RFB918604-01 - Hoover 3rd Floor Schedule (FINAL).pdf
PDF 102 KB Posted
- Attached to
- Hoover 3rd Floor Renovations
- Solicitation number
- RFB918604-01
- Issued by
- Polk County, Iowa
About this file
The document provided is a project schedule for the "Hoover 3rd Floor Renovation" project. This is a state and local contract opportunity managed by the Department of Public Defense in the state of Iowa. The project involves modernizing and renovating the third floor of the Hoover building, with a planned start date of March 25, 2024 and a completion date of January 9, 2025. The key milestones include 50% and 95% completion of construction documents, 100% bid documents, contractors under contract by October 2, 2024, and various construction activities such as demolition, framing, electrical/mechanical work, painting, flooring, and furniture installation.
The procurement process includes a pre-bid meeting, questions due, final addendum, and bids due dates. The contract will be awarded to the successful bidder, with no information provided on any set-asides, incumbents, or funding sources. Pricing details and other commercial terms are not included in the provided documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-Bid Meeting - Google Meet.html | HTML file | |
| Bid Opening - Google Meet.html | HTML file | |
| RFB918604-01 - Bid Form.pdf | ||
| Project Manual RFB918604-01.html | HTML file | |
| RFB918604-01 - Notice.pdf | ||
| RFB918604-01 - Project Manual.pdf | ||
| Bid Documents and Drawings.html | HTML file | |
| 1258264-event.pdf | ||
| RFB918604-01 - Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original
Duration
Remaining
Duration
Schedule %
Complete
Start Finish
9186.04 Hoover 3rd Floor Renovation9186.04 Hoover 3rd Floor Renovation 202 101 0% 25-Mar-24 A 09-Jan-25
MilestonesMilestones 96 26 0% 16-May-24 A 02-Oct-24
A1100 Start of Design 0 0 100% 16-May-24 A
A3100 Designer Under Contract 0 0 100% 16-May-24 A
A1410 50% CDs Complete 0 0 100% 18-Jul-24 A
A1420 95% CDs Complete 0 0 100% 08-Aug-24 A
A3060 CD Estimate 0 0 100% 08-Aug-24 A
A1110 100% Bid Documents 0 0 0% 23-Aug-24
A1230 Contractors under Contract 0 0 0% 02-Oct-24
PreconstructionPreconstruction 134 33 0% 25-Mar-24 A 01-Oct-24
ConstructionConstruction 99 99 0% 15-Aug-24 07-Jan-25
AdministrativeAdministrative 20 20 0% 18-Sep-24 15-Oct-24
A1760 Bid Package Scope Review (Each Prime) 10 10 0% 18-Sep-24 01-Oct-24
A1750 Contractor Site Specific Safety Plans Submitted 5 5 0% 02-Oct-24 08-Oct-24
A1890 DNR Notification of Demolition & Renovation 10 10 0% 02-Oct-24 15-Oct-24
ProcurementProcurement 57 57 0% 15-Aug-24 04-Nov-24
A1740 Early VAV Package 10 10 0% 15-Aug-24 28-Aug-24
A1790 Early Door & Borrow Light Frame Package 10 10 0% 15-Aug-24 28-Aug-24
A1700 VAV Submittal Development 10 10 0% 29-Aug-24 12-Sep-24
A4520 Door & Borrow Light Frame Submittal Development 5 5 0% 29-Aug-24 05-Sep-24
A4530 Door & Borrow Light Frame Submittal Review 5 5 0% 06-Sep-24 12-Sep-24
A1710 VAV Submittal Review 5 5 0% 13-Sep-24 19-Sep-24
A4540 Door & Borrow Light Frame Product Ordered 2 2 0% 13-Sep-24 16-Sep-24
A4550 Door & Borrow Light Frame Delivery 20 20 0% 17-Sep-24 14-Oct-24
A1720 VAV Product Ordered 2 2 0% 20-Sep-24 23-Sep-24
A1730 VAV Delivery 30 30 0% 24-Sep-24 04-Nov-24
ConstructionConstruction 96 96 0% 20-Aug-24 07-Jan-25
A1780 Owner Move Out 5 5 0% 20-Aug-24* 26-Aug-24
A4490 Gov Deals Posting - Furniture 15 15 0% 27-Aug-24 17-Sep-24
A4170 Furniture Removal 10 10 0% 18-Sep-24 01-Oct-24
A1770 Construction Kick-Off Meeting 1 1 0% 02-Oct-24 02-Oct-24
A4310 Mobilization 5 5 0% 02-Oct-24 08-Oct-24
A4160 General Demolition 5 5 0% 09-Oct-24 15-Oct-24
A1460 Raised Floor Demolition 2 2 0% 16-Oct-24 17-Oct-24
A4180 Remove Abandoned in Floor Electrical/Data 5 5 0% 16-Oct-24 22-Oct-24
A4190 Mechanical Rough-Ins 10 10 0% 16-Oct-24 29-Oct-24
A4200 Core Drill New Floor Duct Penetrations 4 4 0% 23-Oct-24 28-Oct-24
A4210 Prime Paint Ceilings 10 10 0% 25-Oct-24 07-Nov-24
A4220 Set Frames 1 1 0% 25-Oct-24 25-Oct-24
A4230 New Wall Framing 3 3 0% 28-Oct-24 30-Oct-24
A4240 In Wall Rough-In 4 4 0% 31-Oct-24 05-Nov-24
A4250 In Wall Inspection 0 0 0% 05-Nov-24
A4270 Drywall, Insulation, and Finishing 10 10 0% 06-Nov-24 19-Nov-24
A4260 In Floor Electrical Rough-In 10 10 0% 08-Nov-24 21-Nov-24
A4280 Prime Paint Walls 5 5 0% 15-Nov-24 21-Nov-24
A4300 Final Paint Ceilings 10 10 0% 15-Nov-24 02-Dec-24
A4290 Mechanical Trimout 2 2 0% 20-Nov-24 21-Nov-24
A4320 Carpet & Vinyl Base Install 10 10 0% 22-Nov-24 09-Dec-24
A4350 Final Paint 5 5 0% 05-Dec-24 11-Dec-24
A4330 Electrical Trim Out 2 2 0% 10-Dec-24 11-Dec-24
A4340 Hang Doors 1 1 0% 10-Dec-24 10-Dec-24
A4480 Owner Contingency 5 5 0% 12-Dec-24 18-Dec-24
A4360 Furniture Install 12 12 0% 19-Dec-24 07-Jan-25
CloseoutCloseout 31 31 0% 22-Nov-24 09-Jan-25
A4370 O&M & Attic Stock Procurement 20 20 0% 22-Nov-24 23-Dec-24
A4440 Building Final Inspection 0 0 0% 18-Dec-24
A4450 Intial Construction Clean 1 1 0% 19-Dec-24 19-Dec-24
A4390 DCI Group Punch List 1 1 0% 20-Dec-24 20-Dec-24
A4400 DCI Punch List Correction 5 5 0% 23-Dec-24 30-Dec-24
A4410 Owner & Design Te am Punch L ist 1 1 0% 31-Dec-24 31-Dec-24
A4380 Owner Training 2 2 0% 02-Jan-25 03-Jan-25
A4420 Owner & Design Te am Punch L ist Corre ctions 5 5 0% 02-Jan-25 08-Jan-25
A4460 Final Clean 1 1 0% 09-Jan-25 09-Jan-25
A4430 Owner Occupancy 0 0 0% 09-Jan-25
A4470 Owner Closeout Conference 0 0 0% 09-Jan-25
04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16
August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025
09-Jan-25, 9186.04 Hoover 3rd Floor Renovation
02-Oct-24, Milestones
95% CDs Complete
CD Estimate
100% Bid Documents
Contractors under Contract
01-Oct-24, Preconstruction95% CD Submittal95% CD Review Meeting 100% Bid Doc Submittal RFB Pre-bid MeetingRFB Questions DueRFB Final AddendumBids DueContractor NOIs
07-Jan-25, Construction
15-Oct-24, Administrative
Bid Package Scope Review (Each Prime)
Contractor Site Specific Safety Plans Submitted
DNR Notification of Demolition & Renovation
04-Nov-24, Procurement
Early VAV Package
Early Door & Borrow Light Frame Package
VAV Submittal Development
Door & Borrow Light Frame Submittal Development
Door & Borrow Light Frame Submittal Review
VAV Submittal Review
Door & Borrow Light Frame Product Ordered
Door & Borrow Light Frame Delivery
VAV Product Ordered
VAV Delivery
07-Jan-25, Construction
Owner Move Out
Gov Deals Posting - Furniture
Furniture Removal
Construction Kick-Off Meeting
Mobilization
General Demolition
Raised Floor Demolition
Remove Abandoned in Floor Electrical/Data
Mechanical Rough-Ins
Core Drill New Floor Duct Penetrations
Prime Paint Ceilings
Set Frames
New Wall Framing
In Wall Rough-In
In Wall Inspection
Drywall, Insulation, and Finishing
In Floor Electrical Rough-In
Prime Paint Walls
Final Paint Ceilings
Mechanical Trimout
Carpet & Vinyl Base Install
Final Paint
Electrical Trim Out
Hang Doors
Owner Contingency
Furniture Install
09-Jan-25, Closeout
O&M & Attic Stock Procurement
Building Final Inspection
Intial Construction Clean
DCI Group Punch List
DCI Punch List Correction
Owner & Design Te am Punch List
Owner Training
Owner & Design Team Punch List Corrections
Final Clean
Owner Occupancy
Owner Closeout Conference
9186.04 Hoover 3rd Floor Renovation Classic Schedule Layout 29-Aug-24 10:14
Actual Work
Remaining Work
Critical Remainin...
Milestone
Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
File details come from the government source that posted it. Updated .