This document outlines the scope of work for a federal contract opportunity to renovate maintenance buildings at Fort Smith National Cemetery. The contract includes general construction such as demolition, building trades work, concrete work, site work, replacement of fuel tanks and HVAC systems, and phased work in the lodge over 270 days. Additional contract line items include door replacement, bathroom accessory installation, and tuckpointing of brick walls. The related solicitation is a 100% set-aside for verified Service-Disabled Veteran-Owned Small Businesses, with a NAICS code of 236220 and size standard of $36.5 million. Electronic bids are due on an unspecified date in accordance with solicitation 36C78621B0019 to be posted on August 10, 2021 to the Department of Veterans Affairs National Cemetery Administration for renovations at Fort Smith National Cemetery.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of work
Fort Smith Renovate Maintenance Building
Project 847CM3020
CLIN 0001 General Construction: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Renovate Maintenance Facility and Lodge at the Ft. Smith National
Cemetery as required by drawings and specifications. Installation of all work shown on the plans and described in the specifications including but not limited to:
Demolition, building trades work, concrete work, site work, replacement of the fuel tank, replacement of the roof unit on the maintenance building and replacement of the furnace in the lodge. Phasing of the work in the lodge will be required. The contractor will develop a phasing plan in coordination with the
Cemetery Director and the COR. Period of performance for all is 270 days.
CLIN 0002: Complete replacement of doors noted to be refurbished on drawings.
CLIN 0003: Installation of bathroom accessories.
CLIN 0004: Complete tuckpointing of brick walls noted to require 30% tuckpointing on drawings.