This is Addendum No. 1 issued by the State of Iowa Department of Administrative Services regarding RFB 952500-01 for IPBS HVAC - Motivair Units Replacement at 6450 Corporate Drive, Johnston, Iowa 50131. The project involves replacement of two Motivair chiller units with associated piping, ancillary components (pumps, dry cooler), and re-insulation of existing piping to remain. The scope includes any necessary roof repair work as part of the base bid. A pre-bid meeting was held on July 21, 2026 from 2:00 PM to 3:00 PM at the project site, with attendees from Boyd Jones Construction Company, Iowa PBS, KCL Engineering, and the Department of Administrative Services. The addendum moves the original bid due date from July 30, 2026 to August 11, 2026 at 2:00 PM, with bid opening scheduled for 3:00 PM on August 11, 2026. Construction is planned for 53 days commencing December 3, 2026, with substantial completion targeted for February 15, 2027 and final completion by March 29, 2027. The contract is issued August 6, 2026, followed by a three-week submittal period to be completed by September 9, 2026.

Key requirements include onsite prime contractor supervision at all times, daily logs for site presence, and adherence to Monday through Friday work hours of 8:00 AM to 5:00 PM. One chiller unit must remain operational throughout construction to maintain facility operations. Contractors must coordinate with Koopman Roofing for all roof work to maintain the existing roof warranty. Site rules prohibit smoking, vaping, and smokeless tobacco; contractors must provide temporary facilities and handle all demolished equipment disposal. Bid security of 5% of the total bid amount is required. Successful bidders must submit a complete list of subcontractors and suppliers within 48 hours of bid opening. The contract will operate under a modified ConsensusDocs 802 form of agreement with project-specific certificates of insurance and performance and payment bonds required prior to contract execution. Procore will be used for project management including submittals, invoicing, RFIs, and change orders at no cost to the contractor.

View the file

Other files

File Type Posted
RFB952500-01 - Bid Form.pdf PDF
RFB952500-01 - Notice To Bidders.pdf PDF
RFB952500-01 - Project Manual.pdf PDF
RFB952500-01 - Drawings.pdf PDF
RFB952500-01 - Addendum No. 1.pdf PDF
RFB952500-01 - Addendum No. 2.pdf PDF
1412843-event.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

Date: 7/27/26

Project Name: 9525.00 – IPBS Motivair Chiller Replacements

DAS RFB #: 952500-01

DAS Project #: 9525.00

PROPOSALS DUE: 8/11/26

The receipt of this Addendum shall be acknowledged by the design firm in their submission.

This Addendum consists of:

1) Moving bid date/time to August 11, 2026 at 2:00 PM

a. Bid will be opened at 3:00 PM on August 11, 2026

2) Pre-Bid Meeting Minutes

a. See attached meeting minutes.

End of Addendum

State of Iowa - Department of Administrative Services 109 SE 13th St.

Des Moines, Iowa 50319 P: (515) 281-7260

Project: 9525.00 IPBS HVAC - Motivair Units Replacement

6450 Corporate Dr Johnston, Iowa 50131

RFB Pre-Bid Minutes: Meeting #1

Meeting Date Jul 21, 2026 Meeting Time 02:00 pm - 03:00 pm Central Time (US & Canada)

Meeting Location 6450 Corporate Drive, Johnston, Iowa 50131 Video Conferencing Link

Join Meeting

Overview Meeting to allow prospective bidders to visit the site, when possible, and learn more about the project.

Notes

Attachments

Scheduled Attendees

Name Company Phone Number Email Attendance

Lily Anderson Boyd Jones Construction Company

P: (402) 553-1804 landerson@boydjones.biz

Katie Bollenbaugh Boyd Jones Construction Company

P: (515) 298-2474 kbollenbaugh@boydjones.biz

Luke Danielson Boyd Jones Construction Company

P: (402) 553-1804 ldanielson@boydjones.biz

Rob Greiner Boyd Jones Construction Company

P: (402) 553-1804 rgreiner@boydjones.biz Present

Leah Malchow Boyd Jones Construction Company

P: (402) 553-1804 lmalchow@boydjones.biz

Adam Papesh Boyd Jones Construction Company

P: (402) 553-1804 apapesh@boydjones.biz

Mike Downey Iowa PBS michael.downey@iowapbs.org Present

Jamie Dye Iowa PBS P: (515) 249-1923 james.dye@iowapbs.org Present

Kris May Iowa PBS P: (515) 321-2791 kris.may@iowapbs.org

Michelle Wendel Iowa PBS michelle.wendel@iowapbs.org Present

Chad Bass KCL Engineering P: (515) 724-7938 cbass@kclengineering.com Present

Eric Heynen KCL Engineering P: (515) 724-7938 eheynen@kclengineering.com Present

Geoff Wheelock State of Iowa - Department of Administrative Services

P: (515) 725-1213 geoff.wheelock@das.iowa.gov Conference

Introduction

State of Iowa - Department of Administrative Services Page 1 of 5 Printed On: Jul 27, 2026 12:53 PM CDT https://teams.microsoft.com/meet/211562880984327?p=EWTVDwgYtzanmwk1i1

No. Mtg Origin Title Assignment Due Date Priority Status

1.1 1 Introductions Open

Description Attendees

Attachments

9525.00 - Pre-Bid Meeting - Sign-in Sheet.pdf

Official Documented Meeting Minutes See attached sign-in sheet

Project Overview

2.1 1 Project Description Open

Description The Iowa Department of Administrative Services will be receiving bids for replacement of two (2) Motivair Chiller Units at IPBS.

Including associated piping/ancillary components (pumps, dry cooler, etc.) and re-insulating existing piping that is to remain.

• Base bid - Complete Scope of Project

• Alternates - NA

• Unit prices - NA

Official Documented Meeting Minutes Contractor asked if Roof repairs are to be included as part of their bid. Documents call for the BP #1 Complete Scope to provide any roof repair work.

Any changes to scope will be issued in future addendum.

2.2 1 Project Schedule Open

Description

• Contract(s) Issued: 8/6/26

• Submittals: 3 weeks after contract signed. Submittal process to be complete by 9/9/26

• Construction: 53 days. Start date based on delivery date of equipment. Work planned for 12/3/26 - 2/15/26

• Closeout: Substantial Completion by 2/15/27 and Final Completion by 3/29/27

A pull-plan session will be held with the successful bid package contractors to finalize the construction schedule.

State Holidays: New Year's Day, Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day, Thanksgiving and day after Thanksgiving, Christmas Day

Official Documented Meeting Minutes The facility has live studio recordings (typically on Fridays) and has requested cooperation with the contractor during construction to limit any loud noises on those days. Team will work together during construction activities to work through any potential days where loud work will need to be prohibited.

Meeting #1 - RFB Pre-Bid Project: 9525.00 IPBS HVAC - Motivair Units Replacement

State of Iowa - Department of Administrative Services Page 2 of 5 Printed On: Jul 27, 2026 12:53 PM CDT https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/42578-c/7592543-p/01KYJACJQZD03JF0K0HDK5Q3YC?companyId=87524&projectId=3452957&sig=7a8634cf964d22b35299706857b52c3ff54bda408fd5f61485099ab1577f6c3b

2.3 1 Site Rules Open

Description

• Onsite supervision by Prime Contractor is required at all times when work by that contractor or their subcontractors/suppliers is taking place.

• Contractors shall provide daily logs for each day they are on site.

• Construction progress meeting will be established once construction starts.

• It is of the utmost importance to show respect and courtesy to all staff at all times.

• Clean all debris, materials, and bring all finishes back to existing conditions in the area they were working in prior to moving to the next area.

• No smoking, vaping or smokeless tobacco use onsite.

• Replacement of the Motivair Units will need to be sequenced so one (1) unit is operational at all times.

• Any damage/repair to the roof will need to be through Koopman Roofing, 641-621-0131 to maintain existing roof warranty.

• Temporary facilities - contractor to provide temporary toilet for workers. Tool storage/parking to be coordinated with BJC

• Demolished equipment - To be disposed of by Contractor

• Work hours: Monday thru Friday 8:00 am - 5:00 pm

• View Specification 01 1200 - Contract Summary for more information.

Official Documented Meeting Minutes Owner is flexible on start/end times during the days and would be open for discussions about work on Saturdays if requested by contractor.

RFB Overview

3.1 1 Bid Submission Open

Description

• Bids are due July 30, 2026 at 2:00 PM

• The Bid shall be submitted to the Issuing Officer through the IMPACS Electronic Procurement System.

o Link and information is in the project manual o Contractors will need to register prior to bidding o Bidders will need to register regardless of whether it has already done business with the State of Iowa.

o Bidders should complete the registration process and ensure the ability to log in as soon as possible to ensure Bids can be submitted on the due date.

o Please make sure the electronic documents submitted contain any required signatures. Digital signatures will be accepted.

• Bid Opening will be held via conference call on July 30, 2026 at 3:00 PM o Microsoft Teams meeting with link in bid documents with Meeting ID and Passcode

• Contractor shall reference section 00 0116 for the bid submittal checklist o Bid Proposal Information o Non Discrimination Clause Information o Contractor Targeted Small Business Enterprise Pre-Bid Contract Information o Bid Security – 5% of total Bid amount

• Apparent low bidder will be required to submit subcontractor/supplier list 48hrs after the bid opening

State of Iowa - Department of Administrative Services Page 3 of 5 Printed On: Jul 27, 2026 12:53 PM CDT

3.2 1 Bid Schedule Open

Description

• Questions/Substitutions Due in Writing to Construction.Procurement@das.iowa.gov: July 22, 2026 by 5:00 PM

• Last Addendum Issued: No later than 7/28/26

• Bids Due: July 30, 2026 at 2:00 PM

• Tentative NOI Issued: August 5, 2026

3.3 1 Administrative Details Open

Description

• Contractors will sign a modified ConsensusDocs 802. Example in the project manual.

• Project-specific Certificate of Insurance must be provided prior to contract execution. Follow example in the project manual and limits in the 802.

• Project-specific P&P bonds must be provided prior to contract execution.

• Successful contractor must turn in their list of subcontractors and suppliers within 48 hours of the bid.

• DAS will provide tax exempt certificates upon request.

• Procore will be used for all project management, at no cost to the trade contractor.

o Submittals, Invoicing, RFIs, ASIs, PRs, RFQs o Contracts, Change Orders and Certificates of Substantial and Final Completion will also use Docusign

• Contractor Schedule of Values shall be broken out as specified in the project manual.

o SOV must contain a closeout line item for at least 1% of the total contract value.

o This line item can only be invoiced once the certificate of final completion has been signed by all parties.

3.4 1 Pre-Bid Site Visits Open

Description Additional site visits to be coordinated through BJC

• Rob Greiner, 515-650-7777

• Leah Malchow, 402-239-5390

Questions

4.1 1 Questions Open

Description Submit all questions in writing to construction.procurement@iowa.gov.

Official Documented Meeting Minutes Where can contractor plan for stating of material? Facility will work to secure multiple parking spaces as close to the work area as possible for the contractor to stage material. Contractor parking to be utilized in available public parking spaces.

Who is facility's contact at JCI - Ford Lillard is facility's direct contact, 515-721-6709, ford.lillard@jci.com.

How many gallons is the current cooling system? Team to review and provide answer via addendum Are the pipe stands/supports (made of wood and metal) to be replaced during the construction? Team to review and provide answer via addendum

State of Iowa - Department of Administrative Services Page 4 of 5 Printed On: Jul 27, 2026 12:53 PM CDT mailto:Construction.Procurement@das.iowa.gov:

mailto:ford.lillard@jci.com

These meeting minutes are believed to be an accurate reflection of those items discussed and the conclusions that were reached during the referenced meeting.

Please contact State of Iowa - Department of Administrative Services if there are any discrepancies or questions with the content of these minutes.