Request for Proposals - Truck Billboard Installation and Maintenance

This is a Request for Proposals (RFP-PW-24-403) issued by the City of Long Beach for truck billboard installation and maintenance services for the Environmental Services Bureau of the Public Works Department. The City seeks a vendor to provide installation of billboard frameworks, printing of weatherproofed panels, panel installation, and ongoing maintenance for approximately 91 existing refuse and organics collection trucks, with plans to add a minimum of 10 trucks annually. The current billboard frames measure 2.25" x 95.5" x 31.5", though vendors may propose alternative mounting systems subject to City approval. An optional site walk is scheduled for July 23, 2024, at 10:00 AM at 2929 E Willow Street, Long Beach. Questions must be submitted by August 6, 2024, at 11:00 AM PST, with responses posted by August 20, 2024. Proposals are due September 5, 2024, at 11:00 AM PST and must be submitted electronically via LongBeachBuys.com. The contract will be awarded for an initial three-year term with options to renew for two additional one-year periods, not to exceed five years total.

Proposals will be evaluated based on organizational capacity and experience (30%), method of approach including maintenance scheduling and demonstrated capacity to service over 100 trucks (40%), communications and reporting capabilities (20%), and cost reasonableness (10%). The City offers five percentage points of preference to local businesses maintaining a principal place of business and current business license in Long Beach. The cost proposal must itemize costs for framework installation per truck per side, panel printing, monthly maintenance, and any other associated costs. The awarded contractor will invoice the City monthly for services rendered, with payment issued within 30 calendar days. Maintenance must be scheduled monthly with panel rotation occurring every one to two months as determined by the City, and the complete process from design receipt through panel installation must not exceed 30 days. All work must comply with California Labor Code prevailing wage requirements, and the contractor must maintain required insurance coverage including $1,000,000 commercial general liability and workers' compensation insurance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Truck Billboard Installation and Maintenance | RFP - PW-24-403 | Template v04.20.23 |

City of

Long Beach Request for Proposals RFP - PW-24-403

Truck Billboard Installation and Maintenance

Truck Billboard Installation and Maintenance | RFP - PW-

24-403 | Template v04.20.23 | 2

Overview

Summary

Truck Billboard Installation and Maintenance

Key Dates

Release Date: July 9, 2024

Optional Site Walk: 10:00 AM (PST), July 23, 2024

Questions Due to the City: 11:00 AM (PST), August 6, Proposals Due: 11:00 AM (PST), September 5, 2024

The City reserves the right to modify these dates at any time, with appropriate notice to prospective Contractors.

Proposal Information

Instructions for what to include in your proposal and how to submit it are detailed in Section 4.

Proposals must be submitted electronically via

LongBeachBuys.com.

Official Contact

Anthony Delgado rfppurchasing@longbeach.gov

All communication with the City related to this RFP must be directed to the contact listed above.

mailto:rfppurchasing@longbeach.gov

Truck Billboard Installation and Maintenance | RFP - PW-

24-403 | Template v04.20.23 | 3

Contents

1 The Opportunity

1.1 Project Summary

1.2 Background

1.3 Goals

1.4 Award Terms

2 Scope of Work

2.1 Description of Services

2.2 Performance Metrics & Contract Management

2.2.1 Performance Metrics

2.2.2 Contract Management

2.2.3 Contract Payment

3 How We Choose

3.1 Minimum Qualifications

3.2 Evaluation Criteria

3.3 Local Preference

4 Proposal Instructions & Content

4.1 Timelines & Instructions

4.2 Proposal Content

4.3 Narrative Proposal Template

5 Terms & Conditions

5.1 Acronyms/Definitions

5.2 Solicitation Terms & Conditions

5.3 Contract Terms & Conditions

5.4 Protest Procedures

1 The Opportunity

1.1 Project Summary

The City of Long Beach (City) is seeking a vendor who can provide truck billboard services for all of the refuse and organics trucks operated by the Environmental Services Bureau

(ESB) of City’s Public Works Department. These services would include, but are not limited to, installation of the framework for the billboards, printing of the weatherproofed panels, installation of the panels, and ongoing maintenance as needed.

1.2 Background

The City has long utilized truck billboards on refuse and organics trucks in order to inform its residents of service information, recycling education messages, or other as-needed informational messages determined by the City.

The City has approximately 91 existing trucks, and anticipates adding a minimum of 10 trucks in the next year. With this expansion, the City requires a vendor to add billboards onto the City’s new trucks. The City also requires a reliable vendor who can maintain all of the billboards and switch out the messaging, upon request by the City.

1.3 Goals

The goal of this Request for Proposal (RFP) is to contract with a vendor to ensure truck billboards are installed on all new trucks and maintained on existing trucks to effectively communicate service information, educational messages and any other messages needed to residents throughout the City .

1.4 Award Terms

This contract will be for a period of three years with the option to renew for two additional one-year periods. The total contract term will not exceed five years.

2 Scope of Work

2.1 Description of Services

The vendor shall install the framework needed to mount the billboards on all new trucks as needed. The current frames are 2.25" x 95.5" x 31.5". If the selected vendor proposes a new mounting system, upon approval by the City, the vendor shall install the framework needed on all new and existing trucks. The City has approximately 91 trucks currently and anticipates adding a minimum of 10 trucks over the next year.

The vendor shall print new panels for the billboards with designs provided by City staff upon request and at a set charge per panel. The panels should be weatherproof. Double-sided panels are preferable, but not required for this proposal.

The vendor shall work with the City on an annual basis to establish a maintenance schedule, which includes a schedule for changing the panel displays on the trucks.

The vendor shall provide monthly maintenance of the billboards, including inspecting the billboards on all trucks on site to determine if any upkeep is needed, including but not limited to, the changing out of the panel.

2.2 Performance Metrics & Contract Management

2.2.1 Performance Metrics

The table below highlights the targets that will be tracked and reviewed collaboratively with the Awarded Contractor during the contract. This list is an indication of the performance metrics of interest to the City, and is not exhaustive or final. As a part of a response to this

RFP, Proposers may propose additional or alternative performance metrics to be tracked on a regular basis. The final set of performance metrics and frequency of collection will be negotiated by the successful Proposer and the City prior to the finalization of an agreement between parties, and may be adjusted over time as needed.

METRIC DESCRIPTION TARGET

1. Effective Communication Creates process to communicate with the City in an clear and effective manner

Vendor meets annually and as requested by the City.

2. Schedule Management Creates a process for maintaining the billboards and scheduling panel rotation with the City

Maintenance to be scheduled monthly with panel rotation scheduled every 1-2 months depending on the campaign. Schedule for panel rotation to be determined by the City annually.

3. Quality Assurance Maintains high-quality materials including the framework and panels for the billboards

Vendor to ensure framework is secure to the vtruck and that panels remain intact. Replacement of damaged panels shall be completed within a two week time frame.

4. Turn-around Time for

Printing and Installation

Establishes and keeps reasonable turnaround time for printing and installation of new panels as requested.

Panel printing schedule will be set in an annual meeting with vendor and the City.

Vendor must ensure ability to stick to the schedule agreed upon by both parties. Entire process of installation of framework, printing of new panels, and installation of new panels should not exceed 30 days after designs are received by vendor.

2.2.2 Contract Management

Communication and Management: The vendor will work collaboratively with the City to establish a maintenance schedule including, but not limited to, a schedule for the rotation of messaging displayed on the billboards through different panels. The City and vendor will meet to discuss initial contract negotiations, meet annually to establish panel rotation schedule, and meet periodically as requested by the City or vendor.

2.2.3 Contract Payment

The City of Long Beach issues payment based upon services rendered. After a contract is finalized and work is performed, the Contractor should invoice the City. The City will remit payment within 30 calendar days of being billed.

Invoices should be sent on a monthly basis and include the details of the services rendered that month, the invoice number, invoice date, and the Purchase Order number provided by the City.

3 How We Choose

3.1 Minimum Qualifications

• Qualification to conduct business in the City

• Not having been debarred by Federal, State or local government

3.2 Evaluation Criteria

Proposals shall be consistently evaluated based upon the following criteria:

CRITERIA Weight

1. Organizational Capacity & Experience

• Organizational capacity to successfully deliver services outlined in scope of work

• Demonstrable experience in maintaining this type of service with other jurisdictions or businesses

30%

2. Method of Approach

• Proposed Maintenance Schedule

• Demonstrated capacity to service over One Hundred (100) trucks

• Proposed Framework Design

• Ability to provide monthly maintenance and as required.

40%

3. Communications & Reporting

• Ability to maintain good communication with City staff in the planning and scheduling around the truck billboards maintenance and ability to meet on an as-needed basis.

20%

4. Reasonableness of Cost 10%

3.3 Local Preference

• The City shall apply five extra credit percentage points to all local businesses which submit proposals for services for the City of Long Beach.

• Local Business shall mean a business which maintains its principal place of business in a fixed office/place of business with the City of Long Beach, possesses a current

City of Long Beach business license and sellers permit if applicable.

• For a business to be eligible to claim preference, the business MUST request the preference in the Solicitation response (see Attachment A) and provide a copy of its current business license and seller’s permit if applicable.

• The local preference does not apply to solicitations for all purchases funded in full or a fraction thereof by any tidelands fund, by any grant funds, nor by any funds received from the State of California.

4 Proposal Instructions & Content

4.1 Timelines & Instructions

MILESTONE

TIME

(PACIFIC) &

DATE LOCATION / ADDITIONAL INFORMATION

Release date July 9th, Optional Site Walk 10:00 AM

(PST)

July 23,

• 2929 E Willow St, Long Beach, CA 90806

• Site walks are available by request only.

Contact Anthony Delgado by emailing rfppurchasing@longbeach.gov to schedule site visit

• Public parking is available in front of the ESB building off Willow St.

• Objective of site walk is to allow the opportunity to view the trucks and site if necessary before writing proposal

Questions due to the

City

11:00 AM

(PST),

August 6,

• Submit all inquiries via email to rfppurchasing@longbeach.gov

Posting of the Q&A August 20,

• Responses to the questions will be posted on

LongBeachBuys.com.

Proposals due 11:00 AM

(PST)

September

5, 2024

• Proposals should be submitted electronically via LongBeachBuys.com.

• Late proposals, or proposals submitted through other channels will not be accepted.

• Proposers are responsible for submitting their proposals completely and on time.

o Proposers will receive an e-bid confirmation number with a time stamp from LongBeachBuys.com indicating that the proposal was submitted successfully. The City will only receive proposals that were transmitted successfully.

o For technical support, email or call the

City during normal business hours at mailto:rfppurchasing@longbeach.gov file:///C:/Users/meid/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/X47PW9A6/LongBeachBuys.com file:///C:/Users/meid/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/X47PW9A6/LongBeachBuys.com file:///C:/Users/meid/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/X47PW9A6/LongBeachBuys.com

LBPurchasing@longbeach.gov or (562)

570-6200.

Evaluation of Narrative

& Cost Proposals

TBD • An Evaluation Committee will review Narrative

& Cost Proposals to select the proposal that best meets the needs of the City.

• Evaluations will be conducted using a methodology derived from the evaluation criteria listed in Section 3.2.

Interviews/ Demos/

Site Visits

TBD • The City may interview or request demos from none, one, some or all Proposers.

Negotiation &

Contractor Selection

TBD • Selected Contractor(s) will be notified in writing.

• Any award is contingent upon the successful negotiation of final contract terms. If contract negotiations cannot be concluded successfully, the City reserves the right to negotiate a contract with another Contractor or withdraw the RFP.

• Negotiations shall be confidential and not subject to disclosure to competing

Contractors unless and until an agreement is reached.

Estimated Contract

Execution

TBD

Proposer Debrief After

Contractor is Selected

• Successful and unsuccessful Proposers are encouraged to request phone call or in person meeting with the City to discuss the strengths and weaknesses of their proposal.

The intent of the debrief is to provide the

Proposer with constructive feedback to equip them with information to effectively meet the

City’s needs and be successful in future proposals.

mailto:LBPurchasing@longbeach.gov

4.2 Proposal Content

Complete proposals will include the following. Proposers are encouraged to use this table as a checklist to ensure all components are included in their proposal.

PROPOSAL

☐ Narrative

Proposal

The Narrative Proposal should provide a straightforward, concise delineation of capabilities to satisfy the RFP. Guidance on preparing a Narrative Proposal is detailed in Section 4.3.

☐ Cost Proposal The Cost Proposal should be provided in excel or a PDF with itemization of the costs proposed:

• Cost of Installation for new framework per truck, per side.

• Cost for printing of new panels o Weatherproofed and double-sided panels preferred

• Cost of monthly maintenance

• Any other costs associated with installation and maintenance of the truck panels, including but not limited to, parts and labor.

PROPOSAL APPENDICES

☐ Financial

Stability

Proposers must include one or more of the following financial statements to provide the City with enough information to determine financial stability of the Proposer and subcontractor.

• Financial Statement or Annual Report

• Business tax return

• Statement of income and balance sheet

☐ Other Addenda

(if applicable)

Colored displays, promotional materials, and other collateral are not necessary or desired. However, if a complete response cannot be provided without referencing supporting documentation, it may be provided as an addendum clearly cited in the Narrative or Cost Proposal.

MANDATORY ATTACHMENTS | The following are included as Attachments in Long

Beach Buys. They must be signed by the individual legally authorized to bind the

Proposer.

☐ A. Authorization & Certification

☐ B. Equal Benefits Ordinance (EBO) Form

Attachments Which May be Submitted Upon Award | Upon award, Awarded

Contractors will be required to submit the following. We encourage you to take note of these requirements, and where possible, include available information as part of your proposal to expedite processing.

☐ C. W-9

☐ D. Business License

☐ E. Proof of Registration with the California Secretary of State

☐ F. Certificates of Insurance

☐ G. Current Contractor’s State License Board print out

☐ Contact Information | Ensure your organization’s profile is up to date in Long Beach

Buys, including an email address, phone number, and for any classifications you may qualify for.

4.3 Narrative Proposal Template

An editable version of the template below has been posted to Long Beach Buys. Proposers should complete the editable template and submit it as their narrative proposal.

Organizational Capacity & Experience

PROPOSER CONTACT INFORMATION

Organization

Company Name

Company Address

Federal Tax ID Number

Website

Authorized

Representative

Name

Title

Email Address

Phone Number

Other Point of

Contact (if required)

Name

Title

Email Address

Phone Number

PROPOSER CAPACITY & EXPERIENCE

What type of enterprise is the organization?

☐ Non-Profit

☐ Sole Proprietorship

☐ General Partnership

☐ Corporation

State and Date of incorporation:

☐ Limited Liability Company

☐ Other _________________________________

Please describe why the organization is qualified to provide the services described in this RFP (1-2 paragraphs).

Please describe the length of time the organization has been providing the services described in this RFP (1-3 sentences).

Please describe the type of billboard mounting system provided by your company, the ability to change out panels, and the upkeep required:

How many employees does the organization have in total and residing in Long Beach?

Where are the representative(s) that would service the City’s account located?

Please provide an overview of how this service will be staffed and the experience of the staff performing the service:

REFERENCES

Reference 1

Company

Project Manager

Phone Number

Project Description

Project Start and

End Dates

Reference 2

Company

Project Manager

Phone Number

Project Description

Reference 3

Project Manager

Phone Number

Project Description

Reference 4

Project Manager

Phone Number

Project Description

Reference 5

Project Manager

Phone Number

Project Description

SUB-CONTRACTOR CONTACT INFORMATION

Does the proposal include subcontractors?

☐ Yes

☐ No

If applicable, provide the following for all subcontractors included in this proposal.

Organization Company Name

Company Address

Authorized

Representative

Name

Title

Email Address

Phone Number

Other Point of

Contact (if required)

Name

Title

Email Address

Phone Number

SUBCONTRACTOR CAPACITY & EXPERIENCE

What type of enterprise is the organization?

☐ Non-Profit

☐ Sole Proprietorship

☐ General Partnership

☐ Corporation

State and Date of incorporation:

☐ Limited Liability Company

☐ Other _________________________________

Which specific requirements of this RFP will the subcontractor perform?

Is the subcontractor registered with the

California Department of Industrial

Relations? If yes, provide registration number.

Please describe why the organization is qualified to provide the services described in this RFP (1-2 paragraphs).

Please describe the length of time the organization has been providing the services described in this RFP (1-3 sentences).

How many employees does the organization have nationally, locally, and residing in Long

Beach?

Where are the representative(s) that would service the City’s account located?

Method of Approach

1. Please summarize your proposal, including a detailed description of the type of billboard mounting system you are proposing and the types of panels that will be utilized (i.e. weatherproofed, double-sided, etc)

2. Do you have the staff and access to materials necessary to complete the installation and monthly maintenance required by the City?

3. Please summarize an example of the timeline for printing, mounting, and installation of a billboard and panel on a new truck:

4. What will you need from the City to implement the contract successfully?

Communications & Reporting

1. Please explain how employees responsible for front-line service delivery will be supervised.

2. How will you communicate with the City to meet the objectives of this RFP?

3. The City requires that the Awarded Contractor provide proof of payment of any subcontractors used for this project. If the proposal includes subcontractors, please describe the plan for how the City will be notified of such payments.

5 Terms & Conditions

5.1 Acronyms/Definitions

1. Awarded Contractor: The organization/individual that is awarded a contract with the

City of Long Beach, California for the services identified in this RFP.

2. City: The City of Long Beach and any department or agency identified herein.

3. Contractor / Proposer: Organization/individual submitting a proposal in response to this RFP.

4. Department / Division: City of Long Beach, Public Works Department

5. ESB: Environmental Services Bureau, Public Works Department

6. Evaluation Committee: An independent committee comprised solely of representatives of the City established to review proposals submitted in response to the RFP, evaluate the proposals, and select a Contractor.

7. May: Indicates something that is not mandatory but permissible.

8. RFP: Request for Proposals.

9. Shall / Must: Indicates a mandatory requirement. Failure to meet a mandatory requirement may result in the rejection of a proposal as non-responsive.

10. Should: Indicates something that is recommended but not mandatory. If the

Proposer fails to provide recommended information, the City may, at its sole option, ask the Proposer to provide the information or evaluate the proposal without the information.

11. Subcontractor: Third party not directly employed by the Proposer who will provide services identified in this RFP.

5.2 Solicitation Terms & Conditions

1. The City reserves the right to alter, amend, or modify any provisions of this RFP, or to withdraw this RFP, at any time prior to the award of a contract pursuant hereto, if it is in the best interest of the City to do so.

2. The City reserves the right to request clarification of any proposal term from

Proposers.

3. The City may contact the references provided; contact any Proposer to clarify any response; contact any current users of a Proposer’s services; solicit information from any available source concerning any aspect of a proposal; and seek and review any other information deemed pertinent to the evaluation process.

4. The level and term of documentation required from the Proposer to satisfy the City will be commensurate with the size and complexity of the contract and Proposers should submit accordingly. If the information submitted by the Proposer, or available from other sources, is insufficient to satisfy the City as to the Proposer’s contractual responsibility, the City may request additional information from the

Proposer or may deem the proposal non-responsive.

5. The City reserves the right to waive informalities and minor irregularities in proposals received.

6. The City reserves the right to reject any or all proposals received prior to contract award.

7. The City’s determination of the Proposer’s responsibility, for the purposes of this RFP, shall be final.

8. Unless otherwise specified, the City prefers to award to a single Contractor but reserves the right to award contracts to multiple contractors.

9. The City shall not be obligated to accept the lowest priced proposal, but will make an award in the best interests of the City of Long Beach after all factors have been evaluated.

10. If the City receives a single responsive, responsible proposal, the City may request an extension of the proposal acceptance period and/or conduct a price or cost analysis on such proposal. The Proposer shall promptly provide all cost or pricing data, documentation and explanation requested by the City to assist such analysis.

By conducting such analysis, the City shall not be obligated to accept the single proposal. The City reserves the right to reject such proposal or any portion thereof.

11. Any irregularities or lack of clarity in the RFP should be brought to the Purchasing

Division designee’s attention as soon as possible so that corrective addenda may be furnished to Proposers.

12. Proposals must include any and all proposed terms and conditions, including, without limitation, written warranties, maintenance/service agreements, license agreements, lease purchase agreements and the Proposer’s standard contract language. The omission of these documents may render a proposal non-responsive.

13. Alterations, modifications or variations to a proposal may not be considered unless authorized by the RFP or by addendum or amendment.

14. Proposals which appear unrealistic in the terms of technical commitments, lack of technical competence, or are indicative of failure to comprehend the complexity and risk of this contract, may be rejected.

15. Proposals may be withdrawn by written notice received prior to the proposal opening time.

16. The price and amount of this proposal must have been arrived at independently and without consultation, communication, agreement or disclosure with or to any other

Contractor or prospective Contractor.

17. No attempt may be made at any time to induce any firm or person to refrain from submitting a proposal or to submit any intentionally high or noncompetitive proposal. All proposals must be made in good faith and without collusion.

18. Prices offered by Proposers in their proposals are an irrevocable offer for the term of the contract and any contract extensions. The Awarded Contractor agrees to provide the purchased services at the costs, rates and fees as set forth in their proposal in response to this RFP. No other costs, rates or fees shall be payable to the Awarded Contractor for implementation of their proposal.

19. The City is not liable for any costs incurred by Proposers prior to entering into a formal contract. Costs of developing the proposals or any other such expenses incurred by the Proposer in responding to the RFP, are entirely the responsibility of the Proposer, and shall not be reimbursed in any manner by the City.

20. Proposal will become public record after the conclusion of the negotiation process and before final approval by the awarding body unless the proposal or specific parts of the proposal can be shown to be exempt by law. Each Proposer may clearly label all or part of a proposal as "CONFIDENTIAL" provided that the Proposer thereby agrees to indemnify and defend the City for honoring such a designation. The failure to so label any information that is released by the City shall constitute a complete waiver of any and all claims for damages caused by any release of the information.

21. A proposal submitted in response to this RFP must identify any subcontractors, and outline the contractual relationship between the Proposer and each subcontractor.

An official of each proposed subcontractor must sign, and include as part of the proposal submitted in response to this RFP, a statement to the effect that the subcontractor has read and will agree to abide by the Proposer’s obligations.

22. If the Contractor elects to use subcontractors, the City requires that the Awarded

Contractor provide proof of payment of any subcontractors used for this project.

Proposals shall include a plan by which the City will be notified of such payments.

23. Each Proposer must disclose any existing or potential conflict of interest relative to the performance of the contractual services resulting from this RFP. Any such relationship that might be perceived or represented as a conflict should be disclosed.

The City reserves the right to disqualify any Proposer on the grounds of actual or apparent conflict of interest.

24. Each Proposer must include in its proposal a complete disclosure of any alleged significant prior or ongoing contract failures, any civil or criminal litigation or investigation pending which involves the Proposer or in which the Proposer has been judged guilty or liable. Failure to comply with the terms of this provision will disqualify any proposal. The City reserves the right to reject any proposal based upon the Proposer’s prior history with the City or with any other party, which documents, without limitation, unsatisfactory performance, adversarial or contentious demeanor, significant failure(s) to meet contract milestones or other contractual failures.

25. The City reserves the right to negotiate final contract terms with any Proposers selected. The contract between the parties will consist of the RFP together with any modifications thereto, and the Awarded Contractor’s proposal, together with any modifications and clarifications thereto that are submitted at the request of the City during the evaluation and negotiation process. In the event of any conflict or contradiction between or among these documents, the documents shall control in the following order of precedence: the final executed contract, the RFP, any modifications and clarifications to the Awarded Contractor’s proposal, and the

Awarded Contractor’s proposal. Specific exceptions to this general rule may be noted in the final executed contract.

26. The City will not be responsible for or bound by any oral communication or any other information or contact that occurs outside the official communication process specified herein, unless confirmed in writing by the City Contact.

27. Any contract resulting from this RFP shall not be effective unless and until approved by the City Council / City Manager, as applicable.

28. The City will not be liable for Federal, State, or Local excise taxes.

29. Execution of Attachment A of this RFP shall constitute an agreement to all terms and conditions specified in the RFP, including all contract terms and conditions therein, except such terms and conditions that the Proposer expressly excludes.

30. Proposer understands and acknowledges that the representations above are material and important, and will be relied on by the City in evaluation of the proposal.

Any Proposer misrepresentation shall be treated as fraudulent concealment from the City of the true facts relating to the proposal.

31. Proposals shall be kept confidential through the negotiation process.

32. No announcement concerning the award of a contract as a result of this RFP may be made without the prior written approval of the City.

Proposers are advised that any contract awarded pursuant to this procurement process that exceeds $100,000 shall be subject to the applicable provisions of Long

Beach Municipal Code Section 2.73 et seq, the Equal Benefits Ordinance.

33. All Proposers shall complete and return, with their bid, the Equal Benefits Ordinance

Compliance form contained in Attachment B, if applicable. Unless otherwise specified in the procurement package, Proposers do not need to submit with their bid supporting documentation proving compliance. However, supporting documentation verifying that the benefits are provided equally shall be required if the proposer is selected for award of a contract.

5.3 Contract Terms & Conditions

1. The Awarded Contractor will be the sole point of contract responsibility. The City will look solely to the Awarded Contractor for the performance of all contractual obligations which may result from an award based on this RFP, and the Awarded

Contractor shall not be relieved for the non-performance of any or all subcontractors.

2. The Awarded Contractor must maintain, for the duration of its contract, insurance coverages as required by the City. Work on the contract shall not begin until after the Awarded Contractor has submitted acceptable evidence of the required insurance coverages. As a condition precedent to the effectiveness of this contract, Contractor shall procure and maintain at Contractor’s expense for the duration of this contract from an insurance company that is admitted to write insurance in the

State of California or that has a rating of or equivalent to an A:VIII by A.M. Best and

Company the following insurance:

a. Commercial general liability insurance equivalent in coverage scope to ISO CG

00 01 10 93 naming the City of Long Beach and its officials, employees, and agents as additional insureds on a form equivalent in coverage scope to ISO

CG 20 10 11 85 from and against claims, demands, causes of action, expenses, costs, or liability for injury to or death of persons, or damage to or loss of property arising out of activities or work performed by or on behalf of the

Contractor in an amount not less than One Million Dollars (US $1,000,000) per occurrence and Two Million Dollars (US $2,000,000) in general aggregate. Such insurance shall not exclude coverage for liability resulting from cross liability protection.

b. Workers’ compensation coverage as required by the Labor Code of the State of

California and Employer’s liability insurance with minimum limits of One

Million Dollars (US $1,000,000) per accident or occupational illness. The policy shall be endorsed with a waiver of the insurer’s right of subrogation against the City of Long Beach and its insurers, officials, employees, and agents.

c. If use of a vehicle is part of the scope of services, commercial automobile liability insurance equivalent in coverage scope to ISO CA 00 01 06 92 in an amount not less than Five Hundred Thousand Dollars (US $500,000) combined single limit (CSL) covering Symbol 1 (“any auto”).

Any self-insurance program or self-insurance retention must be approved separately in writing by City and shall protect the City of Long Beach and its officials, employees, and agents in the same manner and to the same extent as they would have been protected had the policy or policies not contained retention provisions. Each insurance policy shall be endorsed to state that coverage shall not be suspended, voided, or canceled by either party except after thirty (30) days prior written notice to City, and shall be primary and not contributing to any other insurance or self-insurance maintained by City.

Any subcontractors which Contractor may use in the performance of this contract shall be required to indemnify the City to the same extent as the Contractor and to maintain insurance in compliance with the provisions of this section.

Contractor shall deliver to City certificates of insurance and original endorsements for approval as to sufficiency and form prior to the start of performance hereunder. The certificates and endorsements for each insurance policy shall contain the original signature of a person authorized by that insurer to bind coverage on its behalf. “Claims-made” policies are not acceptable unless

City Risk Manager determines that “Occurrence” policies are not available in the market for the risk being insured. If a “Claims-made” policy is accepted, it must provide for an extended reporting period of not less than three (3) years. Such insurance as required herein shall not be deemed to limit Contractor’s liability relating to performance under this contract. City reserves the right to require complete certified copies of all said policies at any time. Any modification or waiver of the insurance requirements herein shall be made only with the approval of City Risk Manager. The procuring of insurance shall not be construed as a limitation on liability or as full performance of the indemnification provisions of this contract.

3. The Long Beach Municipal Code (LBMC) requires all businesses operating in the City of Long Beach to pay a business license tax. In some cases, the City may require a regulatory permit and/or evidence of a State or Federal license. Prior to issuing a business license, certain business types will require the business license application and/or business location to be reviewed by the Development Services, Fire, Health, and/or Police Departments. Additional information is available at www.longbeach.gov/finance/business_license.

4. All work performed in connection with construction shall be performed in compliance with all applicable laws, ordinances, rules and regulations of federal, state, county or municipal governments or agencies (including, without limitation, all applicable federal and state labor standards, including the prevailing wage provisions of

Sections 1770 et seq. of the California Labor Code), and (b) all directions, rules and regulations of any fire marshal, health officer, building inspector, or other officer of every governmental agency now having or hereafter acquiring jurisdiction.

5. Awarded Contractor shall indemnify, protect and hold harmless City, its Boards, Commissions, and their officials, employees and agents (“Indemnified Parties”), from and against any and all liability, claims, demands, damage, loss, obligations, causes of action, proceedings, awards, fines, judgments, penalties, costs and expenses, including attorneys’ fees, court costs, expert and witness fees, and other costs and fees of litigation, arising or alleged to have arisen, in whole or in part, out of or in connection with (1) Awarded Contractor’s breach or failure to comply with any of its obligations contained in this Contract, including any obligations arising from the http://www.longbeach.gov/finance/business_license

Awarded Contractor’s compliance with or failure to comply with applicable laws, including all applicable federal and state labor requirements including, without limitation, the requirements of California Labor Code Section 1770 et seq. or (2) negligent or willful acts, errors, omissions or misrepresentations committed by

Awarded Contractor, its officers, employees, agents, subcontractors, or anyone under Awarded Contractor’s control, in the performance of work or services under this Contract (collectively “Claims” or individually “Claim”).

6. In addition to Awarded Contractor’s duty to indemnify, Awarded Contractor shall have a separate and wholly independent duty to defend Indemnified Parties at Awarded

Contractor’s expense by legal counsel approved by City, from and against all Claims, and shall continue this defense until the Claims are resolved, whether by settlement, judgment or otherwise. No finding or judgment of negligence, fault, breach, or the like on the part of Awarded Contractor shall be required for the duty to defend to arise. City shall notify Awarded Contractor of any Claim, shall tender the defense of the Claim to Awarded Contractor, and shall assist Awarded Contractor, as may be reasonably requested, in the defense.

7. If a court of competent jurisdiction determines that a Claim was caused by the sole negligence or willful misconduct of Indemnified Parties, Awarded Contractor’s costs of defense and indemnity shall be (1) reimbursed in full if the court determines sole negligence by the Indemnified Parties, or (2) reduced by the percentage of willful misconduct attributed by the court to the Indemnified Parties.

8. Any requests for reasonable price adjustments must be submitted 60 days prior to the Contract annual anniversary date. Requests for adjustment in cost of labor and/or materials must be justified based upon verifiable criteria such as the

Consumer Price Index, US City Averages, or other relevant indices.

9. If the Awarded Contractor elects to use subcontractors, Awarded Contractor agrees to require its subcontractors to indemnify Indemnified Parties and to provide insurance coverage to the same extent as Awarded Contractor.

10. If the Awarded Contractor elects to use subcontractors, the Awarded Contractor shall not allow any subcontractor to commence work until all insurance required of subcontractor is obtained.

11. The provisions of this section shall survive the expiration or termination of this

Contract.

12. Awarded Contractor agrees that all public work (as defined in California Labor Code section 1720) performed in relation to this Project (the “Public Work”), if any, shall comply with the requirements of California Labor Code sections 1770 et seq. If there is a difference between the general prevailing wage rates determined by the Director of the Department of Industrial Relations and the applicable minimum wage rates determined by the Secretary of Labor (federal) for similar classifications of work, the

Contractor and its Subcontractor of every tier shall pay their workers not less than the higher wage rate. Contractors are required to pay at least the California minimum wage for the basic hourly rate in all cases where the published prevailing wage rate is below the California minimum wage. Any and all employer payments required by the prevailing wage determinations must also be paid. If the California minimum wage is increased in the future to an amount above that shown in the prevailing wage determination, the basic hourly rate in that determination automatically increases to the new minimum wage.

In all bid specifications, contracts and subcontracts for any such Public Work, Awarded Contractor shall obtain the general prevailing rate of per diem wages and the general prevailing rate for holiday and overtime work in this locality for each craft, classification or type of worker needed to perform the Public Work, and shall include such rates in the bid specifications, contract or subcontract, and post them at each job site. Such bid specifications, contract or subcontract must contain the following provision: “It shall be mandatory for the Awarded Contractor to pay not less than the said prevailing rate of wages to all workers employed by the Awarded Contractor in the execution of this contract. The Awarded Contractor expressly agrees to comply with the penalty provisions of California Labor Code section 1775 and the payroll record keeping requirements of California Labor Code section 1776.” Copies of the prevailing rate of per diem wages are on file at the Labor Compliance Office of City

Hall, which shall be made available to any interested party on request

5.4 Protest Procedures

Who May Protest

Only a Proposer who has actually submitted a proposal is eligible to protest a contract awarded through a Request for Proposals (RFP). A Proposer may not rely on the protest submitted by another Proposer but must pursue its own protest.

Time for Protest

The City will post a notice of the intent to award a contract at least ten (10) business days before an award is made. The notice will be available to all Proposers who submitted a proposal via the City’s electronic bid notification system at http://www.longbeach.gov/purchasing. A Proposer desiring to submit a protest for a proposal must do so within five (5) business days of the electronic notification of intent to award. The City Purchasing Agent must receive the protest by the close of business on the fifth (5th) business day following posting of notification of intent to award the contract.

Proposers are responsible for registering with the City’s electronic bid notification system and maintaining an updated Contractor profile. The City is not responsible for Proposers’ failure to obtain notification for any reason, including but not limited to failure to maintain updated email addresses, failure to open/read electronic messages and failure of their own computer/technology equipment. The City’s RFP justification memo will be available for review by protestors once the notification of intent to award has been posted via the City’s electronic bid notification system.

Form of Protest

The protest must be in writing and signed by the individual who signed the proposal or, if the Proposer is a corporation, by an officer of the corporation, and addressed to the City

Purchasing Agent. Protests must be submitted via the email address above. They must include a valid email address and phone number. Protests must set forth a complete and detailed statement of the grounds for the protest and include all relevant information to support the grounds stated, and must refer to specific portions of the RFP and attachments upon which the protest is based. Once the protest is received by the City Purchasing Agent, the City will not accept additional information on the protest unless the City requests it.

City Response to Protest

The City Purchasing Agent or designee will respond with a decision regarding the protest within five (5) business days of receipt of protest to the email address provided in the protest. This decision shall be final.

Limitation of Remedy

The procedure and time limits set forth herein are mandatory and are the Proposer’s sole and exclusive remedy in the event of a protest. The Proposer’s failure to comply with these procedures shall constitute a waiver of any right to further pursue a protest, including filing a Government Code Claim or initiation of legal proceedings.