This is a Solicitation Tabulation Sheet from the City of Sanford's Finance Department Purchasing Division for a Brownfield Remediation project at the Fulton St Complex, issued under Solicitation Number IFB 24/25-03. The solicitation was opened on 5.29.25 at 2:00 P.M. Local Time, with three vendors submitting bids: Cathcart Construction Company, DPS Construction, and Action Environmental. The project involves comprehensive site remediation activities including general conditions, final site clean-up, mobilization, demobilization, preconstruction video documentation, erosion and sediment control, clearing and grubbing, contaminated subsoil excavation and disposal, seeding and mulching, and post-active remediation monitoring and testing.
The bid tabulation reveals varying pricing structures across the three vendors, with total base bids ranging from $355,250 (Cathcart Construction Company) to $419,100 (Action Environmental). The most significant line item is contaminated subsoil excavation, transport, and disposal, priced between $153 and $190 per cubic yard, with a consistent quantity of 1,200 cubic yards across all bidders. A notable administrative detail is that a bid from Buckeye Elm Contracting was received a day late and was not considered for evaluation. The solicitation was opened by Frank Mascola and verified by Marisol Ordoñez, indicating a formal procurement process adhering to municipal bidding protocols.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Sanford Finance Department |Purchasing Division IFB 24/25-03 300 N Park Ave Brownfield Remediation for Fulton St Complex Sanford, FL 32771 5.29.25 Telephone: (407) 688-5091 2:00 P.M. Local Time Fax: (407) 688-5021 Email: purchasing@sanfordfl.gov
VENDOR NAME→
Cathcart
Construction Company
DPS
Construction
Action Environment al
Solicitation Evaluation Category ↓ Units Quantity Unit Price Total Price Units Quantity Unit Price Total Price Units Quantity Unit Price Total Price
General Conditions LS 1 $17,500 $17,500 LS 1 $10,000 $10,000 LS 1 $10,000 $10,000 Final Site Remediation and Clean Up Plan LS 1 $9,000 $9,000 LS 1 $21,000 $21,000 LS 1 $18,500 $18,500 Mobilization LS 1 $50,000 $50,000 LS 1 $18,000 $18,000 LS 1 $62,500 $62,500 Demobilization, Cleanup, Record Drawings, Project Closeout
LS 1 $5,000 $5,000 LS 1 $24,000 $24,000 LS 1 $41,000 $41,000
Preconstruction Video LS 1 $1,800 $1,800 LS 1 $5,000 $5,000 LS 1 $6,000 $6,000 Erosion and Sediment Control LS 1 $14,000 $14,000 LS 1 $12,000 $12,000 LS 1 $95,000 $9,500 Clearing and Grubbing LS 1 $42,250 $42,250 LS 1 $18,000 $18,000 LS 1 $17,500 $17,500 Contaminated Subsoil Excavation, Transport, and Disposal
CY 1,200 $153 $183,300 CY 1200 $190 $228,000 CY 1200 $180 $216,000
Seeding and Mulching LS 1 $2,400 $2,400 LS 1 $10,000 $10,000 LS 1 $8,000 $8,000
Post Active Remediation Monitoring and Testing LS 1 $30,000 $30,000 LS 1 $25,000 $25,000 LS 1 $30,100 $30,100
TOTAL BASE BID $355,250 $371,000 $419,100
Solicitation Tabulation Sheet Form
OPENED BY: Frank Mascola VERIFIED BY: Marisol Ordoñez
Solicitation Number:
Solicitation Title Solicitation Opening Date:
Solicitation Opening Time:
Remarks: Buckeye Elm Contracting Bid Received a day. Not considered.