotechnical technician to inspect excavation, subsurface preparation, and backfill for structural fill.

B. Testing Compaction:

1. Determine maximum density and optimum moisture content for each type of fill, backfill and subgrade material used, in compliance with

ASTM D698.

2. Make field density tests in accordance with the primary testing method following ASTM D2922 wherever possible. Field density tests utilizing ASTM D1556 to be utilized on a case-by-case basis only if there are problems with the validity of the results from the primary method due to specific site field conditions. Should the testing laboratory propose these alternative methods, they must provide satisfactory explanation to the RE/COR before the tests are conducted.

a. Building Slab Subgrade: At least one test of subgrade for every

185 m2 (2000 square…