RFP Amendment No 2_9.30.2025.pdf
PDF 142 KB Posted
- Attached to
- INDISTRIAL AIR COMPRESSOR, AIR DRYER, AND VACCUM PUMP SYSTEM MAINTENANCE AND REPAIR SERVICES
- Solicitation number
- S-10700-00014813
- Issued by
- Clackamas County, Oregon
About this file
This document is Amendment No. 2 to a Request for Proposal (RFP) No. S-10700-00014813 for Industrial Air Compressor, Air Dryer, and Vacuum Pump System Maintenance and Repair Services. The amendment extends the proposal due date and opening of proposals to Thursday, November 13, 2025 at 4:00 PM PT, and adds two new attachments (Floor Plan and Equipment Location No. 1 and No. 2). The revised schedule includes key dates such as a Pre-Proposal Conference on 10/13/2025, questions/clarification requests due on 10/15/2025, and an approximate Notice of Intent to Award on 11/17/2025.
Potential bidders must submit protests to this amendment by Tuesday, October 7, 2025, at 4:00 PM PT, following the same procedure outlined in the original RFP section 4.4.2. Any questions regarding the amendment should be directed to the Solicitation Point of Contact (SPC) listed on the RFP cover page. The amendment provides updated timeline information and adds supplemental attachments to support the bidding process for the industrial equipment maintenance and repair services contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment F - COBID Business Outreach Plan.docx | DOCX document | |
| Attachment A - Sample Contract~2.docx | DOCX document | |
| Attachment H - Key Persons Resumes and Applicable Credentials~1.docx | DOCX document | |
| RFP No. S-10700-00014813.pdf | ||
| Attachment G - Responsibility Inquiry~1.docx | DOCX document | |
| Attachment I - Floor Plan and Equipment Location No. 1~1.pdf | ||
| Attachment E - Price Proposal Form.docx | DOCX document | |
| Attachment B - Disclosure Exemption Affidavit~2.docx | DOCX document | |
| Gear-Apparel Store.pdf | ||
| Attachment C - Proposer Information and Certification Sheet.docx | DOCX document | |
| RFP Amendment No 1_9.25.2025.pdf | ||
| Attachment J - Floor Plan and Equipment Location No. 2.pdf | ||
| Attachment D - Reference Check Form~1.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP NO. S-10700-00014813 INDUSTRIAL AIR COMPRESSOR, AIR DRYER, AND VACUUM PUMP SYSTEM
MAINTENANE AND REPAIR SERVICES
RFP NO. S-10700-00014813– AIR COMPRESSOP, AIR
DRYER, AND VACUUM PUMP SYSTEM MAINTENANCE AND
REPAIR SERVICES – AMENDMENT NO. 2
SECTION 1: PURPOSE
The purpose of this Amendment is: to extend the Opening (Proposal Due), and the Opening of Proposals to Thursday, November 13, 2025 @ 4:00 PM PT. And to add two additional Attachments to the RFP.
1.1 MODIFICATION OF SECTION 1.2 SCHEDULE
SECTION 2: MODIFICATIONS
Section 1.2 SCHEDULE is modified as follows. New language is indicated by bold underlined font, deleted language is indicated by strikethrough font.
Event Date Time
Pre-Proposal Conference 10/13/2025 10:00 AM PT
Questions / Requests for Clarification Due 10/15/2025 4:00 PM PT
Answers to Questions / Requests for Clarification Issued (approx.) 10/20/2025 4:00 PM PT
RFP Protest Period Ends 09/30/2025 4:00 PM PT
Opening (Proposal Due) 10/29/2025 11/13/2025
4:00 PM PT
Opening of Proposal 10/29/2025 11/13/2025
4:00 PM PT
Issuance of Notice of Intent to Award (approx.) 11/17/2025 4:00 PM PT
Award Protest Period Ends 11/25/2028 4:00 PM PT
List of Attachments is modified as follows:
ATTACHMENT I FLOOR PLAN AND EQUIPMENT LOCATION NO. 1
ATTACHMENT J FLOOR PLAN AND EQUIPMENT LOCATION NO. 2
RFP NO. S-10700-00014813 INDUSTRIAL AIR COMPRESSOR, AIR DRYER, AND VACUUM PUMP SYSTEM
MAINTENANE AND REPAIR SERVICES
SECTION 3: PROTEST
Protests to this addendum must be submitted in the same manner required in RFP section
4.4.2 Protest to Amendment(s) and are due by Tuesday, October 7, 2025, by 4:00 PM
PT.
Any questions regarding this Amendment No. 2 must be directed to the SPC as listed on the cover page of the RFP.
| SECTION 1: PURPOSE |
| SECTION 2: MODIFICATIONS |
| SECTION 3: PROTEST |
File details come from the government source that posted it. Updated .