RFP 1175 - QandA Addendum.pdf

PDF 236 KB Posted

Attached to
RFP 1175 Wintonbury Hill Golf Course - Bunker, Green & Tee Renovations
Solicitation number
RFP 1175
Issued by
Hartford County, Connecticut

About this file

This Q&A Addendum document is issued by the Town of Bloomfield, Connecticut, in response to bidder inquiries regarding RFP #1175 for Wintonbury Hills Golf Course Bunker, Green & Tee Renovation. The addendum, dated August 22, 2026 (with acknowledgment dated October 22, 2026), clarifies that no bid bond or bonding is required; Troon Golf will oversee the proposed work as the course operator; Professional Liability Insurance is not required since no design work will be performed by the contractor; the anticipated project start date is late September 2027; Hole 8 will not include a new tee, and irrigation work at tees 8, 15, and 18 will involve tapping into existing lines and installing piping, valves, heads, and control wires; no drainage is required for the new green on Hole 16; and existing green sod will be reused on the renovated Hole 16 green. The specifications confirm grass types including Bluegrass/fescue blend for rough areas and tee slopes, fairway height bentgrass for fairway areas, and tee height bentgrass for tee surfaces, with contractors required to provide proposed supplier names in their proposals. A site meeting at Wintonbury Hills Golf Course is highly recommended for October 26, 2026, at 10:00 a.m., with attendance notification directed to jmuraca@bloomfieldct.gov.

Bidders must acknowledge receipt of the Q&A Addendum and confirm compliance with any modifications prior to proposal submission. The form requires signature, company name, printed name, title, and date from authorized representatives. All proposal costs must remain valid for 120 days following bid opening on November 5, 2026.

View the file

Other files

File Type Posted
RFP 1175_Nov_27_26_solicitation_doc.pdf PDF
RFP 1175_Nov_6_26_solicitation_doc.pdf PDF
RFP 1175_Nov_13_26_solicitation_doc.pdf PDF
RFP 1175_Nov_20_26_solicitation_doc.pdf PDF
RFP 1175_Nov_17_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_RFP 1175_v2_Oct_26_26.pdf PDF
RFP 1175_Nov_5_26_solicitation_doc.pdf PDF
RFP 1175_Nov_4_26_solicitation_doc.pdf PDF
RFP 1175_Nov_24_26_solicitation_doc.pdf PDF
RFP 1175_Nov_10_26_solicitation_doc.pdf PDF
RFP 1175 WHGC_Cap-con w JM Evalith Bunker Liner Detail 24Jan24.pdf PDF
RFP 1175 Wintonbury Hills Renovation Pricing Form October 2026 Rev. 2.pdf PDF
RFP 1175_Nov_19_26_solicitation_doc.pdf PDF
RFP 1175 - WHGC Bunker_Green_and Tee Renovation.pdf PDF
RFP 1175 WHGC Bunker Renovation and Tee Expansion Plan 18July26.pdf PDF
RFP 1175_Nov_12_26_solicitation_doc.pdf PDF
RFP 1175_Nov_11_26_solicitation_doc.pdf PDF
RFP 1175_Nov_2_26_solicitation_doc.pdf PDF
RFP 1175_Oct_6_26_solicitation_doc.pdf PDF
RFP 1175 Revised Proposal Form - Pricing - Wintonbury Hills Renovation.pdf PDF
RFP 1175 Pre-Bid Follow-up Addendum.pdf PDF
RFP 1175_Nov_26_26_solicitation_doc.pdf PDF
RFP 1175_Nov_18_26_solicitation_doc.pdf PDF
RFP 1175_Nov_9_26_solicitation_doc.pdf PDF
RFP 1175_Nov_25_26_solicitation_doc.pdf PDF
RFP 1175_Nov_3_26_solicitation_doc.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q & A 1 of 2

TOWN OF BLOOMFIELD

RFP #1175

WINTONBURY HILLS GOLF COURSE BUNKER, GREEN & TEE RENOVATION

Q & A ADDENDUM

Question & Responses Addendum – August 22, 2026

The purpose of this addendum is to provide additional information & answers to questions for clarification to the RFP:

1. Q. There is no reference to bid bond or bonding; could you please confirm not required?

A. There is no bonding required.

2. Q. We see on front page of RFP document ‘C/O Troon Golf’, will they be overseeing the proposed work?

A. Yes; the Town has contracted with Troon for the operation of their Wintonbury Hills Golf Course.

3. Q. Insurance requirements stated include Professional Liability; is this intended as a Design Build? Is this coverage required?

A. Professional Liability Insurance should not be required as the contractor will not be doing any design work.

4. Q. Please confirm the anticipated schedule of a late summer/early fall 2027 start date.

A. Yes, we are targeting late September 2027 for a start date.

5. Q. Item 4 – Hole 8 does not show a new tee. Please provide an irrigation plan for tees 8, 15 and 18.

A. No added tee on hole #8 is required that will be eliminated. Expectations for new irrigation to tee is to tap into the existing line, install piping, valves, heads & control wires.

Q & A 2 of 2

6. Q. Item 3 – Is there drainage required for the new green on 16. If so, please provide a spec for this.

A. There is no drainage required here.

7. Q. Item 6 – Quantity for sod, specifically green, green collar, tee surface, rough sod for bunkers, tees and 16 green must be provided on the schedule of values provide a spec for the sod to be installed on the green and on the tee surfaces.

A. They are to re-use the existing green sod on the renovated green on 16, so no spec is needed. Grass types are included in the specs in the RFP as follows:

Bluegrass/fescue blend for rough areas and tee slopes, fairway height bentgrass for all fairway areas, and tee height bentgrass for all tee surfaces. Respondents are required to provide the names of their proposed suppliers with their proposal.

***ATTENDANCE AT THE SITE MEETING AT WHGC ON OCTOBER 26, 2026, AT 10 AM IS HIGHLY

RECOMMENDED. PLEASE NOTIFY JMURACA@BLOOMFIELDCT.GOV IF YOU PLAN ON ATTENDING. ***

We hereby acknowledge receipt of

Q & A Addendum

Dated October 22, 2026

RFP #1175

WINTONBURY HILLS GOLF COURSE BUNKER, GREEN & TEE RENOVATION

And we agree that we have complied with any modifications as set forth in this Addendum.

Company Name:______________________________________________________________________

Signed: ___________________________________________ Date:__________________________

Printed Name:________________________________ Title: _________________________________

TOWN OF BLOOMFIELD
RFP #1175
WINTONBURY HILLS GOLF COURSE BUNKER, GREEN & TEE RENOVATION
Q & A ADDENDUM
RFP #1175
WINTONBURY HILLS GOLF COURSE BUNKER, GREEN & TEE RENOVATION

File details come from the government source that posted it. Updated .