RFQ26006370 Revised Scope of Work.pdf
PDF 212 KB Posted
- Attached to
- DEM The Paddlocks Project
- Solicitation number
- RFQ26006370
- Issued by
- Providence County, Providence City, Rhode Island
About this file
This is a Revised Scope of Work document issued by the Rhode Island Department of Environmental Management (RIDEM) for the Paddocks Project site remediation effort. The solicitation seeks vendor quotations for soil excavation, loading, transportation, and off-site disposal services at a 9.847-acre property located at 651 Narragansett Park Drive in Pawtucket, Rhode Island, formerly used as the Narragansett Racetrack and subsequently as an industrial park. The scope is limited to soil disposal activities only, with an estimated 3,500 tons (approximately 2,500 cubic yards) of contaminated soil containing Total Arsenic and polycyclic aromatic hydrocarbons (PAHs) to be removed to a maximum depth of two feet. Bidders must submit unit pricing per ton for soil disposal, documentation of transportation logs, and disposal weight tickets. The contract period runs from September 1, 2026 through October 31, 2026, with substantial completion targeted for October 2, 2026, representing a single mobilization anticipated to last no more than eight weeks. A non-mandatory pre-bid conference is scheduled for March 24, 2026 at the project site.
Bidders must submit unit pricing for soil excavation, loading, and disposal inclusive of all tasks outlined in the scope of work. The procurement includes three cost allowances totaling $25,000 for unforeseen conditions: $10,000 for underground storage tank identification, $10,000 for unidentified utility strikes, and $5,000 for coordination efforts, with liquidated damages assessed at $100 per day for delays beyond substantial completion. A mandatory Minority and Women Business Enterprise (MBE/WBE) set-aside requirement mandates that a minimum of ten percent of the total dollar value be awarded to MBE/WBE contractors in compliance with Rhode Island General Laws 37-14.1. The successful contractor assumes responsibility for arranging facility payments, scheduling trucking activities, providing certificates of insurance, implementing health and safety plans, and submitting copies of Material Shipping Records Logs and disposal facility weight tickets. Vanasse Hangen Brustlin, Inc. (VHB) will handle soil pre-characterization, site preparation, permitting, and other remedial actions under a separate RIDEM Remedial Approval Letter dated August 7, 2024. The project is funded by the Bipartisan Infrastructure Law.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2021-1.A Page 1 of 4 Revised 01/17/2023
AGENCY SOLICITATION SPECIFICATIONS
RFQ – REQUEST FOR QUOTE PUBLIC WORKS
HEADER
TITLE: REQUEST FOR QUOTES – THE PADDOCK PROJECT
DESCRIPTION: The Paddocks Project has Site Remediation number SR-26-2119. The Site consists of 9.847 acres of land, identified as Plat 41, Lot 391, located at 651 Narragansett Park Drive in Pawtucket, RI. The Site is owned and being developed by the Blackstone Valley Development Corporation (BVDC). Planned redevelopment includes multifamily residential housing, consisting of eight (8) buildings with ninety-five (95) units for adults with disabilities, veterans, elderly residents, and others with low- to moderate- incomes.
Historically, the Site was located within the boundaries of the former Narragansett Racetrack, which was established no later than 1939 and was previously developed as the What Cheer Airfield. From approximately 1939 to 1978, the Site was utilized as a parking lot for the racetrack.
By 1981, the racetrack had been razed, and the area was redeveloped as the Narragansett Industrial Park, which has remained vacant commercial land. Environmental investigations have identified concentrations of Total Arsenic and polycyclic aromatic hydrocarbons (PAHs) in Site soils that exceed RIDEM Residential Direct Exposure Criteria (R-DEC) and/or Industrial/Commercial Direct Exposure Criteria (I/C-DEC). Soils were also analyzed for additional parameters, including pesticides, herbicides, PP-13 Metals, polychlorinated biphenyls (PCBs), volatile organic compounds (VOCs), semi-volatile organic compounds (SVOCs), and total petroleum hydrocarbons (TPH). These additional parameters were reported by the laboratory as either Non- Detect, or below RIDEM R-DEC, I/C-DEC, and GB Leachability Criteria.
This Request for Quotes (RFQ) is limited to the excavation, loading, transportation, and off-site disposal of impacted soils, as well as the submittal of transportation logs and copies of disposal weight tickets only. This scope of work is a single mobilization and is anticipated to have a project duration of no more than eight (8) weeks. Other remedial actions including soil pre-characterization, preparation of a disposal facility application, and oversight shall be conducted by Vanasse Hangen Brustlin, Inc. (VHB) in accordance with the RIDEM Remedial Approval Letter (RAL) August 7, 2024.
The Remedial Action Work Plan (RAWP) associated with this project has been provided for reference, as well as the RAL describing the approved remedial actions. Upon soil disposal contractor selection (herein referred to as the soil disposal contractor), a meeting shall be held to discuss coordination between all parties.
This project will be funded by the Bipartisan Infrastructure Law.
2021-1.A Page 2 of 4 Revised 01/17/2023
SECTION A. BACKGROUND
The Site has been undeveloped and unoccupied since approximately 1978. Site soil has been found to contain concentrations of Total Arsenic and PAHs that exceed RIDEM R-DEC and/or I/C-DEC.
This Request for Quotes (RFQ) is for the excavation, loading, transportation, and disposal of soil, and submittal of transportation logs and copies of disposal weight tickets in accordance with Section B below. Soil pre-characterization and preparation of a disposal facility application Site prep, permitting, observations and other remediation (e.g., capping) shall be completed by VHB in accordance with a RIDEM Remedial Approval Letter (RAL, received 8/7/2024)as specified in Section B. The RAL describes remediation at this site to consist of the following:
• Limited soil excavation of jurisdictional soils and proper off-site disposal to a licensed facility. Confirmatory sampling of all excavation areas shall be conducted in accordance with the Department’s Dig & Haul Policy. Should any jurisdictional soils remain on-site, soils; must be encapsulated by a Department-approved engineered control;
• Encapsulation of Site soils by a Department-approved engineered control consisting of a minimum of two (2) feet of clean fill or an equivalent level of protection (i.e., building foundations, one (1) foot of clean fill over a geotextile fabric, and/or four (4) inches of hardscape (asphalt or concrete) over six (6) inches of clean fill); and
• An Environmental Land Usage Restriction (ELUR) shall be recorded on the deed for the entire property (Plat Map 41 / Lot 391). The ELUR shall require the performance of annual inspections to document the status of the ELUR and the condition of the engineered controls. The ELUR shall also include a Department-approved post-remediation Soil Management Plan (SMP) which will address any future activities that may disturb on-Site soils. The ELUR shall be recorded for the entire property in the Land Evidence Records for the City of Pawtucket, and a recorded copy forwarded back to the Department within fifteen (15) days of recording.
This project will be funded by the Bipartisan Infrastructure Law.
SECTION B: SCOPE OF WORK AND REQUIREMENTS
Task 1: Meetings – A meeting shall be held with RIDEM, BVDC and/or their engineer, and their environmental consultant (VHB) to coordinate the implementation of Task 2 described below. The meeting shall be conducted via Microsoft Teams or in-person. No additional meetings are anticipated.
Task 2: Mobilization & Excavation, Loading, Transportation and Disposal of Site Soil
– This task includes providing all labor and equipment necessary to excavate, load, transport and dispose soil from the Site under the following assumptions and specifications:
a. For cost estimating purposes, the soil disposal contractor shall assume the soil will be acceptable at either the RI Resource Recovery Corporation Landfill in Johnston, RI as Alternative Daily Cover Material, or at the Grotto Landfill in Pawtucket, RI.
b. Assume up to 3,500 tons of soil, estimated to be approximately 2,500 cubic yards, for disposal. The maximum depth of soil excavation is assumed to be two (2) feet.
c. A portable water source (e.g., water tank truck) must be provided and used daily and/or as needed to minimize the generation of nuisance dusts.
2021-1.A Page 3 of 4 Revised 01/17/2023
d. All truck loads must be covered prior to leaving the Site, and all truck wheels shall be brushed such as to minimize tracking of soil onto adjacent roads. Should any soil be tracked on to nearby roads, the contractor shall sweep/cleanup said soils prior to the end of each workday.
e. The soil disposal contractor shall prepare and implement a Health and Safety Plan for all contractor and subcontractor personnel while on Site.
f. The soil disposal contractor will be responsible for providing the required certificate of insurance, arranging payments to the disposal facility, and scheduling/coordinating trucking activities with the disposal facility scale house.
g. The soil disposal contractor shall provide legible copies of the completed MSRLs and of the disposal facility weight tickets for all soils transported/disposed.
h. The soil disposal contractor shall assume the responsibility of proper coordination with RIDEM, the Owner, and/or the environmental consultant.
Daily start time for work at the Site shall be no earlier than 7pm in accordance with Chapter 286 Noise Ordinance for Pawtucket.
The items identified below will be completed by VHB and/or other parties. These activities are not included in the scope of work for this contract and will be performed separately, as required, in accordance with applicable regulatory approvals and requirements:
i. Soil pre-characterization; preparation of a disposal facility application; provision of a disposal facility acceptance/approval letter and a Material Record Shipping Log (MRSL); and QEP observations shall be provided by the environmental consultant (VHB).
j. Any Site preparation activities (e.g., asphalt removal, clearing and grubbing, etc.), installation of soil and erosion controls, and procurement of applicable permits shall be provided by others.
k. No grading, backfilling, compaction, or ground restoration services are included in this scope of work.
l. RIDEM will coordinate access and project agreements with the Owner.
Minority and Women Business Enterprise (MBE/WBE) Participation Please note if any Minority and/or Women Business Enterprises (MBE/WBE) contractors will be utilized. If no MBE/WBE firms will be utilized, please provide an explanation.
General Laws 37-14.1 et al., requires MBE/WBE to be included in all State of Rhode Island-funded and state-directed public construction programs/projects and in-state purchases of good and services. A minimum of ten percent (10%) of the total dollar value of the entire procurement or project shall be awarded to MBE/WBE contractors.
SECTION C: CONTRACT TIME
Start of construction: September 1, 2026
Substantial completion: October 2, 2026
Final completion: October 31, 2026
2021-1.A Page 4 of 4 Revised 01/17/2023
SECTION D: ALLOWANCES
The Base Bid Price includes the cost of Allowances.
1. Unforeseen conditions consisting of identifying underground storage tanks
$ 10,000
2. Unforeseen conditions consisting of hitting an unidentified utility
$ 10,000
3. Unforeseen coordination efforts
$ 5,000
TOTAL ALLOWANCES: $_25,000_
SECTION E: LIQUIDATED DAMAGES
$ ___100___ per day
SECTION F: ALTERNATES
Not applicable
SECTION G: UNIT PRICE
UNIT
1. Soil Excavation, Loading, and Disposal per ton, inclusive of all Tasks and Sub-tasks outlined in the Scope of Work for an assumed 3,500 tons $ _____________
| SECTION A. BACKGROUND |
| SECTION B: SCOPE OF WORK AND REQUIREMENTS |
| SECTION C: CONTRACT TIME |
| SECTION D: ALLOWANCES |
| SECTION E: LIQUIDATED DAMAGES |
| SECTION F: ALTERNATES |
| SECTION G: UNIT PRICE |