RFP 1175 Wintonbury Hills Renovation Pricing Form October 2026 Rev. 2.pdf

PDF 168 KB Posted

Attached to
RFP 1175 Wintonbury Hill Golf Course - Bunker, Green & Tee Renovations
Solicitation number
RFP 1175
Issued by
Hartford County, Connecticut

About this file

This is a Pricing Form for RFP 1175, issued by the Town of Bloomfield, Connecticut, for bunker, green, and tee renovation work at Wintonbury Hills Golf Course. The scope of work includes reconstruction and renovation of approximately 20,445 square feet of existing sand bunkers, construction of 4,265 square feet of new bunkers, renovation of the putting green on Hole #16, and construction and expansion of selected tees including new back tees on Holes #15 and #18. The project encompasses associated grading, drainage improvements, irrigation adjustments, tree clearing, and grassing and sodding of all disturbed areas. The pricing form itemizes quantities and unit costs for mobilization, general conditions, surveys, bunker sand removal and stockpiling, bunker fill-in, sod work, bunker construction and edging, bunker lining with JM Evalith and Capillary Concrete, bunker sand purchase and placement, drainage pipe installation, green renovation work, and tee construction. Proposals were due November 5, 2026 at 1:00 p.m., with questions due October 19, 2026 by 4:00 p.m. A non-mandatory site walk was scheduled for October 26, 2026 at 10:00 a.m. Work is scheduled to begin and complete in late summer/early fall 2027. Contractors must provide one original and two copies of proposals plus a read-only thumb drive copy.

The pricing form indicates that all unit costs and amounts have been left blank for contractor completion, with the exception of Irrigation Adjustments listed at a fixed allowance of $5,000.00, resulting in a total shown as $5,000.00. All proposal costs must remain valid for 120 days following bid opening. Payment is structured as monthly progress-based payments with 5% retainage until substantial completion and net 45 days thereafter. Contractors must carry Commercial General Liability insurance ($1 million per occurrence/$2 million aggregate), Auto Liability ($1 million combined single limit), Workers Compensation (statutory), and Professional Liability ($2 million single limit) within ten days of selection. A one-year warranty period from final acceptance applies. Contractors must demonstrate experience with Capillary Flow and JM Evalith liner systems, golf course drainage, and provide positive references for similar projects completed within the past five years.

View the file

Other files

File Type Posted
RFP 1175 - QandA Addendum.pdf PDF
RFP 1175_Nov_27_26_solicitation_doc.pdf PDF
RFP 1175_Nov_6_26_solicitation_doc.pdf PDF
RFP 1175_Nov_13_26_solicitation_doc.pdf PDF
RFP 1175_Nov_20_26_solicitation_doc.pdf PDF
RFP 1175_Nov_17_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_RFP 1175_v2_Oct_26_26.pdf PDF
RFP 1175_Nov_5_26_solicitation_doc.pdf PDF
RFP 1175_Nov_4_26_solicitation_doc.pdf PDF
RFP 1175_Nov_24_26_solicitation_doc.pdf PDF
RFP 1175_Nov_10_26_solicitation_doc.pdf PDF
RFP 1175 WHGC_Cap-con w JM Evalith Bunker Liner Detail 24Jan24.pdf PDF
RFP 1175_Nov_19_26_solicitation_doc.pdf PDF
RFP 1175 - WHGC Bunker_Green_and Tee Renovation.pdf PDF
RFP 1175 WHGC Bunker Renovation and Tee Expansion Plan 18July26.pdf PDF
RFP 1175_Nov_12_26_solicitation_doc.pdf PDF
RFP 1175_Nov_11_26_solicitation_doc.pdf PDF
RFP 1175_Nov_2_26_solicitation_doc.pdf PDF
RFP 1175_Oct_6_26_solicitation_doc.pdf PDF
RFP 1175 Revised Proposal Form - Pricing - Wintonbury Hills Renovation.pdf PDF
RFP 1175 Pre-Bid Follow-up Addendum.pdf PDF
RFP 1175_Nov_26_26_solicitation_doc.pdf PDF
RFP 1175_Nov_18_26_solicitation_doc.pdf PDF
RFP 1175_Nov_9_26_solicitation_doc.pdf PDF
RFP 1175_Nov_25_26_solicitation_doc.pdf PDF
RFP 1175_Nov_3_26_solicitation_doc.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pricing Form for Golf Course Renovation

Town of Bloomfield - Wintonbury Hills Golf Course

Bloomfield, Connecticut

October 2026

Quantities Units Unit Cost Amount

Mobilization 1 LS -$ -$

General Conditions 1 LS -$ -$

Survey (all disturbed areas, bunkers, tees, green, Cap-con, any added drainage and irrigation infrastructure) 1 LS -$ -$

Bunker Sand Removal and Stockpile On Each Hole 20,445 SF -$ -$

Bunker Fill-in Using On-Site Soil (Quantity based on existing sand square footage) 4,770 SF -$ -$

Sod-strip (3') Around The Perimeter Of Each Bunker To Remain, and Sod Disturbance Areas for Bunker

Removal and New Bunker Construction Areas. Dispose of Sod in On-site Bury Pits (Disturbance area for bunkers being removed assumed to be 2.5 times the sand area) (Allowance)

30,000 SF $ - $ -

Construct New Bunkers Including Shaping and Bunker Edging (Drainage and Bunker Lining Quantities are Included in Below Quantities)

4,265 SF $ - $ -

Purchase and Install Bluegrass/Fescue Sod For Bunker Removals, Areas Of Disturbance, & (3') Bunker

Perimeters Incl Preparation in Rough areas (Allowance)

28,000 SF -$ -$

Purchase and Install Fairway Height Bentgrass Sod For Fairway Areas Of Disturbance for New Bunker

Construction Incl Preparation in (Allowance)

4,000 SF -$ -$

Bunker Edging, Minor Edge Adjustments, and Floor Contouring of Existing Bunkers to Remain (verify functioning drainage outfalls)

15,675 SF $ - $ -

Bunker Lining - JM Evalith on Bunker Floors (assume 30% of new and existing bunker area) 5,982 SF -$ -$

Bunker Lining - Capillary Concrete (assume 70% of new and existing bunker area) 13,958 SF -$ -$

Bunker Sand Purchase 19,940 SF -$ -$

Bunker Sand Placement (Compacted: 4" on faces and 6" on floors) 19,940 SF -$ -$ 6

Irrigation Adjustments (Allowance) 1 LS 5,000.00$ 5,000.00$

(4") Perforated N-12 Drain Pipe With Gravel (Allowance) 600 LF -$ -$

(4") Solid N-12 Drain Pipe (Allowance) 600 LF -$ -$

Sod Cut Green Grass to a Depth of 2" and Place in Adjacent Area as Directed by the Club. Sod to be

Maintained by the Club (Hole #16)

3,400 SF -$ -$

Sod Strip Green Collar and Green Surround Adjacent to Green Sod Cut to provide Transition Area from

Elevated Green Edge to Adjacnet Surround. Dispose of Sod in Bury Pits

1,600 SF -$ -$

Remove the Top 6" of Greensmix from the Sod Cut Area of the Green and Stockpile as Directed by the

Club for re- use in the Green

3,400 SF -$ -$

Add Average of 4" of USGA Greensmix Across Greensmix Removal Area (0" at Edge of remaining

Green and 8" at Edge of Green)

3,400 SF -$ -$

Add Fill on Green Surround to Transition From Raised Green Edge to Limit of Disturbance and

Compact to 95% Standard Proctor Density. Fill to be Generated From Other Construction Activities and

Bury Pits

1,600 SF -$ -$

Replace 6" Depth of Stockpiled Greensmix and Finish Float Green Surface 3,400 SF -$ -$

Purchase and Install Bluegrass/Fescus Sod on Green Surround 1,600 SF -$ -$

Replace Greens Sod 3,400 SF -$ -$

Tree and Brush Removal for Hole #15 Tee. Place Material in Bury Pits 1 LS -$ -$

Add Average of 1" of Fill to Create New Tee Pads. Based on 20' X 25' Tee Surface 1,000 SF -$ -$

Install Tee Irrigation For New Tee Pads per the Specifications (Per Tee) 2 EA -$ -$

Purchase and Install 4" of Approved 80:20 Sand Mix to Cap Tee Surface and Laser Level 1,000 SF -$ -$

Purchase and Install Bluegrass/Fescue Sod on Tee Slopes 1,800 SF -$ -$

Purchase and Install Tee Height Bentgrass Sod for Tee Tops 1,000 SF -$ -$

TOTAL 5,000.00$

File details come from the government source that posted it. Updated .