RFP_24_25-03_Brownfield_Remediation__Bid_Tabulation_Cost.pdf
PDF 204 KB Posted
- Attached to
- Brownfield Remediation for Fulton St. Complex
- Solicitation number
- RFP 24/25-03
- Issued by
- Seminole County, Florida
About this file
The document is a Solicitation Tabulation Sheet from the City of Sanford's Finance Department Purchasing Division for Brownfield Remediation at the Fulton St Complex, solicitation number IFB 24/25-03. The invitation to bid was issued on 5.29.25 with a 2:00 P.M. local time opening, seeking contractors for comprehensive brownfield remediation services. The project involves multiple line items including general conditions, site remediation, clean-up plan, mobilization, demobilization, preconstruction video, erosion control, clearing and grubbing, contaminated subsoil excavation and disposal, seeding, and post-remediation monitoring and testing.
Three vendors submitted bids: Cathcart Construction Company, DPS Construction, and Action Environmental, with total base bids ranging from $355,250 to $419,100. The solicitation includes 1,200 cubic yards of contaminated subsoil excavation, transport, and disposal, with unit prices varying between $153 and $190 per cubic yard. A note indicates that a bid from Buckeye Elm Contracting was received a day late and was not considered. The tabulation sheet provides a detailed breakdown of each vendor's pricing across various project components, allowing for a comprehensive comparison of the submitted proposals.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Sanford Finance Department |Purchasing Division IFB 24/25-03 300 N Park Ave Brownfield Remediation for Fulton St Complex Sanford, FL 32771 5.29.25 Telephone: (407) 688-5091 2:00 P.M. Local Time Fax: (407) 688-5021 Email: purchasing@sanfordfl.gov
VENDOR NAME→
Cathcart
Construction Company
DPS
Construction
Action Environment al
Solicitation Evaluation Category ↓ Units Quantity Unit Price Total Price Units Quantity Unit Price Total Price Units Quantity Unit Price Total Price
General Conditions LS 1 $17,500 $17,500 LS 1 $10,000 $10,000 LS 1 $10,000 $10,000 Final Site Remediation and Clean Up Plan LS 1 $9,000 $9,000 LS 1 $21,000 $21,000 LS 1 $18,500 $18,500 Mobilization LS 1 $50,000 $50,000 LS 1 $18,000 $18,000 LS 1 $62,500 $62,500 Demobilization, Cleanup, Record Drawings, Project Closeout
LS 1 $5,000 $5,000 LS 1 $24,000 $24,000 LS 1 $41,000 $41,000
Preconstruction Video LS 1 $1,800 $1,800 LS 1 $5,000 $5,000 LS 1 $6,000 $6,000 Erosion and Sediment Control LS 1 $14,000 $14,000 LS 1 $12,000 $12,000 LS 1 $95,000 $9,500 Clearing and Grubbing LS 1 $42,250 $42,250 LS 1 $18,000 $18,000 LS 1 $17,500 $17,500 Contaminated Subsoil Excavation, Transport, and Disposal
CY 1,200 $153 $183,300 CY 1200 $190 $228,000 CY 1200 $180 $216,000
Seeding and Mulching LS 1 $2,400 $2,400 LS 1 $10,000 $10,000 LS 1 $8,000 $8,000
Post Active Remediation Monitoring and Testing LS 1 $30,000 $30,000 LS 1 $25,000 $25,000 LS 1 $30,100 $30,100
TOTAL BASE BID $355,250 $371,000 $419,100
Solicitation Tabulation Sheet Form
OPENED BY: Frank Mascola VERIFIED BY: Marisol Ordoñez
Solicitation Number:
Solicitation Title Solicitation Opening Date:
Solicitation Opening Time:
Remarks: Buckeye Elm Contracting Bid Received a day. Not considered.
Sheet1
File details come from the government source that posted it. Updated .