Addendum No. 3 to RFP 112-26 issued by the Massachusetts Bay Transportation Authority (MBTA) on October 1, 2026, amends key terms of the Centralized Train Control (CTC) System replacement solicitation. The addendum updates Section 2.3.2 to clarify that contractors must include visualization of all tracks present on the MBTA rail transit system, including revenue tracks, non-revenue storage tracks, and yards across the Red, Orange, Blue, and Green Lines. The MBTA is providing current track network schematics at implementation, with updates to be provided during CTC design and implementation phases as ongoing projects progress; however, the scope excludes signal or track work. The addendum presents a comprehensive table identifying major rail transit yards by line and their current versus expected CTC status, categorizing track and signal conditions as "Integrated" (visible and controllable on live CTC graphics), "Not Integrated" (signalized but not visible or controllable), "Dark" (not signalized and not currently visible), or "Static Graphics" (visualized but without available indications or controls).
Section 2.6.4 regarding Support & Warranty Requirements has been substantially revised to establish a phased maintenance and warranty structure extending up to fifteen years. The contractor must provide OEM-recommended maintenance during project implementation and transition, with two-year full system warranty commencing upon final CTC commissioning and acceptance. Following the warranty period, the MBTA has options to purchase three successive five-year maintenance extensions (Years 3-7, 8-12, and 13-17), each including Level 3 support on a 24/7 basis for critical issues and within one business day for non-critical items, preventive and corrective maintenance, software upgrades and patches, and supplementary training. During the second half of the first five-year maintenance option, the vendor must perform a comprehensive system assessment with recommendations for software, hardware, and service improvements, subject to MBTA approval. Forms B (Technical Response) and Form D (Pricing Proposal) have been updated and made available on COMMBUYS.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MBTA Logo, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo
Massachusetts Bay Transportation Authority Ten Park Plaza, Boston, MA 02116 mbta.com
October 1, 2026
Attention Bidder(s):
SUBJECT: RFP# 112-26 MBTA ENTRALIZED TRAIN CONTROL SYSTEM
Addendum No. 3
The MBTA is amending the following terms within RFP# 112-26:
1. Updating Section 2.3.2 from “Rail Yards” to “Yards, Non-Revenue Tracks, and Revenue Tracks Visualization”: Section 2.3.2 shall be replaced with the following:
The Contractor is required to include all tracks present on the MBTA rail transit system, including but not limited to revenue tracks, storage tracks, and yards, as noted in the track network schematics or other source documents provided at time of implementation.
MBTA is providing the current track network schematics, which includes yards (see Exhibit A). These schematics reflect the latest version of the track system at this time. However, as MBTA progresses on various ongoing projects, these schematics may get updated. The selected bidder will be given updated versions during CTC design and implementation to ensure most accurate information is reflected in the new CTC system.
As stated elsewhere in the RFP, the scope of the CTC implementation excludes any signal or track work.
Overview of Major Rail Transit Yards (Non-exhaustive)
| Line |
| Yard Name |
| Current CTC Status |
| Expected CTC Status |
| Notes |
Red
| Cabot Yard |
| Not Integrated |
| Static Graphics |
| Codman Yard |
| Dark |
| Static Graphics |
| Network Schematic may change |
| Caddigan Yard |
| Integrated |
| Integrated |
Orange
| Wellington Yard |
| Dark |
| Static Graphics |
Would like to visualize what is inside vs outside the carhouse.
| Forest Hills Yard |
| Integrated |
| Integrated |
Blue
| Orient Heights Yard |
| Dark |
| Static Graphics |
| Bowdoin Storage Tracks |
| Dark |
| Static Graphics |
| Future signal project planned to add track circuit indication. |
Green
| Riverside Yard (D) |
| Dark |
| Static Graphics |
| Reservoir Yard (C) |
| Dark |
| Static Graphics |
| Innerbelt Yard (GLX) |
| Dark |
| Static Graphics |
| Lake Street Yard (B) |
| Dark |
Static Graphics
Definitions of Track/Signal Status Terms:
· Integrated: Visible and controllable on the CTC's live track graphics.
· Not Integrated: Signalized, but not visible or controllable on the CTC’s live track graphics.
· Dark: Not signalized and not currently visible on the current CTC’s live track graphics.
· Static Graphics: Track and signal locations are visualized in the CTC’s live track graphics, but any indications or controls are not available.
2. Updating Section 2.6.4 “Support & Warranty Requirements”:
Section 2.6.4 shall be replaced with the following:
| # |
| Project/Contract Phase |
| MBTA Expectations |
| 1. |
| Project Duration – Start to Final Acceptance |
| a. Maintenance performed by the vendor in accordance with procedures and schedules recommended by the OEMs of all equipment and software. This should include all services required for maintenance and keeping all related documentation (design, configurations, bug tracking, etc.) and records up to date and accessible by MBTA. |
b. As the system becomes operational during Installation and through Transition Period, same level of maintenance support should be provided per agreed upon Service Level Agreements (SLAs) up to final acceptance.
c. Provide the necessary manuals and training to the MBTA staff to manage day-to-day operation and support of the system during the project as the new system is commissioned.
| 2. |
| (2) Two-Year System Warranty |
| a. Provide a two-year Warranty which will begin once CTC is fully commissioned on all lines and formally accepted by MBTA. |
b. During this period, vendor will continue to provide software, hardware, and services support and maintenance of all products supplied under this contract. The vendor will also continue to maintain all system documentation (design, configurations, bug tracking, etc.) and provide monthly maintenance reports to MBTA.
c. If there are any material changes to the system during Warranty in response to issue resolutions, necessary maintenance and training manuals should be updated and MBTA staff be provided related supplementary training.
| 3. |
| Maintenance Option 1: 5 Years |
| a. MBTA will have the option to purchase additional Maintenance Support at any time up through the end of the Warranty period. This option will include system and software maintenance services for a five-year period commencing at the completion of the two-year Warranty period. |
b. This Maintenance Option will include:
i. Level 3 Support available to MBTA:
1. For issues escalated by the MBTA team from Level 1 and Level 2 actions taken by MBTA.
2. On a 24/7 basis for critical items as determined by MBTA.
3. Within one-business day of the vendor being informed for non-critical items as determined by MBTA.
ii. Preventive and corrective maintenance of the implemented system.
iii. Troubleshooting and repair of system integration and software issues escalated by MBTA team.
iv. Regular software maintenance, upgrades (including operating system patches & updates, networking software utilities, etc.), and third-party software updates.
v. Support to MBTA team for installation of the new software versions as needed.
vi. Updates to the application software (e.g. new signaled areas) to support integration of additional field equipment as MBTA completes field projects.
vii. Supplementary training as requested by MBTA related to aforementioned tasks.
c. During the second half of the 5-year period, at a time determined by MBTA, the vendor will perform a full assessment of the delivered system and recommend improvements. Areas of improvement may include:
i. Software
1. Supplier’s application software updates to the latest version.
2. System and third-party software updates to the latest versions compatible with the application.
3. Enhancements to address operational and/or service changes based on MBTA programs impacting CTC.
ii. Hardware
1. Hardware and software changes due to failure rates, obsolescence or pending obsolescence.
2. Assessment and replenishment of system spares.
iii. Services
1. All services required for design, implementation, testing, installation, and cutover of the upgrades.
2. Updates to all as-built documentation to reflect the upgraded system.
3. Revision of training documents to reflect the upgraded system and MBTA training related to updates.
d. Recommendations shall be discussed with MBTA and finalized in a formal report.
e. Final set of software, hardware, and services to be provided will be approved by MBTA based on the report and the vendor will update the system accordingly.
| 4. |
| Maintenance Options 2 & 3: Up to 10 Years & 15 years Respectively |
| MBTA may exercise additional options to extend maintenance support at years 5 and 10 after Option 1 at any time up through the completion of the preceding 5-year maintenance period. The 5-year extensions may include another cycle of software, hardware, and service updates as stated under Option 1 or may be modified at MBTA’s discretion to align with MBTA’s operational and technical needs at that time. |
3. Updating Form B: Technical Response (Excel Doc):
Form B: Technical Response Form (Excel Doc) has been updated. The revised form is on COMMBUYS.
4. Updating Form D Pricing Proposal Form:
Form D: Pricing Proposal Form has been updated. The revised form is on COMMBUYS.
All other terms and conditions of RFP# 112-26 shall remain in effect.
Respectfully, Kiana Hall and Terunii Senevirratne