RFB952500-01 - Addendum No. 2.pdf
PDF 3 MB Posted
- Attached to
- IPBS HVAC - Motivair Units Replacement
- Solicitation number
- RFB952500-01
- Issued by
- Polk County, Iowa
About this file
This Addendum No. 2, issued by the Iowa Department of Administrative Services on August 7, 2026, modifies the original Project Drawings and Specifications for RFB 952500-01 regarding the replacement of two Motivair chillers at the Iowa PBS facility located at 6450 Corporate Drive, Johnston, Iowa 50131. The addendum clarifies scope items by removing associated roofing work from the bid, specifically excluding patching of existing curbs of removed chillers and patching of existing roof for installation of new support beams. The document provides answers to contractor questions regarding equipment locations, pump inertia base replacements, and base grout specifications, with acceptable products identified as SikaGrout-212/713, Dayton Superior 1107 Advantage, or Euclid NC Grout. Revised mechanical and electrical drawings have been updated to reflect modifications to chilled water piping, proposed chiller staging notes, chilled water system piping and controls diagrams, chiller and dry cooler schedules, and electrical panel clarifications. The addendum identifies approved manufacturers for hydronic specialties (American Wheatley), hydronic pumps (Grundfos), and dry coolers (USA Coil, Guntner). Proposals remain due August 11, 2026.
The addendum emphasizes that all roof work must maintain existing roof warranty through Koopman Roofing (641-621-0131) and that the receipt of this addendum must be acknowledged by the design firm in their submission. Key technical clarifications include the location of electrical panel EDP08 adjacent to the MDP08 panel, confirmation that new inertia bases will replace existing pump bases, and detailed specifications for base grout materials. The revised drawings address modifications to chilled water piping configurations, inclusion of proposed chiller staging procedures, updates to the mechanical details and control diagrams, and clarifications to electrical panel types and locations to match existing site conditions. The document confirms that five revised drawing sheets (MD101, M101, M301, M501, and E101) are included with the addendum and supersede previous versions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB952500-01 - Bid Form.pdf | ||
| RFB952500-01 - Notice To Bidders.pdf | ||
| RFB952500-01 - Project Manual.pdf | ||
| RFB952500-01 - Drawings.pdf | ||
| RFB952500-01 - Addendum No. 1.pdf | ||
| RFB952500-01 - Addendum #1.pdf | ||
| 1412843-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 2
Date: 8/7/26
Project Name: 9525.00 – IPBS Motivair Chiller Replacements
DAS RFB #: 952500-01
DAS Project #: 9525.00
PROPOSALS DUE: 8/11/26
The receipt of this Addendum shall be acknowledged by the design firm in their submission.
This addendum is issued to modify, clarify, or amend the original Project Drawings and
Specifications and is hereby made part of the Contract Documents. The Contractor shall be responsible for incorporating items in this Addendum to the Work. The following shall take precedence over anything to the contrary in the Drawings or Specifications.
This Addendum consists of:
1) Scope Clarification:
a. Remove associated roofing work from bid
i. Exclude patching of existing curbs of removed chillers
ii. Exclude patching of existing roof for installation of new support beams
2) Questions/Reponses:
a. Q: Where is the location of the EDP08 that is referenced in the electrical drawings?
i. R: It is adjacent to the MDP08 panel in the electrical room.
b. Q: Are the existing pump inertia bases being replaced with new inertia bases?
i. R: Yes, new inertia bases are to be provided.
c. Q: Provide specifications for the base grout.
i. R: Any high strength, non-shrink cementitious grout will be acceptable.
Example products would be SikaGrout-212/713, Dayton Superior 1107 Advantage or Euclid NC Grout.
3) Drawing Updates:
a. Mechanical Drawings
i. Drawing MD101 – FLOOR PLAN HVAC DEMOLITION
1. MODIFY chilled water piping as shown.
2. ADD proposed chiller staging note as shown.
3. Refer to attached full size sheet MD101.
ii. Drawing M101 – FLOOR PLAN HVAC
1. MODIFY chilled water piping as shown.
2. Refer to attached full size sheet M101.
iii. Drawing M301 – MECHANICAL DETAILS
1. MODIFY chilled water system piping and controls diagram as shown.
2. ADD glycol note as shown.
3. Refer to attached full size sheet M301.
iv. Drawing M501 – MECHANICAL SCHEDULES
1. MODIFY chiller and dry cooler schedules as shown.
2. Refer to attached full size sheet M501.
b. Electrical Drawings:
i. Drawing E101 – ELECTRICAL POWER
1. CLARIFY panel types for panels SB-4 and BE with provided pictures on drawing.
2. CLARIFY existing panel locations in the electrical room.
Updated to match existing conditions.
3. Refer to attached full size sheet MD101.
c. Revised drawings included: MD101, M101, M301, M501, E101
4) Approved Manufacturers:
Spec Reference Equipment Type Manufacturer
23 21 23 Hydronic Specialties American Wheatley
23 21 23 Hydronic Pumps Grundfos
23 65 33 Dry Cooler USA Coil, Guntner
End of Addendum
A. REFER TO M000 FOR GENERAL NOTES & SYMBOLS.
B. REFER TO M301 FOR MECHANICAL DETAILS AND CONTROLS.
GENERAL NOTES:
AIR COOLED CU
(EXIST)
AIR COOLED CHILLER
(DEMO)
AIR COOLED CHILLER
(DEMO)
RTU
(EXIST)
RTU
(EXIST)
BUFFER TANK
(EXIST)
AIR COOLED CU
(EXIST)
AIR COOLED CU
(EXIST)
EXISTING REF PIPING TO REMAIN (E).
REMOVE ALL EXISTING EXTERIORINSULATION AND
PREPARE PIPING FOR NEW INSULATION AND JACKET.
(TYP. ALL CWS/CWR PIPING ON ROOF AND DOWN TO BUFFER TANK.)
REMOVE EXISTING EXTERIOR PIPING INSULATION AND
EXTERIOR JACKET FROM REFRIGERANT PIPING
FOR CONDENSING UNIT.
REMOVE PUMPS AND
INTERTIA BASES.
PREPARE PIPING FOR
NEW CONNECTION.
6" CWS (E)
6" CWR (E)
3" CWR (E)
3" CWR (E)
3" CWS (E)
3" CWS (E)
ROOF HATCH
(E)
ALL ROOF WORK SHOULD
MAINTAIN EXISTING ROOF
WARRANTY. EXISTING ROOF
WARRANTY CONTACT IS KOOPMAN
ROOFING (641-621-0131).
REMOVE EXISTING CHILLER
CURBS AND PATCH ROOF TO
MATCH EXISTING.
(TYP.)
PROPOSED CHILLER CONSTRUCTION STAGING:
1) SET BOTH NEW CHILLERS.
2) ISOLATE AND DEMO EXISTING CH-1.
3) COMPLETE PIPING AS SHOWN TO NEW CH-1 & 2.
4) STARTUP NEW CH-1.
6) ISOLATE AND DEMO EXISTING CH-2.
7) COMPLETE PIPING AS SHOWN TO NEW CH-2.
8) START UP CH-2.
EXISTING GLYCOL FEED STATION
AIR
SEPARATOR
(E)
EXPANSION TANK
(E)
EXISTING CONTROL
VALVE TO BE REMOVED.
(TYP.)
REMOVE EXISTING
BALANCING VALVE.
(TYP.) 1
C W
R
C W
R
4" CWR (E)
4" CWR (E)
REMOVE CAP
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/7
/2
:3 :2
A
M
MD101
CONSTRUCTION
DOCUMENTS
07/06/2026
9525.00
D A
S I
P B
S M
O T
IV
A
IR
C
H
IL
L E
R R
E P
L A
C E
M E
N T
C
O R
P O
R A
T E
D R
IV
E
J O
H N
S T
O N
IA
FLOOR PLAN HVAC
DEMOLITION
N
1/8" = 1'-0"
LEVEL 2 HVAC DEMOLITION PLAN
# Revision Date
1 Addendum 2 8.07.26
A. REFER TO M000 FOR GENERAL NOTES & SYMBOLS.
B. REFER TO M301 FOR MECHANICAL DETAILS AND CONTROLS.
GENERAL NOTES:
B B
C C
D D
CONDENSERS
EMERGENCY GENERATOR
MECHANICAL / EQUIP.
EQUIP. ROOM
CONTROL
MECHANICAL / EQUIP.
RTU
(E)
RTU
(E)
BUFFER TANK
(E)
AIR COOLED CU
(E)
AIR COOLED CU
(E)
AIR COOLED CU
(E)
EXISTING REF PIPING TO REMAIN (E).
3" CWS (E)
3" CWS (E)
3" CWR (E)
3" CWR (E)
6" CWS (E)
6" CWR (E)
PROVIDE NEW INSULATION
AND JACKET FOR EXTERIOR
REF LINES. REFER TO HVAC
PIPING AND INSULATION SCHEDULE,
MECHANICAL SPECIFICATIONS
FOR ADDITIONAL INFORMATION.
PROVIDE NEW INSULATION
AND JACKET FOR EXTERIOR
CWS/CWR LINES. REFER TO HVAC
PIPING AND INSULATION SCHEDULE,
MECHANICAL SPECIFICATIONS
FOR ADDITIONAL INFORMATION.
(TYP. ALL CWS/CWR LINES ON ROOF
AND TO BUFFER TANK.)
AHU
(E)
AHU
(E)
EXPANSION TANK
(E)
AIR SEPARATOR
(E)
DC
CWP
CWP
3-WAY VALVE
ROOF HATCH
(E)
C W
R (E
C W
R (E
3" CWS
3" CWR
CH
CH
ALL ROOF WORK SHOULD
MAINTAIN EXISTING ROOF
WARRANTY. EXISTING ROOF
WARRANTY CONTACT IS KOOPMAN
ROOFING (641-621-0131).
LOCK EXISTING
DECOUPLE VALVE
CLOSED
1 1/2"
4" CWR (E)
4" CWR (E)
ISOLATE GYLCOL FEED STATION
AND EXPANSION TANK PIPING AT
EXISTING VALVES NEAR MAIN AND
RE-PIPE TO BLIND FLANGE WITH
VALVE ON SUCTION SIDE OF PUMPS.
1 2
3 4
MANUAL VALVE OPERATION SCHEDULE:
1: CH-1 CHILLER ISOLATON - CLOSE VALVES 1&2
2: CH-2 CHILLER ISOLATON - CLOSE VALVES 3&4
3: SERIES CONFIGURATION:
(NORMAL OPERATION) - CLOSE VALVE 5 AND
OPEN VALVE 6)
CLOSE VALVE
AND REMOVE
HANDLE.
CLOSE VALVE
AND REMOVE
HANDLE.
GLYCOL FEED
STATION (E)
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/7
/2
:3 :2
A
M
M101
CONSTRUCTION
DOCUMENTS
07/06/2026
9525.00
D A
S I
P B
S M
O T
IV
A
IR
C
H
IL
L E
R R
E P
L A
C E
M E
N T
C
O R
P O
R A
T E
D R
IV
E
J O
H N
S T
O N
IA
FLOOR PLAN HVAC
N
1/8" = 1'-0"
LEVEL 2 HVAC PLAN
EXPANSION
TANK
BYPASS
FILTER
100 MICRON (E)
AIR
SEPARATOR (E)
1/
4" C
W R
1/
4" C
W S
MANUAL AIR
VENT
4"CWS 4"CWS 4"CWS
4"CWR
4" C
W R
AUTOMATIC AIR VENT
(TYP.)
67 TOTAL GALLONS,
34 GALLONS ACCEPTANCE.
4"CWR
THERMOMETER
(TYP.)
3" C
H R
3" C
H
TO AHU-1
CHILLED
WATER COILS
WITH 3-WAY
VALVES (E)
3"CWS
3"CWR
EXTERIOR
WALL
170 GPM
80 GPM
80 GPM
80 GPM
40 MESH
STRAINER
BYPASS FILTER. 100 MICRON
STARTUP, 20 MICRON FINAL.
TO AHU-2
CHILLED
WATER COILS
WITH 3-WAY
VALVES (E)
PRIMARY
PUMP
TRIPLE DUTY
VALVE (TYP.)
PRIMARY
PUMP
3"CWS
(35 TONS)
80 GPM
(35 TONS)
4" DECOUPLE
LINE
4"CWR
170 GPM
170 GPMGLYCOL FEED
STATION (E)
4"CWS
CH-1
80 TON AIR
COOLED
CHILLED
WATER BUFFER
TANK (E)
(1,000 GAL.)
GRADE
6"CWR
LOCKED CLOSED VALVE
3" C
W R
CHILLER WATER PUMP OPERATION:
WHEN THE COOLING SYSTEM IS MANUALLY ENABLED AT THE DDC, THE CHILLED WATER PUMP SHALL BE ENABLED AND SHALL RUN CONTINUOUSLY. PUMP SPEED SHALL BE ESTABLISHED BY THE TAB CONTRACTOR TO PROVIDE 170 GPM. SYSTEM HAS FULLY REDUNDANT CHILLERS/PRIMARY PUMPS THAT SHOULD BE USED IN ALTERNATING
SCHEDULE DETERMINED BY THE OWNER.
CHILLER OPERATION:
THE CHILLER SHALL BE CONTROLLED BY THE LOCAL CONTROLLER. THE CHILLER CONTROLLER WILL MODULATE AND ADJUST COMPRESSOR STAGING, CONDENSER FAN OPERATION, HOT GAS BYPASS CONTROL TO ACHIEVE CHILLED WATER SUPPLY SETPOINT, THE DRY COOLER WILL BE CONTROLLED BY THE DDC. WHEN THE COOLING
SYSTEM IS MANUALLY ENABLED AT THE DDC, THE FOLLOWING SEQUENCE WILL OCCUR:
• CHILLED WATER PUMP WILL START
• CHILLED WATER FLOW SWITCH WILL BE SET
• CHILLED WATER SETPOINT WILL BE SET TO 44F (ADJ.).
• AFTER A 10 MIN. WAIT, CHILLER WILL BE ENABLED.
WHEN THE COOLING SYSTEM IS MANUALLY DISABLED AT THE DDC, THE FOLLOWING SEQUENCE WILL OCCUR:
• AFTER A 10 MIN. WAIT, CHILLER WILL BE DISABLED.
• AFTER A 20 MIN. WAIT, CHILLED WATER PUMP TO BE STOPPED.
ADDITIONAL COOLING MODE:
• IF CHILLED WATER SETPOINT IS NOT ABLE TO BE MAINTAINED FOR 20 MIN. (ADJ.) WITH ENABELED CHILLER FULLY LOADED, THEN REDUNDANT CHILLER SHALL BE
ENABLED AND BOTH CHILLERS SHALL MODULATE TO MAINTAIN SETPOINT. AFTER CHILLED WATER SETPOINT HAS BEEN MAINTAINED FOR 30 MIN., REDUNDANT
CHILLER SHALL BE DISABLED AND RETURN TO ALTERNATING SCHEDULE.
DRY COOLER OPERATION:
• IF O.A. TEMP IS BELOW 35F (ADJ.) FOR 1 HOUR (ADJ.) THEN DRY COOLER 3-WAY VALVE SHALL FULLY OPEN AND FANS SHALL MODULATE TO MAINTAIN SETPOINT IN
CONJUCTION WITH CHILLER.
• WHEN DRY COOLER IS ABLE TO MAINTAIN SET POINT WITH ALL FANS OFF FOR 1 HOUR (ADJ.), CHILLER SHALL BE DISABLED AND 3-WAY VALVE SHALL START TO
MODULATE TO MAINTAIN SETPOINT AS REQUIRED.
WHEN O.A. TEMP RISES ABOVE 38F (ADJ.) FOR 1 HOUR (ADJ.), FULLY CLOSE 3-WAY VALVE TO ALLOW FULL BYPASS AND DISABLE DRY COOLER.
EXISTING BUFFER TANK BYPASS VALVE CONTROL. PROVIDE ABILITY ON USER INTERFACE TO MANUALLY OPEN BYPASS VALVE FOR BUFFER TANK. NORMAL OPERATION IS
TO HAVE CLOSED.
EXISTING ISOLATION CONTROL VALVES SHALL REMAIN AND BE USED AS NEEDED TO ISOLATE EACH CHILLER IF SERVICE IS NEEDED. CHILLERS CAN ALSO BE ISOLATED
MANUALLY VIA MANUAL VALVES.
TRENDS
ALL POINTS SHALL BE HISTORICALLY TRENDED. TREND POINTS EVERY 15 MIN OVER A 365 DAY PERIOD OF TIME.
FLOW METER SHOWN SHALL BE USED TO VERIFY FLOW AND CALCULATE APPROXIMATE CURRENT TONNAGE ON USER INTERFACE.
ALARMS AND INTERLOCK SAFETIES:
THE FOLLOWING SHALL SHUT DOWN THE ENABLED CHILLER AND PUMP AND SHALL INDICATE AN ALARM CONDITION. DDC SHALL ENABLE REDUNDANT CHILLER AND PUMP:
- PUMP STATUS CAN NOT BE VERIFIED WITH CURRENT RELAY (AUTO RESET)
- FLOW SWITCH CAN NOT BE VERIFED (AUTO RESET)
THE FOLLOWING SHALL DISABLE THE ENABLED PUMP AND SHALL INDICATE AN ALARM CONDITION. DDC SHALL ENABLE REDUNDANT PUMP.
- PUMP STATUS CAN NOT BE VERIFIED WITH CURRENT RELAY (AUTO RESET)
- DRY COOLER FAN STATUS CAN NOT BE VERIFIED WHEN ENABLED
ALARMS
THE FOLLOWING SHALL INDICATE AN ALARM CONDITION:
- A GENERAL VFD ALARM
- A GENERAL CHILLER ALARM
- CHILLED WATER SUPPLY TEMPERATURE IS > OR < 5°F FROM SETPOINT FOR MORE THAN 10 MIN.
COOLING SYSTEM REPORT GENERATION:
BAS SHALL MONITOR THE FOLLOWING POINT ON 5 MIN. (ADJ.) INTERVALS WITH SIGNAL TREND. THE TREND SHALL RUN FOR A 365 DAY (ADJ.)
DURATION AT WHICH POINT THE NEWEST VALUES SHALL OVERWRITE THE OLDEST VALUES:
• DATE
• TIME
• GLOBAL OUTSIDE AIR TEMP. (F)
• SYSTEM CHILLED WATER SUPPLY TEMP (F)
• SYSTEM CHILLED WATER SUPPLY TEMP SETPOINT (F)
• SYSTEM CHILLED WATER RETURN TEMP (F)
• SYSTEM CHILLED WATER FLOW RATE (GPM)
• COOLING SYSTEM LOAD (TONS)
• OPERATIONAL STATUS OF CHILLER, CHILLED WATER PUMP.
THIS INFORMATION SHALL BE ACCESSIBLE TO VIEW IN NEITHER TABULAR OR GRAPHICAL FORM ON THE BAS.
ONCE PER MONTH THE BAS SHALL RECORED THE LARGEST COOLING SYSTEM LOAD (IN TONS) WHICH OCCURED DURING THAT MONTH, THE DATE, TIME, OUTSIDE AIR TEMPERATURE, CHILLED WATER SUPPLY AND RETURN TEMPERATURES WHICH COINCIDED WITH THAT EVENT SHALL ALSO BE RECORDED. THIS INFORMATION SHALL BE STORED TO A MEMORY LOCATION ON THE BAS OPERATOR INTERFACE THAT IS MAINTAINED
(NOT AUTOMATICALLY OVERWRITTEN).
CWP-1
CWP-2
CH-2
80 TON AIR
COOLED
N.C.
DC-1
DRY COOLER
N.C.
AI-3-WAY VALVE MODULATION
AI-CHILLER SETPOINT
DI-CHILLER ALARM
DO-CHILLER ENABLE
BACNET CONNECTION
CHILLER
CONTROL
PANEL
(ADDITIONAL STANDARD
CHILLER POINTS THRU
BACNET CONNECTION)
(TYP. 2)
POWER WIRING BY EC
CONTROL WIRING BY TCC
VFD'S PROVIDED BY TCC,
POWERED BY EC.
TO PUMP
(TYP. 2)
AO-VFD SPEED
DI-VFD ALARM
DO-VFD ENABLE
PUMP VFD
170 GPM
DI - CWP-2
PUMP STATUS
DI - CWP-1
PUMP STATUS
N.O.
FM
RECALIBRATE EXISTING
FLOW METER
CONNECT COMBINED
LINE HERE TO EXISTING
BLIND FLANGE WITH VALVE.
PROVIDE REDUCER FROM
LINE SIZE AS REQUIRED.
1 1/2"
CLOSE EXISTING VALVE
AND REMOVE HANDLE.
1"
1"
M.C. SHALL BE RESPONSIBLE TO PROVIDE ADDITIONAL UNDILUTED
PROPYLENE GLYCOL AND ANY ASSOCIATED CHEMICAL WATER
TREATMENT AS REQUIRED TO INCREASE THE EXISTING CHILLED
WATER SYSTEM FROM 35% TO 50% PROPYLENE GLYCOL. SYSTEM
VOLUME IS ESTIMATED TO BE APPROXIMATELY 2,500 GALLONS.
100 PSI
PT PORT (TYP.)
TEMPERATURE GAUGE (TYP.)
PRESSURE GAUGE (TYP.)
FLEXIBLE CONNECTOR
(TYP.)
STRAINER (TYP.)
DO - DRYCOOLER FAN ENABLE/DISABLE (TYP. 12)
DI - DRYCOOLER FAN STATUS (TYP. 12)
3-WAY CONTROL VALVE
FLEX CONNECTOR
(TYP.)
3"CWS
3"CWR
3" CWS/CWR
INSULATE ALL PUMP SURFACES INCLUDING VOLUTE
AND SUCTION DIFFUSER
TRIPLE DUTY VALVE
FLEX CONNECTOR (TYP. OF 2)
GAUGE ISOLATION VALVE
BUTTERFLY
VALVE
PRESSURE GAUGE
SUCTION DIFFUSER
REMOVE STARTUP
STRAINER
AFTER STARTUP
OF SYSTEM.
GROUT BASE
FULL OF
CONCRETE.
PUMP
ANCHOR BOLTS SET
IN BASE AT TIME OF
POUR
UNHOUSED SPRING
ISOLATORS W/ 2"
DEFLECTION
CONCRETE FILLED
INERTIA BASE W/ WEIGHT
EQUAL TO OR GREATER
THAN PUMP ASSEMBLY
NEW PUMP WITH INERTIA
BASE WITH ISOLATORS TO BE
LOCATED ON EXSITING PAD.
FIELD VERIFY ALL FINAL
EQUIPMENT DIMENSIONS
PRIOR TO RELASING
SUBMITTALS FOR REVIEW.
DIGITAL OUTPUT
DIGITAL INPUT
ANALOG OUTPUT
DO
DI
AO
TEMPERATURE SENSOR AS INDICATED
STATIC PRESSURE SENSOR
ANALOG INPUT
NORMALLY OPEN
NORMALLY CLOSED
AI
NO
NC
TS
SP
DIFFERENTIAL PRESSURE SENSOR
FREEZE STAT
ENTHALPY SENSOR
TEMPERATURE SENSOR (AVERAGING)
DPS
ES
FZ
TS
DUCT DETECTOR (BY OTHERS)SD
NORMALLY OPEN (POWERED CLOSED)
VELOCITY TRANSMITTERVT
24V DAMPER/VALVE MOTORM
VFD
ADJ ADJUSTABLE
VARIABLE FREQUENCY DRIVE
NORMALLY CLOSED (POWERED OPEN)
DEW POINT SENSORDP
N.O.
N.C.
CONTROL DIAGRAM SYMBOLS
GENERAL CONTROL NOTES:
TEMPERATURE CONTROL CONTRACTOR TO PROVIDE A COMPLETE
CONTROL SYSTEM, INCLUDING SENSORS, RELAYS, WIRING, CONDUIT,
CONTROLLERS, AND OTHER COMPONENTS. INSTALL ALL CONTROL
COMPONENTS PER MANUFACTURER'S RECOMMENDATIONS. TCC TO
INSTALL ALL MFR PROVIDED CONTROLS COMPONENTS FURNISHED
LOOSE FROM FACTORY.
ALL DIFFERENTIAL / STATIC PRESSURE TRANSMITTERS ARE TO BE
HARDWIRED BACK TO THEIR CONTROLLERS IN LIEU OF BEING
TRANSMITTED OVER THE COMMUNICATION NETWORK.
ALL AVERAGING SENSORS (LOW LIMIT, MAT, ETC) SHALL HAVE ONE
LINEAL FOOT OF SENSOR PER SQUARE FOOT OPENING AND WITHIN 6"
OF ALL EDGES OF OPENINGS.
ALL SENSORS ARE TO BE SUPPLIED WITH APPROPRIATE RANGES TO
ACCOMPLISH STATED CONTROL SEQUENCES.
ALL SAFETY SENSORS (FREEZE STATS) SHALL BE HARD WIRED TO
STOP FANS, CLOSE OUTSIDE DAMPERS, AND RELIEF DAMPERS.
TCC TO PROVIDE A FULL GRAPHICS CONTROL PACKAGE AS PART OF
PROJECT.
ALL VFD'S ARE TO COME WITH SURGE PROTECTION. REFER TO DIV 26
VFD SPECIFICATION.
DIAGRAMS ARE SCHEMATIC. PROVIDE ADDITIONAL POINTS WHERE
REQUIRED TO MEET SEQUENCE OF CONTROL.
COORDINATE WITH EC ON REQUIRED POWER REQUIREMENTS AND
LOCATIONS.
UNLESS STATED OTHER, ELECTRICAL CONTRACTOR IS TO PROVIDE
ALL LINE VOLTAGE POWER AND CONDUIT FOR CONTROL SYSTEM AND
ALL CODE REQUIRED HARD WIRED POINTS FOR INTERACTION WITH
FIRE ALARM SHUTDOWN.
MECHANICAL CONTRACTOR IS RESPONSIBLE FOR INSTALLING ALL
CONTROL VALVES, DAMPERS, AND DAMPER ACTUATORS.
BACNET PROTOCOL SHALL BE IP/MSTP.
CONTROLS SHALL BE BY JCI CONTROLS (NO EQUALS). CONTROLS
SHALL MATCH EXISTING FACILITY STANDARDS FOR DYNAMIC
GRAPHICS, TRENDING, ETC.
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/7
/2
:3 :2
A
M
M301
CONSTRUCTION
DOCUMENTS
07/06/2026
9525.00
D A
S I
P B
S M
O T
IV
A
IR
C
H
IL
L E
R R
E P
L A
C E
M E
N T
C
O R
P O
R A
T E
D R
IV
E
J O
H N
S T
O N
IA
MECHANICAL DETAILS
NOT TO SCALE
CHILLED WATER SYSTEM PIPING AND CONTROLS DIAGRAM
NTS
END SUCTION PUMP WITH INERTIA BASE DETAIL
NTS
CONTROL DIAGRAM GENERAL NOTES & SYMBOLS
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/7
/2
:3 :2
A
M
M501
CONSTRUCTION
DOCUMENTS
07/06/2026
9525.00
D A
S I
P B
S M
O T
IV
A
IR
C
H
IL
L E
R R
E P
L A
C E
M E
N T
C
O R
P O
R A
T E
D R
IV
E
J O
H N
S T
O N
IA
MECHANICAL
SCHEDULES
5. BASE MOUNTED PUMP, PROVIDE INTERTIA PAD.
4. PROVIDE WITH SHAFT GROUNDING KITS.
3. MOTORS TO BE SUITABLE FOR OPERATION WITH VARIABLE FREQUENCY DRIVE (VFD).
2. TCC TO PROVIDE VFD'S WITH INTEGRAL DISCONNECT. VFD'S INSTALLED BY EC.
1. REFER TO CONTROL DRAWINGS.
NOTES:
NOTES 1 THROUGH 5
VOLTAGE - PH 480 - 3
RPM 3,500
BHP 8.0
MOTOR HP 10
ELECTRICAL DATA
PUMP EFFICIENCY % 74%
IMPELLER DIAMETER RANGE (INCH) 4 - 6.25
IMPELLER DIAMETER (INCH) 5.80
OPERATING PRESSURE (FT. HEAD) 130
FLOW RATE (GPM) 170
DIMENSIONS - L x W x H (INCHES) 40 x 16 x 20
WEIGHT (LBS) 450
SERVES CHILLED WATER
TYPE END SUCTION
MODEL # FI2506D
MANUFACTURER TACO
REFERENCE CWP-1 & CWP-2
PUMP SCHEDULE
5. EXPOSED PIPING MOUNTED BELOW 6'-0" ABOVE FLOOR SHALL HAVE PVC AND EXTERIOR PIPING SHALL HAVE ALUMINUM JACKET.
4. REFER TO SPECIFICATIONS FOR FURTHER VALVE REQUIREMENTS.
3. INSULATION APPLIED TO PIPING LOCATED IN RETURN AIR PLENUMS SHALL MEET ASTM E84 25/50 FLAME AND SMOKE SPREAD RATING, AND COMPLY WITH NFPA STANDARD 90A.
2. REFER TO SPECIFICATIONS FOR FURTHER INSULATION REQUIREMENTS. INSULATION R-VALUE SHALL MEET ENERGY CODE REQUIREMENTS.
1. REFER TO SPECIFICATIONS FOR FURTHER PIPE MATERIAL, JOINT AND INSTALLATION REQUIREMENTS. PUSH TO CONNECT / PUSH ON TYPE CONNECTIONS ARE NOT ALLOWED.
NOTES:
REFRIGERANT PIPING - EXTERIOR FIELD VERIFY N/A N/A N/A ELASTOMERIC 1 1/2 ALUMINUM
CHILLED WATER - EXTERIOR 2 1/2 - 10 SCHED. 40 STEEL GROOVED OR WELDED DUCTILE IRON,BUTTERFLY ELASTOMERIC 3 ALUMINUM
CHILLED WATER - INTERIOR 2 1/2 - 10 SCHED. 40 STEEL GROOVED OR WELDED DUCTILE IRON,BUTTERFLY ELASTOMERIC 2 PVC
SYSTEM
PIPE SIZE
(INCHES)
PIPE MATERIAL
(NOTE 1)
JOINT TYPE
(NOTE 1)
SHUT-OFF VALVE TYPE
(NOTE 4)
INSULATION TYPE
(NOTE 2,3)
INSULATION
THICKNESS
(INCHES)
JACKET
(NOTE 5)
HVAC PIPING AND INSULATION SCHEDULE
CONTRACTOR SHALL PROVIDE GLYCOL ANALYSIS AND FREEZE
PROTECTION VERIFICATION AT STARTUP. REFER TO SPECIFICATIONS FOR
ADDITIONAL DETAILS.
5. PROVIDE COTTONWOOD SCREENS BY CHILLER MANUFACTURER.
4. PROVIDE INTERIA BASE FRAME.
3. UNIT TO HAVE LOW AMBIENT OPERATION CABABILITIES TO OPERATE DOWN TO -20F.
2. PROVIDE WITH SINGLE POINT POWER & NON-FUSED DISCONNECT.
1. UNIT PROVIDED WITH FACTORY INSTALLED FREEZE PROTECTION.
NOTES:
NOTES 1 THROUGH 5
STARTER TYPE ACROSS THE LINE
SINGLE POINT MOCP 200
SINGLE POINT MCA 163
TOTAL UNIT POWER (kW) 85.50
VOLTAGE / PHASE 460/3
ELECTRICAL DATA
CAPACITY STEPS 4
NUMBER OF COMPRESSORS 4
NUMBER OF CIRCUITS 2
CONDENSER AMBIENT TEMP. (°F) 95
EVAP. PRESS. DROP (FT HD) 18.00
EVAPORATOR LVG. TEMP. (°F) 40
EVAPORATOR ENT. TEMP. (°F) 52
EVAPORATOR FLOW (GPM) 170
EVAPORATOR FLUID 50% PROP. GLYCOL
REFRIGERANT CHARGE (LBS) 134
REFRIGERANT R454B
IPLV.IP (BTU/W-H) 18
FULL LOAD EFFICIENCY (EER) 10.1
NET COOLING CAPACITY (TON) 72
NOMINAL CAPACITY (TON) 80
DIMENSIONS - L x W x H (INCHES) 146 X 89 X 93
OPERATING WEIGHT (LBS) 5,700
SERVES MASTER CONTROLS
TYPE (AIR COOLED) AIR COOLED SCROLL
MODEL # CGAM
MANUFACTURER TRANE
REFERENCE CH-1 & CH-2
CHILLER SCHEDULE
5. PROVIDE COTTONWOOD SCREENS BY CHILLER MANUFACTURER.
4. INTENT IS FOR DRY COOLER TO HANDLE CHILLED WATER COOLING LOAD BELOW 30F TO INCREASE EFFICIENCY AND REDUCE MECHANICAL COOLING.
3. UNIT SOUND IS 83 DB.
2. PROVIDE SINGLE POINT CONNECTION WITH INTEGRAL NON-FUSED DISCONNECT AND 22" HEIGHT SUPPORT LEGS.
1. SEE CONTROL DRAWINGS FOR ADDITIONAL INFORMATION.
NOTES:
NOTES 1 THROUGH 5
MOP 40.0
MCA 32.1
VOLTAGE - PH 480 / 3
MOTOR HP 1.5
ELECTRICAL DATA
FAN QTY. / RPM 12 / 1140
PRESSURE DROP (FT HD) 10
AIR VELOCITY (FPM) 645
AIR FLOW (CFM) 123,000
AMBIENT AIR TEMP (°F) 30
LWT (°F) 42
EWT (°F) 52
FLOW RATE (GPM) 170
TOTAL CAPACITY (MBH) 769
FLUID TYPE 50% PROP. GLYCOL
INTERNAL VOLUME (GAL) 72
DIMENSIONS - L x W x H (INCHES) 330 x 90 x 64
WEIGHT (LBS) 5,400
SERVES CHILLED WATER
MODEL # FEVF 26412
MANUFACTURER KRACK
REFERENCE DC-1
DRY COOLER SCHEDULE
# Revision Date
1 Addendum 2 8.07.26
W
M
M
W
POWER GENERAL NOTES
A. COORDINATE LOCATION/INSTALLATION OF MECHANICAL AND ELECTRICAL
WORK WITH ALL OTHER TRADES. NO ASPECT OF A SYSTEM INSTALLATION
OR ITS ROUGH-IN SHALL COMMENCE UNTIL PROPER AND TIMELY
COORDINATION WITH ALL TRADES ASSOCIATED WITH THE INSTALLATION HAS
TRANSPIRED. ITEMS TO BE COORDINATED SHALL INCLUDE BUT NOT BE
LIMITED TO: BUILDING STRUCTURE, SHEET METAL, PIPING SYSTEMS, LIGHT
FIXTURES, CONDUITS, CABLE TRAYS, ETC. REFER TO ALL GENERAL,
MECHANICAL, AND ELECTRICAL DRAWINGS AND SPECIFICATIONS FOR THIS
PROJECT.
B. COORDINATE ELECTRICAL REQUIREMENTS FOR MECHANICAL UNITS WITH
MECHANICAL CONTRACTOR AND FINAL MECHANICAL SHOP DRAWINGS.
C. PROVIDE PENETRATIONS REQUIRED FOR ROUTING RACEWAYS THROUGH
THE BUILDING. COORDINATE FIRE RATED WALL PENETRATIONS AND
PROVIDE CONDUIT SLEEVES AND FIRE STOPPING TO MAINTAIN RATING.
PROVIDE ALL INTERIOR PENETRATIONS ARE 1 HOUR WALLS AND EXTERIOR
PENETRATIONS ARE 2 HOURS.
LUNCH ROOM
VENDING
STORAGE ROOM
WOMENS
MENS
ELEC. RM.
MECH RM.
CORRIDOR
EFP
1169A
FIBER
GENERAL SERVICES
1170A
COMP. ROOM
TECHNICAL STORAGE
RECEIVING
CLOSET
CLOSET
JAN.
1167A
VEST.
EXISTING PANEL SB-2
DC
PANEL BE
PANEL EM
PANEL G
INSTALL 40A 3P BREAKER IN
BREAKER SPACES 1,3,5 FOR
DRY COOLER. EXISTING
WESTINGHOUSE 480V PANEL.
BE-1,3,5
CONNECT NEW
RECEPTACLES TO
EXISTING PANEL G
CIRCUIT. VERIFY EXISTING
RECEPTACLE QUANTITY
ON CIRCUIT #12. IF 6 OR
LESS, INSTALL NEW
RECEPTACLES ON #12
CIRCUIT.
G-12 EXISTING PANEL EDP08
CONDENSERS
MECHANICAL / EQUIP.
EMERGENCY GENERATOR
MECHANICAL / EQUIP.
EQUIP. ROOM
CONTROL
CWP-1
CWP-2
EXISTING PANEL SB-4
(WESTINGHOUSE)
INSTALL 20A FUSES IN
30A BUCKETS IN PANEL
FOR NEW CWP-1 AND
CWP-2. REUSE EXISTING
CONDUIT AND
CONDUCTORS FROM
SB-4 TO VFD LOCATION.
REFEED FROM NEW BREAKER IN EDP08.
REFER TO ONE-LINE FOR MORE INFORMATION.
G-12
SB-4
SB-4
EXISTING PANEL P
REMOVE BREAKERS AND INSTALL
NEW BREAKER FOR DRY COOLER
Drawing #:
Date:
Project No:
© 2022 KCL Engineering L.L.C. These documents have been prepared specifically for this project. they are not suitable for use on other projects or in other locations without the expressed written approval and participation of KCL Engineering L.L.C. A limited license is granted to the owner/contractor to reproduce these documents or portions thereof, but only for use in connection with this project. Unauthorized reproduction is prohibited.
P lo t D a te
T im e
Drawing Name:
info@kclengineering.com
300 4th St West Des Moines, IA 50265 515-724-7938
/6
/2
:5 :4
P
M
E101
CONSTRUCTION
DOCUMENTS
07/06/2026
9525.00
D A
S I
P B
S M
O T
IV
A
IR
C
H
IL
L E
R R
E P
L A
C E
M E
N T
C
O R
P O
R A
T E
D R
IV
E
J O
H N
S T
O N
IA
ELECTRICAL POWER
1/8" = 1'-0"
LEVEL 1 POWER PLAN
1/8" = 1'-0"
ROOF POWER PLAN
N
N
INSTALL NEW LIQUID
TIGHT FLEXIBLE CONDUIT
WITH #12 AWG FROM VFD
TO NEW PUMPS.
# Revision Date
1 Addendum 2 8.06.26
NOT TO SCALE
SB-4 PANEL
REPLACE FUSES IN EXISTING BUCKET
NOT TO SCALE
BE PANEL
File details come from the government source that posted it. Updated .