PAVING IDIQ 1637384
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00.00 25 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 32 17.00 25 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 13.00 25 SPECIAL PROJECT PROCEDURES
01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 25 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 50 00.00 25 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 25 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00.00 25 PROJECT IDENTIFICATION
01 74 19.00 25 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00.00 25 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 10 - SPECIALTIES
10 14 53 TRAFFIC SIGNAGE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 23 00.00 20 EXCAVATION AND FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 01 13.64 BITUMINOUS PAVEMENT LIQUID REJUVENATING
32 01 16.71 COLD MILLING ASPHALT PAVING
32 01 17.61 SEALING CRACKS IN ASPHALT PAVING
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 01 19.61 RESEALING OF JOINTS IN RIGID PAVEMENT
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 ASPHALT PAVING FOR AIRFIELDS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 12 36.13 BITUMINOUS SEAL COAT
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
PROJECT TABLE OF CONTENTS Page 1
32 92 19 SEEDING
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 01 30.16 TV INSPECTION OF SEWER PIPELINES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Contract Drawings and Applicable Specification by Task Order
1.2.3 Location
1.3 WORK RESCHEDULING
1.4 EXISTING WORK
1.5 LOCATION OF UNDERGROUND UTILITIES
1.5.1 Notification Prior to Excavation
1.6 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This contract is an Indefinite Delivery, Indefinite Quantity (IDIQ) contract to be utilized for all aspects of airfield and roadway paving and marking for three Naval installations. The work includes all labor, materials, equipment, transportation and supervision needed to construct, maintain, repair and/or mark asphaltic and Portland Cement concrete pavement, concrete sidewalks, curbs and gutters, storm drainage conveyances and structures. The work also includes all incidental related work such as, but not limited to, seeding and sodding, sealing of cracks, demolition and removal, clearing and grubbing, excavation, grading, milling, etc.
1.2.2 Contract Drawings and Applicable Specification by Task Order
Project specific drawings will accompany each separate Task Order (TO) under this IDIQ contract and will become part of the TO requirements.
Project specific specifications may or may not accompany each separate TO but the specifications contained in this IDIQ contract document will govern all TO work whether or not project specific specifications are provided for the TO. If project specific specifications are provide for a TO and a conflict occurs between the project specific TO specifications and the IDIQ specifications, the most stringent shall apply.
Unless indicated in the specific statement of work/task order, TO's with a value less than $750,000 and a duration less than six (6) months, shall include specification sections 01 32 16.00 25 CONSTRUCTION PROGRESS SCHEDULE and 01 45 00.10 25 QUALITY CONTROL FOR MINOR CONSTRUCTION; for TO's with a value equal to or greater than $750,000 and a duration equal to or greater than six (6) months, specification sections 01 32 17.00 25 NETWORK ANALYSIS SCHEDULES and 01 45 00.10 25 QUALITY CONTROL FOR MINOR CONSTRUCTION shall apply. Additionally, when work is in the vicinity of the airfield, specification section 01 35 13.00 25 SPECIAL PROJECT PROCEDURES shall apply.
The Contractor shall immediately check the project drawings and specifications for each TO and notify the Government of any discrepancies.
SECTION 01 11 00 Page 2
For both initial TO's, specification sections 01 32 16.00 20 and 01 45
00.00 25 shall apply.
For work at NAS Pensacola, specification section 01 35 13.00 25 shall apply.
1.2.3 Location
The work associated with this IDIQ contract may be located at any one of twenty-nine (29) sites with in the states of Alabama and Florida. The sites include the primary installations Naval Air Station (NAS) Pensacola in Pensacola, Florida; NAS Whiting Field in Milton, Florida and Naval Support Activity (NSA) Panama City in Panama City, Florida. Additional outlying properties for NAS Pensacola include Navy Outlying Landing Field (NOLF) Bronson, Corry Station, Escambia County, Mariner Housing and Saufley Field. Outlying properties for NAS Whiting Field include NOLF Barin, Site X, NOLF Choctaw Field, NOLF Holley, NOLF Santa Rosa, NOLF Silverhill, NOLF Spencer, NOLF Summerdale, NOLF Wolf, NOLF Evergreen, NOLF Brewton, NOLF Pace, NOLF Harold, VORTAC Brooklyn, VORTAC Gateswood, Whiting Pines, EOD School at Eglin AFB, Allentown NDB, Foley Tower and Whiting Park Boat Dock. Outlying properties for NAS Panama City include St Andrews St Park, Site No. 1, Site No. 2, Site No. 3 and NOSC-MRCRC Tallahassee. The exact location of each project will be identified in each individual TO issued under this IDIQ contract.
TO's can be issued for work at any single location, or work at multiple locations simultaneously during the performance period of this IDIQ contract. The Contractor must acknowledge their ability to execute various quantities of work at multiple locations simultaneously during the full period of performance under this IDIQ contract.
There are two seed projects (TO's) for this IDIQ contract solicitation that will be executed simultaneously. One project is located at NAS Pensacola includes asphalt pavement overlay for approximately two (2) miles of roadway. The other project is located at NAS Whiting Field and includes approximately two (2) miles of roadway.
1.3 WORK RESCHEDULING
The Contractor shall allow for periods no more than 30 days at each occurrence where construction activity is prohibited. The Contractor shall also allow for periods no more than 14 days at each occurrence where excavation is halted and prohibited but other activities will be allowed to continue. The Government must provide 24 hours advance notice each time the restrictions are invoked.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00 Page 3
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits from the Government prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. A dig permit must be requested in writing 10 business days in advance.
Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground, pier deck or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Work shall be scheduled to minimize outages. Utility outages and connections shall be coordinated at the convenience of the Government and shall be scheduled outside regular installation work hours. Requests for utility outages and connections shall be made in writing to the Contracting Officer at least seven (7) calendar days in advance. Each request shall identify the systems involved, area involved, approximate duration of outage and the nature of work involved.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contact Sunshine One Call of Florida (800-432-4770), or CALL811 for other states, for utilities not owned by the Government.
Contact locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
1.6 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 15 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.00 25
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
1.3.1.1 Subcontractors and Personnel Contacts
1.3.1.2 Installation Access
1.3.1.2.1 Registration for DBIDS
1.3.1.2.2 DBIDS Eligibility Requirements
1.3.1.2.3 DBIDS Notification Requirements
1.3.1.2.4 One-Day Passes
1.3.1.3 No Smoking Policy
1.3.2 Working Hours
1.3.3 Work Outside Regular Hours
1.3.4 Occupied and Existing Buildings
1.3.5 Utility Cutovers and Interruptions
1.3.6 Service Work
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00.00 25 Page 1
SECTION 01 14 00.00 25
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the installation.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy
SECTION 01 14 00.00 25 Page 2
Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.
1.3.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or
SECTION 01 14 00.00 25 Page 3 former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.3 No Smoking Policy
Smoking (including e-cigarettes) is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period, between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied and Existing Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm and compressed air are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor
SECTION 01 14 00.00 25 Page 4 disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.3.6 Service Work
For projects located at, or in conjunction with, NAS Pensacola sites, the Contractor shall obtain all service work directly from the Public Works Department, Base Operations Service (BOS) contractor. The Contractor shall contact the BOS contractor directly to obtain pricing. This type of work includes any service call work (or disruption in service) including electrical, gas, chilled water, steam, water, wastewater, fire protection systems (alarms, detectors, sprinklers) chillers, boilers, pumps, cooling tower, DDC and services for gas, electrical, steam and water systems. Cost of such work shall be managed between the Contractor and the BOS contractor. The BOS POC is Henri Fuentes, Project Manager, henri.fuentes@fluor.com or (850)452-5051 ext. 3200.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00.00 25 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 SCHEDULE OF PRICES AND EARNED VALUE REPORT
1.3.1 Data Required
1.3.2 Schedule Instructions
1.3.3 Real Property Assets
1.4 CONTRACT MODIFICATIONS
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
1.5.2 Submission of Invoices
1.5.3 Final Invoice
1.6 PAYMENTS TO THE CONTRACTOR
1.6.1 Obligation of Government Payments
1.6.2 Payment for Onsite and Offsite Materials
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 20 00.00 20 Page 1
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices; G
Earned Value Report; G
Each individual TO will identify whether the Schedule of Prices or Earned Value Report will be required. If neither is identified in the TO, the following shall apply:
Schedule of Prices shall be used when the TO is less than $750,000 and the duration is less than six (6) months;
Earned Value Report shall be used when the TO is equal to or greater than $750,000 and the duration is equal to or greater than six (6) months.
1.3 SCHEDULE OF PRICES AND EARNED VALUE REPORT
1.3.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS) for some of the Task Orders. When the Network Analysis Schedule is prescribed for use, the information required for the Schedule of Prices will be entered as an integral part of the NAS. Within 15 calendar days of notice of award of each TO, prepare and deliver to the Contracting Officer either a Schedule of Prices or an Earned Value Report as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until either the Schedule of Prices or Earned
SECTION 01 20 00.00 20 Page 2
Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer.
1.3.3 Real Property Assets
The Government will provide the Draft DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes to summarize the designed real property assets that apply to this contract. The Contractor shall meet with the Contracting Officer and the Real Property Accounting Officer during the Pre Construction Meeting and the Project Closeout Meetings to modify and include any necessary changes to the DD Form 1354. The Contractor shall provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost.
Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs/ Category Codes.
Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/ Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during course of the work.
Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.
Cost data accumulated under this section are required in the preparation of DD Form 1354.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP 1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's Monthly Estimate for Voucher (NAVFAC LANT Form 4-330/110 (New 7/84)) with Subcontractor and Supplier payment certification.
b. Affidavit to accompany invoice (NAVFAC LANT NORVA Form 4-4235/4 (Rev.
5/81)).
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
SECTION 01 20 00.00 20 Page 3
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Contractor's Subcontractor and supplier payment certification.
i. Materials On-Site.
1.5.2 Submission of Invoices
If DFARS Clause 5252.232-7006 is included in the contract, provide the documents listed in paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR 32.503-6 Suspension or Reduction of Payments:
a. Reasonable deductions due to defects in material or workmanship;
SECTION 01 20 00.00 20 Page 4
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings,precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices or Earned Value Report requirement of this contract. Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
g. Materials in transit to the job site or storage site are not acceptable for payment.
SECTION 01 20 00.00 20 Page 5
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00.00 20 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 MINIMUM INSURANCE REQUIREMENTS
1.3 SUPERVISION
1.3.1 Minimum Communication Requirements
1.3.2 Superintendent Qualifications
1.3.2.1 Duties
1.3.3 Non-Compliance Actions
1.4 PRECONSTRUCTION MEETING
1.5 PARTNERING
1.5.1 Informal Partnering
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State's workers' compensation and occupational disease laws
d. Employer's liability coverage of $100,000, except in states where workers compensation may not be written by private carriers
e. Others as required by State law
Prior to commencement of work hereunder, the Contractor shall furnish to the Contracting Officer a certificate or valid proof of the above required insurance.
1.3 SUPERVISION
1.3.1 Minimum Communication Requirements
Have at least one qualified superintendent capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.3.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be
SECTION 01 30 00 Page 2 capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.3.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.3.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.4 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.5 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.5.1 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
SECTION 01 30 00 Page 3
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC office or the Contractor).
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer.
The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PRE-CONSTRUCTION SCHEDULE REQUIREMENT
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
1.3.1.1 Activity Requirements
1.3.1.2 Anticipated Weather Lost Work Days
1.3.1.3 Activity Identification
1.3.1.4 Responsibility Code
1.3.1.5 Primavera P6 Settings and Parameters
1.3.2 Bar Chart Schedule
1.3.3 Schedule Submittals and Procedures
1.4 SCHEDULE MONTHLY UPDATES
1.5 CONTRACT MODIFICATION
1.6 3-WEEK LOOK AHEAD SCHEDULE
1.7 CORRESPONDENCE AND TEST REPORTS:
1.8 ADDITIONAL SCHEDULING REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 32 16.00 20 Page 1
SECTION 01 32 16.00 20
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Baseline Construction Schedule; G
SD-07 Certificates
Monthly Updates; G
1.2 PRE-CONSTRUCTION SCHEDULE REQUIREMENT
Prior to the start of each TO, prepare and submit to the Contracting Officer a Baseline Construction Schedule in the form of a Network Analysis Schedule (NAS) Bar Chart Schedule in accordance with the terms in Contract Clause FAR 52.236-15 Schedules for Construction Contracts, except as modified in this contract. The approval of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting demolition work or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Construction Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6.
The scheduling software that will be utilized by the Government on this project is Primavera P6. Notwithstanding any other provision in the contract, schedules submitted for this project must be prepared using Primavera P6. Submission of data from another software system where data conversion techniques or software is used to import into Primavera P6
SECTION 01 32 16.00 20 Page 2 scheduling software is not acceptable and will be cause for rejection of the submitted schedule. Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule.
Within 15 calendar days after approval of the Initial Schedule or approval of the final design for a design build project, submit to the Contracting Officer a final NAS schedule.
1.3.1.1 Activity Requirements
a. At a minimum, identify the following in the schedule:
(1) Design and Construction time for major systems and components
(2) Each activity assigned with its appropriate Responsibility Code
(3) Each activity assigned with its appropriate Phase and Area Codes
(4) Major submittals and submittal processing time
(5) Major equipment lead time
b. Build the Schedule as follows:
(1) Show design periods, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities.
Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days for 5-day work week calendars.
(2) With the exception of the Contract Award and End Contract milestone activities, use of open-ended activities is not allowed;
each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic.
Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook," including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.
(3) Assign each activity its appropriate Responsibility Code and Area Code, indicating location and responsibility to accomplish the work indicated by the activity, Phase Code, and Work Location Code. Include anticipated tasks to be assigned Government responsibility.
(4) Date/time constraints or lags, other than those required by the contract, are not allowed unless approved by the Contracting Officer. Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".
(5) Include the following Contract Milestones:
SECTION 01 32 16.00 20 Page 3
(a) Include as the first activity on the schedule a start milestone titled "Contract Award", which must have a Mandatory Start constraint equal to the Contract Award Date;
(b) Include Interim or Phased Completion Milestones required by the Contract or as approved by the Contracting Officer;
(c) Include Facility Turnover Planning Meeting Milestones;
(d) Include an unconstrained finish milestone on the schedule titled "Substantial Completion". Substantial Completion is defined as the point in time the Government would consider the project ready for beneficial occupancy wherein by mutual agreement of the Government and Contractor. Government use of the facility is allowed while construction access continues in order to complete remaining items (e.g. punch list and other close out submittals).
(e) Include an unconstrained finish milestone on the schedule titled "Projected Completion". Projected Completion is defined as the point in time the Government would consider the project complete. This milestone must have the Contract Completion Date (CCD) milestone as its only successor.
(f) Include as the last activity on the schedule a finish milestone titled "Contract Completion (CCD)" with constraint type "Must Finish No Later Than". Calculation of schedule updates must be such that if the finish of the "Projected Completion" milestone falls after the contract completion date, then negative float will be calculated on the longest path and if the finish of the "Projected Completion" milestone falls before the contract completion date, the float calculation must reflect positive float on the longest path. This milestone must be set to 5:00 pm.
(6) Provide lead time for major equipment.
1.3.1.2 Anticipated Weather Lost Work Days
Use the National Oceanic and Atmospheric Administration's (NOAA) Summary of Monthly Normals report to obtain the historical average number of days each month with precipitation, using a nominal 30-year, greater than 0.10 inch precipitation amount parameter, as indicated on the Station Report for the NOAA location closest to the project site as the basis for establishing a "Weather Calendar" showing the number of anticipated non-workdays for each month due to adverse weather, in addition to Saturdays, Sundays and all Federal Holidays as non-work days.
Assign the Weather Calendar to any activity that could be impacted by adverse weather. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual adverse weather delay if the number of actual adverse weather delay days exceeds the number of days anticipated for the month in which the delay occurs and the adverse weather delayed activities are critical to contract completion. A lost workday due to weather conditions is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
SECTION 01 32 16.00 20 Page 4
1.3.1.3 Activity Identification
a. Identify Government, Construction Quality Management (CQM), Construction activities planned for the project and other activities that could impact project completion if delayed.
b. Identify administrative type activity/milestones including pre-construction submittal and permit requirements prior to demolition or construction stage.
c. Create separate activities for each Phase, Area, Floor Level, and Location the activity is occurring.
d. Do not use construction category activity to represent non-work type reference (Such as, Serial Letter or Request for Information) in NAS.
e. Place non-work reference within P6 activity details notebook. Activity categories included in the schedule are specified below.
1.3.1.4 Responsibility Code
Assign each activity its appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.
1.3.1.5 Primavera P6 Settings and Parameters
Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.
(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
c. Admin Drop-Down Menu, Admin Preferences, Earned Value Tab: Earned Value Calculation: Use "Budgeted values with current dates".
d. Project Level, Dates Tab: Set "Must Finish By" date to "Contract Completion Date", and set "Must Finish By" time to 05:00pm.
e. Project Level, Defaults Tab:
(1) Duration Type: Set to "Fixed Duration & Units".
(2) Percent Complete Type: Set to "Physical".
(3) Activity Type: Set to "Task Dependent".
(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.
SECTION 01 32 16.00 20 Page 5
Alternative calendars may be used with Contracting Officer approval.
f. Project Level, Calculations Tab:
(1) Activity percent complete based on activity steps: Must be Checked.
(2) Reset Remaining Duration and Units to Original: Must be Checked.
(3) Subtract Actual from At Completion: Must be Checked.
(4) Recalculate Actual units and Cost when duration percent (%) complete changes: Must be Checked.
(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.
(6) Price/Unit: Set to "$1/h".
(7) Update units when costs change on resource assignments: Must be Unchecked.
g. Project Level, Settings Tab:
(1) Define Critical Activities: Check "Longest Path".
h. The NAS must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 20 working days.
1.3.2 Bar Chart Schedule
The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet program.
1.3.3 Schedule Submittals and Procedures
Submit Schedules and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
1.4 SCHEDULE MONTHLY UPDATES
Update the Construction Schedule at monthly intervals or when the schedule has been revised. Keep the updated schedule current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
a. Narrative Report: Identify and justify the following:
(1) Progress made in each area of the project;
(2) Longest Path: Include printed copy on 11 by 17 inch paper, landscape setting;
SECTION 01 32 16.00 20 Page 6
(3) Date/time constraint(s), other than those required by the contract;
(4) Listing of changes made between the previous schedule and current updated schedule including: added or removed activities, original and remaining durations for activities that have not started, logic (sequence, constraint, lag/lead), milestones, planned sequence of operations, longest path, calendars or calendar assignments, and cost loading.
(5) Any decrease in previously reported activity Earned Amount;
(6) Pending items and status thereof, including permits, changes orders, and time extensions;
(7) Status of Contract Completion Date and interim milestones;
(8) Current and…