This is an addendum to RFP 197F-24 issued by the Massachusetts Bay Transportation Authority (MBTA) for the overhaul of HSP46 locomotives. The addendum adds Section 4.12 Contract Bid Option #8, which covers the Traction Motor Combo Overhaul (5GEB15) for 80 traction motor combos, with scope including cleaning, inspection, overhaul, testing, and assembly according to OEM specifications. Additional changes include updating Section 5.8 to modify language regarding engine overhaul specifications, revising Section 11.2.3.F (now 11.2.3.E) regarding CDS system remote access requirements, and updating Section 18.11.A to specify replacement of existing air horns with new heated five-chime Nathan Airchime Model K-5LA-5HSC-BJ-CDF units or approved equals.
The addendum modifies payment milestone percentages, changing Milestone F from 3% to 2% (cumulative 28%) and Milestone G from 3.5% to 4.5%. Options exercise periods are updated, with Option 3 (Engine Overhaul) now requiring exercise within 30 days of NTP instead of 120 days. The new Option 8 (Traction Motor Combo Overhaul) must be exercised within 30 days of NTP for 80 units, with additional units covered under hidden damage at the Authority's discretion. A revised Price Proposal (Rev A) is referenced as an attachment to accommodate these changes.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Bay Transportation Authority
Ten Park Plaza, Boston, MA 02116 mbta.com
January 24th , 2025
SUBJECT: Request for Proposal - RFP 197F-24 –Amendments to Technical
Specification No. VE-23-055 and RFP 197F-24
To All Bidders:
The Massachusetts Bay Transportation Authority (MBTA), through this addendum, notifies all interested parties of the following amendments to the Request for Proposal (RFP) RFP 197F-24.
TECHNICAL SPECIFICATION NO. VE-23-055
Amend as follows:
Section 4.12
Add Section 4.12 Contract Bid Option #8 Traction Motor Combo Overhaul (5GEB15)
A. The Authority will identify via serial number the traction motor combos for overhaul.
B. The Contractor shall clean, inspect, overhaul, test, and assemble the traction motor combos according to the OEM Running and Heavy Maintenance Manuals.
C. Work shall include but not limited to Traction Motor, Traction Motor Leads, Gear Case, Gear, U-tube, Bearings, Bearing Housing, caps, cups, collars, housings, spacers, grease and all miscellaneous parts to assemble a complete wheel/axle/motor assembly. Wheel and axle assembly overhaul are not included in the scope but must be properly stored and maintained per
Section 22.5 Parts Preservation Plan. All hardware, seals, gaskets, and bearings shall be 100% replaced with new.
D. In addition to following all OEM cleaning, inspecting, testing, and overhaul requirements, all
5GEB15B1 motors shall undergo the Vacuum Pressure Impregnation (VPI) process to ensure enhanced insulation, durability, and operational reliability. The VPI process shall include the following steps: pre-inspection of each motor to identify any damages or deficiencies;
disassembly and thorough cleaning to remove contaminants; and baking of components to eliminate moisture. The process shall then employ a vacuum to remove air and moisture from the windings, followed by the application of OEM-specified insulating resin under pressure to ensure complete penetration into the windings. Components must be cured in a controlled oven environment to solidify the resin and achieve optimal insulation integrity. Post-VPI, all motors shall be subjected to comprehensive electrical and operational testing to verify compliance with technical and reliability standards. The VPI process shall strictly adhere to OEM specifications, including resin type, pressure levels, temperature, and curing times, ensuring consistent performance across all treated motors.
Section 5.8 (Section number change executed in Addendum #3)
Update section header from “CONTRACT BID OPTION #3 CAPITAL SPARE ENGINE OVERHAUL” to
“CONTRACT BID OPTION #3 ENGINE OVERHAUL”
Section 5.8.A
Update 5.8.A from “The Authority is in possession of a capital spare GEVO3 engine delivered to the
Authority in 2014 for use with the HSP46 Locomotive. This engine has been in storage since delivery.” to
“The Authority is in possession of a damaged GEVO3 engine. The engine will be provided to the Contractor within 30 days of NTP.”
Section 5.8.B
Update 5.8.B from “The Authority requests the Contractor provide a cost proposal for the overhaul and testing of this engine per TS 5 and all associated paperwork.” to “The Authority requests the Contractor provide a cost proposal for overhaul and testing of this engine per Section 5 of this Specification and all associated paperwork. Any repairs outside of the OEM overhaul scope shall be considered hidden damage.”
Section 11.2.3.F
Update 11.2.3.F section number to 11.2.3.E (change executed in addendum #4) and update language from
“The Contractor shall provide all on-board hardware and software necessary to allow remote access to all data on the CDS system. It shall be possible to perform all CDS functions via the remote access, including access to all CDS screens and download of all data logs, etc. The CDS shall be capable of being accessed from any internet-connected computer through any HTML web browser via a secure VPN connection as provided by the Contractor. The wireless data link protocol (CDMA, EVDO, GPRS, etc.) shall be approved by the
Authority based on coverage, cost, etc. at the final design review. The Contractor shall be responsible for the cost of the wireless data link service during the warranty period. If prior to the end of the warranty period, the wireless data link protocol is obsoleted or if the wireless provider gives notice that the service will be discontinued within two years, the contractor shall upgrade the wireless data link to a current technology at no cost to the Authority.”
to the following
“The Contractor shall provide all on-board hardware and software necessary to allow remote access to all data on the CDS system compatible with the Authority’s Legacy fleet latest and compatible version. It shall be possible to perform all CDS functions via the remote access, including access to all CDS screens and download of all data logs, etc. The CDS shall be capable of being accessed from any internet-connected computer through any HTML web browser via a secure VPN connection as provided by the Contractor or alternative method approved by the Authority.”
Section 18.11.A
Replace Section 18.11.A “The air horn shall be overhauled to OEM guidelines or renewed.” with the following: “Existing Air Horn shall be replaced with new heated five chime Nathan Airchime Model K-5LA-
5HSC-BJ-CDF or Authority approved equal. Horn shall include but not limited to horn and all necessary hardware and wiring for OEM approved operation and maintenance. New horn shall not exceed existing dynamic envelope. Horn sound level shall comply with FRA Part 229.129 as installed. All functionalities from current onboard systems shall remain the same unless approved by the Authority. Any new systems or software that may interact with the functionality or recording of the horn shall be submitted to the Authority for review and approval.”
Clarifications:
Contract Bid Option #7 Additional 1 year Warranty is not mentioned in the technical specification but is included in the RFP (No. 197F-24).
RFP NO. 197F-24
Amend as follows:
Section 1.1
Update the following section from “Option 3 – Spare Engine Overhaul, Verification Testing, & Storage
Maintenance Plan: Contractor to overhaul, verify, and develop a long-term storage maintenance plan for one
(1) GEVO 3 main engine per technical specification VE-23-055 section 5.9. Authority reserves the right to exercise Option 3 within 120 days of NTP.” to “Option 3 –Engine Overhaul: Contractor to overhaul, verify, and develop a long-term storage maintenance plan for one (1) GEVO 3 main engine per technical specification VE-23-055 section 5.8. Authority reserves the right to exercise Option 3 within 30 days of
NTP.”
Add the following to Section 1.1 Invitation and Description of Work
Option 8 Traction Motor Combo Overhaul
Contractor to provide comprehensive overhaul services for the traction motor combo, which includes but not limited to traction motor, U-tube assembly, and gear case. The scope of work encompasses inspection, overhaul, and testing to restore components to OEM specifications per technical specification VE-23-055 section 4.12. The Authority reserves the right to exercise Option 8 within 30 days for 80 traction motor combos. Any additional units will be covered by hidden damage at the Authority’s discretion.
The table in the section is updated as follows:
Option
No.
Option Title Quantity Exercised Date
Option 1 ECU System Upgrade
(TS 5.6)
Qty 1-40 Within 30 days of
NTP
Option 2 Turbo Investigation
(TS 5.7)
Qty 1 Within 30 days of
NTP
Option 3 Engine Overhaul
(TS 5.8)
Qty 1 Within 30 days of
NTP
Option 4 Fuel Tank Investigation
(TS 6.6)
Qty 1-40 30 days following each fuel tank inspection
Option 5 Water/Moisture Ingress
Investigation
(TS 7.5)
Qty 40 Within 240 days of NTP
Option 6 Locomotive Decommissioning
(TS 11.4)
Qty 38 At time of award
Option 7
Additional 1 year Warranty
(RFP 197F-24)
Qty 40 Within 1 year of
NTP
Option 8 Traction Motor Combo Overhaul
(TS 4.12)
Qty 80 Within 30 days of
NTP
Section 7.2
Update Milestone F
Incremental Payment %:
Changes from 3% to 2%
Accumulative Payment %:
Changes from 29% to 28%
Milestone Description to read as follows:
Delivery of Both Pilot Units, Completion of all Type and Routine Tests, Vehicle History Books, Approved
MBTA Safety & Security Certification Program Plan (SSCPP Attachment 5). All defined by (VE-23-055)
Section 7.2
Update Milestone G
Incremental Payment %:
Changes from 3.5% to 4.5%
Milestone Description to read as follows:
Pilot Units must run in service 60 days with no failures and 7,500 miles defined by (VE-23-055 Section 20.6)
Clarifications:
RFP 197F-24 Attachment 6 Price Proposal will be issued as a Rev A.
Attachment 6: Price Proposal Rev.A is also given as an attachment.
All other terms, conditions, and requirements of RFP 197F-24 remain unchanged.
Please be guided accordingly in preparing your submissions.
Bidders are reminded to acknowledge receipt of this addendum in their proposal submission.
Sincerely, Terunii Senevirratne.