About this file

This is a contractor's bid schedule and signature document for the New Hampshire Department of Environmental Services, New Hampshire Geological Survey, for the 2026 Bedrock Monitoring Well Installation Project under the Groundwater Level Monitoring Network. The project involves bedrock well installations at eight locations across New Hampshire: Bath, Concord, Errol, Exeter, Franklin, Lebanon, Lyndeborough, and Walpole. Contractors must bid on a minimum of four sites to be considered for award. The scope of work includes pre-job virtual meetings, site mobilization, site preparation and restoration, overburden drilling, bedrock socket drilling, bedrock drilling in various borehole sizes, steel casing installation, cement grouting, and locking caps. Work is to commence upon issuance of a Notice to Proceed and be completed by June 30, 2027. Example scopes of work provided detail site-specific quantities for each drilling and installation task, with drilling depths and casing requirements varying by location.

Bidders must provide unit prices for each line item, including lump sum prices for mobilization to each site, hourly rates for additional site preparation, and per-foot or per-unit rates for drilling, casing, and related work. The bid schedule format allows contractors to calculate total bid amounts by applying their unit prices to the specified quantities for each site. All work must be performed in accordance with specifications and in a workmanlike manner, with contractor guarantee of quality and remediation of any defective work. Bidders are required to certify they are not debarred from federal transactions and must execute a contract affidavit confirming compliance with competitive bidding regulations under Title 23 USC, Section 112(c).

View the file

Other files

File Type Posted
rfb-des-2026-20.pdf PDF
rfb-des-2026-20-attachment-2.pdf PDF
rfb-des-2026-20-attachment-3.pdf PDF
rfb-des-2026-20-addendum-1.pdf PDF
rfb-des-2026-20-attachment-1--amended-.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

STATE OF NEW HAMPSHIRE

DEPARTMENT OF ENVIRONMENTAL SERVICES

NEW HAMPSHIRE GEOLOGICAL SURVEY

Groundwater Level Monitoring Network 2026 Bedrock Well Installation Project

Attachment 1 - CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES

CONTRACTOR NAME

CONTRACTOR

ADDRESS

SIGNATURE OF

BIDDER

TITLE

Please indicate by marking with an “x” in the circle next to the locations for which of the eight (8) Bedrock Well Installations your firm is providing a bid.

Minimum of 4 sites required for bid consideration

1. Bath ⃝

2. Concord ⃝

3. Errol ⃝

4. Exeter ⃝

5. Franklin ⃝

6. Lebanon ⃝

7. Lyndeborough ⃝

8. Walpole ⃝

The CONTRACTOR’s unit prices, provided on pages 2 and 3 of this document will be used along with the quantities specified in the Example Scopes of Work for each BEDROCK WELL INSTALLATION Site, specified on pages 4, 5, 6, and 7 of this document, to calculate the CONTRACTOR’s total bid amount for each site.

Groundwater Level Monitoring Network 2026 Bedrock Monitoring Well Installation Project

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

ITEM ITEM AND UNIT PRICES BID IN WORDS PAY UNIT UNIT PRICE

1.1 Pre-job virtual meeting

Each $

______________________________________DOLLARS

1.2.1 Mobilization to Bath, NH

Lump Sum $

______________________________________DOLLARS

1.2.2 Mobilization to Concord, NH

Lump Sum $

______________________________________DOLLARS

1.2.3 Mobilization to Errol, NH

Lump Sum $

______________________________________DOLLARS

1.2.4 Mobilization to Exeter, NH

Lump Sum $

______________________________________DOLLARS

1.2.5 Mobilization to Franklin, NH

Lump Sum $

______________________________________DOLLARS

1.2.6 Mobilization to Lebanon, NH

Lump Sum $

______________________________________DOLLARS

1.2.7 Mobilization to Lyndeborough, NH

Lump Sum $

______________________________________DOLLARS

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

ITEM ITEM AND UNIT PRICES BID IN WORDS PAY UNIT UNIT PRICE

1.2.8 Mobilization to Walpole, NH

Lump Sum $

______________________________________DOLLARS

1.3.1 Standard Site Preparation and Restoration

Lump Sum $

______________________________________DOLLARS

1.3.2

Hourly Rate for Additional Site Preparation and Restoration Per Hour $

______________________________________DOLLARS

2.1 Overburden Drilling Rate, nominal 8-inch borehole

Per Foot $

______________________________________DOLLARS

2.2 Bedrock Socket Drilling Rate, nominal 8-inch borehole

Per Foot $

______________________________________DOLLARS

2.3 Bedrock Drilling Rate, nominal 6-inch borehole

Per Foot $

______________________________________DOLLARS

2.4 Steel Casing, 6-inch diameter, Schedule 40

Per Foot $

______________________________________DOLLARS

2.5 Cement Grout Casing

Lump Sum $

______________________________________DOLLARS

2.6 Locking Cap

Each $

______________________________________DOLLARS

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

Example Scopes of Work for Bedrock Well Installation Site 1 - Bath

Item Nos. Item Description Quantity Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.1 Mobilization to Bath, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 20 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 460 Item No. 2.4 Steel Casing, per foot 43 Item No. 2.5 Cement Grout Casing, lump sum 1 Item No. 2.6 Locking Cap, each 1

Site 2 - Concord

Item Nos. Item Description Quantity Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.2 Mobilization to Concord, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 8 Item No. 2.1 Overburden Drilling Rate, per foot 160 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate, per foot 320 Item No. 2.4 Steel Casing, per foot 183 Item No. 2.5 Cement Grout Casing, lump sum 1

Item No. 2.7 Haulage of Drilling Spoils, per cubic yard 8

Site 3 - Errol

Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.3 Mobilization to Errol, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 120 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 360 Item No. 2.4 Steel Casing, per foot 143

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

Example Scopes of Work for Bedrock Well Installation, continued Site 4 - Exeter

Item Nos. Item Description Quantity Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.4 Mobilization to Exeter, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 60 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 420 Item No. 2.4 Steel Casing, per foot 83

Site 5 - Franklin

Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.5 Mobilization to Franklin, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 140 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 340 Item No. 2.4 Steel Casing, per foot 43

Site 6 - Lebanon

Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.6 Mobilization to Lebanon, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 20 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 460 Item No. 2.4 Steel Casing, per foot 43

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

Site 7 - Lyndeborough

Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.7 Mobilization to Lyndeborough, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 8 Item No. 2.1 Overburden Drilling Rate, per foot 25 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 15 Item No. 2.3 Bedrock Drilling Rate , per foot 460 Item No. 2.4 Steel Casing, per foot 43

Site 8 - Walpole

Item No. 1.1 Pre-job virtual meeting, lump sum 1 Item No. 1.2.8 Mobilization to Walpole, NH, lump sum 1 Item No. 1.3.1 Standard Site Preparation and Restoration, lump sum 1 Item No. 1.3.2 Hourly Rate for Additional Site Preparation and Restoration 4 Item No. 2.1 Overburden Drilling Rate, per foot 150 Item No. 2.2 Bedrock Socket Drilling Rate, per foot 20 Item No. 2.3 Bedrock Drilling Rate , per foot 330 Item No. 2.4 Steel Casing, per foot 43

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

It is proposed:

To execute the Contract and begin work on the date specified in the “Notice to Proceed” and to prosecute said work so as to complete the BEDROCK WELL INSTALLATION and its appurtenances on or before June 30, 2027.

To guarantee all work performed under this Contract to be done in accordance with the Specifications and in good and workmanlike manner, and to renew or repair any work that may be rejected, because of defective materials or workmanship, prior to final completion and acceptance of the project.

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER RESPONSIBILITY MATTERS.

PRIMARY COVERED TRANSACTIONS.

(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and all its principals: (a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency; (b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statues or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property; (c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, or local) with commission of any of the offenses enumerated in paragraph (1) (b) of this certification and (d) Have not within a three-year period preceding this application/proposal had one or more public transactions (Federal, State or local) terminated for cause or default. (2) Where the prospective primary participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal.

CONTRACT AFFIDAVIT

I/We declare under penalty of perjury under the laws of the United States and the State of New Hampshire that, in accordance with the provisions of Title 23 USC, Section 112(c), have not either directly or indirectly entered into any agreement, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this Proposal.

Attachment 1 – CONTRACTOR'S BID SCHEDULE and SIGNATURE PAGES continued

New Hampshire Geological Survey Groundwater Level Monitoring Network Contractor Initials ________ 2026 Bedrock Monitoring Well Installation Project Date ________

Dated: ______________________________ (If a firm or individual)

Signature of Bidder ________________________________

By ________________________________

Address of Bidder ________________________________

Names and addresses of members of the Firm or Organization:

(If a Corporation)

Signature of Bidder ________________________________

Title ________________________________

By ________________________________

Business Address ________________________________

Incorporated under the laws of the State of _______________________________________

Names of Officers:

President: ________________________________________________________ Name Address

Secretary: ________________________________________________________ Name Address

Treasurer: ________________________________________________________ Name Address

File details come from the government source that posted it. Updated .