RFB 7945 Upper Havemeyer Field Drainage Improvements - Technical Specifications Summary
This is a comprehensive technical specification document (Exhibit H) prepared by Weston & Sampson Engineers, Inc. for the Town of Greenwich, Connecticut, detailing requirements for the Upper Havemeyer Field drainage improvements project (RFB #7945). The project encompasses field improvements including natural turf field construction, drainage system installation, seed and sod application, and replacement of the existing irrigation system. The work includes furnishing all labor, materials, equipment, and transportation necessary to complete the project in accordance with the drawings and specifications. Key divisions of work addressed include procurement/contracting requirements, general requirements, existing conditions assessment, earthwork, exterior improvements, and utilities installation. The specifications reference numerous construction sections covering control of work and materials, special provisions, dust control, construction meetings and scheduling, submittals, traffic control signage, temporary fencing, tree protection, environmental protection, cutting and patching, cleanup, project closeout, and operations and maintenance manuals. Specific technical work includes loam and topsoil preparation, filter fabric installation, rock excavation, dewatering operations, earthwork and compaction, natural athletic field turf installation, irrigation system design and installation, seeding, sodding, tracer tape placement, precast manhole installation, polyethylene and reinforced concrete pipe installation, and PVC yard drain structure installation.
The specifications establish detailed requirements for materials, products, and execution standards across all project phases, with emphasis on quality assurance, testing, inspection, and compliance with applicable ASTM standards, Connecticut Department of Transportation specifications, and local codes. The document mandates contractor qualifications, including minimum experience requirements for specialized work such as natural turf field installation (minimum five years of experience) and irrigation system installation. Environmental protection measures are extensively detailed, including requirements for silt fencing, erosion control, dewatering discharge procedures, dust control, and protection of existing landscapes and utilities. The specifications require comprehensive submittals including shop drawings, product data, test results, soil analysis, as-built drawings prepared by Connecticut licensed surveyors, and operations and maintenance manuals in specific formats. Contractor responsibilities include maintaining construction schedules using Critical Path Method scheduling, providing project signage, conducting pre-construction and progress meetings, obtaining necessary permits, providing temporary facilities and site security with chain-link fencing, coordinating with utility companies, and maintaining the work through a one-year warranty period following substantial completion, including first-year winterization and spring start-up for the irrigation system.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WESTON & SAMPSON ENGINEERS, INC.
712 Brook Street, Suite 103 Rocky Hill, CT 06067 tel: 860.513.1473
March 4, 2026
TOWN OF
Greenwich
CONNECTICUT
Upper Havemeyer Field
TOWN PROJECT NUMBER:
RFP 7945
TECHNICAL
SPECIFICATIONS
RFB #7945 EXHIBIT H
04/20/2022 00 01 10-1
SECTION 00 01 10: TABLE OF CONTENTS
DIVISION 00: PROCUREMENT/CONTRACTING REQUIREMENTS
00 01 10 Table of Contents 00 31 43 Permits 00 43 43 Prevailing Wage Rates – BY TOWN
DIVISION 01: GENERAL REQUIREMENTS
01 11 00 Control of Work and Materials 01 12 16 Scope and Sequence of Work 01 14 00 Special Provisions 01 14 19.16 Dust Control 01 31 19.23 Construction Meetings 01 32 16 Construction Schedule 01 32 33 Construction Photographs 01 33 23 Submittals 01 55 26.13 Signage (Traffic Control) 01 56 26 Temporary Chain Link Fence 01 56 39 Temporary Tree and Plant Protection 01 57 19 Environmental Protection 01 73 29 Cutting, Coring & Patching 01 74 13 Cleaning Up 01 78 00 Project Closeout 01 78 39 Project As-Built Record Drawings 01 92 13 Operations and Maintenance Manuals
DIVISION 02: EXISTING CONDITIONS
02 41 13 Selective Site Demolition 02 41 19.16 Minor Electrical Demolition
DIVISION 31: EARTHWORK
31 00 00 Earthwork 31 05 13.13 Loam (Topsoil) 31 05 19.13 Filter Fabric 31 23 16.23 Rock Excavation and Disposal 31 23 19 Dewatering 31 50 00 Support of Excavation
04/20/2022 00 01 10-2
DIVISION 32: EXTERIOR IMPROVEMENTS
32 18 23 Natural Athletic Field Turf 32 84 00 Irrigation System 32 92 19 Seeding 32 92 23 Sodding
DIVISION 33: UTILITIES
33 05 26.13 Tracer Tape 33 39 13 Precast Manholes and Catch Basins 33 41 13.16 Polyethylene Drainage Pipe (Perforated) 33 41 13.28 Reinforced Concrete Pipe 33 44 00 PVC Yard Drain Structure
06/15/2022 00 31 43-1
SECTION 00 31 43
PERMITS
PART 1 – GENERAL
1.01 DESCRIPTION:
This Section provides specific information and defines specific requirements of the Contractor regarding the preparation and acquisition of permits required to perform the work of this project.
1.02 RELATED WORK:
A. Section 01 11 00, CONTROL OF WORK AND MATERIALS
B. Section 01 14 19.16, DUST CONTROL
C. Section 01 55 26.13, SIGNAGE (TRAFFIC CONTROL)
D. Section 01 57 19, ENVIRONMENTAL PROTECTION
I. Section 31 00 00, EARTHWORK
J. Section 31 23 19, DEWATERING
1.03 GENERAL REQUIREMENTS:
A. The Owner has obtained or will obtain and pay for the permits listed below, which are required for this project. The Contractor shall assist in obtaining certain permits, as indicated. The Contractor shall obtain and pay for all other permits required, as defined under the Permits subsection of Section 00 72 00, GENERAL CONDITIONS.
06/15/2022 00 31 43-2
Permits by Owner Status
Building Permit *
Backflow Preventers *
*Contractor shall prepare permit application and obtain the permit after contract is awarded, bearing all expenses. Owner will pay for and/or waive the permit application fee, if applicable.
PART 2 - PRODUCTS
Not Used.
PART 3 – EXECUTION
3.01 PERFORM WORK IN ACCORDANCE WITH REQUIREMENTS:
A. The Contractor shall perform the work in accordance with the Contract Documents, including the attached permits/order of conditions, and any applicable municipal requirements.
B. Prior to commencing any construction activities, the Contractor shall demonstrate to the Owner and the Engineer, through on-site inspection and submitting copies of permits or approvals, that it is in full compliance with the terms and conditions of all permits specified herein. The Contractor shall maintain full compliance with all permits throughout the performance of the work, and upon request, grant access to permitting authorities to inspect the site for the purpose of verifying such compliance.
END OF SECTION
\\Wse03.local\WSE\Projects\CT\Greenwich CT\Greenwich- Upper Havemeyer\Specifications\00 31 43 Permits.docx
SECTION 00 43 43
PREVAILING WAGE RATES
08/07/2018 01 11 00-1
SECTION 01 11 00
CONTROL OF WORK AND MATERIALS
PART 1 – GENERAL
Not Used.
PART 2 – PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 HAULING, HANDLING AND STORAGE OF MATERIALS:
A. The Contractor shall, at its own expense, handle and haul all materials furnished by it and shall remove any of its surplus materials at the completion of the work.
B. The Contractor shall provide suitable and adequate storage for equipment and materials furnished by it that are liable to injury and shall be responsible for any loss of or damage to any equipment or materials by theft, breakage, or otherwise.
C. All excavated materials and equipment to be incorporated in the Work shall be placed so as not to injure any part of the Work or existing facilities and so that free access can be had at all times to all parts of the Work and to all public utility installations in the vicinity of the work. Materials and equipment shall be kept neatly piled and compactly stored in such location as will cause a minimum of inconvenience to public travel and adjoining owners, tenants and occupants.
D. The Contractor shall be responsible for all damages to the work under construction during its progress and until final completion and acceptance even though partial payments have been made under the Contract.
*3.02 EASEMENTS:
A. As indicated on the drawings, the work is located in easements obtained by the Owner.
The Contractor has no rights outside of the easements unless they are obtained from the property owner.
B. Contractor shall schedule work so that it will cause minimum inconvenience and nuisance to abutting property owners, over the shortest possible time.
C. Easements shall be kept clean; no rubbish or discarded construction materials shall be allowed to accumulate. Storage of excess construction materials, including soil, ledge, equipment, or machinery on easements will not be allowed.
08/07/2018 01 11 00-2
D. Restoration of fences, shrubs, trees and grass shall be completed promptly following completion of the work in an easement, to minimize disruption and inconvenience to property owners.
E. Unless approved by the Engineer, the use of easements for ease of access to and egress from other areas of the project will not be permitted.
3.03 OPEN EXCAVATIONS:
A. All open excavations shall be adequately safeguarded by providing temporary barricades, caution signs, lights and other means to prevent accidents to persons, and damage to property. The Contractor shall, at its own expense, provide suitable and safe means for completely covering all open excavations and for accommodating travel when work is not in progress.
B. Bridges provided for access to private property during construction shall be removed when no longer required.
C. The length of open trench will be controlled by the particular surrounding conditions but shall always be confined to the limits prescribed by the Engineer.
D. If the excavation becomes a hazard, or if it excessively restricts traffic at any point, then special construction procedures shall be taken, such as limiting the length of trench and prohibiting stocking excavated material in the street.
E. All street excavations shall be completely closed at the end of each work day. Backfilling or use of steel plates of adequate strength to carry traffic shall be used.
3.04 MAINTENANCE OF TRAFFIC:
A. Unless permission to close the street is received in writing from the proper authority, all excavated materials and equipment shall be placed so that vehicular and pedestrian traffic may be safely maintained at all times.
B. Should the Chief of Police deem it necessary, uniformed officers will be assigned to direct traffic. The Contractor shall make all arrangements in obtaining uniformed officers required.
C. The Contractor shall at its own expense, as directed by the Police Traffic Control/Safety Officer, provide and erect acceptable barricades, barrier fences, traffic signs, and all other traffic devices not specifically covered in a bid item, to protect the work from traffic, pedestrians, and animals. It shall provide sufficient temporary lighting such as lanterns/flashers (electric battery operated) or other approved illuminated traffic signs
08/07/2018 01 11 00-3 and devices to afford adequate protection to the traveling public, at no additional cost to the Owner.
D. The Contractor shall furnish all construction signs that are deemed necessary by and in accordance with Part VI of the Manual on Uniform Traffic Control Devices as published by the U.S. Department of Transportation. In addition, the Contractor may be required to furnish up to 128 square feet of additional special construction warning signs. Size and exact wording of signs shall be determined by the Engineer during construction.
E. The intent of policing is to ensure public safety by direction of traffic. Police officers are not to serve as watchmen to protect the Contractor's equipment and materials.
F. Nothing contained herein shall be construed as relieving the Contractor of any of its responsibilities for protection of persons and property under the terms of the Contract.
3.05 CARE AND PROTECTION OF PROPERTY:
The Contractor shall be responsible for the preservation of all public and private property, and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be promptly restored by the Contractor, at its expense, to a condition similar or equal to that existing before the damage was done, to the satisfaction of the Engineer.
3.06 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND
UTILITIES:
A. All existing buildings, utilities, pipes, poles, wires fences, curbings, property line markers and other structures which the Engineer decides must be preserved in place without being temporarily or permanently relocated, shall be carefully supported and protected from damage by the contractor. Should such property be damaged, it shall be restored by the Contractor, at no additional cost to the Owner.
B. The Contractor shall determine the location of all underground structures and utilities (including existing water services, drain lines, electrical lines, and sewers). Services to
08/07/2018 01 11 00-4 buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by Contractor.
C. When fences interfere with the Contractor's operations, it shall remove and (unless otherwise specified) promptly restore them in accordance with Section 01 14 19.19
EXISTING FENCES.
D. On paved surfaces the Contractor shall not use or operate tractors, bulldozers, or other power-operated equipment with treads or wheels which are shaped so as to cut or otherwise damage such surfaces.
E. All property damaged by the Contractor's operations shall be restored to a condition at least equal to that in which it was found immediately before work was begun. Suitable materials and methods shall be used for such restoration.
F. Restoration of existing property and structures shall be carried out as promptly as practicable and shall not be left until the end of the construction period.
3.07 MAINTENANCE OF FLOW:
A. The Contractor shall at its own cost, provide for the flow of sewers and drains interrupted during the progress of the work, and shall immediately cart away and dispose of all offensive matter. The entire procedure of maintaining existing flow shall be fully discussed with the Engineer well in advance of the interruption of any flow.
B. All existing drainage facilities including, but not limited to; brooks, streams, canals, channels, ditches, culverts, catch basins and drainage piping shall be adequately safeguarded so as not to impede drainage or to cause siltation of downstream areas in any manner whatsoever. If the Contractor damages or impairs any of the aforesaid drainage facilities, it shall repair the same within the same day.
C. At the conclusion of the work, the Contractor shall remove all silt in drainage structures caused by its operations as described in Section 01 74 13, CLEANING UP.
3.08 REJECTED MATERIALS AND DEFECTIVE WORK:
A. Materials furnished by the Contractor and condemned by the Engineer as unsuitable or not in conformity with the specifications shall forthwith be removed from the work by the Contractor, and shall not be made use of elsewhere in the work.
B. Any errors, defects or omissions in the execution of the work or in the materials furnished by the Contractor, even though they may have been passed or overlooked or have appeared after the completion of the work, discovered at any time before the final
08/07/2018 01 11 00-5 payment is made hereunder, shall be forthwith rectified and made good by and at the expense of the Contractor and in a manner satisfactory to the Engineer.
C. The Contractor shall reimburse the Owner for any expense, losses or damages incurred in consequence of any defect, error, omission or act of the Contractor or its employees, as determined by the Engineer, occurring previous to the final payment.
3.09 SANITARY REGULATIONS:
Sanitary conveniences for the use of all persons employed on the work, properly screened from public observation, shall be provided in sufficient numbers in such manner and at such locations as may be approved. The contents shall be removed and disposed of in a satisfactory manner as the occasion requires. The Contractor shall rigorously prohibit the committing of nuisances within, on or about the work. Any employees found violating these provisions shall be discharged and not again employed on the work without the written consent of the Engineer. The sanitary conveniences specified above shall be the obligation and responsibility of the Contractor.
3.10 SAFETY AND HEALTH REGULATIONS:
This project is subject to the Safety and Health regulations of the U.S. Department of Labor set forth in 29 CFR, Part 1926, and to the Connecticut Department of Labor Division of Occupational Safety and Health (CONN-OSHA). Contractors shall be familiar with the requirements of these regulations.
3.11 SITE INVESTIGATION:
The Contractor acknowledges that it has satisfied itself as to the conditions existing at the site of the work, the type of equipment required to perform this work, the quality and quantity of the materials furnished insofar as this information is reasonably ascertainable from an inspection of the site, as well as from information presented by the drawings and specifications made a part of this contract. Any failure of the Contractor to acquaint itself with available information will not relieve it from the responsibility for estimating properly the difficulty or cost of successfully performing the work. The Owner assumes
08/07/2018 01 11 00-6 no responsibility for any conclusion or interpretation made by the Contractor on the basis of the information made available by the Owner.
3.12 HANGERS, PADS, AND SUPPORTS:
A. Unless otherwise indicated, hangers and supports shall be by the trade providing the supported item.
B. Except where detailed or specified, design of hangers and supports shall be the responsibility of the Contractor. All parts of such hangers or supports shall be designed in accordance with accepted engineering practice, using a factor of safety of at least 2½.
C. When proprietary hangers, etc., are supplied, satisfactory evidence of the strength of such items shall be furnished.
D. Hangers for items hung from steel and concrete shall be centered on the vertical center of gravity of the beam.
E. Locations and sizes of openings, sleeves, concrete pads, steel frames, and other equipment supports are indicated on the drawings for bidding purposes only. Final sizes and locations of such items shall be obtained from the shop drawings.
3.13 SLEEVES, HOLES, HANGERS, INSERTS, ETC.:
A. Except where holes and openings are dimensioned, and hangers, inserts, and supports are fully called for on the architectural and structural drawings (or reference is made thereon to drawings containing such information) to accommodate mechanical or electrical items, they shall be by the mechanical or electrical trade concerned.
B. Sleeves, inserts, anchors, etc., supplied under the mechanical and electrical contracts in sufficient time to so permit, shall be set in concrete, masonry, etc., or fastened to steel deck, etc., by the respective architectural or structural trade. Where not supplied in
08/07/2018 01 11 00-7 sufficient time, installation of such items shall be the responsibility of the mechanical or electrical trade involved.
C. Nothing shall be suspended from the steel roof deck and no fastenings made to it, except with the prior permission of the Engineer. Request for permission shall be accompanied by full details of the hanger or fastener, including the weight of the item to be suspended.
D. Nailers and other wood members attached to steel or masonry, for which fasteners are not indicated on the design drawings or in the specification, shall be fastened with the equivalent of ½-inch diameter bolts at 3 feet o.c.
E. Openings for mechanical and electrical items in finished areas of the building shall be closed off with near escutcheon plates or similar closures. These closures shall be by the mechanical or electrical trade involved.
3.14 ROOF PROTECTION:
Where work must be performed over completed roofing, the roofing shall be protected by 2 layers of ½-inch thick plywood, laid with joints in the second layer offset 1/2 sheet width and length from joints in the first layer. No material shall be stored or work performed on areas of roof which are not so protected.
3.15 WEATHER PROTECTION:
The Contractor shall install weather protection and shall furnish adequate heat in the area so protected during the months of November through March.
3.16 ELECTRIC SERVICE:
A. The Contractor shall make all necessary applications and arrangements and pay for all fees and charges for electrical energy for power and light necessary for the proper completion of this contract during its entire progress. The Contractor shall provide and pay for all temporary wiring, switches, connections, and meters.
B. There shall be sufficient electric lighting so that all work may be done in a workmanlike manner where there is not sufficient daylight.
*3.17 HAZARDOUS WASTE:
Should the Contractor, while performing work under this contract, uncover hazardous materials, as defined in Connecticut Remediation Standard Regulations, it shall immediately notify the Engineer. The Contractor is not, and has no authority to act as, a
08/07/2018 01 11 00-8 handler, generator, operator or disposer of hazardous or toxic substances found or identified at the site, and the Owner shall undertake all such functions.
END OF SECTION
\\Wse03.local\WSE\Projects\CT\Greenwich CT\Greenwich- Upper Havemeyer\Specifications\01 11 00 CONTROL OF WORK AND MATERIALS.docx
04/18/2013 01 12 16 - 1
SECTION 01 12 16
SCOPE AND SEQUENCE OF WORK
PART 1 – GENERAL
1.01 WORK INCLUDED:
A. Field improvements including but not limited to natural turf field improvements, drainage system, seed & sod, and replacement of existing irrigation system.
1.02 RELATED WORK:
A. SECTION 01 11 00 – CONTROL OF WORK AND MATERIALS
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
3.01 GENERAL:
A. The Contractor shall be responsible for scheduling its activities and the activities of any subcontractors involved, to meet the completion date, or milestones, established for the contract. Scheduling of the work shall be coordinated with the Owner and Engineer.
B. The Construction Sequence Requirements shall be used by the Contractor to form a complete schedule for the project, which shall be coordinated with the Owner and Engineer. Prior to performing any work at the site, the Contractor shall submit a detailed plan to the Engineer for review. The plan shall describe the proposed sequence, methods, and timing of the work.
END OF SECTION
\\Wse03.local\WSE\Projects\CT\Greenwich CT\Greenwich- Upper Havemeyer\Specifications\01 12 16 SCOPE AND SEQUENCE OF WORK.docx
SECTION 01 14 00
SPECIAL PROVISIONS
PART 1 - GENERAL
Not used
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
3.01 WATER FOR CONSTRUCTION PURPOSES:
A. In locations where water is in sufficient supply, the Contractor may be allowed to use water without charge for jetting backfill and other construction purposes. The express approval of the Owner shall be obtained before water is used. Waste of water by the Contractor shall be sufficient cause for withdrawing the privilege of unrestricted use.
B. If no water is available, the Contractor shall supply water at no additional cost to the Owner.
3.02 PIPE LOCATION:
Pipe shall be located substantially as indicated on drawings. The Owner reserves the right, acting through the Engineer, to make such modifications as may be deemed desirable to avoid interference with existing structures or for other reasons.
3.03 DIMENSIONS OF EXISTING STRUCTURES:
Where the dimensions and locations of existing structures are of critical importance in the installation or connections of new work, the Contractor shall verify such dimensions and locations in the field before the fabrication of any material or equipment that is dependent on the correctness of such information.
3.04 OCCUPYING PRIVATE PROPERTY:
The Contractor shall not enter upon nor occupy with men, equipment or materials any property outside of the public highways or Owner’s easements, except with the written consent of the property owner or property owner’s agent.
3.05 EXISTING UTILITY LOCATIONS – CONTRACTOR’S RESPONSIBILITY:
A. The location of existing underground services and utilities shown on the drawings is based on available records. It is not warranted that all existing utilities and services are shown, or that shown locations are correct. The Contractor shall be responsible for
08/07/2018 01 14 00-2 having the utility companies locate their respective utilities on the ground prior to excavating.
B. To satisfy the requirements of Connecticut law, the Contractor shall, at least 72 hours, exclusive of Saturdays, Sundays and holidays, prior to excavation in the proximity of telephone, gas, cable television and electric utilities, notify the utilities concerned by calling “CALL BEFORE YOU DIG” at telephone number: 1-800-922-4455.
C. The Contractor shall coordinate all work involving utilities and shall satisfy itself as to the existing conditions of the areas in which it is to perform its work. It shall conduct and arrange its work so as not to impede or interfere with the work of other contractors working in the same or adjacent areas.
3.06 COORDINATION OF WORK:
The General Contractor shall be responsible for coordinating its own work as well as that of any subcontractors. He shall be responsible for notification of the Engineer when each phase of work is expected to begin and the approximate completion date.
3.07 TIME FOR COMPLETION OF CONTRACT:
The time for completion of this contract is stipulated in the Form of/for General Bid.
The Bidder shall base its bid on completing the proposed work by the completion date stipulated in Section 00 41 43, FORM OF GENERAL BID/FORM FOR GENERAL
BID.
3.08 MAINTENANCE OF TRENCH SURFACE:
After backfilling and compacting the trench, the Contractor shall be responsible for keeping the ground surface dry and passable at all times until the surface has been restored to original conditions.
3.09 DESIGN OF EQUIPMENT:
Attention is directed to the fact that the layout of certain equipment is based on that of one manufacturer. If other equipment is submitted for approval, the Contractor shall prepare and submit for approval at its expense, detailed structural, mechanical and electrical drawings, equipment lists, maintenance requirements, and any other data required by the Engineer, showing all necessary changes and embodying all special
08/07/2018 01 14 00-3 features of the equipment he proposes to furnish. Such changes, if approved, shall be made at the expense of the Contractor.
3.10 SERVICES OF MANUFACTURER’S REPRESENTATIVE:
A. The Contractor shall arrange for a qualified service representative, at a time suitable to the Engineer, from the company manufacturing or supplying certain equipment as indicated on the detailed specifications, to perform the duties described herein.
B. After installation of the listed equipment has been completed and the equipment is presumably ready for operation, but before others operate it the representative shall inspect, operate, test, and adjust the equipment. The inspection shall include, but shall not be limited to, the following points as applicable:
1. Soundness (without cracks or otherwise damaged parts); completeness in all details, as specified; correctness in setting, alignment, and relative arrangement of various parts; adequacy and correctness of packing, sealing and lubricants.
2. The operation, testing, and adjustment shall be as required to prove that the equipment is left in proper condition for satisfactory operation under the conditions specified. Where called for in the specifications, vibration readings shall be made and the equipment balanced accordingly.
3. On completion of its work, the Contractor shall submit in triplicate to the Engineer the manufacturer’s or supplier representative’s complete signed report of the results of its inspection, operation, adjustments, and test. The report shall include detailed descriptions of the points inspected, tests and adjustments made, quantitative results obtained if such are specified, and suggestions for precautions to be taken to ensure proper maintenance. The report shall also include a certificate that the equipment conforms to the requirements of the
08/07/2018 01 14 00-4 contract and is ready for permanent operation and that nothing in the installation will render the manufacturer’s warranty null and void.
4. After the Engineer has reviewed the reports from the manufacturer’s representative, the Contractor shall make arrangements to have the manufacturer’s representative present when the field acceptance tests are made.
3.12 PROJECT SIGN:
A. The sign shall be erected within ten (10) days after the construction contract is awarded.
The sign shall be fabricated, erected, and maintained by the Contractor.
B. The Contractor shall provide adequate support for the sign as determined by the Engineer. All supports, trim, and back of sign shall be painted with at least two coats of exterior paint.
C. The project sign shall be maintained by the Contractor in good condition at all times for the duration of construction. The Contractor shall remove the sign upon completion of construction.
3.13 COMPLIANCE WITH PERMITS:
A. The Contractor shall perform all work in conformance with requirements of the Permits, which appear in Section 00 31 43 – PERMITS.
3.14 CUTTING, FITTING AND PATCHING:
A. The Contractor shall do all cutting, fitting, or patching of its work that may be required to make its several parts come together properly and fit it to receive or be received by work of other Contractors, as shown upon or reasonably implied by the drawings and the specifications for the completed structure, including all existing work.
B. The Contractor shall not endanger any work by cutting, digging, or otherwise and shall not cut or alter the work of any other Contractor, save with the consent of the Engineer.
C. All holes or openings required to be made in new or existing work, particularly at pipe, conduit, or other penetrations not covered by escutcheons or plates shall be neatly patched. All such holes shall be made completely watertight as approved by the Engineer.
D. Size and locations of holes required in steel, concrete, or other structural or finish materials for piping, wiring, ducts, etc., which have not been located and detailed on the drawings shall be approved by the Engineer prior to layout and cutting thereof. All holes shall be suitably reinforced as required by the Engineer.
E. Workmanship and materials of patching and repair work shall match the adjacent similar work and shall conform to the applicable sections of the specification. Patches and joints
08/07/2018 01 14 00-5 with existing work shall provide, as applicable in each case, visual, structural, and waterproofing continuity.
3.15 CONNECTIONS TO EXISTING WATER SYSTEMS:
A. The Owner will, upon 72-hour notice from the Contractor, assist the Contractor by locating and opening or closing any and all valves required for draining or admitting water to the various sections of the water main as required to perform the proposed work.
No damages shall be claimed by the Contractor for delays in dewatering pipelines nor shall any damages be claimed because of water leaking through closed valves after dewatering is completed.
B. Connections to the existing distribution system shall be made with the mains under pressure unless the lines can be temporarily taken out of service as approved by the Owner.
C. The Contractor will be required to make test excavations to ascertain that the proposed position of the connections will be clear of joints, fittings, or other obstructions.
D. If any failure occurs in connection to existing mains, service shall be restored in the shortest possible time, the Contractor working around the clock, if necessary. He shall cooperate with the Owner in notifying the consumers or supplying emergency water. If required by Owner, the Contractor shall make connections to water mains during night hours, on Sunday or at other times of off-peak demand for water.
3.17 CONTRACTOR’S REPRESENTATIVE:
The Contractor shall designate a representative who will be available to respond to emergency calls by the Owner at any time day and night and on weekends and holidays should such a situation arise.
3.18 VISUAL RECORDING:
Before beginning construction, the Contractor shall make a color DVD recording along the entire work length. One complete recording, for the entire project length, shall be
08/07/2018 01 14 00-6 furnished to the Engineer prior to the start of the work. The visual recording shall be identified by street name, as applicable, and station.
3.19 OPERATOR TRAINING:
A trained representative of the manufacturer of all equipment shall instruct the plant operating personnel on the operation and maintenance of the equipment. The Owner reserves the right to videotape all training sessions.
3.20 HOURS OF CONSTRUCTION ACTIVITY:
A. The Contractor shall conduct all construction activity between 7:00 a.m. and 5:00 p.m., Monday through Friday. No construction work shall be allowed on Saturdays, Sundays or Holidays without written authorization from the Owner.
B. The Owner will provide personnel for assistance in locating and operating valves at no cost to the Contractor during the Owner’s normal working hours (Monday through Friday 7:00 a.m. to 3:00 p.m.). When this assistance is required by the Contractor outside of the Owner’s normal working hours the cost will be incurred by the Contractor at the prevailing overtime rate of pay for the personnel providing the assistance. The Owner will bill the Contractor directly.
3.21 CONSTRUCTION CREWS:
The Contractor shall not increase the number of construction crews assigned to the work without providing one-week advance notice to the Engineer.
3.25 WINTER WORK:
Work will not be allowed within the public ways on this project during the winter months.
END OF SECTION
\\Wse03.local\WSE\Projects\CT\Greenwich CT\Greenwich- Upper Havemeyer\Specifications\01 14 00 SPECIAL PROVISIONS.docx
01 14 19.16-1
SECTION 01 14 19.16
DUST CONTROL
PART 1 - GENERAL
1.01 DESCRIPTION:
This section of the specification covers the control of dust via water, complete. The contractor shall provide all equipment, labor, materials and related work necessary for the prevention and control of dust resulting from operations in the performance of the work.
PART 2 - PRODUCTS
2.01 CALCIUM CHLORIDE:
A. (Not Applicable)
2.02 WATER:
A. Water shall not be brackish and shall be free from oil, acid, and injurious alkali, vegetable matter or pollutants.
PART 3 - EXECUTION
3.01 APPLICATION:
A. (Not Applicable)
B. (Not Applicable)
C. Water may be sprinkler applied with equipment including a tank with gauge-equipped pressure pump and a nozzle-equipped spray bar.
D. Water shall be dispersed through the nozzle under a minimum pressure of 20 pounds per square inch, gauge pressure.
E. The contractor shall exercise every precaution and means to prevent and control dust arising out of all construction operations from becoming a nuisance to abutting property owners or surrounding neighborhoods. Pavements adjoining the project site shall be kept broomed off and washed clean of excess material wherever and whenever directed.
Water shall be applied to surface of all disturbed areas at such rates and at such times as may be directed by the Engineer to allay dust conditions.
F. Should the contractor of his employees neglect to provide proper dust control, as required in these specifications, the owner immediately, and without notice may furnish such dust control measures as are deemed necessary. The cost thereof shall be borne
01 14 19.16-2 by the contractor and may be deducted from any amount due or to become due to the contract under this contract.
END OF SECTION
\\wse03.local\WSE\Projects\CT\Greenwich CT\Greenwich- Upper Havemeyer\Specifications\01 14 19.16 Dust Control.docx
09/30/2011 01 31 19.23-1
SECTION 01 31 19.23
CONSTRUCTION MEETINGS
PART 1 - GENERAL
1.01 DESCRIPTION:
A. This Section specifies requirements for project meetings including but not limited to Pre-Construction Conference and Progress Meetings.
B. It shall be the responsibility of the Contractor to coordinate work between all subcontractors, sections, and trades required for the proper completion of the Work.
1.02 PRE-CONSTRUCTION CONFERENCE:
A. After the bids have been opened but prior to the start of the construction there will be a pre-construction conference to discuss the phasing and scheduling of the Project. The specific time and place of the conference shall be arranged by the Engineer after the Contract has been awarded.
B. This pre-construction conference is intended to establish lines of communication between the parties involved, review responsibilities and personnel assignments, establish project schedules, discuss proposed performance methods, and coordinate Work to be performed by subcontractors.
C. Authorized representatives of the Owner, Engineer and their consultants, the Contractor, its Superintendent and Site Foreman, and all others invited by the Contractor, shall attend the pre-construction conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
D. Discuss items of significance at the pre-construction conference that could affect progress including at least the following:
1. Tentative construction schedule
2. Critical Work sequencing
3. Designation of responsible personnel
4. Procedures for processing field decisions and Change Orders
5. Procedures for processing Applications for Payment
6. Distribution of Contract Documents
7. Submittal of Shop Drawings, Product Data and Samples
09/30/2011 01 31 19.23-2
8. Preparation of record documents
9. Use of the premises
10. Office, work and storage, and laydown areas
11. Equipment deliveries
12. Construction safety procedures
13. Environmental health and safety procedures
14. First aid
15. Security
16. Housekeeping
17. Working hours
18. Traffic Control
19. Emergency Vehicle Access to and around work site
20. Environmental protection measures for construction site
1.03 PROGRESS MEETINGS:
A. During the course of the Project, the Contractor shall attend weekly progress meetings as scheduled by the Owner. The Owner, based on work progress and activities, may adjust the progress meetings to biweekly or other. The attendance of subcontractors may be required during the progress of the Work. The Contractor's delegate to the meeting shall be prepared and authorized to discuss the following items:
1. Progress of Work/Critical Work Sequencing in relation to Contract Schedule.
2. Proposed Work activities for forthcoming period.
3. Resources committed to Contract.
4. Coordination of Work with others.
5. Status of procurement of equipment and materials.
6. Status of Submittals.
7. Outstanding actions, decisions, or approvals that affect Work activities.
8. Site access and/or security issues
9. Hazards and risks
10. Housekeeping
11. Quality issues
12. Potential Claims
13. Change Orders
14. Costs, budget, and payment requests
B. The Contractor shall revise the construction schedule after each progress meeting where revisions to the schedule have been made or recognized and the revised schedule shall be submitted to the Engineer and Owner.
09/30/2011 01 31 19.23-3
PART 2 - PRODUCTS
Not used.
PART 3 – EXECUTION
Not used.
END OF SECTION
P:\CT\Greenwich CT\Greenwich- Upper Havemeyer - ReBid\Specifications\01 31 19.23 Construction Meetings.docx
08/11/2019 01 32 16-1
SECTION 01 32 16
CONSTRUCTION SCHEDULING
PART 1- GENERAL
1.01 PROGRAM DESCRIPTION:
A. A Critical Path Method (CPM) construction schedule shall be used to control the work of this Contract and to provide a definitive basis for determining job progress. The Contractor shall prepare the construction schedule. All work shall be done in accordance with the established CPM schedule and the Contractor and his subcontractors shall be responsible for cooperating fully with the Engineer and the Owner in effectively utilizing the CPM schedule.
B. The CPM schedule to be prepared and submitted by the Contractor shall consist of a CPM network (diagram of activities) and a computer-generated schedule (print-out) as specified herein. The format shall be the activity-on-node precedence network.
C. The Contractor shall develop his own outline of the work and prepare his proposed CPM schedule. The computer-based schedule shall be the product of a recognized commercial computer software producer and shall meet all of the requirements defined herein.
1.02 QUALIFICATIONS:
A. The Contractor shall have the capability of preparing and utilizing the specified CPM scheduling technique. A statement of CPM capability shall be submitted by the Contractor in writing to the Engineer within 10 days after the issuance of the Notice to Proceed to verify that either the Contractor's organization has in-house capability qualified to use the technique or that the Contractor employs a consultant who is so qualified. Capability shall be verified by description of the construction projects to which the Contractor or his consultant has successfully applied the CPM scheduling technique and which were controlled throughout the duration of the project by means of systematic use and updating of a computer-based CPM schedule. The submittal shall include the name of the individual on the Contractor's staff who will be responsible for the CPM schedule and for providing the required updating information.
1.03 SUBMITTALS:
A. Submit under provisions of Section 01 33 23.
B. Within 10 days following the issuance of the Notice to Proceed, the Contractor shall submit the CPM Schedule to the Engineer for review and acceptance. The Contractor shall submit to the Engineer a preliminary network defining the planned operations during the first 60 calendar days after the issuance of the Notice to Proceed. The Contractor's general approach for the balance of the project shall be indicated. Cost of
08/11/2019 01 32 16-2 activities expected to be completed or partially completed before submission and approval of the complete network shall be included.
1.04 APPROVED CPM SCHEDULE:
A. Following review by the Engineer, the Contractor shall incorporate the Engineer's comments into the network and submit the revised network and computer-generated schedule. This final submittal shall be delivered to the Engineer within 60 days after the issuance of the Notice to Proceed.
B. CPM schedules, which contain activities showing negative, float or which extend beyond the contract completion date in the computer-generated schedule will not be approved.
C. The approved network shall then be the approved CPM schedule to be used by the Contractor for planning, organizing and directing the work, and reporting progress.
D. Approval of the CPM activity network by the Engineer is advisory only and shall not relieve the Contractor of responsibility for accomplishing the work within the contract completion date. Omissions and errors in the approved CPM schedule shall not excuse performance less than that required by the Contract. Approval by the Engineer in no way makes the Engineer an insurer of the CPM schedule's success or liable for time or cost overruns flowing from its shortcomings. The Owner hereby disclaims any obligation or liability by reason of approval by its agent, the Engineer, of the CPM schedule.
E. The CPM activity network shall be submitted on sheets 24-in by 36-in and may be divided into as many separate sheets as required. An electronic file in PDF format shall be submitted concurrent with the hard copy schedule.
PART 2 – PRODUCTS
NOT USED
PART 3 – EXECUTION
3.01 NETWORK REQUIREMENTS:
A. The network shall show the order and inter-dependence of activities and the sequence in which the work is to be accomplished as planned by the Contractor. The basic concept of a network analysis diagram shall be followed to show how the start of a given activity is dependent on the completion of preceding activities and its completion restricts the start of following activities.
B. Detailed network activities shall include: construction activities, the submittal and approval of shop drawings, the procurement of materials and equipment, fabrication of materials and equipment and their delivery, installation and testing, start-up and training.
The Contractor shall break the work into activities with durations no longer than twenty working days each, except as to non-construction activities (such as procurement of materials and delivery of equipment) and any other activities for which the Engineer may
08/11/2019 01 32 16-3 approve the showing of longer duration. To the extent feasible, activities related to a specific physical area of the work should be grouped on the network for ease of understanding and simplification.
C. Separate activities shall be provided for each significant identifiable function in each trade area in each facility. Activities shall be so identified that there will be no reasonable doubt as to how much work remains on each. Specific activities which shall be included are: all subcontract work, all interface work between subcontractors and between the Contractor and subcontractors, leakage tests of pipelines, electrical connections to each item of equipment, supplier and manufacturer technical assistance, mechanical connections to each item of equipment, all tests, concrete finishing, each item of site work, (including restraints on other activities) and all utilities, fuels and chemicals.
D. Each activity on the network shall have the following indicated on the NODE representing it.
1. A single duration (i.e., the single best estimate of elapsed time considering the scope of the work involved in the activity and the resources planned for accomplishing the activity) expressed in working days.
2. A five character (or less) code indicative of the party responsible for accomplishing the activity.
3. A cost estimate for each activity which, when accumulated with the cost of all activities, equals the total contract cost. Estimated overhead and profit shall be prorated throughout all activities. Materials costs shall be assigned to delivery activities.
4. A brief description of the activity.
E. The selection and number of activities shall be subject to the Engineer's approval. The detailed network need not be time scaled but shall be drafted to show a continuous flow from left to right with no flow from right to left. In addition to the brief description, the Contractor shall submit a separate list of all activities containing a detailed narrative of the scope of each activity, including the trades, subcontractors involved, and number of man-hours estimated.
F. To the extent that the network or any revision thereof shows anything not jointly agreed upon or fails to show anything jointly agreed upon, it shall not be deemed to have been approved by the Engineer. Failure to include on a network any element of work required for the performance of this Contract shall not excuse the Contractor from completing all work required within any applicable completion date, notwithstanding the review of the network by the Engineer.
G. Except where earlier completions are specified, CPM schedules, which show completion of all work prior to the contract completion date, may be approved by the Engineer but
08/11/2019 01 32 16-4 in no event shall they be acceptable as a basis for claim for delay against the Owner by the Contractor.
3.02 COMPUTER-GENERATED SCHEDULE REQUIREMENTS:
A. Each computer-generated schedule submittal from the CPM activity network shall include the following tabulations: a list of activities in numerical order, a list of activity precedence’s, a schedule sequenced by Early Start Date and a schedule sequenced by Total Float. Each schedule shall include the following minimum items:
1. Activity numbers
2. Estimated duration
3. Activity description
4. Early start date (calendar dated)
5. Early finish date (calendar dated)
6. Latest allowable start date (calendar dated)
7. Latest allowable finish date (calendar dated)
8. Status (whether critical)
9. Estimated cost of the activity
10. Total float and free float
B. In addition, each schedule shall be prefaced with the following summary data:
1. Contract name and number
2. Contractor's Name
3. Contract duration
4. Contract schedule
5. The effective or starting date of the schedule.
C. The workday to calendar date correlation shall be based on an 8-hour day and 40-hour week with adequate allowance for holidays, adverse weather and all other special requirements of the work.
3.03 PROGRESS REPORTING:
08/11/2019 01 32 16-5
A. Progress under the approved CPM schedule shall be evaluated monthly by the Contractor. Not less than seven days prior to each monthly progress meeting, The Contractor shall evaluate the status of each activity on which work has started or is due to start, based on the preceding CPM schedule; to show actual progress, to identify those activities started and those completed during the previous period, to show the estimated time required to complete or the percent complete of each activity started but not yet completed and to reflect any changes indicated for the network. Activities shall not be considered complete until they are, in fact, 100 percent complete.
B. At each progress meeting the Contractor shall submit a narrative report based on the CPM schedule evaluation described above, in a format agreed upon by the Contractor and the Engineer. The report shall include a description of the progress during the previous period in terms of completed activities, an explanation of each activity which is showing a delay, a description of problem areas, current and anticipated delaying factors and their estimated impact on performance of other activities and completion dates and an explanation of corrective action taken or proposed. This report, as well as the CPM Status Report, will be discussed at each progress meeting.
3.04 RESPONSIBILITY FOR SCHEDULE COMPLIANCE:
A. Whenever it becomes apparent from the current CPM schedule and narrative report that delays to the critical path have resulted and the contract completion date will not be met, the Contractor shall take some or all of the following actions at no additional cost to the Owner. He shall submit to the Engineer for approval, a written statement of the steps he intends to take to remove or arrest the delay to the critical path in the approved schedule.
3.05 ADJUSTMENT OF CONTRACT SCHEDULE AND COMPLETION TIME:
A. If the Contractor desires to make changes in his method of operating which affect the approved CPM schedule, he shall notify the Engineer in writing stating what changes are proposed and the reason for the change. If the Engineer approves these changes, the Contractor shall revise and submit for approval, without additional cost to the Owner, all of the affected portions of the CPM network. The Contractor shall adjust the CPM schedule only after prior approval of his proposed changes by the Engineer.
B. If the completion of any activity, whether or not critical, falls more than 100 percent behind its approved duration, the Contractor shall submit for approval a schedule adjustment showing each such activity divided into two activities reflecting completed versus uncompleted work.
C. Shop drawings which are not approved on the first submittal or within the schedule time and equipment which do not pass the specified tests shall be immediately rescheduled.
D. The contract time will be adjusted only for causes specified in this Contract. In the event the Contractor requests an extension of any contract completion date, he shall furnish such justification and supporting evidence as the Engineer may deem necessary to determine whether the Contractor is entitled to an extension of time under the provisions of this Contract. The Engineer will, after receipt of such justification and supporting evidence, make findings of fact and will advise the Contractor in writing thereof. If the
08/11/2019 01 32 16-6
Engineer finds that the Contractor is entitled to any extension of any contract completion date, the Engineer's determination as to the total number of day’s extension shall be based upon the currently approved CPM schedule and on all data relevant to the extension.
Such data shall be included in the next updating of the schedule. Actual delays in activities, which, according to the CPM schedule, do not affect any contract completion date shown by the critical path in the network, will not be the basis for a change therein.
E. Each request for change in any contract completion date shall be submitted by the Contractor to the Engineer within 30 days after the beginning of the delay for which a…