About this file

This is a Request for Proposal (RFP) #378469-RK issued by Fermi Forward Discovery Group, LLC (FFDG) on behalf of Fermi National Accelerator Laboratory (Fermilab/FNAL), a Department of Energy facility. FFDG seeks a subcontractor to fabricate, assemble, test, and deliver PIP-II BTL Collimator steel plates in accordance with specifications in the Statement of Work (Exhibit A) and drawing package (Exhibit B, available upon request). The NAICS code is 332312 (Fabricated Structural Metal Manufacturing) with a small business size standard of 500 employees. This is an unrestricted acquisition with no set-aside provisions. A small business subcontracting plan is required if the awardee exceeds $750,000 and does not meet the small business definition. The proposal deadline is March 20, 2026, at 2:00 P.M. CST, with a question submission deadline of March 6, 2026, directed to Procurement Specialist Richard Konan at rkonan@fnal.gov or (630) 840-2835.

The pricing structure is firm-fixed-price with a 90-day validity period from the proposal due date. Offerors must submit unit pricing using the provided Excel Bid Form (Exhibit H) and complete the Price Proposal Form (Exhibit C), identifying any shipping costs and delivery dates. Domestic vendors should provide FOB Destination pricing (Batavia, IL) including freight; non-domestic vendors should quote DAP per Incoterms 2020. No overhead, profit, surcharges, or handling costs are permitted in invoices; FFDG reimburses only actual costs (freight, pre-pay, add). Economic price escalation language is not accepted. All pricing must be submitted in USD with no currency conversion allowances. The award will be made to the lowest-priced, technically acceptable proposal. Required submissions include completed SARC (Exhibit E), PUR-466 certification (Exhibit F), and acknowledgment of any amendments. FFDG reserves the right to reject all proposals and cancel the solicitation without liability.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL (RFP)

#378469-RK

BTL COLLIMATOR STEEL PLATES

February 20, 2026

Table of Contents

1. INTRODUCTION

2. INVITATION TO SUBMIT PROPOSAL

3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND

SMALL BUSINESS SUBCONTRACTING PLAN

4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION PERIOD ... 2

5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD

6. AMENDMENT OF SOLICITATION

7. PROPOSAL DUE DATE

8. LATE SUBMISSION

9. EXCEPTIONS AND DEVIATIONS

10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS

11. ORDER OF PRECEDENCE

12. SUBCONTRACT AWARD

13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS

14. DESCRIPTION OF WORK

15. DELIVERY TERMS

16. RESTRICTION ON DISCLOSURE AND USE OF DATA

17. EXHIBITS

The following requirements must be adhered to for the Offeror’s submission of Proposals to Fermi Forward Discovery Group, LLC (FFDG) in support of this specific requirement.

1. INTRODUCTION

Fermi National Accelerator Laboratory (Fermilab or FNAL), managed and operated by Fermi Forward Discovery Group, LLC (FFDG) under the prime contract with the U.S.

Department of Energy (DOE), is seeking to subcontract for the fabrication, assembly, testing, and delivery of PIP-II BTL Collimator steel plates, in accordance with the requirements set forth in this Request for Proposal (RFP) and the Statement of Work (SOW), Exhibit A.

2. INVITATION TO SUBMIT PROPOSAL

You are invited to submit a proposal for the items specified in this Request for Proposal (RFP), by the provisions contained herein, and the terms and conditions of the proposed firm-fixed price subcontract entered into as a result of this solicitation.

3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE

AND SMALL BUSINESS SUBCONTRACTING PLAN

This acquisition is unrestrictive and contains no set-aside provisions. The North American Industry Classification System (NAICS) code for this solicitation is 332312 - Fabricated Structural Metal Manufacturing. The small business size standard for this NAICS code is 500 employees.

A small business subcontracting plan will be required should the awardee not meet the definition of a small business as described in the paragraph above, and the subcontract exceed $750,000.00. The Subcontracting Plan shall follow the Federal Acquisition Clause, 52.219-9, Small Business Subcontracting Plan (See Exhibit D. FL-55 - Small Business Subcontracting Plan). A draft plan must be submitted with your RFP response.

4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION

PERIOD

The prospective offeror should examine and review the solicitation with care. Any prospective offeror who has questions or desires an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing by 2:00 P.M. CST, March 6, 2026, and be submitted to the Procurement Specialist at the email address identified on the Request for Proposal Form and below. Oral explanations or instructions given before the award of a subcontract will not be binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation if that information is necessary for submitting proposals or if the lack of the information would be prejudicial to other prospective offerors.

Any and all changes to these specifications are valid only if they are included by a written addendum and shall become a part of the subcontract.

All questions concerning this RFP should be submitted in email form and directed to the Procurement Specialist identified below.

Procurement Specialist: Richard Konan Phone: (630) 840-2835 Email: rkonan@fnal.gov

Fermi Forward Discovery Group, LLC Procurement Department Kirk Road & Wilson Street Batavia, IL 60510-0500

5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD

All offerors are prohibited from making any contact (including sales calls) with officials or employees of FFDG (collectively “FFDG personnel”) with regard to the request for proposals, other than in the manner and to the persons designated herein, until after an award has been made. The Chief Procurement Officer or their designee reserves the right to disqualify any offeror found to have contacted FFDG personnel in any manner regarding the proposal request.

6. AMENDMENT OF SOLICITATION

FFDG may, by addenda/amendment, modify any provision or part of this RFP at any time before the award of any resultant subcontract. All terms and conditions that are not modified remain unchanged.

An offeror shall acknowledge receipt of any addenda/amendments to this RFP. Failure to acknowledge may result in the disqualification of an offeror’s proposal with no further consideration for an award. The acknowledgment shall be provided in one of the following ways:

• Immediately upon receipt of the amendment via an email sent to the FFDG Procurement

Specialist.

• Return of the Amendment with a signature on the acknowledgment signature line; or

• In the offeror’s proposal.

7. PROPOSAL DUE DATE

The offeror’s proposal shall be emailed to the Procurement Specialist no later than 2:00 P.M. CST, March 20, 2026. Partial or incomplete proposals [including required documents (e.g. project timeline, examples of prior work, references, submission of the Request for Proposal Form)] may be considered non-responsive and will not be considered for an award.

8. LATE SUBMISSION

mailto:rkonan@fnal.gov

Proposals received by FFDG after the Submittal Date and Time indicated may not be considered. The Respondent assumes the risk of the method of dispatch chosen.

9. EXCEPTIONS AND DEVIATIONS

Any exceptions to the General Terms and Conditions identified herein MUST be documented on a separate sheet on the Offeror’s Letterhead with your proposal submission. Exceptions to FFDG’s Terms and Conditions MUST be clearly and completely indicated on a company letterhead. FFDG is not required to accept any exceptions or deviations.

Any exceptions or additional terms noted on a Quote Form will not be considered and are hereby expressly rejected. Likewise, any references—whether through language or hyperlink—to additional terms and conditions are not accepted and are similarly rejected.

Offerors taking exceptions, deviations, or conditional assumptions to the specifications provided herein must clearly identify and explain each exception/deviation, or conditional assumption taken with sufficient amplification and justification to permit evaluations. Such exceptions, deviations, or conditional assumptions will not themselves automatically cause a proposal to be deemed unacceptable to FFDG. However, a large number of exceptions or one or more significant exceptions not providing benefit to FFDG may result in the rejection of the offeror’s proposal as unacceptable.

NOTE TO OFFERORS: Please be advised that any exceptions to the specifications or to FFDG’s terms and conditions may cause your proposal to be disqualified.

10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS

The offeror may submit modifications to its proposal at any time before the solicitation closing date and time and may submit modifications in response to an amendment or to correct a mistake at any time before award.

Proposals may be withdrawn at any time before the submission deadline. Withdrawals are effective upon receipt of notice by the Procurement Specialist.

11. ORDER OF PRECEDENCE

Where there appear to be variances or conflicts, the following order of precedence shall prevail: FFDG’s drawings (if applicable), FFDG’s Statement/Scope of Work, and the RFP General Terms and Conditions.

12. SUBCONTRACT AWARD

Issuance of the RFP does not compel FFDG to make an award. FFDG reserves the right to accept or reject all proposals if that is determined to be in its best interest. A decision may be made without discussion; hence, an offeror’s proposal should be submitted initially on the most favorable terms. The proposed award is based on a continuing program requirement and the issuance of obligation authority from the Procurement Department of the Fermi National Accelerator Laboratory (FNAL). Any subsequent award issued by

FFDG shall be constituted in writing by authorized representatives of the Procurement Department of the FNAL.

No other representatives of FFDG are authorized to issue contracts or agreements or bind FFDG to any form of agreement or understanding. The authorized Procurement Department official of the FNAL is the only individual who can legally commit FFDG to the expenditure of funds in connection with this proposed procurement.

13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS

This is a lowest price-technically acceptable source selection. An award shall be made to the lowest evaluated proposal that meets or exceeds the acceptability standards for non-cost factors, including past performance. FFDG shall be the sole determiner of what is deemed to be technically acceptable.

FFDG reserves the right to cancel this solicitation at any time without incurring any liability or damages associated with such cancellation.

Under no circumstances shall FFDG be responsible for any proposal preparation expenses, submission costs, or any other expenses, costs, or damages, of whatever nature, incurred as a result of an offeror’s participation in this RFP process. The Offeror understands and agrees that it submits its proposal at its own risk and expense and releases FFDG from any claim for damages or other liability arising out of the RFP and award process.

FFDG shall not be liable for any errors in the offeror’s proposal submission. Except during negotiations initiated by FFDG, no modifications to the proposal shall be accepted from the offeror after the Submittal Date. The offeror is responsible for a careful review of their entire proposal to ensure that all information, including pricing, is correct and complete.

Offerors are liable for all errors or omissions contained in their proposals.

FFDG reserves the right to award a subcontract only to responsive and responsible proposers. Responsive offers are defined as a proposal that meets all of the minimum requirements (e.g. submits all required documents, meets minimum years requirement, etc.).

Responsible proposers are defined as companies that demonstrate the financial ability, resources, skills, capability, willingness, and business integrity necessary to perform on the subcontract. FFDG shall be the sole determiner of whether an offer or Offeror is considered responsive and/or responsible.

Any information of a proprietary nature shall be CLEARLY MARKED and identified in the offeror’s submission.

13.1 Price Proposal

The offeror shall provide unit pricing for BTL collimator steel plates using the Excel Bid Form (Exhibit H). In addition, the offeror shall complete Exhibit C, Price Proposal Form.

In the Price Proposal Form, the offeror shall provide the total calculated on Excel Bid Form (Exhibit H). The offeror shall identify shipping costs, if applicable, and the delivery date of the items upon receipt of an award.

13.1.1 Exhibit H – Excel Bid Form

Due to the significant number of individual items under this RFP, an Excel Unit Pricing Sheet has been created for submission. The Unit Pricing Sheet is restricted, but will allow entry in Columns F and H, and in the Vendor Name field, Row 4.

To ensure accuracy, Column G will self-calculate, based on the price entered into Column F.

13.1.2 Exhibit C – Price Proposal Form

Please transfer the total value calculated in cell G113 of Excel Bid Form ( Exhibit H) to the Excel Bid Form provided herein. Additionally, on this sheet, please identify any shipping costs not included in the unit pricing. Finally, please identify the proposed delivery date after an award is made.

FFDG understands some items may have longer lead times. Therefore, please document any extended lead times on Exhibit H – Excel Bid Form. If there are no extended lead times for any of the items, please leave Column H on Exhibit H – Unit Pricing Sheet blank.

The proposed pricing shall be a firm-fixed price for the items as identified herein, and the price proposal shall be valid for 90 days from the final proposal due date. An Offeror allowing less than the minimum acceptance period as identified herein may be rejected without further consideration for an award.

All pricing must be submitted in USD, and no allowances for currency conversion shall be made during the term of the subcontract.

Economic price escalation language will not be accepted or considered.

FFDG may consider a proposal nonresponsive if the prices proposed are materially unbalanced. A proposal is considered materially unbalanced when the price of one or more line items in a submission is significantly overstated or understated, even though the total price may be acceptable when reviewing using cost or price analysis techniques.

This would include a reasonable doubt that the proposal will result in the lowest overall cost to FFDG, even if it is the lowest evaluated proposal, or if it is so unbalanced as to be tantamount to an advance payment.

When applicable, FFDG will reimburse the subcontractor for actual costs incurred (e.g., freight, pre-pay, and add). No allowance shall be made for overhead and profit; any invoice containing overhead, profit, surcharges, handling costs, etc., will be rejected.

The proposed pricing of the assemblies in accordance with the specifications as defined in the SOW (Exhibit A) shall be included on the Request For Proposal Form provided herein. THE OFFEROR MUST SUBMIT THEIR PRICING

USING THE FORM PROVIDED HEREIN.

If a subcontract is awarded to the offeror, payment shall be issued upon delivery, inspection, testing (if applicable) and acceptance of each assembly as defined on the Request for Proposal Form, pursuant to the General Terms and Conditions, and the Statement of Work as identified herein.

The proposed pricing shall be a firm-fixed price for the work as identified herein, and the price proposal shall be valid for 90 days from the final proposal due date.

An Offeror allowing less than the minimum acceptance period as identified herein may be rejected without further consideration for an award.

All pricing must be submitted in USD, and no allowances shall be made for currency conversion during the term of the subcontract.

Economic price escalation language will not be accepted or considered.

FFDG may consider a proposal nonresponsive if the prices proposed are materially unbalanced. A proposal is considered materially unbalanced when the price of one or more line items in a submission is significantly overstated or understated, even though the total price may be acceptable when reviewing using cost or price analysis techniques. This would include a reasonable doubt that the proposal will result in the lowest overall cost to FFDG, even though it may be the lowest evaluated proposal, or if it is so unbalanced as to be tantamount to allowing an advance payment.

When applicable, FFDG will reimburse the subcontractor for actual costs (e.g., freight, pre-pay and add) incurred. No allowance shall be made for overhead and profit; any invoice containing overhead, profit, surcharges, handling costs, etc., will be rejected.

13.2 Duties/Tariffs

FFDG recognizes that international shipments may be subject to additional charges related to duties and tariffs. Shipping terms shall be DAP with the Subcontractor responsible for all shipping and handling costs to Batavia, Illinois. FNAL will be responsible for payment of duties. FNAL will provide its designated customers broker information to the Subcontractor following award and prior to shipment.

13.3 Milestone Payments

FFDG may, at its discretion, consider milestone payments as part of the award determination process. If an offeror proposes milestone payments, such requests must be clearly identified in the original pricing proposal and accompanied by detailed terms and justification. Milestone payments will be evaluated as part of the overall proposal review.

FFDG reserves the right to accept or decline milestone payments based on what is determined to be in the best interest of FNAL. FNAL may reject any proposal that includes milestone payments if such terms are determined to introduce undue risk, administrative burden, or misalignment with project objectives.

13.4 Subcontractor Annual Representations & Certifications (SARC), Form SARC

The SARC certification submitted by the successful Offeror will be incorporated into the subsequent subcontract. If an offering entity is a joint venture, association, consortia, or partnership, each member entity must submit an individual Representations and Certifications Form (Exhibit E). The Form SARC must be submitted as a separate file.

13.5 Proposal Certifications, Form PUR-466

The PUR-466 certification submitted by the successful Offeror will be incorporated into the subsequent subcontract. All sections are required to be completed and must be signed by a company official (Exhibit F). The Form PUR-466 must be submitted as a separate file.

14. DESCRIPTION OF WORK

The selected subcontractor shall provide all labor, materials, tools, equipment, and supervision required to complete all fabrications and assemblies as defined as follows:

• Exhibit A: BTL Collimator SOW - Steel Plates Procurement Specification

• Exhibit B: Drawing Package (Provided Upon Request)

“Exhibit B: Drawing Package” will be provided upon request to the Procurement Specialist listed in Section 4.

The awarded offeror shall deliver the specified quantities of the fabricated assemblies in full compliance with the fabrication requirements outlined in the referenced specifications and drawings. All fabrication shall follow the approved quality assurance plan and will be subject to the acceptance criteria defined herein.

15. DELIVERY TERMS

The Offeror shall propose a schedule that meets the lead times as defined in the SOW (Exhibit A).

Delivery terms shall be FOB Destination Fermilab, Batavia, IL for domestic offerors, which shall include shipping/freight costs within their firm-fixed-price proposal submission.

Delivery terms shall be DAP Fermilab, Batavia IL per Incoterms 2020 for non-domestic vendors. Non-domestic offerors will be provided with FFDG’s Customs Clearance Broker Information upon subcontract award.

The Subcontractor shall handle and transport the assemblies to Fermilab site in strict adherence to the clauses in the SOW (Exhibit A).

The Offeror must include their shipping/freight costs on the Price Submission Sheet within their proposal.

16. RESTRICTION ON DISCLOSURE AND USE OF DATA

Offerors or quoters who include in their proposals or quotations data that they do not want to be disclosed to the public for any purpose or used by FFDG except for evaluation purposes, shall –

A. Mark the title page with the following legend:

“This proposal or quotation includes data that shall not be disclosed outside FFDG and shall not be duplicated, used, or disclosed – in whole or in part – for any purpose other than to evaluate this proposal or quotation. If, however, a subcontract is awarded to this Offeror or quoter as a result of – or in connection with – the submission of this data, FFDG shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting subcontract. This restriction does not limit FFDG’s right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets (insert numbers or other identification of sheets)”, and

B. Mark each sheet of data it wishes to restrict with the following legend “Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal or quotation.”

17. EXHIBITS

A. BTL Collimator SOW - Steel Plates Procurement Specification B. Drawings Package C. Price Proposal Form D. FFDG General Terms and Conditions For Supplies (08.2025) E. FL-55 – Small Business Subcontracting Plan F. Subcontractor Annual Representations & Certifications (SARC) G. PUR-466 Proposal Certifications H. Excel Bid Form

1. INTRODUCTION
2. INVITATION TO SUBMIT PROPOSAL
3. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE AND SMALL BUSINESS SUBCONTRACTING PLAN
4. EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS / QUESTION PERIOD
5. CONTACT WITH FFDG PERSONNEL/BLACKOUT PERIOD
6. AMENDMENT OF SOLICITATION
7. PROPOSAL DUE DATE
8. LATE SUBMISSION
9. EXCEPTIONS AND DEVIATIONS
10. OFFEROR’S MODIFICATION AND WITHDRAWAL OF PROPOSALS
11. ORDER OF PRECEDENCE
12. SUBCONTRACT AWARD
13. PREPARATION, SUBMISSION, AND EVALUATION OF PROPOSALS
14. DESCRIPTION OF WORK
15. DELIVERY TERMS
16. RESTRICTION ON DISCLOSURE AND USE OF DATA
17. EXHIBITS

File details come from the government source that posted it. Updated .